Professional Documents
Culture Documents
OneWa-003DEL-Project Management Playbook
OneWa-003DEL-Project Management Playbook
Version Control
Table of Contents
1. Purpose ............................................................................................................................................................. 10
2. Project Organization ......................................................................................................................................... 11
2.1 Project Operational Chart .......................................................................................................... 11
2.2 Project Team Roles and Responsibilities .................................................................................... 12
2.3 One Washington Program and Technical RACI Matrix............................................................... 16
3. Project Governance Plan .................................................................................................................................. 18
3.1 Governance Framework ............................................................................................................. 18
3.2 One Washington Governance Model ......................................................................................... 22
3.3 One Washington Governance Charts ......................................................................................... 25
3.4 Governance Model Detailed Roles and Responsibilities ............................................................ 26
4. Schedule Management Plan ............................................................................................................................. 38
4.1 Introduction and Purpose .......................................................................................................... 38
4.2 One Washington Program Roadmap ......................................................................................... 38
4.3 Project Schedule Approach and Tools........................................................................................ 39
4.4 Project Schedule Roles and Responsibilities .............................................................................. 41
4.5 Project Schedule Development .................................................................................................. 42
4.6 Project Schedule Maintenance .................................................................................................. 52
4.7 Project Schedule Reporting and Communications..................................................................... 55
5. Cost Management Plan .................................................................................................................................... 58
5.1 Introduction ............................................................................................................................... 58
5.2 Purpose ...................................................................................................................................... 58
5.3 One Washington Budget Background ........................................................................................ 58
5.4 Roles and Responsibilities .......................................................................................................... 59
5.5 Cost Management Approach ..................................................................................................... 60
5.6 Plan Funding Requests ............................................................................................................... 62
5.7 Funding and Budget Development ............................................................................................ 64
5.8 Invoice Processing ...................................................................................................................... 64
5.9 Cost Control and Reporting Processes ....................................................................................... 65
5.10 Agency Pool Funds ..................................................................................................................... 66
5.11 Funding Oversight ...................................................................................................................... 67
Table of Tables
Table of Figures
1. Purpose
The Project Management Playbook (PMP or “Playbook”) documents the structure, processes, and resources that
will be used to plan and execute a successful One Washington implementation. The PMP covers: the project
organization; governance structure; standard project processes and controls; resources and tools; quality
activities and project protocols for onboarding/offboarding, meetings and communications; and refers to the
Information Security and Risk Management Plan (ISRMP) for how to handle personally identifiable information
(PII) on the project.
The Project Management Playbook is approved by the One Washington PMO Manager during the Plan-Imagine
Phase and is maintained throughout the life of the project. It is a living document that is kept up-to-date and
should be considered the primary source of information about the project’s organization, processes, tools, and
terminology. Once this Playbook has been approved, all new project team members will be indoctrinated in its
practices.
The PMP will be reviewed by the PMO, with input from both the State and Deloitte, at the beginning of each
project phase to confirm its accuracy and completeness. Major, substantive updates to the Project Management
Playbook, particularly regarding governance procedures or other project standard processes or protocols, will
require a change request and must go through the project’s approved change control process, described later in
this PMP.
2. Project Organization
State PMO Manager Leads the One Washington Project Management Office (PMO), managing business
and project management aspects required to deliver the business outcomes of the
project.
Deloitte Project Manager/PMO In accordance with methodologies and standards found in Project Management
Lead Institute's (PMI) Project Management Body of Knowledge (PMBOK® Guide), IT
Infrastructure Library (ITIL) and the Project Delivery Framework, responds to day-to-
day problems, manages issues and risks, provides status reports, participates in
weekly status meetings, develops and timely submits deliverables set forth in the
SOW 1A and manages resources.
Provides input into the project to mitigate risks: Conducts Project Work Plan, Testing
Plan, and Cutover Plan reviews. Performs Operation Readiness Checkpoints –
progressive discussion and updates throughout the One Washington deployment.
Executes day-to-day project operations in collaboration with Deloitte leadership.
Confirms road map aligns with project priorities and business case. Responsible for
managing the project to completion.
Performs a variety of tasks, including: 1) co-developing, managing and maintaining
the Project Work Plan; 2) managing the issue and decision log; 3) setting deadlines
and evaluating Milestones; 4) assigning responsibilities; and 5) delivering status
reports to upper management on a regular basis. Operates as a liaison between
executive management and escalates project issues and risks to the Project Steering
Committee.
Manages the deployment to completion.
Identifies change control issues and highlights.
State Organizational Change Leads the One Washington OCM efforts, directing organizational and stakeholder
Management (OCM) Lead change programs to help transform the State workforce to effectively adopt the new
Workday solution and deliver the business goals of the project.
Deloitte OCM Lead Leads the OCM-focused project activities and integrates them into the overall
project solution deployment strategy.
Defines the OCM work plan across all areas of focus, including communications,
leadership and stakeholder engagement and action planning, end-user training,
organizational alignment, transition, and capability transfer.
Develops the One Washington OCM strategy and manages its successful execution.
Assesses leadership alignment, defines and executes leadership engagement plans.
State Finance Lead Coordinates and participates in One Washington design workshops, assists in the
development of business process and role design documents, reviews impact
assessment, and assists in the identification of gaps.
Completes hands-on functional and technical project activities and provides
guidance to State resources for the Financials functional areas in scope.
Demonstrates and explains product features, documents requirements and design,
provides knowledge transfer to the project team, configures the corresponding
functionality, and assists in testing and supporting the roll-out.
Escalates issues and risks, as appropriate.
Deloitte Finance Lead Provides overall leadership and subject matter expertise in the implementation of
the Financials functionality, in-scope functionality and contractual deliverables.
Coordinates and participates in One Washington design workshops, assists in the
development of business process and role design documents, reviews impact
assessment, and assists in the identification of gaps.
Responsible for overall management of the Financials functional team and for the
coordination of their work with the work of other team members/leaders.
