Professional Documents
Culture Documents
The Private
The Private
The Private
www.emeraldinsight.com/1463-578X.htm
Abstract
Purpose – The paper aims to define and measure value for money (VFM) within the concept of
private finance initiative (PFI), and investigate the principal factors in which opinions are formed.
Design/methodology/approach – Literature review of texts, published papers, and reports are
used to identify relevant parameters to the research. The sources support the arguments of opinion
within the paper.
Findings – PFI is still perceived by the government as the most cost effect means of procuring public
infrastructure. The positive aspects of PFI are the competition generated by the concept, and improved
risk management. Negative aspects include the lack of agreed formulae by all stakeholders by which
to benchmark VFM, and an increasing sceptical electorate to the PFI concept of providing short and
long term VFM.
Research limitations/implications – By virtue of PFI being a dynamic, changing, and complex
means of procurement, this research will be valid in its own right. However more up to date
government policies must be consulted to take the determination of VFM in any further research.
Practical implications – The research and conclusions will provide add to the current debate as to
the viability of PFI, with VFM the main key point as to the ongoing success of the governments
strategy this method of procurement.
Originality/value – The paper adds, to the “VFM” drivers that have been identified by identifying
principle factors in creating VFM. This will be a sound basis for the justification of VFM in PFI.
Keywords Partnership, Private finance, Public finance
Paper type Research paper
1. Introduction
Under the private finance initiative (PFI) the performance of projects in terms of
completion of work within time and budget is a considerable improvement when
compared to projects procured in a traditional manner (Comptroller and Auditor
General, 2003) (Table I).
Construction companies involved in PFI expect to make anything from three to ten
times as much profit when compared to the profit made on traditional contracts. This
increase in profits is made because the construction companies are assuming the risks
previously retained by the client and not by “profiteering” (Walker, 2004). The Journal of Property Investment &
fluctuation in margin is attributed to the amount of equity held in the consortium Finance
Vol. 24 No. 4, 2006
completing the PFI by the construction company. pp. 363-373
The public sector comparator (PSC) is deemed by some commentators to be flawed. q Emerald Group Publishing Limited
1463-578X
One area of question is that the PSC may inflate the cost of risks transferred to the DOI 10.1108/14635780610674534
JPIF private sector. Risks which are transferred to the private sector have to be identified,
24,4 quantified and costed it is these that can easily be inflated to make the PFI option
appear to provide “value for money” (Centre for Public Services, 2001). Other reasons
cited by the CPS include under-estimating PFI monitoring costs and/or showing higher
costs under the PSC model.
A survey of 200 members of the Association of Chartered Certified Accountants
364 found that only 1 percent strongly agreed that PFI provided value for money (Staff and
Agencies, 2002).
The HM Treasury’s document on PFI (HM Treasury, 2003) states the following:
The government aim in procurement decision-making is to secure the maximum
improvement in public services from investment through maintaining an unbiased stance
on which procurement route will offer value for money in each case.
This quote quantifies the Government stance on the value for money (VFM) issue
within PFI However with this alliance of public and private sector interests there is a
conflict from the onset of any negotiations of a PFI project.
All stakeholders agree that the fundamental requirement of PFI is that it must offer
value for money on a project-by-project basis. The real difficulty appears to come when
stakeholders assess value for money relative to their own positions and interests in the
PFI process.
PFI is one of several procurement routes that fall under the general heading of
public private partnerships (PPP), the rational of PPP is described as, “the combination
of the resources of the public and private sectors, in the quest for more efficient service
provision” (Akintoye et al., 2003). At present PFI is the most frequently used form of
PPP. Government publications (Public Private Partnerships, 2000) subdivide the PPP
label into three different types of “partnership”:
(1) The introduction of private sector ownership into state owned businesses
(strategic partnering).
(2) The PFI and other arrangements (design and build, prime contracting) where
the public sector contracts to purchase quality services on a long term basis so
as to take advantage of private sector management skills with the incentive of
having private finance at risk.
(3) Selling government services into wider markets and other partnership
arrangements where private sector expertise and finance are used to exploit the
commercial potential of government assets.
