Deshuttering EPC10 RA15 R1

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 3

ABU DHABI GAS DEVELOPMENT COMPANY LIMITED

SHAH GAS DEVELOPMENT (SGD) PROGRAM


RISK ASSESSMENT and WORK INSTRUCTIONS

Task/Activity Description: De-Shuttering Reference Number:


EPC10-RA15-R1
Note : Risk Assessment Matrix adopted from ADNOC-CoPV5-06 Date of Issue: 30 Oct t 13
Page 1 of 3

Risk Hazard Risk/Impact Risk Assessment Control Measures Risk Assessment Responsible
No (Pre Controls) (Post Controls) Person

Risk Rating

Risk Rating
Probability

Probability
Categories

Categories
Severity

Severity
De shuttering to be carried out strictly under close supervision
Incorrect design Serious physical
1. 5 C P High as per the approved safe work method statement. 2 A P Low Site Engineer
input regarding Injury, Fatality,
loading/  Shutters to be removed in marked/ identified
Property Damage
sequence.
Premature, De
 Ensure that workmen engage are competent.
shuttering, Improper
De shuttering  Proper barrication and signage are posted to prevent
sequence leading to unauthorised entry in the de shuttering area.
collapse of  Work to be carried out under strict supervision.
structure. .

High
Inadequate access 4 C P 2 A P Low
2. Serious physical
platforms/fall Injury, Fatality, Access platforms to be erected by certified scaffolders based Site
protection system on the intended load and tag system to be followed to validate supervisor/F/M
while de-shuttering it
 Adequate access platform with fall protection system
to be provided to Workmen while working at height.
 Lifting activity to plan to minimised risk of exposure to
workmen below /Working under suspended load to be
avoided.
 Shutter is handled carefully to prevent slip and fall
P while manual handling 2 A P Low
High
 Ensure that the lifting devices are certified and free
3. Improperly Serious physical 4 C
from defect prior to use.
handling /lifting of Injury, Fatality,  Tag line having sufficient length to be provided to
ABU DHABI GAS DEVELOPMENT COMPANY LIMITED
SHAH GAS DEVELOPMENT (SGD) PROGRAM
RISK ASSESSMENT and WORK INSTRUCTIONS

Task/Activity Description: De-Shuttering Reference Number:


EPC10-RA15-R1
Note : Risk Assessment Matrix adopted from ADNOC-CoPV5-06 Date of Issue: 30 Oct t 13
Page 2 of 3

Risk Hazard Risk/Impact Risk Assessment Control Measures Risk Assessment Responsible
No (Pre Controls) (Post Controls) Person

Risk Rating

Risk Rating
Probability

Probability
Categories

Categories
Severity

Severity
guide the formwork material without coming under Rigging
shutter (formwork) supervisor/ Banks
suspended load.
man
 Training and Closed supervision to ensure that the
workers do not deviate from safe work practices.
 Ensure that safe rigging practices are adopted under
competent person.
 Certified Operator, Cranes, Equipments and Lifting
Tackles to be used.
 Do not exceed the Safe Working Load (SWL) of any
P High lifting equipment, use load chart. 2 A P Low
 Do not carry out the lifting operation in adverse
weather conditions.
4. Falling of concrete/ 4 C Supervisor/
shutter while de Serious physical Foremen
shuttering injury/ fatality  Ensure that the de shuttering portion is maintained
hygienic to remove unwanted material
P High  Ensure that the area below is secured with barrication
and safety signage and a person assign to prevent physical 2 A P Low
Inadequate entry.
5. housekeeping Physical injury  Closed supervision for the activity.
4 C
leading to Slip , trip, Supervisor/
Fall hazard P High  Minimum inventory of material to be adopted. Foremen
 Area to be kept free of unwanted materials. 2 A P Low
Serious physical
6. Lack of emergency injury/fatality
4 C Ensure that an emergency preparedness arrangement Project
preparedness manager/HSE
available, know and executed properly.
ABU DHABI GAS DEVELOPMENT COMPANY LIMITED
SHAH GAS DEVELOPMENT (SGD) PROGRAM
RISK ASSESSMENT and WORK INSTRUCTIONS

Task/Activity Description: De-Shuttering Reference Number:


EPC10-RA15-R1
Note : Risk Assessment Matrix adopted from ADNOC-CoPV5-06 Date of Issue: 30 Oct t 13
Page 3 of 3

Risk Hazard Risk/Impact Risk Assessment Control Measures Risk Assessment Responsible
No (Pre Controls) (Post Controls) Person

Risk Rating

Risk Rating
Probability

Probability
Categories

Categories
Severity

Severity
Emergency plan is conducted to familiarize the workers and
staff so as to execute safely real Case.

Work Instructions:
1. All hazard control measures prescribed in this Risk Assessment is issued as a work instruction to be implemented by site supervision.
2. All persons and vehicles must comply with Site HSE Rules and Requirements.
3. Under no circumstance shall any person will work under suspended load / bucket while manually handling/ loading / offloading from equipment.
4. Hand brake to be applied when workers are working near equipment for lifting/ transferring load to and from the equipment
5. Do a tool box talk with all site supervision, operators and operatives. Explain these control measures to all relevant operatives.
6. Housekeeping to be done and workplace to be made safe prior to leaving the workplace.
7. All persons shall sign their understanding and confirmation in the Tool Box Talk attendance sheet.
8. All construction waste will be removed daily from the work area.
9. All Near Misses and Accidents will be reported immediately to the on-duty Medic and site safety officers
10. Copy of this RA will be discussed in pre- start TBT. Copy will be available on site.

In Case of emergency, contact ASCON 24 Hour Emergency Numbers - 0566848083 or 0566848220

Prepared by Name Date and Signature Approved by Name Date and Signature
Project Engineer HSE Manager
Project Engineer Issued by Name Date and Signature
HSE Engineer Mohd. Salauddin Construction Manager
Cc: HSE Files, Worksite

You might also like