Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

CONCRETE QUARTERLY

SPRING 2007
ISSUE NUMBER 219

Into the woods Domestic bliss Miami nice


Cass Sculpture Foundation’s Everything’s out in the open There are plently
new building by Studio at architect Jamie Fobert’s of eco-friendly features —
Downie Architects echoes Victorian conversion, which both inside and out — in this
its woodland setting features fair-faced concrete residential tower design
Welcome News round-up

Concrete sustainability Study confirms concrete’s


The evidence of the impact of climate
change and the consensus that it is the
competitive edge over steel
result of man’s activities is growing. With A forthcoming cost model study cost consultants Davis Langdon
the built environment being responsible has found that reinforced con- with programming carried out by
for over 50% of our CO2 emissions, the crete can be up to 5% cheaper Mace. The study was carried out
role that design and construction can play than steel frames for typical com- on an independent basis and
in reducing the environmental impact of mercial buildings. Furthermore, compared the cost of construct-
buildings is of increasing importance. when only frame costs are con- ing three- and six-storey office
As summers get hotter the probability sidered concrete flat slab was buildings using a variety of rein-
of buildings overheating will increase. The use of passive found to be an average of 36% forced concrete and steel framed
sustainability design and construction techniques, that have cheaper than its flat-slab equiva- short and long span options.
at their heart the thermal mass of concrete construction to lent steel Slimdek construction. The main conclusion of the
modulate the extremes of temperature, will enable buildings These significant cost advan- cost study was that, for commer-
to reduce their requirements for air conditioning and, there- tages were compounded by a cial buildings, concrete-framed
fore, their CO2 emissions. In a similar way, the thermal sink lead time of only four to six solutions are highly competitive
capacity of concrete allows it to trap solar heat gains in the weeks for reinforced concrete with steel-framed solutions and,
winter and so reduce heating requirements. Furthermore, the compared with up to 18 weeks when overall project programme
long-term robustness of concrete will mitigate the impacts of for steel. is considered, they can be pro-
winter storms and flooding that are predicted to increase in The study, Commercial Build- cured and constructed in a
severity. ings: Cost Model Study, was car- shorter overall time frame than
The full utilisation of a building’s thermal mass and its ried out for The Concrete Centre steel-framed buildings.
fabric energy storage will provide buildings that work with by architects Allies & Morrison, For further information visit:
and not against the environment. This is explained in a new structural engineers Arup and www.concretecentre.com
report from The Concrete Centre: Utilisation of Thermal Mass
in Non-residential Buildings.
Meanwhile, projects such as the proposed COR building
in Miami prove that being green does not mean being dull.
For in addition to its functional benefits, concrete offers an
Ecohouse student design
almost limitless range of aesthetic possibilities both in terms
of structural form and in terms of a building’s finish.
competition launched
This is further demonstrated by the structural form of the Architectural and design students
Goodwood gallery and by the cladding finish of the from around the world are invited
Masshouse project in Birmingham. to submit entries for the 2006/07
Guy Thompson Ecohouse Student Design
head of architecture & housing, The Concrete Centre Competition. Launched by The
Concrete Centre, in conjunction
with the Architectural Press and
Inside Teachers in Architecture, the
competition invites students to
4 Jamie Fobert Architects design an Ecohouse for their
Concrete is the main attraction inside this London home hometown, wherever it is, what-
6 Cass Sculpture Foundation ever the local environment.
Studio Downie Architects returns to Goodwood to create This year, the competition
an archive and display centre among the trees seeks to explore two new Eco- Procter Rihl’s Slice House in
10 Precast cladding house ideas: Slow Buildings and Porto Alegre, Brazil, demonstrates
The striking facade of Birmingham’s new Masshouse Low Carbon Buildings. In addi- the potential of concrete for
12 Sustainable design tion to examining these ideas, sustainable construction that
This Miami apartment building will be filled with students will need to ensure that is architecturally exciting.
green features and wrapped in a stylish concrete shell their house design is a 21st cen-
14 Fabric energy storage tury future proof home that is sustainability can be used to reduce
How thermal mass can reduce the need for air conditioning robust against extreme climate the CO2 impact of a home. Open
conditions and constructed using to university-registered students
locally sourced material and skills of architecture or other design
All advice or information from The Concrete Centre is intended for those
who will evaluate the significance and limitations of its contents and take where possible. disciplines, the closing date for
responsibility for its use and application. No liability (including that for negligence) The competition submissions entries is May 8. For further
for any losses resulting from such advice or information is accepted. will be expected to demonstrate a information and registration visit:
On the cover: Cass Sculpture Foundation. Photo by Peter Cook/VIEW full understanding of how passive www.concretecentre.com/ecohouse

