INSPECTION REPORT

Issued Date: Jun. 29, 2023


Project Number: L-0207 [H2528]
Project Name: MARAN GAS 174K CBM LNGC

Name of Inspector: Kyung-Min, Oh


Date of Visit: Jun. 29, 2023
Place of Visit: 123, Daebulsandan 5-ro, Yeongam-gun, Jeollanam-do, 58460, Republic of Korea.
Supplier: SUNBO UNITECH.
Inspection Activities are as follows:
1. Introduction:
– This report describes the inspection activities of HI Compressor (L-0207) of “HI Compressor-Package Project”
were performed in accordance with applicable specification, data sheet and drawing at SUNBO UNITECH. in
Daebulsandan-ro on Jun. 29, 2023 and the detail activities are described as follows;

2. Reference:
2.1. Attendee.
Name Company Position H.P
Mr. Kyung-Min, Oh On Behalf of BCKB Inspector +82-10-3137-4626
Mr. Sang-Gyu Nam DSEC T&S QM +82-10-8667-7065
Mr. Hyun-Woo Lee SUNBO UNITECH. QA/QC General Manager +82-10-7557-6148
Mr. Hun, Lee SUNBO UNITECH. QC Inspector +82-10-6470-2052
Mr. Bong-Hun, Koo KJ Ind. Co., Ltd. Director +82-10-2636-2849
Mr. Ji-Woong, Kang KJ Ind. Co., Ltd. QC Inspector +82-10-5015-8110

2.2. Applicable Reference Procedure / Specification / Standards


Document No. Document Title Rev. No. Code
QDK_1070940_001 Inspection & Test Plan 0 -
KV 5026 Clean Prefabricated & Final Fitted Piping G -
Guidelines for Pressure Boundary Bolted Flange Lasted
ASME PCC-1
Joint Assembly Edition
Lasted
ASME B16.5 Pipe Flange and Flanged Fittings
Edition
KV 5029 Cleanness Criteria for Gas-, Water-, & Oil Systems A
TSP_2081845_D_E_02- Painting specification for compressor & auxiliaries
B
Painting_Specification for various temp. ranges and substrates
BCX_PAINT_SYST_18 Paint Specification -
TDO_2072271_E01_Interbond
IPK Paint Data Sheet -
2340UPC
Paint and varnished – Corrosion protection of steel
Lasted
ISO 12944-5 structures by protective paint System
Edition
Part5 : Protective paint systems

3. Inspection Activities

3.1 Internal Cleaning Inspection (For L-0207 C-002 SKID-B GA/LG Line)

① ITP Activities No. : 1.8 / Internal cleaning gas affected part. (Hold point)
- The cleanliness of the inside of the pipe was visually checked, and the inspection was
performed by referring to KV 5026 & KV5029 for related procedures.
- In order to check the damage during transportation of the pipe spool, it was visually checked
after removing the serration protect cover of the flange.
② Checked Point are as follows
- Checked piping spool Q’ty. (20 pcs)
- Checked internal pickling and passivation, mechanical brushing condition.
- Checked not covered with dark layer. (discolorations)
- Checked not finest dust, weld spatter, corrosion.
- Checked rust and lose particles shall be remove condition.
- Checked negative welding back seam in internal.
- Checked damage of flange serration. (as per ASME B16.5 and ASME PCC-1)

③ Item No. (or Piping Spool List): See attached D2528_5LP250V_PCS_LIST (GA,LG LINE)-
20PC'S

④ Acceptance Criteria
- Inspection was performed based on the internal condition of Picture 7 of para 6.1 of KV 5049,
following BCKB's Spec.

Acceptable (Picture 7 of KV5049) Not Acceptable (Picture 8 of KV5049)

⑤ Results were found to be Satisfactory.


GA001-02 (B) Serration damage should rectify.

3.2 Surface Preparation Inspection (Shot Blasting Inspection)

① ITP Activities No.: 4.2.8 / Painting Inspection (only Shot Blasting)


- The surface roughness was checked, and it met the required roughness specifications.
- Surface roughness: as per ISO 8501-1 Near white blasting (SA 2 1/2)
Required roughness - 60um
Actual roughness - 92 um

② Item No. : C-002 (SKID-B), M1

③ The calibration report for the instrument used during the inspection was verified.
- Surface roughness gauge, DT/WT Gauge, Surface Temp’ Gauge.

④ Required Shot Blasting Condition


- Dry Temp’(DT) : > 10 ℃
- Relative Humidity (RH) : < 85%
- Surface Temp’ (ST) : > 3℃ above Dew point
After shot blasting, the atmospheric conditions for the subsequent paint process were checked,
and it was confirmed that the required spec. was satisfied.
⑤ Actual Shot Blasting Condition
- See refer to below Activities Photo.
- Abbreviation: DT (Dry Temp’), WT (Wet Temp’), RH (Humidity), ST (Steel Temp), DP (Dew point).

⑥ The specifications and expiry date / Lot No. of the paint for the next process were confirmed.

⑦ Results were found to be Satisfactory.

4. Next Inspection Tasks:


Painting Inspection (Item #: C-002 SKID-B, M1) / 2023.07.04

5. Photos were taken: Yes (V) / No ( )


PIPING INSIDE CLEANING
SHOT BLASTING INSPECTION
Note (if any):