Completes hands-on functional and technical project activities and provides
guidance to State resources for the Financials functional areas in scope.
Demonstrates and explains product features, documents requirements and design,
provides knowledge transfer to the project team, configures the corresponding
functionality, and assists in testing and supporting the roll-out.
Responsible for providing functional expertise for the financials components in
scope. Recommends solutions to One Washington requirements and manages the
design of cross-application solutions.
Escalates issues and risks, as appropriate.
State Technical Lead Responsible for providing overall leadership and subject matter expertise in the
implementation of the technical areas in scope and overseeing the timely
completion of deliverables required by the Project Work Plan.
Oversees the overall design, testing and deployment of the technical areas.
Responsible for overall management of the Technical functional team and for
ensuring the coordination of their work with the work of other team
members/leaders.
Deloitte Technical Lead Responsible for providing overall leadership and subject matter expertise in the
implementation of the technical areas in scope and overseeing the timely
completion of deliverables required by the Project Work Plan.
Oversees the overall design, testing and deployment of the technical areas.
Responsible for overall management of the Technical functional team and for
ensuring the coordination of their work with the work of other team
members/leaders.
State Data Governance Lead Oversees One Washington data programs and standards.
Provides current State data quality processes and procedures and overall data
quality reports.
Provides oversight to the team to define future State Data Quality Requirements.
Provides input to, reviews and approves Data Cleansing Plan and Data Cleansing
Approaches.
State Architecture Lead Provides subject matter expertise on State technical requirements and standards.
Oversees the overall design of integrations, conversions, and reporting solutions.
Serves as an adviser on complex issues technical issues facing the team.
Deloitte Architecture Lead(s) Drives the overall design of integrations, conversions, and reporting solutions for the
One Washington Workday solution.
Serves as an adviser on complex issues technical issues facing the team.
State Integration Lead Responsible for providing overall leadership in the implementation of the
Integration functionality in scope and overseeing the timely completion deliverables
required by the Project Work Plan.
Responsible for overall management of the Technical Integration functional team
and for the coordination of their work with the work of other team
members/leaders.
Deloitte Integration Lead Responsible for providing overall leadership and subject matter expertise in the
implementation of the Integration functionality in scope and overseeing the timely
completion of deliverables required by the Project Work Plan.
Responsible for overall management of the Technical Integration functional team
and for the coordination of their work with the work of other team
members/leaders.
Serve as subject matter advisors on Informatica™ configuration and implementation
for integration.
State Data Conversion Lead Coordinates and participates in One Washington design workshops and assists in the
development of conversion data mappings.
Responsible for overall management of the conversion team and for the
coordination of their work with the work of other team members/ leaders.
Responsible for converting data from the existing system into Workday’s data
objects. Assists conversion team in resolving any source data or mapping errors.
Provides leadership and subject matter expertise in State requirements for data
extracts, transformation and cleansing and oversees the timely completion of
Deliverables required by the Project Work Plan.
Deloitte Data Conversion Lead Responsible for providing overall leadership and subject matter expertise for One
Washington conversion to Workday and overseeing the timely completion of
Deliverables required by the Project Work Plan.
Coordinates and participates in One Washington design workshops and assists in the
development of conversion data mappings.
Responsible for overall management of the conversion team and for the
coordination of their work with the work of other team members/ leaders.
Responsible for converting data from the existing system into Workday’s data
objects. Assists conversion team in resolving any source data or mapping errors.
Serve as subject matter advisors on informatica™ configuration and implementation
for conversions.
State Reporting Lead Responsible for providing overall leadership and subject matter expertise for State
Workday reporting requirements and overseeing the timely completion of
deliverables required by the Project Work Plan.
Coordinates and participates in State design workshops and assists in the
development of Reports mappings.
Responsible for overall management of the reporting team and for ensuring the
coordination of their work with the work of other team members/leaders.
Deloitte Reporting Lead Responsible for providing overall leadership and subject matter expertise for State
Workday reporting requirements and overseeing the timely completion of
deliverables required by the Project Work Plan.
Coordinates and participates in State design workshops and assists in the
development of Reports mappings.
Responsible for overall management of the reporting team and for ensuring the
coordination of their work with the work of other team members/leaders.
State Test Lead Responsible for coordinating testing efforts that validate State project deployments.
Works with the Subject Matter Experts (SMEs) to develop the test strategy and test
plans, identify test requirements, create test scenarios, and oversee the execution of
the test scenarios.
Deloitte Test Lead Develop the Testing Strategy deliverable with the State and guide its review and
approval process.
The test manager is responsible for planning, managing, directing, and coordinating
the test phase of the project.
State Security Lead Responsible for providing leadership support and subject matter expertise in the
implementation of the User Security functionality in scope and overseeing the timely
completion of deliverables required by the Project Work Plan.
Coordinates and participates in One Washington design workshops, assists in the
development of business process and role design documents, reviews impact
assessment, and assists in the identification of gaps.
Deloitte Security Lead Responsible for providing leadership support and subject matter expertise in the
implementation of the User Security functionality in scope and overseeing the timely
completion of deliverables required by the Project Work Plan.
Coordinates and participates in One Washington design workshops, assists in the
development of business process and role design documents, reviews impact
assessment, and assists in the identification of gaps.
Completes hands-on functional and technical project activities and provides
guidance to State resources for the Security functional areas in scope.
Demonstrates and explains product features, documents requirements and design,
provides knowledge transfer to the project team, configures the corresponding
functionality, and assists in testing and supporting the roll-out.
Escalates issues and risks, as appropriate.
Per the sample below, the RACI can be filtered by State Agency, Category (i.e., Business or Technical), Role and
Name (First and Last Name), so a user can get a summary of the One Washington functions where each
role/person is responsible, accountable, consulted, or informed.
The Program and Technical RACI Matrix is maintained by the One Washington Project Management Office
(PMO).