The above perhaps explains why the acronym PPP can be used, and is used widely,
when authors refer specifically to PFIs. As this paper deals specifically with the private
finance initiative and not another procurement route within the PPP stable the
acronym PFI will be used in this paper.
Thus the selection of PFI as the procurement process of choice must be made on the
basis of PFI offering best VFM when compared against other procurement routes –
both traditional and other routes from within the PPP set.
A PFI is usually commissioned by an awarding authority, and executed by a
consortium. The awarding authority is the public sector client responsible for
procuring the project. An awarding authority may be a central government
department, local authority, or government agency. The objective of the awarding
authority is to achieve value from public money by transferring to the private sector
the risk associated with providing infrastructure and services (Fox and Tott, 1999).
The consortium will have been assembled for a particular PFI project and will often be
a joint venture by several different types of organisations, e.g. contractors, facility
management companies and financiers (debt and equity). The joint ventures are often
referred to as special purpose vehicles (SPV). The SPV has two principle benefits in the
area of risk management. First, it allows the project specific risks to be allocated to the
JPIF most appropriate consortium member, and second, it allows a company to finance a
24,4 project without putting the entire company at risk.
Prior to starting “work on site” the PFI will have gone through the clearly defined 14
stage process that has been developed, and continues to be developed, in order to
confirm that the PFI procurement route, for a specific project, represents VFM. At
present the primary test of VFM is the comparison of the proposed PFI against a public
368 sector comparator.
It is important that this process should be critically reviewed at all stages by all
stakeholders to ensure true VFM.
4.6 Innovation
The ability of the SPV to innovate is directly related to the quality of the output
specification and the element of competition during the initial stages. This has been
exemplified in successive rounds of PPP (PFI) prison procurement that showed that a
combination of innovation and competition led to reductions in costs at each stage (HM
Treasury, 2003)
JPIF 4.7 Borrowing costs – financing of the project
24,4 The fact that the government can borrow more cheaply than the private sector is an
accepted fact. It is assumed by many that the differential in the cost of capital between
the public and private sectors means that the consortiums higher cost of capital will
have a negative impact on the VFM case, but, it is argued determining VFM is not
simply about comparing interest rates. This is not correct when the cost of the project
370 is the same regardless of the procurement route (Grout, 1997). Thus if the cost of capital
is to be considered it should be on the difference between the cost of purchasing the
asset traditionally and through PFI. Therefore the cost of capital has a lesser role to
play in the VFM argument than many may first appreciate. Additionally, there is
always the assumption made that the government would be able to raise the capital if
the project were not to proceed as a PFI.
Conclusion
The PFI is a complicated and protracted method of procuring government projects, 371
largely, but not exclusively, roads, schools, hospitals and prisons. In the 12 years that
PFIs have been in existence many opinions have been voiced on whether or not the PFI
procurement route is one that can provide VFM. Maltby (2003) suggests the Treasury
should be applauded, with dogma thriving in the PFI debate, but still questioning the
effectiveness of PFI. Importantly, though, there does not appear to be anyone willing of
able to confirm from an objective stance, that PFI offers VFM. Until a legal definitive
definition of VFM in the context of PFI, this situation is likely to continue for some
time.
The high profile of the criticism of PFI projects in the media and, research in
published journals, have encouraged trends to develop slowly, and more precise and
objective information is appearing in the public domain. The government is keen to put
the positive case for PFI over to the electorate, and is aware of the implications of the
Freedom of Information Act 2002.
To move the debate of VFM forward, and to promote all stakeholders to reach an
agreement on VFM, a balanced argument must be set out.
Positive messages include:
. PFIs are seen as attractive by large contractors thus the benefits of competition
in terms of VFM remain.
.
Between 1997 and 2001 the cost of finance (adjusted for the change in interest
rates) has reduced and the affordability of the PPPs to the public sector clients
(Middleton, 2001) has improved. This change is attributed to a greater
understanding of PPP, improved risk management and competition to provide
finance (usually in the form of debt). It is acknowledged that the author refers to
PPP rather than PFI but as the subject matter being discussed is “finance” it is
considered reasonable to assume the author is talking about PFI.
References
Akintoye, A., Hardcastle, C., Beck, M., Chinyio, E. and Asenova, D. (2003), “Achieving best value
in private finance initiative project procurement”, Construction Management and
Economics, Vol. 21 No. 5, pp. 461-70.
