BILL OF QUINTITY & PRICE

JOB TITLE : Install Pintu Sliding Aluminium & Partisi QC RTC


LOCATION : Ref LT 2

MATERIAL LABOUR GRAND


N0 ITEM PEKERJAAN VOLUME
U/Pr Total U/Pr Total TOTAL
SCOP PEKERJAAN
A INSTALL PINTU SLIDING ALUMINIUM
1 Preparation 1.00 ls - - 500,000 500,000 500,000
2 Bongkar Pintu Sliding Multiplex Existing 6.00 unit - - 750,000 4,500,000 4,500,000
( 1000 x 3250 )
3 Buang Bongkaran 1.00 ls - - 1,500,000 1,500,000 1,500,000
4 Install Pintu Sliding ALUMINIUM 4B 6.00 unit 8,500,000 51,000,000 1,000,000 6,000,000 57,000,000
( 1000 x 3250 )
Include :
- Frame
- Spandril
- Kaca
- Pegangan Pintu & Lock
- Doule Rail
A INSTALL PARTISI AREA QC
1 Schafolding Frame 2.00 set - - 750,000 1,500,000 1,500,000
Include :
- Jackbase
- Bracing & Staik
- Asahan / Catwalk
2 Frame Aluminium 4B 102.00 m' 250,000 25,500,000 135,000 13,770,000 39,270,000
Include :
- Sealen
- Scrup
3 Install Spandril Aluminium 81.00 m2 400,000 32,400,000 50,000 4,050,000 36,450,000
4 Install Pintu Aluminium (1500x2100) 1.00 unit 5,500,000 5,500,000 800,000 800,000 6,300,000
Include :
- Frame Aluminium 4B
- Kaca
- Pegangan Pintu & Lock
- Rail
- Sealen
5 Cleaning Area 1.00 Ls - - 500,000 500,000 500,000
GRAND T O T A L : 114,400,000 33,120,000 147,520,000
DIBULATKAN : 147,500,000