Figure 2. Sample screenshot cut-out of the One Washington Program and Technical RACI Matrix.
Deloitte will help the State PMO define and execute effective project governance aligned with standard project
management principles. Deloitte’s Project Management Center (PMC) tool will be used to document and
manage project risks, action items, issues, and decisions (RAID) to closure throughout the life of the project.
1. “Implementation of the project governance framework should be based on the context of the
organization and project. There is no one governance framework that is effective for all situations”
2. “Project governance should establish transparency and confidence in decision making and clarify roles
and responsibilities”
3. “Project governance should involve the least amount of authority structure possible because time and
costs are associated with governance decision-making and oversight activities”
The diagram below sets the stage for the relationships between the One Washington Governance Teams and the
project management team:
Based on Legislature-appropriated funding and subsequent decisions by the Executive Steering Committee, the
program defined the following phased approach:
The One Washington governance model leverages statewide functional business owner expertise, partnership,
support and leadership at all levels of governance.
Executive Sponsor: The executive sponsor is the single point of authority and accountability for the program and
has authority to make decisions on any matter escalated by the ESC or executive director. Most decisions are
expected to be made by subordinate governance bodies.
Business Transformation Board (BTB): The BTB board has authority to make decisions regarding statewide
planning, implementation, and operation of the program, so long as those decisions do not change critical
program phase scope, schedule, or budget. The BTB has authority over change orders that do not change critical
scope, schedule or budget. BTB has authority over risk mitigations, issue resolutions, or any other matters that
impact the One Washington program at the operational and enterprise level. The BTB makes operational
decisions with a multi-agency level impact to overall business function(s) of the State. BTB establishes cross-
agency strategy and alignment, as well as cross-business-function (i.e., finance, HR, payroll, budget, and
procurement) and cross-program-function (i.e.: OCM, data, technology) strategy and alignment.
Advisory Committees (AC): Within the scope of their authority of the specific business or program function, the
advisory committees are authorized to make decisions on matters related to the business function and/or area
of expertise as well as deliverables, requirements, business capabilities, change orders, risk mitigations, issue
resolutions, or any other matter regarding delivery of enterprise business and functional capabilities to program
stakeholders. Advisory committees have authority over business and technical planning, implementation and
operational decisions. Advisory committee decisions focus on improving the alignment and integration of
business function processes across the enterprise.
Project Management Office (PMO): With support from the business owners, the PMO has authority over core
and day-to-day operations of the project and program. The PMO will triage matters escalated by the program’s
functional teams and has authority to make decisions on matters regarding the planning, coordination, direction,
control, and reporting tasks/activities to complete the program’s scope of work within the parameters of the ESC
and BTB.
Business Owners: The business owners are essential to program success.1 They know their customers and how
best to work with them. Business owners play a unique and critical role that allows them access and mobility
within several groups of the governance structure. Business owners attend and provide information, as needed
to ESC members. Business owners are voting members of the BTB and chair an Advisory Committee that
corresponds to their business function. Business owners have authority to make decisions regarding program
readiness and agency readiness for their respective business areas. There are main business owners and sub-
business owners, as defined in the details below. The business owners have a unique decision-making position
because they support all levels of governance.
1
One Washington is committed to empowering business owners to lead the state to a different way of doing business. In this
way, impacted stakeholders will have confidence that the leaders they currently look to for guidance on a host of policy
questions are the true “owners” of any future solution. This strategic decision will reduce resistance, increase trust across the
enterprise and put the One Washington effort on a path to sustainable results.
In alignment with the guiding principle “Decisions are made at the lowest level possible,” escalation should be
the exception, not the rule. In addition, given the ability to quickly change Workday configurations during Phase
1A Design and Build activities, the goal is to get escalated items resolved no later than fifteen (15) working days
from the initial escalation date.
Business Escalation 3: The Advisory Committee RAID items and CRs will be escalated to the BTB
Transformation Chair(s), will determine when RAID items or when:
Board (BTB) CRs need to be escalated to the BTB; and
when escalated, will receive process The RAID item cannot be resolved by PMO
support from the PMO. working with the appropriate Advisory
Committees, and the RAID priority is not Low
To escalate a RAID item or CR to the BTB,
the PMO will work under the direction of The CR will impact Phase 1A scope,
schedule or budget < 10%
the appropriate Chair(s) to:
1. Change the escalation level for the
RAID item in PMC to 3
2. Confirm that the RAID
documentation in PMC or CR form
is accurate and complete
3. Send the RAID item or CR with
recommendation(s) to the BTB
The circuit-breaker process can be invoked by the executive sponsor or designee, working with the PMO
Manager, in the event of an impasse on a decision or when an issue requires an immediate decision not allowing
time to assemble the entire ESC. Upon notification from the executive director or program director, the
executive sponsor or designee would identify key ESC and/or BTB members who would be assembled to hear
positions on the project issue and make a decision.
A circuit-breaker event will always include the business owner(s) or delegate for the business area of the issue or
impasse, and the PMO Manager. The diagram below illustrates the circuit-breaker process and its ability to fast-
path a project item or CR to the ESC/Executive Sponsor level when needed:
Executive Sponsor
Authority The executive sponsor is the single point of authority and accountability for the program
and has authority to make decisions on any matter escalated by the ESC or executive
Voting and Ex- See the One Washington Governance Membership Chart
officio Members
Membership Members are appointed by the executive sponsor. The executive sponsor has full
selection authority to appoint and remove members to ensure the success of the program.
Authority The ESC has authority to make decisions on scope, schedule, and budget as well as
matters escalated by the BTB, executive director, program director, and/or business
owners.
Performance and Monthly executive director’s ESC briefing including program performance
Oversight measures
Controls Monthly reports from quality assurance consultant
Recommendations from the Office of the Chief Information Officer
Stakeholder Agency leaders are expected to involve and inform all relevant parties in their agencies
communication and/or the agencies they represent.
responsibility
Voting members Please see the One Washington Governance Membership Chart
Authority The BTB is authorized to make high-level operational decisions that impact the
program and agencies; scope of decisions should be enterprise-wide across
agencies and business functions.