2 | CQ | Spring 2007
In brief

Crack control
New guide CIRIA has published
Early Age Thermal
eases Crack Control in
calculation Concrete.
The book is an
of hospital update of CIRIA’s
bestselling guide
vibration R91, and includes
current European
Vibration control is an important codes. Visit
consideration for the design and www.ciriabooks.com
construction of hospitals, for information
especially for operating theatres, on this and other
night wards and intensive care publications.
units. Concrete’s mass means that
it offers the most cost effective New data sheets
way to control vibration. A new Following the recent
design guide, A Design Guide changes to British
for Footfall Induced Vibration Standards and
of Structures, from The Concrete Building Regulations
Centre explains how to predict concerning
and design for footfall induced aggregate concrete
vibration. blocks, the Concrete
In contrast to other construc- Block Association
tion materials, concrete can be has created a set
designed to meet vibration criteria of technical data
with minimal or often no addi- sheets that can be
tional floor thickness. Research downloaded from
by Arup examined the vibration www.cba-
performance of floor structures blocks.org.uk
comprising different structural A lot of bottle
materials. In particular, the Spiral Cellars has designed a concrete underground cellar as
research investigated the addi- a storage solution for wine lovers. The cylindrical underground
tional mass and stiffness required extension, which can be fitted to an existing building, has
to upgrade a basic “office” struc- a two-metre diameter and can be accessed via a discreet trap door.
ture to meet the higher vibration The cellar, which maintains a constant temperature, has good
criteria of hospitals. The research ventilation and remains slightly damp, is an optimum environment
found that concrete can meet the for wine storage and can hold up to 1,600 bottles.
strict vibration criteria of hospi-
tals with only small increases in Jointing seal
mass and depth and, therefore, Tremco Illbruck has
cost, compared with other frame
Devon holiday homes on the fast track produced a durable
solutions. Construction has started on Contractor Buildtec South West jointing seal for use
The basis of the research was 18 holiday apartments in Devon of Exeter is using a combination in floors and
a method of vibration prediction using the H&H Celcon’s Rå of Celcon’s foundation blocks, concrete structures
developed by Arup and exten- House concept. The apartments flooring system and 215mm that is resistant to
sively validated against measure- at Dawlish Warren use H&H blocks with the thin joint system water pressure and
ments on both concrete and com- Celcon’s aircrete blocks, a light- for the solid walls. chemicals. The
posite floors. The new guide from weight material that provides H&H Celcon says interest in Compriband
The Concrete Centre explains the thermal and acoustic insulation. the concept is growing after Hydrospan sealing
method in detail and provides an architects and housebuilders tape, made from
informative description of the watched the apartments con- high strength foam
factors effecting footfall induced structed — with 781sq m of floor- and damp resistant
vibration together with worked ing — in less than four days. epoxy adhesive, can
examples. Rå House is a modern method resist a 10m head of
A Design Guide for Footfall of construction that provides hydrostatic pressure
Induced Vibration of Structures installers and the build materials and bonds easily to
is available from The Concrete for the construction of the concrete, masonry
Bookshop. Tel: 0700 4607 777. The Devon site under construction. masonry shell of a house. and steel.

Spring 2007 | CQ | 3
Jamie Fobert Architects

Casting
spells in
concrete
Smooth, fair-faced
concrete creates a warm
family environment
at the Kander House
in north London
By Beatrice Galilee

The ordered facade of a grand four-


storey Victorian terrace in Primrose
Hill, north London, conceals a striking
addition to a family home by architect
Jamie Fobert. Using in situ concrete to
cast a double-height living space open-
ing on to a terraced garden, the archi-
tect has created a model example to
demonstrate the subtlety and warmth
of concrete in a domestic setting.
The concrete plays important
structural, as well as aesthetic, roles in
this part extension, part conversion. Above
A large open-plan living space and din- Additional living
ing area, with a further living area space hangs
hanging above it in a mezzanine box, in a concrete
has been cast at the rear of the house mezzanine box
and serves to support the more domes- above the heart
tic top two floors of bedrooms and of the house.
bathrooms, finished in white plaster. Left
Ground floor plan.
Walking down the concrete stairway
to the vast open space on the lower-
ground floor, the sheer strength of the they soon agreed it was both the right Most architects find a way of making
concrete is immediately visible. This is aesthetic and structural solution. the texture of fair-faced concrete their
the key to its success in interior and “It just wouldn’t have been the same own, whether it’s a special mix or a
housing projects, says Fobert. in any other material,” says Fobert. secret trick when casting. Fobert’s
“It’s the solidity of the material that is “You can’t get that kind of fluidity of technique is to smooth the material by
so important,” he explains. “It doesn’t form with steel or wood, and you don’t lining the plywood shuttering with a
feel superficial, it’s not an applied need to do anything else to it. It’s just polythene, damp-proof membrane.
surface. You are looking at the core of there. That’s the beauty of it.” The effect of this process is to ensure
the house, and it’s very substantial. This is also, of course, the difficulty no grout seeps into the concrete, leav-
PHOTOS: SUE BARR AND JAMIE FOBERT

