COMMENTS REGARDING ON THE MODEL TC 25 3 PHASE 4 WIRE 3*220/380V 5(100) A

ITECHENE

1. NO Phase Voltage is displayed. (V1,V2,V3)


2. NO Phase Current is displayed. (I1,I2,I3)
3. NO Phase Power Factor is displayed. (PF 1,2,3)
4. NO Frequency is displayed.
5. NO Alarm indication on the screen when phase voltage is Reversed.
6. The meter must Record the Events like overcurrent, overload, overvoltage and Under
voltage Also must supports 12 months historical records.
7. By default (Battery mode) the meter must display time,date,property
number,kwh,kvarh,maximum demand, MD time, voltage and current.
8. On the meter name plate must include Guarantee period and EEU logo.
9.