Decision-making 1. Discussion of the recommendations put forward by the One Washington program or
process advisory committees.
2. Dissenting opinions on the recommendations are identified. A motion is put forth
followed by a vote of the members.
3. Action steps based on that decision are then identified and assigned.
Quorum Voting will be by simple majority, with the program director breaking any tie. In order to
conduct a vote on any proposal, three quarters (11) of the voting members of the board
must be present, in person or via mobile participation, to constitute a quorum.
Recommendation decisions are simply majority vote.
Roles and Promote continuous alignment of the program’s strategic objectives, timelines,
Responsibilities and business processes
Review and consider redesign and/or standardization of existing business
processes
Function as program leaders and provide strategic leadership for enterprise
conversations, discovery, understanding, and collaboration with business
stakeholders on such topics as: business capabilities, change management, risk
and issue management, testing, lessons learned and continuous improvement
Approve and propose to the ESC any recommended changes to the BTB Charter
Recommend changes to the ESC on project management plans: e.g., RAID,
Change Control, etc.
Approve project deliverables
Review and advise performance measures/metrics
Champion desired outcomes and capabilities in partnership with the program,
and advocate for successful adoption within the agency community
Implement or recommend program strategies to the ESC for consideration
Monitor program plans for enabling business function strategies
Review external assessments and benchmarking activities
Review business continuity capabilities, including vendor disaster recovery plans
Review and provide resource and issue recommendations to the ESC
Review and provide scope, schedule or budget recommendations to the ESC that
are outside of BTB responsibilities
Share pertinent information and obtain feedback from other agency leaders
and/or departments, stakeholders, and sub-business process owners; bring
feedback and information from these stakeholders to the decision-making
process
Involve relevant sub-business owners and other agency leaders, as needed
Performance and Monthly program director’s BTB briefing, including program performance
Oversight measures
Controls Monthly reports from quality assurance
Recommendations from the Office of the Chief Information Officer
Stakeholder Business owners are expected to involve other sub-business owners: e.g., HR
communication may include leaders of HCA, DRS and DES, as needed
responsibility Agency leaders are expected to involve and inform all relevant parties in their
agencies and/or the agencies they represent, as well as agencies who may be
impacted
Advisory Committees
Chair Business owners for finance, procurement, budget, HR and payroll
One Washington staff for OCM, technical and data governance
(Note: The chairperson sets the agenda for the monthly meeting and with support from
the PMO will create and present the meeting materials.)
Charters will reside on the One Washington SharePoint site in the PMO site under Project
Management Plans -->Charters.
Membership 1 Chairperson/facilitator
Makeup: 10-15 members total; membership will be diverse in agency size,
complexity and how they perform business
Selection: Members must apply via an email to the One Washington program
director and/or the chairperson with an explanation of their skills and experience
as well as their agency support of the program. The chairperson has authority to
approve/disapprove membership and will do so with the input of the program
director.
Decision-making 1. Discussion of the recommendations put forward by the chairperson, the One
process Washington program or advisory committee members.
2. Dissenting opinions on the recommendations are identified. A motion is put forth
followed by a vote of the members.
3. Action steps based on that decision are then identified and assigned.
Quorum Voting will be by simple majority, with the chairperson breaking any tie. Half of the
members of the committee must be present, in person or via mobile participation, to
constitute a quorum.
Recommendation decisions are simply majority vote.
Roles and Vet issues, analyze business priorities and propose enterprise-level
Responsibilities recommendations for program action; Committee outputs will be routed to the
next level up in the current Program organizational structure
Be knowledgeable of the Program Blueprint and strategy documents and
promote continuous alignment of the committee’s activities with the Program’s
strategic objectives, timelines and processes
Function as an agency business liaison, and provide strategic leadership for
enterprise conversations, discovery, understanding, and collaboration with
agency business stakeholders, on such topics as business capabilities, change
management, risk and issue management, testing, lessons learned and
continuous improvement, review and validation of performance
measures/metrics
Champion desired outcomes and capabilities in partnership with the program,
and advocate for successful adoption within the agency community, both
discretely and broadly
Secure or solicit volunteer resources, when needed
Depending on committee, approve business capabilities and/or technical
requirements, including any future updates
Approve recommendations for risks and issues escalated by the PMO
Provide guidance to ensure delivery of technical requirements and business
capabilities meet the expectations of program stakeholders
Provide leadership in enforcing, carrying out, and/or communicating decisions
If a project issue (e.g., RAID or CR ticket) is escalated to the BTB, a member of the
Advisory Committee must:
o Request the topic be added to the BTB agenda
o Send corresponding information and/or recommendations to the BTB via
an issue paper (and/or reference to RAID item in PMC, where
appropriate)
o Attend the BTB to explain, discussion and obtain decision
o Report back to the Advisory Committee the BTB decision/action
Creating focused-task sub-groups and sub-committees around program and/or
agency readiness
Inform the BTB and the One Washington program of any major decisions
Performance and Chairperson is responsible for ensuring documentation of the meetings (this can be
Oversight delegated) that includes:
Controls Attendees
Agenda
Highlights and decisions
Stakeholder Involve and inform leaders and subject matter experts for all relevant parties in their
communication respective agencies and/or the agencies they represent as well as agencies who may be
responsibility impacted.