That’s not something you see a great of it, and persuading contractors to ing an almost polished finish, but
deal of in architecture at the moment.” treat what they usually consider to be a because the process isn’t perfect, the
Fobert is keen to emphasise that the simple frame, to be covered up in the concrete harbours the remnants —
decision for concrete was not his, but finished product, is something of a trial ghost-like memories of the plastic —
that of the clients. He showed them the for architects. The team had to contend with subtle folds and lines left imbed-
Anderson House, his previous one-off with their contractors spray-painting ded in the wall. These give the effect of
house project, inspired by a gritty inte- marks on to the concrete, and admit it a weathered, familiar face and make for
rior fit out of a bar in east London, and could have been easier. personality traits — the things that

4 | CQ | Spring 2007
Left The double-height living and dining
space opens on to the terraced garden.
Above Cleverly placed lightwells
flood the house with warmth.

make a place a home — rather than


stark white walls.
Throughout the house, every detail
has been considered and reconsidered,
from the order of casting for the floors
and stairs, to the location of the heating
and cabling. Planning ahead for serv-
ices is a crucial lesson for domestic uses
of concrete, because once it’s cast, it’s
cast, and there can be no second
thoughts about the location of sockets,
cabling or electricity conduits.
The concrete floors in the main
living space are power-floated for a
mechanically smooth finish, and are
divided into 3m bays to minimise the
cracking as it dries, although some
cracking is inevitable, as Fobert has
learned from his previous project, the
Anderson House.
Again, as with his last successful
project, this extremely warm and
domesticated house is filled with secret
surprises — lightwells over benches,
and skylights. In each case, the frame is
set back, meaning that glimpses of sky
are framed only by the sharp lines of
concrete, not by unsightly details.
The architect has dealt with the space
formed by the material with ease, as
well as with subtle touches and the
careful, clever manipulation of space,
to create a warm, light and eminently
liveable home.

PROJECT TEAM
Architect: Jamie Fobert Architects
Structural engineer:
Elliott Wood Partnership
Services engineer: Mendick Waring
Quantity surveyor: Measur

Spring 2007 | CQ | 5
Studio Downie Architects

Goodwood’s hidden art


The woods surround-
ing Cass Sculpture
Foundation were the
inspiration for a new
archive and display
centre dedicated to
preserving the best
of British sculpture
On the South Downs of the Goodwood
Estate, Studio Downie Architects has
completed a new archive and display
centre for 21st century British sculp-
ture. A designated area of outstanding
natural beauty, it is the home of the
Cass Sculpture Foundation founded by
Wilfred and Jeanette Cass and is
currently displaying the work of the
eminent sculptor Tony Cragg.
Inspiration for the 500sq m building
came from the beautiful sylvan setting
of the copse. To respond to the ran-
domness and verticality of the screens
of trees, the flat, simple planes reflect
the surrounding landscape and chang-
ing light and shadows. A series of basic
wood fins are hung from the facades as
a continuum of the tree trunks
opposite. When viewed through the
shadowy copse, these dark vertical
elements become at one, blending
between the trees. The spacing of the
fins also responds to the spirit of the
place as an interpretation of rhythms
from Debussy’s score for Prélude a
l’après-midi d’un faune, also set in a beau-
tiful woodland setting of secret glades.
Following the lines of the landscape
within a triangular piece of land, a
trapezoidal form is set down low into a
small valley with a sedum-planted roof.
This forms a visual extension of the
surrounding grass and with concrete
fingers stretching into the chalk slopes,
interlocks existing and new. Colour
changes to the textured facades reflect
the landscape: dark-grey with the fins
facing the trees, light grey facing the
PHOTOS: PETER COOK/VIEW

newly cut and planted chalk slopes.


This lower element is also designed
to conceal, enveloping the largest
volume within the building, a 7m-high
display space which partly protrudes