Allen, G. (2003), “The private finance initiative (PFI), economic policy and statistics section”,
research paper 03/79, House of Commons Library, London.
Arthur Andersen and Enterprise LSE (2000), Value for Money Drivers in the Private Finance
Initiative, The Treasury Taskforce, London.
Bresnen, M. and Marshall, N. (2000), “Motivation, commitment and the use of incentives in
partnerships and alliances”, Construction Management and Economics, Vol. 18 No. 5,
pp. 587-98.
Brigham, E.F. (1985), Financial Management Theory and Practice, 4th ed., The Dryden Press,
New York, NY.
Broadbent, J., Gill, J. and Laughlin, R. (2003), “Evaluating the private finance initiative in the
National Health Service in the UK”, Accounting, Auditing & Accountability Journal, Vol. 16
No. 3, pp. 422-45.
Centre for Public Services (2001), Private Finance Initiative and Public Private Partnerships:
What Future for Public Services, Centre for Public Services, Sheffield.
Comptroller and Auditor General (2003), PFI: Construction Performance, NAO, London.
Dixon, T., Pottinger, G. and Jordan, A. (2005), “Lessons from the private finance initiative in the
UK”, Journal of Property Investment & Finance, Vol. 23 No. 5, pp. 421-3.
Foundation for Built Environment (2004), Lessons from UK PFI and Real Estate Partnerships: Practice briefing
Drivers, Barriers and Critical Success Factors, Foundation for Built Environment, Reading.
Fox, J. and Tott, N. (1999), PFI Handbook, Jordan Publishing, Bristol.
Gosling, T. (2004), Openness Survey Paper, Institute for Public Policy Research, London.
Grout, P.A. (1997), “The economics of the private finance initiative”, Oxford Review of Economic
Policy, Vol. 13 No. 4, pp. 53-66.
HM Treasury (1999), Treasury Taskforce “Step by Step Guide to the PFI Procurement Process”, 373
HMSO, Norwich.
HM Treasury (2003), PFI: Meeting the Investment Challenge, Norwich, HMSO.
Heald, D. (2003), “Value for money tests and accounting treatment in PFI schemes”, Accounting,
Auditing & Accountability Journal, Vol. 16 No. 3, pp. 342-71.
Kee, J.E. and Forrer, J. (2002), “Private finance initiative: the theory behind the practice”, paper
presented at the 14th Annual Conference of the Association for Budgeting and Financial
Management, Kansas City, MO, October.
Lenihan, M. (2002), Private Finance Initiative/Public Private Partnerships: A Contractor’s
Perspective, Society of Construction Law, London.
McDowall, E. (2001), “Does PFI offer best value?”, Facilities Management, September, pp. 8-9.
Maltby, P. (2003), “PPPs in perspective, has the PFI grown up?”, Public Finance Magazine,
August 8.
Mathiason, N. (2004), “Unions force u-turn on PFI”, The Guardian, 11 July.
Merna, A. and Smith, N.J. (1999), “Privately financed infrastructure in the 21st century”,
Proceedings of the Institution of Civil Engineers, November 1999, pp. 166-73.
Middleton, N. (2001), Public Private Partnerships: Arguments Turn to Action,
Pricewaterhousecoopers, London.
Public Private Partnerships (2000), Public Private Partnerships: The Government’s Approach,
The Stationery Office, London.
Spoehr, J., Whitfield, D., Sheil, C., Quiggin, J. and Davidson, K. (2002), Partnership’s Privatisation
and Public Interest, Public Service Association of South Australia, Adelaide.
Staff and Agencies (2002), “PFI”more expensive” than public funding”, The Guardian,
11 October.
Treasury Taskforce Private Finance (1997), Technical Note No. 5: How to construct a Public
Sector Comparator, Office of Government Commerce, London.
Walker, D. (2004), “Contract sport”, The Guardian, 8 September.
Winch, G.M. (2000), “Institutional reform in British construction: partnering and private finance”,
Building Research and Information, Vol. 28 No. 2, pp. 141-55.
Corresponding author
Michael Pitt can be contacted at: m.r.pih@ljmu.ac.uk