Roles and Prepare briefings and reports for ESC and BTB meetings
Responsibilities Develop charters for both ESC, BTB and advisory committees
Work with the BTB to develop program performance measures
Develop project management plans and processes for the program
Ensure compliance with established program processes (e.g. issue, risk, and
requirements management)
Plan program tasks/activities to meet program objectives and program
performance measures
Ensure accurate project reporting
Performance and Briefings and reports from ESC, BTB and advisory committees
Oversight PMO reports of performance and quality
Controls
Feedback from the executive sponsor, executive director, program director, ESC,
BTB and advisory committees
Reports from the quality assurance consultant
Stakeholder Communicate with all stakeholders through all branches of State government, including
communication higher education as appropriate.
responsibility
Business Owners
Members: See the One Washington Governance Membership Chart
statewide business owners for finance, procurement, budget, HR and payroll
Decision-making There is no formal decision-making process: Issues must either go to the BTB or an
process advisory committee or be handled within the authority of the business owner.
Roles and Actively participate and provide information and issues at the ESC
Responsibilities meetings
Act as a voting member of the BTB meetings
Chair or provide a delegate to chair an advisory committee
Approve advisory committee charters
Approve and manage membership of an advisory committee
Approve project management plans (e.g. issue, risk, etc.) and project
deliverables
Approve technical requirements and business capabilities, including any
future updates
Approve recommendations for risks and issues escalated by the program
or project management
Provide guidance to ensure delivery of technical requirements and
business capabilities meet the expectations of program stakeholders
Provide leadership in enforcing, carrying out, and/or communicate
decisions
The One Washington program is a complex business transformation and modernization effort to replace aging
statewide enterprise systems with a modern enterprise resource planning (ERP) system. “A program is defined as
related projects, subsidiary programs, and program activities managed in a coordinated manner to obtain
benefits not available from managing them individually…” (The Standard for Program Management, 4th Edition).
This project spans budget cycles of multiple biennia. It is under both OCIO oversight and quality assurance
services provided by a third-party contractor.
The size and complexity of this project will demand close attention to the program’s master schedule. This is
particularly important to maintain the quality of deliverables and to avoid project slippage by closely monitoring
tasks and key milestones.
The schedule management plan provides guidance on how the One Washington PMO will develop, manage and
control the schedule throughout the lifecycle of the program. The plan defines:
The program approach to schedule management. This will provide the basis for developing the overall
structure of the schedule.
Roles and responsibilities for tracking and reporting schedule progress, including who is responsible for
tracking and reporting schedule progress and the frequency of these updates.
The processes and tools used for schedule management, including the preferred level of granularity for
tasks and mandatory schedule components to allow for proper monitoring and status reporting.
How the schedule will be baselined and how approved changes will be incorporated.
Status metrics and reporting needs, used to illustrate progress and determine variances.
The distribution, storage, version control and access to both the schedule management plan and the
master project schedule.
Please Note: This management plan was built around the need for flexibility and provides the ability to adapt to
changes quickly. It aims to avoid being too prescriptive in schedule management.
Please note that One Washington defines a workstream as the progressive completion of distinct tasks
and core activities that are completed by a specific work group and focused on a specific purpose. The
terms workstreams and subprojects may be used interchangeably throughout this plan.
Currently, the PMO has the Microsoft Project 2016 desktop application and NOT project server’s
project web application. Without PWA, the program is unable to incorporate certain enterprise
functionality, such as assignment owners. It is important to consider this current constraint in the
development of project schedules and communications.
Other tools used by the One Washington program to manage project schedules include:
Visio
PowerPoint (PPT), including Office Timeline Pro for PPT
Excel
SharePoint
Microsoft Teams
Planner
Planner is used within the One Washington program to create Kanban boards. The PMO Kanban board is used to
track the status of individual workstream activities and action items and is used to supplement the project
schedule. This tool helps organize and track workstream activities and action items that may feed into tasks in
the integrated project schedule.
The PMO Kanban board is used in PMO daily standup meetings to coordinate PMO team activities and ensure
that the team is working on the right priority items. The use of the PMO Kanban is expected to evolve and adjust
For more information on the program-wide tools that will be used on Washington, please see Section 12 Project
Tools Strategy Plan.
Roles Responsibilities
Deloitte Project Manager Oversee weekly updates to the integrated master schedule
Monitor schedule for accuracy and impacts on critical path
Check quality of schedule in terms of compliance with best practices for using
Microsoft Project as a scheduling tool
Present task status weekly in the PMO Standup meeting
Provide task status input for weekly workstream status report
Provide status of schedule baseline; recommend when a baseline revision may
be necessary
OneWa PMO Review project weekly and communicate findings to the Deloitte Project
Manager, OneWa Program Director, and Deloitte Program Director
OneWa Project Manage program-level schedule status information; that is, budget, funding,
Coordinator and policy activity
Collaborate with Project Manager and Scheduler on integrating program-level
status into the OneWa Phase 1A schedule
Create weekly reports and/or ad-hoc reports, as needed
Deloitte Project Scheduler Manage the Microsoft Project schedule
Enter updates into the schedule
Solicit updates weekly from Workstream Leads and the OneWa Project
Coordinator
Ensure quality of the schedule in terms of compliance with best practices for
using Microsoft Project as a scheduling tool
Workstream Lead Provide on-time input on task status within the workstream defined at Level 2
of the project work breakdown
OneWa Program Director Provide guidance and oversight on the development and management of the
+ Deloitte Program project schedule
Director Consider and make decisions on schedule-driven change requests
PMO manager Provide guidance on the development and maintenance of the project schedule
Program leadership Provide guidance on the development and maintenance of the project schedule
QA/OCIO oversight Provide guidance on the development and maintenance of the project schedule
Changes to the project schedule baseline must be approved by the proper authority(ies) before being
incorporated into the plan and master project plan. The table below provides guidelines on the approval
authority required based upon the magnitude of the requested change.
Change to task Impacts major milestones but does not impact critical Business
dependencies release budget or project completion date Transformation Board
Executive Steering
Impacts release budget, critical path or project completion date
Committee
Provides a mechanism to re-align the schedule to Executive Steering
Re-baseline
negotiated, revised milestones or to address Committee
schedule
additions/removals of tasks.
Predictive approach for well-known, linear or sequential projects, such as for development of the
project management plans and program’s budget requests.