6 | CQ | Spring 2007
through the sedum, reflecting the scale
and material of Studio Downie’s 1994
visitor gallery. Greys and whites refer to
the indigenous flint and provide a stark-
ness between inside and out, hard and
soft. The calm, robust interior of
exposed white concrete and blockwork
walls contrast with the softness and
changing spectrum of the outside land-
scape. Unlike their earlier visitor gallery
where boundaries were blurred with a
flow between inside and out, here there
is clear separation with the wood fins
a link to the copse.
Along a woodland track the
approach is down into the valley and
the eastern entrance facade. This is a
long simple elevation punctuated with
only two large windows. The first at the
corner serves the entrance space with
Opposite page an oblique view through the full depth
Wood fins of the building to a chalk slope. The
on the south
second much larger one is to the display
elevation blend
space with a cross defining four large
with the trees.
Top panels. It opens up dramatic views both
West elevation inside and out: from the outside, the
showing the space’s ribbed concrete ceiling and yel-
sedum-planted low spine wall, and from inside a wall
roof. of trees and ivy slopes, with the lower
Middle panels sliding apart. (See Detail, page 8.)
The exposed The ancillary spaces, wrapped
concrete and around the central display are linked
blockwork walls by the yellow spine wall. The display
of the lecture hall. space is defined by a tall concrete-
Below ribbed table set separately within a
The large blockwork enclosure. Its restraint
windows open up heightens the presence of the feature
dramatic views window and the impact of the view
both inside to the colourful landscape. Changing
and out. light patterns are provided by three
north-facing rooflights, set over the
deep ceiling ribs, to both control day-
light and create a series of glowing light
sources within the ceiling patterns.
The new foundation centre houses
the charity’s sculpture archive and
library. The archive houses an extensive
and continually growing collection of
artists’ drawings, maquettes, videos
and other source material. The library
stretches the length of the administra-
tion office and is an important resource
of the works of today’s sculptors.
The main space will also be used for
lectures, symposiums and conferences.
PROJECT TEAM
Architect: Studio Downie Architects
Structural engineer:
Jane Wernick Associates
Service engineer:
Peter Deer & Associates
Landscape designer: Russell Hanslip
Main contractor: Ceecom Construction

Spring 2007 | CQ | 7
Studio Downie Architects Detail

Cass Sculpture Cut-away section


Foundation, Goodwood through display space
Roof covering
A new concrete building provides a 2
home for the Cass Sculpture Founda-
tion set amongst the trees in its own
estate on the South Downs. A single- Roof light
storey archive, library and administra-
tion office wrap around three sides of 1
a 6.5m-high display and lecture space.
In the display space eight 300 x
300mm concrete columns support a
roof-level ring beam. The roof slabs
span 10m aided by tapered profile
down-stand ribs at 900mm centres.
The ribbed slab supports three profiled
rooflights which have 150mm-thick
concrete upstand walls. The depth of plasterboard to conceal two siphon
the rooflights and the beam beneath ducts and fan units which extract warm
obviate the need for solar shading. air at the top of the room and re-circu- 16
The columns are braced by late to the bottom. Lighting bars
reinforced concrete shear walls in two Four-hour fire protection was
corners and a 975mm-high ring beam required for the structure, so concrete
at mid-height which has been cast out- was able to achieve this with no addi-
side the columns. Blockwork infill is set tional finishes. The greys of the interior
in the plane of the beam so the columns reflect the exposed chalk excavated to 15
Roof structure
appear to be free-standing in the room. accommodate the building while the
The blockwork has bed-joint reinforce- rhythms of timber on the outside asso-
ment to resist lateral wind loads. ciate it visually with the nearby trees.
The west wall of the display space is
infilled with timber studwork and Detail drawing and text by Graham Bizley
Top
The concrete
beams of the 14
Structural frame
lecture hall under
construction.
Right
Aluminium-
framed doors
Air circulation
slide between
ductwork
external render
and timber screen 12
on either side
of the opening
to the lecture hall.

