Ir 006 - 230629
2. Reference:
2.1. Attendee.
Name Company Position H.P
Mr. Kyung-Min, Oh On Behalf of BCKB Inspector +82-10-3137-4626
Mr. Sang-Gyu Nam DSEC T&S QM +82-10-8667-7065
Mr. Hyun-Woo Lee SUNBO UNITECH. QA/QC General Manager +82-10-7557-6148
Mr. Hun, Lee SUNBO UNITECH. QC Inspector +82-10-6470-2052
Mr. Bong-Hun, Koo KJ Ind. Co., Ltd. Director +82-10-2636-2849
Mr. Ji-Woong, Kang KJ Ind. Co., Ltd. QC Inspector +82-10-5015-8110
3. Inspection Activities
3.1 Internal Cleaning Inspection (For L-0207 C-002 SKID-B GA/LG Line)
① ITP Activities No. : 1.8 / Internal cleaning gas affected part. (Hold point)
- The cleanliness of the inside of the pipe was visually checked, and the inspection was
performed by referring to KV 5026 & KV5029 for related procedures.
- In order to check the damage during transportation of the pipe spool, it was visually checked
after removing the serration protect cover of the flange.
② Checked Point are as follows
- Checked piping spool Q’ty. (20 pcs)
- Checked internal pickling and passivation, mechanical brushing condition.
- Checked not covered with dark layer. (discolorations)
- Checked not finest dust, weld spatter, corrosion.
- Checked rust and lose particles shall be remove condition.
- Checked negative welding back seam in internal.
- Checked damage of flange serration. (as per ASME B16.5 and ASME PCC-1)
③ Item No. (or Piping Spool List): See attached D2528_5LP250V_PCS_LIST (GA,LG LINE)-
20PC'S
④ Acceptance Criteria
- Inspection was performed based on the internal condition of Picture 7 of para 6.1 of KV 5049,
following BCKB's Spec.
③ The calibration report for the instrument used during the inspection was verified.
- Surface roughness gauge, DT/WT Gauge, Surface Temp’ Gauge.
⑥ The specifications and expiry date / Lot No. of the paint for the next process were confirmed.