Adaptive approaches for work with a larger amount of uncertainty, ranging from complicated to
complex.
Iterative: allows for feedback on partially completed or unfinished work to improve or modify the work.
This approach is currently being used in developing the solution architecture and security
documentation by the One Washington technical team.
Incremental: provides smaller finished deliverables within a given time increment. This approach has
been used for program planning, such as a rolling wave planning for the transitions to different phases as
outlined in the modernization roadmap.
Agile: leverages both iterative and incremental characteristics.
For the One Washington program, the project schedule development process follows these development steps:
1. Statement of Work
2. PMO Project Intake Form
3. Standard WBS template
Regarding a vendor SOW, the contract manager is responsible to ensure that the schedule is produced and
integrated into the program’s Master Project Plan. Please refer to the One Washington Vendor Management
Plan for more information.
1. Identify the need for a project, subproject, or workstream by any One Washington team member.
2. Fill out the project intake form in collaboration with the One Washington Project Management Office:
This involves an iterative process to define the scope, deliverables, team members, and overall
timeline with key stakeholders.
The PMO is responsible for ensuring that sufficient detail is included for the proposed body of work,
and that alignment with program goals and priorities is clear.
The PMO Manager will work with the One Washington leadership team to validate the priority of the
proposed project/body of work.
3. Obtain signature(s) from the sponsor to authorize the use of resources on the identified body of work
outlined in the project intake form.
4. The identified project lead will work with the PMO to develop the project schedule – please see the
Work Breakdown Structure section below. The PMO will also assist the project lead with baselining the
completed, approved project schedule and integrating it into the One Washington Master Project Plan.
5. The project lead will provide status updates and reporting, as outlined in the Project Schedule
Maintenance section of this document.
A template of the Project Intake Form is available for use.
A milestone is, “a significant point or event in a project or program” (Practice Standard for Scheduling,
3rd edition).
A deliverable is, “any unique and verifiable product, result, or capability to perform a service that is
produced to complete a process, phase, or project” (Practice Standard for Scheduling, 3rd edition).
Please note that the term deliverable may have additional meaning within the One Washington program.
Please refer to the Quality Management Plan section in this Playbook for the program’s defined
processes for deliverable management, which includes contract deliverables, non-payment deliverables,
and work products.
Creating a hierarchical decomposition of a project deliverable into subcomponents through progressive
elaboration makes identifying all the work packages needed for creating that deliverable much easier. According
the Practice Standard for Scheduling, 3rd edition:
Progressive Elaboration is: “…the iterative process of increasing the level of detail in a project
management plan as greater amounts of information and more accurate estimates become available.”
A Work Package is: “…the work defined at the lowest level of the work breakdown structure for which
cost and duration are estimated and managed.”
The One Washington project schedule will be deliverable-based. The standard WBS for One Washington projects
is defined in the table below:
In addition, the One Washington PMO has created a WBS dictionary template for use with the project intake
form. Please see the figure below for a sample of this standard WBS template and contact the PMO for further
assistance with development of a project WBS.
The One Washington program will decompose all project work to a level that enables
adequate management, monitoring, and progress reporting.
Specific deliverables or sections of the plan may have differing levels of detail, in accordance with PMI best
practices to ensure enough useful details to complete the work successfully.
The schedule includes all the activities and tasks needed to produce the deliverables. An activity is a collection of
tasks, and a task is a distinct, scheduled portion of work performed during the course of a project. When creating
the description of tasks, each activity should start with a verb and contain a unique, specific objective so it is
clear and not ambiguous or open to individual interpretation.
For additional clarity and consistency in the project schedule mpp file, One Washington also specifically identifies
deliverables and milestones within a project schedule using standard naming conventions and call-outs to
further enhance specificity. For example:
M: name of milestone
Deliverable: name of deliverable
Per the 1A SOW: “No individual task will be longer than four weeks in duration, with a preference for less than
two weeks per Contractor’s QA vendor.” So, where possible, activities should be decomposed into tasks that can
completed in two weeks or less (i.e., 10 working days); or four weeks (i.e., 20 working days) at a maximum. One
exception to this Decomposition guideline is an activity or task within the project schedule that represents a
continuous activity, to be performed throughout a project phase or the entire project lifecycle. We may identify
other exceptions as the project schedule continues to be progressively elaborated.
According the Best Practice Standard for Scheduling (3rd Edition), consideration to the level of
granularity should be considered and the level of detail can be different for every project.
Finish-to-Start (FS): The initiation of the successor activity depends upon the completion of the
predecessor activity.
Finish-to-Finish (FF): The completion of the successor activity depends upon the completion of the
predecessor activity.
Start-to-Finish (SF): The completion of the successor activity depends upon the initiation of the
predecessor activity.
Start-to-Start (SS): The initiation of the successor activity depends upon the initiation of the predecessor
activity.
Tasks are linked together and sequenced to identify the relationships between deliverables, sub-deliverables,
activities, tasks and subtasks.
Dependencies
1. With minimal exceptions, all tasks should have at least one successor and predecessor, so there are no
unlinked tasks to avoid open-ended or “Fixed Date”-constrained activities.
Open-ended or “Fixed Date” activities are any activities that lack either predecessor or successor
and obscure the logical relationships between project activities, creating the false appearance of
float in a project schedule.
2. Summary activities or tasks should not have any specific successor or predecessor identified. Summary
activities are a group of related schedule tasks aggregated and displayed as a single activity. For
purposes of modeling the critical path, all dependencies should be linked to a detail task or deliverable
and NOT to a summary activity or task.
3. Start and finish dates should not be entered when creating new tasks. Instead, predecessor activities
determine the start date and the estimated duration determine the finish date.
4. Date constraints should be applied sparingly (i.e., only when required or when actual constraint exists) in
order to maintain a dynamic, realistic schedule. For example, only hard deadlines that represent a
constraint to the One Washington program should be entered into the project schedule as Fixed Date
tasks; self-imposed, internal team deadline dates should not be defined for a task.
