Professional Documents
Culture Documents
2020 Construction Shutdown Checklist
2020 Construction Shutdown Checklist
Cessation of Works
This should be considered a dynamic procedure and should therefore be reviewed and updated regularly, to
reflect conditions and changes.
Specific consideration should also be made for reduced staffing levels and lone working to ensure that there is
appropriate supervision oversight of site activities, including health and safety, quality assurance, environmental
management and permit to work systems.
Site security
› Ensure that the site perimeter is secure, with robust fencing able to withstand anticipated weather
conditions during the shutdown period
› Provide CCTV monitoring of the site perimeter (and inside the site), preferably with PIR sensors and
loudspeakers to warn trespassers. CCTV must be linked to a 24-hour manned Alarm Receiving Centre
Source: Aviva Loss Prevention Standard: Temporary shutdown and mothballing of construction sites; AXA XL Project shut-down checklist
Touchstone Underwriting Limited is authorised and regulated by the Financial Conduct Authority. Registered in England No 2264985.
Registered office: 156 South Street, Dorking, Surrey RH4 2HF Page 1 of 5
Liability & Construction
Cessation of Works
Temporary works
› Carry our structural reviews and risk assessments for all temporary works
› Carry our regular inspections and maintenance of temporary works during extended shutdown periods
Specialist partners
› Help minimise risks with Aviva’s Specialist Partners
Source: Aviva Loss Prevention Standard: Temporary shutdown and mothballing of construction sites; AXA XL Project shut-down checklist
Touchstone Underwriting Limited is authorised and regulated by the Financial Conduct Authority. Registered in England No 2264985.
Registered office: 156 South Street, Dorking, Surrey RH4 2HF Page 2 of 5
Liability & Construction
Cessation of Works
Additional information
› Pandemic planning and the coronavirus
› Arson prevention
› Control and management of combustible waste materials
› Unoccupied premises
› Escape of water on construction sites
Further risk management information may be obtained from Aviva Risk Management Solutions.
Please note
This document contains general information and guidance and is not and should not be relied on as specific
advice. The document may not cover every risk, exposure or hazard that may arise and Aviva recommend that
you obtain specific advice relevant to the circumstances.
Source: Aviva Loss Prevention Standard: Temporary shutdown and mothballing of construction sites; AXA XL Project shut-down checklist
Touchstone Underwriting Limited is authorised and regulated by the Financial Conduct Authority. Registered in England No 2264985.
Registered office: 156 South Street, Dorking, Surrey RH4 2HF Page 3 of 5
Liability & Construction
Cessation of Works
Security
Perimeter fencing / hoarding is to be secure (heras panels ‘double’ clipped etc.)
Entrance ways / gates are to be locked
Key(s) to entrances, stores areas and site cabins are to be kept with the nominated key holder
Scaffold
Scaffold boards are to be secured to prevent displacement
ALL materials are to be removed from the scaffold
Monoflex / Debris Netting is to be securely tied to scaffold
Scaffold is to be inspected immediately prior to site closure
Ladders used for accessing scaffold are to be removed and stored securely
ALL mobile / alloy towers are to be dismantled and secured (or off hired and removed from site)
Housekeeping
Site is to be tidy and cleared of ALL rubbish
ALL skips are to be removed from site for the duration of the shutdown period
Materials that are left on site are to be secure and stacked in a stable condition
Access / egress routes are to be kept clear and free from obstruction
Excavations / Groundworks
Where possible ALL open excavations / groundworks are to be backfilled prior to shutdown
If unable to backfill – area is to have suitable barriers / edge protection in place
Shallow excavations are to be covered where possible / suitable battered
Deep excavations are to be suitably shored – and inspected prior to site closure
Plant / vehicles
ALL plant is to be removed from site for the duration of the shutdown period (unless this has
been cleared through the Operations Manager / Director)
Any plant remaining on site is to be immobilised and secured (screens fitted where able) to
prevent access
Any plant remaining on site is to be parked on level ground away from the perimeter fence
Source: Aviva Loss Prevention Standard: Temporary shutdown and mothballing of construction sites; AXA XL Project shut-down checklist
Touchstone Underwriting Limited is authorised and regulated by the Financial Conduct Authority. Registered in England No 2264985.
Registered office: 156 South Street, Dorking, Surrey RH4 2HF Page 4 of 5
Liability & Construction
Cessation of Works
Services
Water systems are to be drained down to prevent damage through burst pipes
Temporary supplies to site is to be isolated at the stopcock
ALL mains supplies (Gas & Electric) is to be turned off at meter – except where lighting /
illumination is essential
Miscellaneous
ALL small tools are to be secured in a lockable container / chest
A copy of the Public Notice is to be correctly displayed at the site entrance
All site personnel are to be briefed on Toolbox Talk – Covid-19
Name Signature
Title Date
Source: Aviva Loss Prevention Standard: Temporary shutdown and mothballing of construction sites; AXA XL Project shut-down checklist
Touchstone Underwriting Limited is authorised and regulated by the Financial Conduct Authority. Registered in England No 2264985.
Registered office: 156 South Street, Dorking, Surrey RH4 2HF Page 5 of 5