Professional Documents
Culture Documents
Module 2b Equipment Schedule
Module 2b Equipment Schedule
CE168P-2 .
Prepared By:
2
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
BENEFITS:
3
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
SAMPLE PROBLEM:
The construction of an office building with two separate units is to be undertaken
concurrently and the project is considered finished after completion of the two units.
Unit A Unit B
Construction Phase(s)
(Weeks) (Weeks)
Excavation works for Foundation 4 8
Concreting works for Foundation 5 3
Concreting works for
6 10
Superstructure
Prefab panels erection 4 4
Finishing works 5 7
4
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
Proposed Solution:
•First, draw the network diagram based on the technical requirements ONLY
•Second, identify the critical path
•Third, propose an alternative considering the constraints listed above.
5
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
During the planning of the equipment schedule, the longer week is the basis
of the project duration (same as discussed with the previous topics)
Therefore, the project duration is 32 weeks.
6
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
ALTERNATIVES:
• Excavate A ahead of B, positioning panels A ahead of B (figure 1)
• Excavate A ahead of B, positioning panels B ahead of A (figure 2)
• Excavate B ahead of A, positioning panels A ahead of B (figure 3)
• Excavate B ahead of A, positioning panels B ahead of A (figure 4)
*Figures on next slides
7
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
ALTERNATIVE A (FIGURE 1)
The project duration is 36 weeks, which is 4 weeks longer than 32 weeks computed
when there is no constraint
8
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
ALTERNATIVE B (FIGURE 2)
The project duration is 38 weeks, which is 6 weeks longer than 32 weeks computed
when there is no constraint
9
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
ALTERNATIVE C (FIGURE 3)
The project duration is 38 weeks, which is 6 weeks longer than 32 weeks computed
when there is no constraint
10
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
ALTERNATIVE D (FIGURE 4)
The project duration is 34 weeks, the shortest duration of all the alternatives.
Therefore, among the choices, Alternative D is the most recommended in the
execution of the work given the constraints in the project/site condition.
11
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
In the above results and diagram from previous slides, it can be seen that an arbitrary selection of a possible
sequence gives us NO ASSURANCE of a GOOD SCHEDULE.
On the contrary, a complete enumeration of all the possible schedules for MORE COMPLEX PROJECTS is time-
consuming and therefore NOT ADVISABLE.
12
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
17
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
4M’s in Construction
Manpower: This refers to the human workforce, including skilled workers, technicians,
engineers, supervisors, and project managers involved in the construction process.
Machinery: This includes the various types of construction equipment and machinery
used on the site, such as excavators, cranes, bulldozers, loaders, and specialized
tools.
Materials: This encompasses all the physical materials required for construction,
including raw materials like cement, steel, bricks, wood, aggregates, pipes,
electrical components, and finishing materials.
Money: This refers to the financial resources required to fund the construction
project, including the costs of labor, materials, machinery, permits, overhead
expenses, and any other financial considerations.
18
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
19
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
20
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
21
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
22
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
23
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
24
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
25
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
26
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
27
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
28
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
29
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
“The only reason that a company fails is because they run out of money”
Sometimes companies fail because they have a product
problem or poor business, but other times it's simply because
of poor cash flow management.
Cash flow in construction is slightly different from cash flow in
many industries. Construction cash flow typically refers to the
analysis of when costs will be incurred and how much those
costs will be over the course of a project.
For companies running construction projects, understanding
cash flow is critical to ensuring the right level of funding is in
place to deliver the whole project or phase of work.
30
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
31
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
32
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
33
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
34
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
35
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
36
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
What is S-CURVE?
37
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
PROJECT RESOURCES
CASH FLOW FORECASTING
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
39
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
TODAY’S SCENARIO
Need for accurate and consistent status information
Numerous complex (and interrelated) projects
Projects with many WBS activities
Virtual offices
Diverse technology platforms
40
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
41
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
42
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
43
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
44
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
100000
80000
56000 BCWS
60000 BCWP
55000
49000 ACWP
40000
20000
Nov-03
Jul-03
Jan-03
Jun-03
Oct-03
Mar-03
Apr-03
Aug-03
Sep-03
Dec-03
Feb-03
May-03
45
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
46
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
20000
Cost Variance = BCWP – ACWP
0
PhP 49,000
Nov-03
Jul-03
Jan-03
Jun-03
Oct-03
Mar-03
Apr-03
Aug-03
Sep-03
Dec-03
Feb-03
May-03
- 56,000
CV = - PhP 7,000
47
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
48
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
Nov-03
Jul-03
Jan-03
Jun-03
Oct-03
Mar-03
Apr-03
Aug-03
Sep-03
Dec-03
Feb-03
May-03
49
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
20000
Nov-03
Jul-03
Jan-03
Jun-03
Oct-03
Mar-03
Apr-03
Dec-03
Feb-03
May-03
Aug-03
Sep-03
50
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
51
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
Nov-03
Jul-03
Jan-03
Jun-03
Oct-03
Mar-03
Apr-03
Aug-03
Sep-03
Dec-03
Feb-03
May-03
52
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
Nov-03
Jul-03
Jan-03
Jun-03
Oct-03
Mar-03
Apr-03
Dec-03
Feb-03
May-03
Aug-03
Sep-03
situation, the primary focus should be
on completing the remaining work
within the budgeted values.
53
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
20000
Nov-03
Jul-03
Jan-03
Jun-03
Oct-03
Mar-03
Apr-03
Aug-03
Sep-03
Dec-03
Feb-03
May-03
54
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
Nov-03
Jul-03
Jan-03
Jun-03
Oct-03
Mar-03
Apr-03
Dec-03
Feb-03
May-03
Aug-03
Sep-03
Cost Performance Index (CPI) or
Schedule Performance Index (SPI).
55
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
BAC – BCWP 0
ETC =
Nov-03
Jul-03
Jan-03
Jun-03
SPI
Mar-03
Apr-03
Oct-03
Feb-03
May-03
Aug-03
Sep-03
Dec-03
102,000 – 49,000
=
0.891
= 59,489.80
56
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
Nov-03
Jul-03
Jan-03
Jun-03
Mar-03
Apr-03
Oct-03
Feb-03
May-03
Aug-03
Sep-03
Dec-03
It is the most accurate of the three
(3), but it is also the most tedious.
57
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
= 116,571.43 0
Nov-03
Jul-03
Jan-03
Jun-03
Oct-03
Mar-03
Apr-03
Aug-03
Sep-03
Dec-03
Feb-03
May-03
58
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
100000
20000
Nov-03
Jan-03
Jun-03
Jul-03
Mar-03
Apr-03
Oct-03
Feb-03
May-03
Aug-03
Sep-03
Dec-03
[1] = 56,000 + 53,000
= 109,000 140000
120000 116,571
03
03
04
3
4
3
03
3
-0
-0
l-0
-0
v-
n-
n-
p-
ar
ar
ay
Ju
No
Ja
Ja
Se
M
M
M
59
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
60
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
61
SCHOOL OF CIVIL, ENVIRONMENTAL, GEOLOGICAL ENGINEERING
62