13 Internal wall lining


on west elevation
PHOTOS: PETER COOK/ VIEW; STUDIO DOWNIE ARCHITECTS

11 Heating
Ground floor slab trench
10

8 | CQ | Spring 2007
1. Roof light 75mm painted steel RSA 11. Ground floor slab
Roof edge 150mm-thick reinforced bolted to concrete to support 75mm power-floated mesh
3 concrete upstand. bottom rail for sliding doors reinforced concrete topping
Polyester powder coated with 75 x 50mm stainless-steel with electrical conduits and
proprietary aluminium rooflight angle threshold. power outlets within.
frame with glazing bars at 120 x 120mm painted steel 250mm-thick reinforced
Timber 1200mm centres. angle bolted to UB to support concrete slab spanning
rainscreen Hermetically sealed double top guide for sliding doors. between edge beams.
cladding glazed units consisting of 2630mm-wide x 3200mm-high Bituminous waterproof
6mm clear toughened outer PPC aluminium framed doors tanking membrane.
pane, 12mm argon filled cavity, sliding between external 50mm sand-cement blinding
6.4mm laminated super low ‘E’ render and timber screen on over compacted chalk bedrock.
inner pane. either side of opening. 12. Air circulation ductwork
2. Roof covering PPC aluminium flashing to 600 x 50mm galvanised steel
3mm bitumen felt vapour cover tops of doors fixed to duct and fan unit concealed in
High-level
4 control layer. continuous 70 x 50 x 7mm depth of wall lining.
glazing
5 Rigid polyurethane insulation painted steel angle bolted to 600 x 50mm aluminium slots
cut to fall from 265mm thick at 120 x 120mm RSA welded to painted black for extract at
east edge to 80mm thick at vertical flange of UB. ceiling and supply at floor level.
west gutter edge. 7. Timber fins 13. Internal wall lining
Single-ply membrane. 205 x 90 x 7mm painted steel on west elevation
Fall restraint system anchors T-section fascia extending 15mm external WBP plywood
fixed through insulation into along full length of elevation sheathing with vapour barrier
concrete slab. fixed back to concrete on with external timber rain-
3. Roof edge 75 x 75mm painted steel screen as per blockwork walls.
Primed steel Z-section to T-section brackets. Softwood internal battening.
support coping. 50 x 50mm galvanised steel 12.5mm plasterboard internal
350 x 140 x 8 by 100mm wide T-sections hung off continuous lining.
steel support angles at T-section steel fascia at 14. Structural frame
nominal 1220mm centres varying centres and buried in Eight 300 x 300mm reinforced
bolted to concrete slab. gravel at base. concrete columns cast in-situ.
Proprietary coated aluminium 3600 x 150 x 50mm 975mm-deep x 200mm-wide
edge flashing hot-air welded Thermowood fins routed with reinforced concrete ring beam
to single ply membrane. groove to slot over steel at mid-height cast in-situ with
Rigid phenolic board insulation. T-sections and fixed with 75mm shadow gap at
Breather membrane. countersunk stainless-steel junctions with columns.
4. Timber rainscreen cladding screws at 600mm centres. 2650mm-wide full-height
140mm fair-faced concrete 8. Low level external wall shear walls in both planes in
blockwork left exposed. 140mm fair-faced concrete south-west and north-west
rame 50mm-deep vertical treated blockwork left exposed. corners.
softwood battens with 120mm rigid phenolic board 15. Roof structure
8 50mm thick rigid phenolic insulation. 400 x 475mm deep reinforced
insulation boards cut to size to 10mm coloured acrylic render concrete perimeter ring beam
Sliding Low fitted between battens. external finish with mesh cast in-situ on top of columns.
doors level 63mm-deep horizontal treated reinforcement. 450mm-deep reinforced
external softwood battens with 60mm 9. External drain concrete beams cast in-situ
6 wall thick rigid phenolic insulation 110mm-thick extruded poly- spanning between perimeter
boards cut to size to fitted styrene perimeter insulation. edge beams at 900mm centres.
between battens. Minimum 500mm-wide x Beams taper from 285mm wide
Breather membrane. 700mm-deep gravel zone at top to 150mm at bottom.
7 38 x 25mm vertical treated around perimeter of building 100mm-thick reinforced
Timber softwood battens. with perforated plastic pipe concrete roof slab.
fins 68 x 19mm western red cedar routed to soakaway. 16. Lighting bars
V-joint horizontal cladding 10. Heating trench 100 x 50 x 9000mm-long
fixed with stainless-steel lost 600mm-wide x 750mm-deep high-strength aluminium
head nails. trench formed from 200mm lighting tracks suspended
5. High-level glazing thick reinforced concrete walls from concrete soffit on pulley
254 x 146mm x 43kg painted and base. and winch with steel cables.
steel universal beam spanning 2200 x 500mm standard high- Support cables looped over
between outer faces of temperature hot water pulleys bolted to concrete
concrete ring beams. radiators fixed to wall of trench. soffit and attached to winch at
100 x 50mm PPC aluminium Heavy duty removable one end and electrical cable
curtain wall section frame galvanised steel grating to reel system at other end.
ating bearing on UB. withstand loads from 600mm-wide x 300mm-deep
ench 70 x 50mm PPC aluminium articulated forklift truck and holes cast in perimeter roof
opening lights for ventilation. carriage over trench, set into beams to house winches.
10 6. Sliding doors concrete recesses. 425mm-wide x 330mm-deep
9 External drain 100 x 50mm steel box section Folded stainless-steel holes cast in perimeter roof
welded to 250 x 50 x 12mm threshold plate between beams to house electrical
rolled steel angle and 120 x grating and sliding doors. cable reels.

Spring 2007 | CQ | 9
Precast cladding

A study in black and white


The first phase of David McLean’s development at Masshouse rises from
the heart of Birmingham with a bold, two-toned Techrete facade
By David Kennell

