Professional Documents
Culture Documents
Article-Risk Response (250-235) 222
Article-Risk Response (250-235) 222
by Lisa Young
There are four different types of risk Examples: Avoidance: With this strategy, there
responses. For every risk you will could be a couple of approaches. One
want to decide which type of risk Again, using our original example of is to recognize early on that if this risk
response to utilize. The four types of the risk of delay in receiving the is very likely to occur, then an
risk response are: cutting edge Sun SPOT technology alternative approach to the underlying
necessary for the project to deliver its architecture/technology design needs
· Mitigation – Mitigation is reducing solution, here is how the various risk to be developed—one that avoids the
the probability of occurrence or impact responses would play out. use of this specific technology. An
of a risk, before it happens, to below alternative avoidance approach is to
an acceptable threshold. Mitigation Acceptance: Assume there is only one shield your project from the impact of
may also include contingency, in the vendor, Sun Microsystems, to provide a delay by specifically negotiating
event the risk still happens. this technology. We have a long early on in the project that the delivery
Mitigation requires action, resulting in standing relationship with this vendor of the total solution, in terms of time
some level of planned response prior and they have always delivered to us frame, will be promised once we have
to the risk manifesting and/or on time. In this scenario, we could do an actual delivery date of the
contingent after the risk manifests. nothing, relying solely on our strong technology.
relationship with the vendor. This is
· Acceptance – Acceptance is not the best strategy, but a possible Transference: To transfer this risk, we
deciding not to change the project one. could outsource the responsibility for:
management plan to deal with a risk. · ordering the Sun SPOT technology
This may be due to having no other Mitigation: With this type of response, · managing the relationship with Sun
appropriate response strategy. we could have a planned course of · receiving/installing the new
Acceptance is a passive response. action as well as a contingency technology
Acceptance entails no action on your response. Our planned course of · integrating and deploying the total
part, but also does nothing to change action, which would occur before any solution
the risk exposure. delay manifested itself, is to keep in
regular contact with Sun to assess And then what? - Ongoing
· Avoidance – Avoidance is their progress—ensuring our need is Monitoring and Control:
eliminating the risk, or protecting the always kept current in their mind, as
project objectives from its impact (i.e. well as guaranteeing the earliest Once you have successfully defined
If the risk were to occur, it would not possible detection of a potential your risk response, you monitor the
impact the project). Avoidance delay. Our contingent course of environment and invoke the response
requires more action, but provides the action, should we still end up with a plans as necessary to control the risk
biggest benefits in reduction of risk delay, could be to invoke a plan B, and/or impact. Risk Management is an
exposure—your risk is eliminated or which segments out the delivery of the ongoing effort throughout the life of
you have completely shielded your solution. In this case, rather than your project. New risks may materialize
project from any impact. delivering the total solution all at and existing risks which have been
once, we would instead deliver realized and responded to, or whose
· Transference – Transference is solution components not dependent probability has been eliminated, may be
shifting the threat of impact and on that technology earlier, and closed out.
ownership of response to a third party, schedule the other dependent
through a contractual agreement solution components later in the So now that you have your risks under
between the two parties. Liability for delivery cycle. control, you can get back to delivering
the costs of a risk is transferred to the what you promised!
other party. In other words, your risk
is eliminated and the risk now rests
with the third party.
1-800-600-7785 • www.itx.net
A Model for Risk Response on Projects cont’d Page 3