Article in International Journal of Structural Glass and Advanced Materials Research · January 2018
DOI: 10.3844/sgamrsp.2018.66.72
CITATIONS READS
9 465
4 authors, including:
All content following this page was uploaded by Marco Zucca on 13 January 2020.
Article history Abstract: In this study the Construction Stage Analysis (CSA) of a new
Received: 30-01-2018 mixed structure building is discussed in order to identify the best timing
Revised: 22-02-2018 and execution activities scheduling. The building is part of a new university
Accepted: 5-03-2018 campus that will be realized close to the center of the city. The CSA is
Corresponding Author:
carried out by the implementation of two models: the finite element model
Marco Zucca for the structural analyses and the BIM model for controlling the sequence
Department of Architecture of the construction phases. Once fixed the structural model, in the
Built Environment and preliminary design phase, different sequences are analyzed in order to
Construction Engineering, optimize the construction management in terms of timing and costs.
Politecnico di Milano, Italy Moreover, the optimization of the construction phases is set by considering
Email: marco.zucca@polimi.it the creep and shrinkage of the concrete material.
© 2018 Marco Zucca, Nicola Longarini, Federico de Socio and Iacopo Migliori. This open access article is distributed
under a Creative Commons Attribution (CC-BY) 3.0 license.
Marco Zucca et al. / International Journal of Structural Glass and Advanced Materials Research 2018, Volume 2: 66.72
DOI: 10.3844/sgamrsp.2018.66.72
67
Marco Zucca et al. / International Journal of Structural Glass and Advanced Materials Research 2018, Volume 2: 66.72
DOI: 10.3844/sgamrsp.2018.66.72
68
Marco Zucca et al. / International Journal of Structural Glass and Advanced Materials Research 2018, Volume 2: 66.72
DOI: 10.3844/sgamrsp.2018.66.72
In the FEM software, the functions describing actual having not developed flexural rigidity, acts as a
concrete performances are introduced. The functions ballast, burdens on the underlying vertical elements,
(CEB-FIB, 2010) reproduce how creep, shrinkage and according to their specific areas of influence. It has
the increase of compressive strength influence the been possible to see that at the end of the first stage,
evolution of the structure. Particularly, the last of these props and pillars, are loaded with the same value of
three phenomena makes it possible to appreciate the normal effort
parallel increase in resistance and elastic modulus of the • In the second and third stage, representing the
concrete, during the 28 days of maturation. moments of second and third floor casting, it was
These three functions are useful to obtain results of possible to see how the P1 slab, having developed
stresses and deformations of structural elements in every much of its resistance. It behaves as a distribution
moment during the construction. Consequently, transient element, with its flexural rigidity, that transmits the
structural checks can be carried out. load to the vertical support elements, depending on
Once all the information necessary for the correct their axial rigidity. This causes the columns and
development of the building has been obtained, the BIM walls to load considerably more than the props.
model becomes useful to transfer them directly to the
site, in the exact phase in which they are needed. This Table 1 shown the results of the axial stress on the
operation is performed by combining a BIM card, shown most loaded prop at ground level, for each step of load.
in Fig. 5, to each element in the model, both structural or Transient Study of on Ground Floor Props
not. In these cards are shown all the information
regarding the element, that come from FEM model, Thanks to this transient study it is possible to evaluate
technical data sheets or other sources. the stress condition on the first floor slab after the
construction stage which involves the removal of the
Transient Study of on Ground Floor Props ground floor props, represented in Fig. 8. During this action
Through FEM, it is possible to verify the correct there is a change in the load path: Before removal, the load
design and the best choice of the props section and reached the ground thanks to a large number of props and
number, used to hold up the slab during transitory pillars; after removal, the slab starts to flex, concentrating
phases. These elements are modeled in the Finite the uniformly distributed load on few pillars.
Element Software using beam elements. Thanks to this The sum of all axial loads coming from the props
kind of study it was possible to evaluate props’ supporting the second floor, which is assimilable to a
maximum load before their removing. distributed load on the first floor slab, is greater than the
Figure 6 shows the phase after the realization of the one considered for the slabs design at the project state
third slab. (without considering combining coefficients).
After thirty days from the execution of the first Because of this greater load, it is necessary to recheck
floor, the maximum value of the axial force acting on the structural element using DM 2008 for bending (ULS),
the ground floor prop is equal to 38,9 kN, slightly less shear (ULS) and cracking (SLS) and using EC2 for
than the maximum axial resistance of 40 kN, certified punching (ULS), which is more detailed than in DM 2008.
by the manufacturer. This maximum allowable load Given the temporary nature of this load condition, which
concerns only the props of the ground floor. In fact, it will insist on the slab for a maximum of fifteen days, it is
was decided to analyze specifically only the on considered reasonable to reduce the combination
ground floor props as, having to reach a higher height, coefficients for ULS, using 1,2 instead of 1,3 and 1,5
they have a lower allowable. (NTC, 2008). Thanks to this reduction, the ULS checks
The props that undergoes this great effort is located (bending, shear and punching) are satisfied with a higher
far from the elevation structures with greater axial margin than the project state. On the other hand, the
stiffness, approximately in the center of the slab span. reduction cannot be applied to the SLS check, where the
Consequently, to optimize the number of the props, on coefficients are 1,0 or less.
one hand a major density of them must be positioned in Figure 9 shown the bar chart of the values obtained
the center of the spans, on the other hand just few of for bending, shear, punching and cracking related to the
them must be positioned close to elevation structures. limits imposed by the Code, at project state.
Figure 7 shown the next step during CSA, where the Results show how, during transitional phases of
ground floor props are removed. construction, considerable unforeseen cracks can be
The trend of the load regarding the maximum loaded created, as shown from Fig. 10. They can negatively
prop shows that: affect the durability of the structure.
Therefore, by means of a CS analysis, it can be possible
• In the first stage, which represents the moment of to prevent durability problems and enhance the control’s
the first floor casting, the concrete of the P1 slab, rate on solicitations that are, otherwise, unforeseeable.
69
Marco Zucca et al. / International Journal of Structural Glass and Advanced Materials Research 2018, Volume 2: 66.72
DOI: 10.3844/sgamrsp.2018.66.72
Fig. 6: FEM model - study of props stress condition (axial load on most stressed prop, Ned = 38,9 kN)
70
Marco Zucca et al. / International Journal of Structural Glass and Advanced Materials Research 2018, Volume 2: 66.72
DOI: 10.3844/sgamrsp.2018.66.72
Fig. 9: Project state checks: In red the fraction between action and ULS limit; in orange the fraction between action and SLS limit
2.0
1.8
1.6
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0
Bending Shear Punching Cracking
Fig. 10: Transitional checks: In red the fraction between action and ULS limit; in orange the fraction between action and SLS limit
71
Marco Zucca et al. / International Journal of Structural Glass and Advanced Materials Research 2018, Volume 2: 66.72
DOI: 10.3844/sgamrsp.2018.66.72
72