Professional Documents
Culture Documents
Useful Document
Useful Document
method?
ial
client or a contract r assumes he cen responsibility. There are in
addition many varia its, h rid and compnc hese methods. Moreover there
have been many r cent developm s, w Ithough possibly termed a
procurement mig more cu ra described as an approach to
procuremen For e Cam e mo part ring arrangements are an over-arching
agreement hich comDa one or er co tracts let under one of the three key
methods. imilarl is it is freq ently possible to identify contracts let
on a desig sand b ,nageme It is therefore useful to start by clearly
(DD
differe e three prj cipal i ods, before moving on to discuss some more
rece
r+.
od is Fikely to rove the most appropriate in a given situation
natu and sc pe of the work proposed, how the risks are to
+-V
po rta n
led til the procurement method and the type of contract have
been established' twill can considering the following:
It is important to establish:
31
3 Which procurement method?
suppliers;
what contractual provisions will apply to the desi
Coordination responsibility
This might include responsibility for workm nship, g
3-l
It is important to establish:
sum is
i^.
Plan of Work
The procurement thod fbe ad typeof contract will have implications
,-r
vim,
d a d
fl)
but the desi uction work stages are separated as is usual with
i,Q,nal procure is in a linear pattern (see Figure 3.1).
Itho gh similar work stages are still present, they are not so
r will normally be involved at design stage, to an extent
he contrac
muc he is responsible for scheme design as opposed to
t.0
Q-0
developing a design already produced by the client's consultants and embodied in the
client's requirements. Some of the work stages are arranged in a different sequence,
,O+
permitting parallel working or fast tracking to save time overall. The contractor will
((DD
normally continue detailed design during construction stages (see Figure 3.2).
Plan of Work is still relevant to management procurement, whether management
32
Which procurement method? 3
--0
design, cost control, and con ct atminis` +-- ion, d t the contractor is
responsible for carrying out Th onsibili atter extends to all
u..
the contractor may ake full res onsibiNY- for t ance, or the contractor's
responsibility may be limite me way, in hich e a collateral warranty between
client and sub-contr ctor ill be esse con ractor is usually chosen after
competitive to nd o uments ete information. However, the
contractor ca be a e d ea r, eit ugh negotiation or on the basis of
partial or n 4ional i
n
-t,
There is certaty-ecost, to the extent that a lump sum is known before work begins,
even if it has to be adjusted during the construction period as provided for in the
contract.
The contractor depends heavily upon the necessary information and instructions from
(-r
Q-3
the architect being issued on time. There is a risk of claims if they are delayed.
E
33
3 Which procurement method?
1 AB
3 F
4 5 H
6 J
7 K
L
Consultan s
Contractor
Key
1 Appraisal and strategic briefing work by consultants
2 Outline and detailed proposals by consultants
3 Final proposals and production information by consultants
34
Which procurement method? 3
1 AB 2 C
D 5 H T__ E
6 F 6 F
7 J
8 K
L
Consultants
Contractor
Key
1 Appraisal an tegic iefing work by consultants
2 Outline proposals/client's requirements
3 Detailed proposals by contractor
4 Tender action including contractor's proposals
5 Final proposals by contractor and specialists
6 Production information
7 Mobilisation by contractor
8 Construction to completion and after completion
35
3 Which procurement method?
-0O
The contractor may be appointed either by comp eti veent t
+-I
ten er or the
T-0
negotiated agreement. Where a design and build agr, errs
,.+
ne ate c
e, he agree ent is om
referred to as 'Competitive Design and Buil . It tend o f e sligh ger, b I
r;,
Frequently, in deign-build procurement e cn he req cont ctor to
appoint some or all of its consultants at e time the a uild
i
tra is entered
fl,
een cli
E+-
into
contractor. In addition to the c t-arch d ctor-a' itect terms of
appointment published by the RIBA, th IC pu ita b or novation and
collateral warranties.
Watchpoints
Inthe most straightforward de 'gn and burnt
theory there is usually
a single point of respo si ility. he cli t there re ha thevantage of only one firm
15.
client's requireme s are ten de led to extent that the contractor's design
contribution, an theref re lick lit, is diminished.
The client lacks c trol or detai ects T design; however, this might be
acceptable road lin eme are satisfactory and the detail
relatively le,
Often the client requires that the contractor appoints the client's consultants to develop
the design under a consultant switch agreement or by novation. If this is not the case,
+.V
it is always advisable to ask for information about who the contractor intends using as
E
36
Which procurement method? 3
-.0
and it is important that adequate time is all hese a-be oerly
The requirements might include specific ?fovisio
generally it is prudent to prescribe pe that a/
,--t
reliance is placed on the contractor.
r-r
-6'
.-+
used, and whether ice is likely e pri ider, tion.