10 | CQ | Spring 2007
When approaching the heart of texture were the order of the day and
Birmingham, care of Richard Branson’s Techrete set about producing a series
Virgin Pendolino, it is difficult not to of samples and mock-ups to arrive at
notice a stunning black-and-white what is now a very striking building.
building that now graces the city A bright white reconstructed stone was
skyline. David McLean’s prestigious produced for the basic panel finish,
development at Masshouse covers a the standard finish being acid-etched.
large area close to the new Bullring Within many of the panels, the
retail development and similarly change of texture has been achieved
benefits from being near Birmingham’s with horizontal bands of lightly
central railway and bus stations. exposed aggregate, using the same base
A number of somewhat tired 1950s material. As the panels for the areas
and 1960s buildings of various types of heavy colour contrast had
and usages previously occupied the site. to be as black as possible and highly
It is proposed that the McLean site will polished, Techrete developed a black
include a number of predominantly basalt mix to satisfy these require-
residential medium- and high-rise ments, the polishing being carried out
buildings with varying facade by computer-controlled equipment.
treatments, the common denominator The mid-grey colour areas of cladding
being quality of finishes. at roof level, originally scheduled to be
This approach is echoed in the first metal-clad, were eventually faced with
phase — a 15-storey apartment building a silver grey precast cladding, again
sitting on the prow of this triangular appointed to supply the precast Above polished. The final panel configuration
site. The whole project was originally concrete cladding that, apart from The 15-storey necessitated the use of two-colour
conceived as steel-framed, but with the fenestration, forms the entire facade. apartment casting, not the easiest of operations
exception of phase, 1 which is being The treatment to the elevations building is near but the result certainly justifies the
built in steel, the remainder of the proj- includes stepped balconies with a bold Birmingham’s efforts that went into devising a casting
Bullring.
ect looks as if it will be concrete-framed. double-sweeping curve — concave and system to produce a precise demarca-
Opposite
Thanks to its position and imaginative convex — gracing the front facade. tion between the black and the
Masshouse’s
cladding, the new building competes Fortunately, Techrete was instructed white areas.
precast,
very favourably with the other promi- at an early stage and so was able to polished facade. Altogether almost 400 cladding
nent new city developments such as the assist Kevin Slack, McLean’s chief panels were supplied, the total area
Bullring, the Beetham Tower and, of architect in charge of the design for the being 6,000sq m. Many of the panels
course, the Rotunda, the 1960s icon development, in deciding on the most were delivered complete with windows,
currently being extensively refurbished. suitable finishes for the cladding and previously fixed at Techrete’s Brigg
Following a series of meetings and “panelisation”. Finishes with high factory, by the window trade contractor.
“proving” exercises, Techrete was colour contrast and mild changes in David Kennell, Techrete UK Ltd

Factory-made precast cladding allows flexibility and speeds construction


The choice of cladding finishes handling of materials and tempo- team of erectors can safely and
and facings is almost limitless. rary storage on site. The ability to efficiently install six to eight large
Reconstructed stone finishes that provide a factory-finished prod- precast cladding panels per day,
mimic the appearance of natural uct with preassembled stone, generally without the need for an
limestones and sandstones are brick or tile facings avoids the external scaffold. Access for the
often specified. Panels may also common concern about the local subsequent external pointing of
be faced with natural stone, availability of sufficient suitably the joints between them is then
granites, bricks and tiles. qualified masons or bricklayers often provided by platform or
The inherent advantages of to fit in with the programme. cradle or even by abseiling.
precast cladding construction are In addition, weather becomes far Further options include the
valuable and merit full considera- less critical to progress being opportunity for any window
tion. As each precast cladding achieved. apertures within a precast
panel is cast off site in a purpose- Large cladding panels, in cladding panel to be framed and
built factory, it is inspected, held particular, facilitate the rapid glazed before despatch to site.
in store and available for delivery enclosure of all forms of struc- Many of the Masshouse panels A panel may also be supplied with
on a just-in-time basis for off- tural frame and, where spanning were delivered complete with insulation, either as a lining to its
loading and hoisting directly between floor slabs or structural windows inserted. internal face or as a core between
to its final fixing position, thereby columns, avoid the need for sec- two concrete wythes, to enhance
ensuring quality with efficient ondary backing structure for their edge conditions. Moreover, con- its thermal performance.
performance. This method of support and restraint. It may also crete panels are fire resistant and For more information go to:
construction also eliminates the be possible to design them to provide effective sound control. www.architectural-cladding-
need for wasteful double reduce mid-span loads in slab Typically, a four- or five-person association.org.uk

Spring 2007 | CQ | 11
Sustainable design
Lean, green eco-machine
Architecture, structural engineering and ecology have combined to produce Miami’s
ground-breaking COR tower, packing green technologies beneath its concrete shell