Use caution when adding date constraints to project schedules, as they restrict the dependency
relationships and affect the schedules flexibility by limiting its ability to react to changes. Date
constraints should be avoided when possible and only be used after careful consideration of how they
impact the project schedule over its entire lifecycle. Within One Washington, only deliverables or
milestones with hard deadlines should be inserted as date constraints and not include any internal self-
imposed deadlines.
Based on an 8/24/2020 meeting between One Washington, WaTech and OFM IT, a carrot symbol (<< or >>) will
be used in the task naming convention to denote dependencies between One Washington, WaTech and OFM IT
project plans, where relevant:
The organizational chart is a useful reference document that provides a hierarchical-tree diagram of the
organization and resources. The One Washington business operations team manages the organizational chart for
the program. Additional information is available in the Resource Management Plan section of this Playbook.
For external projects related to the One Washington program, it may be necessary for the
project manager to create an organizational chart that identifies resources specific to their
project.
Another tool that can be useful is a resource assignment matrix (RAM). The most common RAM is the RACI
matrix for describing resource assignments and responsibilities in relation to tasks. The previous Project
Organization section of this Playbook presents the Program and Technical RACI for the One Washington
program.
For the One Washington Phase 1A implementation project, project schedule tasks will be assigned at the “Team
Lead” level, and that person will be responsible/accountable for getting the work done, as well as providing
weekly updates on his/her respective assigned tasks. The best practice is to assign one accountable person or
Team Lead to each task.
For the One Washington program schedule, each summary activity will at a minimum, specify the
main contact that is responsible for ensuring the work is tracked through completion.
Field Description
Task Name The Name field contains the name of a task or a resource.
Predecessors The Predecessors field lists the task ID numbers for the predecessor tasks on which
the task depends before it can be started or finished.
Start The Start field shows the date when an assigned resource is scheduled to begin
working on a task.
Finish The Finish field shows the date when a task is scheduled to be complete. It is automatically
calculated, based on the task duration and project working time defined (including holidays
and/or black-out dates).
Duration The Duration field shows the total span of active working time for a task.
Percent (%) The % Complete field contains the current status of a task, expressed as the
Complete percentage of the task's duration that has been completed.
Team The Team name of the resource(s) responsible for a task.
Resource The Resource Name field contains the name of an individual(s) responsible for a task.
Names
The following fields are optional but encouraged when information is available:
Table 13. Project Schedule Fields - Optional
Field Description
Notes The Notes field contains comments you can enter about a task, resource, or assignment.
Work The Work field shows the total effort scheduled on a task for the assigned resource(s), in
hours.
Actual Start The Actual Start field shows the date and time that a task or an assignment actually began,
based on progress information that you entered.
Actual Finish The Actual Finish field shows the date and time when a task or assignment was completed.
Deadline The Deadline field shows the date you enter as a deadline for the task. A deadline is a
target date that indicates when you want a task to be completed.
Priority The Priority field indicates the level of importance given to a task, which in turn indicates how
readily a task or assignment can be delayed or split during resource leveling.
The 8/80 rule, which decomposes tasks to no less than 8 hours or no more than 80 hours, will
be encouraged, unless project managers can explain when and why it is not applicable for a
task.
Within MS Project, durations are calculated based on the project calendar and working time/day definitions. The
following conversion table can be used to determine durations in the project schedule:
The documented change control process described in Section 7 of this Project Management Playbook
will be used when the schedule needs to be re-baselined.
A baseline is a group of nearly 20 primary reference points (in five categories: start dates, finish dates,
durations, work, and cost estimates) that are set to record the original project plan.
As the project progresses, One Washington can set up to a total of 11 additional baselines for each
project in order to assist with measuring changes to the project plan.
o The latest baseline will always be used by MS Project to measure and report progress against the
plan, based on the Project Status Date specified.
For more information about baselining in MS Project, please refer to this Microsoft article: Set and save a
baseline.
For the One Washington Phase 1A project, the project schedule should be baselined once fully complete and
approved by the One Washington PMO during planning; then the baseline will be used to measure “progress
against the plan” during execution and implementation of the project.
New tasks added to the baselined project schedule will need to be individually baselined when approved by the
One Washington PMO (plus their respective roll-up tasks to account for them properly), but the entire project
schedule should only be re-baselined after an approved CR to change the critical path components of a One
Washington release, including scope, schedule and cost/budget. Please see Section 7 Scope Management and
Change Control in this Playbook for more information.
Schedule updates will be published weekly, or as often as necessary and will be posted to the program’s
SharePoint site. The schedule information will be presented to executives and staff in the weekly status report.
For additional understanding of how the One Washington master schedule is updated and weekly
reports are developed, please refer to the weekly schedule updates and reports guide in
SharePoint.
Appropriate tasks and resources are represented at a level of detail needed to support status reporting
requirements, the variable demands of management review and decision-making, and the operational
demands of managing time and scope.
Changes to the project schedule are accommodated by the approved addition, deletion or changing of
tasks, as defined in the Project Governance Plan and Scope Management and Change Control Plan
sections of this Project Management Playbook.
Changes to task status (i.e., percentage complete), durations and resources are addressed by the update
process.
The schedule task/activity update process for One Washington projects will strictly follow the update parameters
defined in the table below:
% Complete Description
0% Task has not started
20% Task is started and there is documented progress
40% Task is well underway with documented progress
60% Task is more than half complete and remaining work is well understood
80% Task is close to complete and remaining work is well understood
100% Task is complete
The six (6) update options in the table above are the only updates that will be used in updating the One
Washington Phase 1A project schedule.