Benefits can arise fro desi neN and estim to work closely together. The
contractor's awaren s of arrent mar and delivery times can ensure
that a contract oth Ieconom
, al editiously.
ent or rrepres tative oul be s ected with great care. He or she can
mber the Jai is organisatio a professional consultant, a project
,-+
9-'
x-r
of th
tis e power, d to for e client needs to be clearly established.
,-+
T re are
nage nt ontra is an onstru ion management are the two most common.
it ent ntracts lent usually starts by appointing consultants to
.3+
.-+
ana
=+;
v,'
are ro ject dra tings and a project specification. The management contractor is
seec td by roces f tender and interviews, and paid on the basis of the scheduled
e es e sts an management fee.
Its role is literally nag the execution of the work, and he is not usually directly
.-+
,-+
involved in g
(.0
a design ability. In ' management contracting', works contractors are directly and
contractually nsible to the management contractor. Its coordinated approach
,-r
and potential for flexibility results in greater operational speed and efficiency.
Where the management contractor's obligation is total where, that is, it accepts -
responsibility for both design and construction -
the arrangement is sometimes
(1)
37
3 Which procurement method?
fl,
contracts and coordinated by the Architect in the of a ain ntr tor, t
3rD
comes close to being such a procurement mtho a how er, dem d 4
degree of highly specialised expertise and e
operations which most architects are unlikel to poss
'+'
some ways less accountable for time gist the'd takes the greater risk.
Watchpoints
Management procurement methods a ebest ited t
projects where early compl Lion i able.
'ration's ackages, thus reducing the time needed before the project
arts on sit atdeal of detailed design will need to be left to specialist
b-c
38
Which procurement method? 3
O..
A competitive tendering element is retained
usually account for most of the overall pri
normally be on a lump sum basis.
This method of procurement is most a le, co ex
that only large construction firms 'th the nce re lik
suitable. At present these are relat ely i
management is only likely to b int est'Ao ex rien
-+0
FtRq
e
involved.
Above all,a manag ment cont actor o onstr nager should be appointed
because of his or h r assu e r preferab rove bility to manage. He or she will
need to use and be milia with a vari istic ted techniques to deal with the
coordination at ofte a large ?Nmb rks contracts.
Wor*,,stage's a age
1 A 2 CD
3 5 J
4 EF 6 EFG 6 EFG
7 H
8 K
L
Consultants/Managing Contractor
T
Managing Contractor /Works Contractors
I
39
3 Which procurement method?
Key
1 Appraisal and strategic briefing by consultants and contractor
2 Outline and detailed proposals
3 Appointment of contractor and agreement on trade or works a
4 Final proposals and production information (continuing pr,
5 Mobilisation
6 Production information and coordination of works pac
7 Tender action and adjustments (continuing process)
8 Construction to practical completion and after co
Contractual relationships
The pattern of contractual and func fta tionss shifts or cording to
the procurement method adopte 11
Collateral
-aqreemen
Contract for ant
services
Consult
tractor.
Domestic
sub-contractors
suppliers
Inthe traditional approach, the client is in direct contractual relationship with the
consultants on the one hand and the contractor on the other. Any contractual links
40
Which procurement method? 3
Consultants
sign
) ild
Sub-contractors
suppliers
With de gna d buil , it is likely that in the absence of in-house professional staff,
'm'
the clie will wish o engage outside consultants to advise on the preparation of
r-.
requiremen to evaluate and select tenders etc. Often one or more of these
r+'
consultants will switch from being appointed by the client to being appointed by the
contractor at the time the contractor is engaged. The main contractual link is between
the client and the contractor and if the client's agent or representative has only a
limited role. The contractor might also have a contractual link with his own design
consultants, and with sub-contractors and suppliers. As the contractor is wholly
41
3 Which procurement method?
Ilat I agr en
Client
Contract for
services
ks
contrac s
Manageme
contra t
Works
tract
Consultants
Nominated/
Sub contractors
domestic suppliers
42
Which procurement method? 3
construc ' man er, with all trades contractors in direct relationship with the former.
,-+
43
3 Which procurement method?
obligation to take out the cover required (for exam againjA pel on
damage to property due to fire, storm, water, collap encepyibra` Qn, et
Another category of risk is fundamental risk. This ill inc e amag due war,
fl,
nuclear pollution, supersonic bangs, etc. Such in is re all t e sub' ct of situ
liability, and no insurance cover is normally av able or n ded. T -third cate
(2'
As can be see from Fig lance o pec tive-,rAk will lie almost wholly
with the contractor i the' se T a a buil contract, where a complete
package is supplied onver -ely, te e
al ance st on ous for the client where the
management pro reme pat is o d.
44
Which procurement method? 3
Traditional Ment
Percentage cost ,
Mana nt c
0
45