The latest addition to Miami’s skyline, solar hot water generation means that Above Happold. It is being developed by
the 25-storey COR project, offers a COR will produce its own energy to The 25-storey 4 Projects Miami and is scheduled for
prototype for high-rise environmental meet the needs of the common areas. COR tower will completion in 2009.
be a prototype
living. Designed by Miami-based The integration of concrete’s ther- COR will contain 113 apartments
for high rise
architect Oppenheim Architecture mal mass with shading and ventilation ranging from studios to two-storey
environmental
& Design, and located in Miami’s is a passive sustainability strategy that penthouses. The apartments will
living.
fast-regenerating design district, can significantly reduce a building’s Left include energy efficient appliances,
COR will integrate a wide range of carbon footprint. Buildings with a A multipurpose recycled glass tile flooring and
green technologies. high level of thermal mass reduce the shell provides the environmentally friendly bamboo-lined
The 116m-tall tower represents a risk of overheating by absorbing building structure hallways.
dynamic synergy between architecture, daytime heat and so stabilise internal and elements to The industrially inspired interior
structural engineering and ecology. temperatures. Cooler, night-time air reduce its energy spaces of the apartments are designed
An integral part of the design is a can then be used to ventilate the footprint. to combine functionality with flexibility
hyper-efficient, exoskeleton concrete building and purge the accumulated and aim to reflect the building’s urban
shell that features dozens of circular heat from the building’s fabric. location. Office space, restaurants and
cut-outs, which the project team As well as passive sustainability, retailers on the ground floor will add to
believes is a major design and engi- COR will actively aim to reduce its the structure’s urbanist character and
neering breakthrough. This multipur- carbon footprint further through the allow the building to fully engage with
pose shell will provide both the build- energy produced from the wind tur- its location.
ing structure and thermal mass for bines located in armatures in the top The design approach of COR offers
insulation, as well as solar shading and storeys of the structure and with the a prototype for high-rise construction
armatures for wind turbines. Here, installation of photovoltaic panels. that could produce more energy effi-
energy efficient elements will play an The project is a collaboration cient cities. This is a project designed to
integral part of the structural design. between Oppenheim Architecture & set an example of how energy efficiency
The provision of built-in wind turbines Design, structural engineer Ysrael can be fully integrated within a build-
together with photovoltaic panels and Seinuk and energy consultant Buro ing’s structure and operation.

Spring 2007 | CQ | 13
Fabric energy storage

Utilisation of thermal mass


in non-residential buildings
Air conditioning can be
a major contributor to
the CO2 emissions of a
building, but utilisation
of a building’s thermal
mass can significantly
reduce or even remove
the need for air condi-
tioning and therefore
its CO2 emissions. New
technical design guid-
ance from The Concrete
Centre explains how
By Tom De Saulles

As summers get hotter due to climate


change, the use of air conditioning is
increasing. In the UK the uptake of air
conditioning is rising by 8% per year.
This could result in an extra six million
tonnes of CO2 per year by 2020. To
counter this, the 2006 edition of Part
L2A of the Building Regulations sets
tough targets for CO2 emissions,
making the installation of full air- Above Exposed
conditioning system harder to justify concrete soffits
help to regulate
especially in the face of rising energy
the internal
costs. Furthermore, Building Regula-
temperature
tions now include clear overheating at Brighton’s
limits for non air-conditioned build- Jubilee Library.
ings to future-proof against the impact Left Precast
of climate change. Against this elements provide
background, passive cooling tech-
PHOTOS: TERMODECK AND FOGGO ASSOCIATES

fabric thermal
niques are being increasingly applied storage. The
in non-residential buildings. multi-service
At the heart of low-energy design is blades include
the thermal mass provided by the lighting and
building fabric and the way in which it chilled beams.
interacts with the internal and external
environment. Here, the unrivalled,
inherent thermal mass of concrete
plays an important role in ensuring

14 | CQ | Spring 2007
comfortable internal conditions.
The use of exposed concrete to provide Stabilising effect of thermal mass on internal temperature
passive cooling can achieve significant
savings in terms of capital and operat-
ing costs through avoiding or minimis-
Peak Up to 6-8°C
ing the need for air conditioning.
temperature difference between
The basic approach is to expose the delayed by up peak external and
soffit of the floor slabs, which can then to six hours internal temperatures
absorb heat gains during warm weather
30°C
and stabilise the internal temperature.
Typically, night air is then used to
ventilate and cool the building in
readiness for the following day. This
cycle of heating and cooling using the
thermal mass of a building is often
referred to as fabric energy storage.
For a typical office, FES can help
delay the onset of peak internal temper-
ature by some six hours, usually after
the occupants have left the building.
At this point the FES cycle is reversed.
As evening progresses, the external
temperature drops making night venti-
lation an effective means of removing
the accumulated heat from the building 15°C
fabric in preparation for the next day.
The UK variation in diurnal tempera- DAY NIGHT DAY
ture rarely drops below 5°C making
night cooling relatively effective. ■ Internal temperatures with high thermal mass
As an alternative or addition to night
ventilation, water cooling may be used. ■ Internal temperatures with low thermal mass
This can offer improved flexibility ■ External temperatures
and control of slab cooling.
There are a number of generic
FES systems. These include: heat transfer is provided by the address issues of security and occupant
exposed slab soffit. The system is control of windows.
■ Natural ventilation typically referred to by the trade name A high thermal mass building will
with exposed soffits Termodeck. provide a high quality, well-ventilated
Flat or profiled floor slabs used in space in which occupants are empow-
conjunction with natural ventilation. ■ Water-cooled slabs ered to take control of their environ-
This may be wind-driven, or a combi- Precast or cast in-situ slabs with water ment. The building operator will
nation of wind and stack ventilation. cooling via embodied polybutylene benefit from lower operating costs and
pipework, which can be used in con- everyone will benefit from reduced
■ Underfloor ventilation junction with a night ventilation strat- CO2 emissions. There is already a
with exposed soffits egy. The precast option is trademarked significant number of FES designed
The void created by a raise floor is used as Thermocast. bespoke buildings and increasing
as a plenum for mechanical ventilation evidence that FES is being used for
maximising exposure of the thermal ■ Chilled beams with exposed speculative office developments. This is
mass by allowing heat transfer with top or partially exposed soffits being driven not only by awareness of
of the slab in addition to the soffit on Concrete soffits (flat or coffered) with the need for greater sustainability, but
the underside. Air enters the occupied chilled beams suspended directly also by developers and building
space through floor diffusers. This sys- below. A permeable ceiling may be occupants recognising the long-term
tem is often used in conjunction with used, or the soffit left exposed. cost benefits of high thermal mass
an exposed, profiled slab and with FES is provided in the usual way, buildings. This may well result in FES
openable windows to provide a mixed- using natural and/or mechanical becoming the norm for 21st century
mode solution. ventilation, with additional cooling commercial design and construction.
from the chilled beams. Authored by Tom De Saulles,
■ Exposed hollowcore slabs For many developments, FES design Utilisation of Thermal Mass in
with mechanical ventilation will be combined with mixed-mode Non-residential buildings: Guidance on
Precast hollowcore concrete slabs with ventilation, and/or air conditioning. System Design, Floor Finish & Integration
mechanical ventilation via the cores, This is due to the need for enhanced of Services is available from
providing good convective heat transfer cooling performance for demanding www.concretebookshop.com
between the air and concrete. Further office environments and in order to or Tel: 0 700 4 607 777.

Spring 2007 | CQ | 15
The Concrete Centre Events
For further details and registration visit: www.concretecentre.com/events
Tel: 0700 4 500 500 or 0700 4 CONCRETE

Introduction to Concrete Solutions for


Eurocode 2: Design Sustainable Housing
of Concrete Structures May 15, London
March 20, Manchester June 19, Birmingham
In partnership with IStructE Heavyweight forms of
European codes and construction continue
standards will soon replace to evolve. The course
the current British will discuss passive
Standards. Designers will design strategies
have to become familiar and architecture in an
with a new set of docu- ecoculture, including both
ments and terminology, low- and multi-storey
and understand the solutions, and will also
interaction between them. give an update on Part L.
This seminar introduces
Eurocode 2 and aims to Concrete Surfaces
assist construction June 14, London
practitioners in making the Achieving quality in visual
transition to the new code. concrete is key. The
course covers the
Concrete Design for essentials of the concrete
a Sustainable Future mix to ensure consistent
May 3, London colour, selection of form
June 21, Scotland face materials, good
The presentation will formwork practice, site
examine how concrete is workmanship in handling
one of the most effective and compaction of
sustainable building concrete, plus guidance
materials when both on achieving fine concrete
energy consumed during finishes with a minimum
the manufacture and the of blemishes or surface
building’s use are taken discolourations.
into account. Concrete
construction offers the Design Tools
solution to combat the and Techniques
effects of climate change June 26, London

PHOTO: FEILDEN CLEGG BRADLEY. CONCRETE QUARTERLY IS ISSUED AS A SUPPLEMENT TO BUILDING DESIGN
by lowering energy This course will provide
consumption and by recently graduated
minimising the need engineers with the
for air conditioning. practical tools and
techniques with which
Design & Construction to design reinforced
of Concrete Flat Slabs Concrete The lecture will examine Case studies will include concrete structures,
April 26, London sustainable concrete the National Trust’s Heelis ranging from quick design
Flat slabs are highly Elegance — architecture and how it headquarters in Swindon, methods for initial sizing
versatile elements that Developments can both reduce Feilden Clegg Bradley’s of members to best
provide minimum depth, embodied CO2 and lower Persistence Works arts practice advice for using
fast construction and in Sustainable CO2 emissions during a complex in Sheffield finite element analysis.
flexible column grids. Concrete building’s working life. It (pictured above), the use Delegates will have the
Case studies, the latest will also look at carbon- of hemcrete in brewer opportunity to use
design and construction Architecture neutral concrete and the Adnams’ Suffolk concrete design software
information, and tips April 25, London design of single-skin, self- warehouse, and Peter for both element design
for using finite element In partnership with the finished external concrete Zumthor’s work at Chur and the conceptual
analysis will be presented. Building Centre Trust walls without insulation. in Switzerland. design of frames.

Contact details: The Concrete Centre, Riverside House, 4 Meadows Business Park, Station Approach, Camberley, Surrey GU17 9AB
Tel: 0700 4 822 822 web: www.concretecentre.com

You might also like