Publish Assignments – let team members know their tasks for the week
Track Progress – each accountable/responsible Team Lead will provide the PMO their respective task
updates by 12 noon PT every Friday, following the progress options defined in the previous table:
o Task update options are: 0%, 20%, 40%, 60%, 80% or 100% Complete
Analyze Performance – the project manager and PMO Manager will leverage MS Project capabilities to
review the project schedule after the track progress activity is complete. This analysis will consider:
o Critical Path
o Late/slipping Tasks
o Deliverable/Activity/Milestone Completion Rate
o Actuals versus scheduled work
Re-plan – the project manager and PMO Manager will review the latest project schedule in MS Project
after incorporating progress tracking updates, as well as any other date changes to in-inflight or
upcoming tasks.
o This review will evaluate currently planned vs. baseline dates for milestones to determine if
actual progress is impacting critical dates
o If issues are identified, the project manager and PMO Manager will revise the project schedule
(e.g., add lag, adjust assignments, augment resources, etc.) to bring the schedule back on track
o Significant delinquencies and/or correction actions impacting the 1A critical path will need to be
escalated to the ESC
The project manager and PMO Manager also need to adjust the project schedule during re-planning to
implement any approved change requests for the project received that week.
In preparation for the weekly status report, any concerns or issues about late/slipping tasks and impacts on the
critical path will be discussed between the Deloitte Project Manager and PMO Manager, and corresponding
corrective actions will be identified. The updated project schedule from last week will be archived; and the
revised project schedule for the upcoming week will be published.
When reporting schedule progress, the project manager responsible for the project schedule will set the status
date within MS Project. Please see the Microsoft article: Set the status date for project reporting.
The PMO maintains the official version of all project schedules within the One Washington
program SharePoint repository, as part of its configuration control to ensure proper records
management.
The PMO will determine the appropriate and logical naming convention for the project schedules, including
version control and backups.
Records Retention
The One Washington program will follow state laws and OFM record management policy 1.09 for all records
retention. For more information about records retention and the OFM records coordinator, please see this OFM
website for retention RCW/WACs, schedules, policies, forms, and coordinators.
Chapter 42.56 RCW requires that state and local agencies to disclose any public record upon request, unless the
record falls within certain specified exemptions.
Clear, timely and concise communications help the One Washington program build credibility. The project
schedules and Master Project Plan serve as strategic documents used to guide the program and stay on target.
Project schedules with the appropriate level of detail will aid in effective communications and minimize delays by
identifying and addressing delinquencies in project schedule progress on a weekly basis.
The One Washington program will continue to maintain transparency, and the Master Project Plan is one of the
key ways the program will communicate with stakeholders.
4.7.1 Reporting
The PMO is responsible for creating multiple reports based on the One Washington Master Project Plan and
project schedule. Some examples of weekly reports include:
Timeline Updates
Late Tasks Report
Upcoming Tasks Report
Milestone Report
Please see the Project Status, Internal Communications, and Meeting Management section of this Playbook for
more details on the templates and processes that will be used to create regular status reports for the One
Washington program.
4.7.1.1 Timelines
The One Washington program timelines are used to show progress in different workstreams based on updates
derived from their related project schedules.
Late Tasks: The late tasks report is based on the pre-defined MS Project formula for filtering on late
tasks. The report lists all tasks that started or finished later than their scheduled start and finish dates
and are not progressing as planned.
Upcoming Tasks: The upcoming tasks report is based on the predefined MS Project report. This report
shows the work that has been done in the current week, the status of any remaining tasks that were
due, and what tasks are starting in the next week.
Milestones: The milestone report looks at past due milestones and milestones that are coming within
the next month.
The One Washington program does not currently use, and does not intend to use, earned
value management.
Please see the Project Status, Internal Communications and Meeting Management section of this Playbook for
more details on how One Washington status reports will be produced and distributed.
This table below describes what metrics will be reported on a monthly basis for inclusion into the monthly PMO
status report:
5.1 Introduction
This One Washington project cost management plan includes the processes involved in planning, estimating,
budgeting, financing, funding, managing and controlling costs so the project is able finish within the approved
budget. A glossary of key cost management terms is provided at the end of this Playbook section for reference.
The overall success of the One Washington program depends on effective cost management, as cost will be a
primary determining factor for the success or failure of the overall ERP implementation.
5.2 Purpose
The purpose of the cost management plan is to:
The table below shows the current schedule of past, present, and future biennial funding.
Table 18. One Washington Budget and Cost Management Stakeholders Roles and Responsibilities
Roles Responsibilities
One Washington Budget Develop, oversee and report on budget
Manager Provide budgeted cost and actual spend figures upon request
Review and code invoices after they have been
reviewed/approved by the appropriate contract manager
Send invoices and related documentation to the OFM Finance
team for payment processing
Complete necessary allotments/journal vouchers and other
finance-related activities for the program
Provide oversight for any One Washington funding pools
Serve as OCIO technology budget point-of-contact
Develop and maintain all One Washington technology budgets
Provide input for all One Washington investment plans
One Washington Budget Help manage funding/reporting for the Agency OCM pool and One
Analysts Washington technology pool
(If funded) Conduct bill analysis-during legislative sessions, review bills that
may impact One Washington and identify/quantify any impacts
One Washington Business Support the Budget Manager in developing the budget, and
Operations Manager oversee the change control and deliverable review processes
Work with appropriate resource managers and HR representatives
for program staffing
One Washington Program Verifies that deliverables are complete before an invoice is
Director approved
One Washington Approves changes, from the currently approved technology
Executive Director budget, to the finally submitted budget
One Washington Approves all budget changes of more than 10% of project total,
Executive Sponsor phase total, biennium total, FY total, gate total
One Washington Project Oversees the development and quality of for the deliverables
Management Office within the technology budget
OFM Finance Team Executes, or assists with finance activities: e.g., vendor payment
processing, official contract payment logs and financial records
retention, allotments, journal vouchers
OFM Budget Office Provide assistance with budget request development
Roles Responsibilities
Helps with OCIO-Gated Funding process and legislative staff
engagements
Office of the Chief Oversees the Gated Funding process that One Washington must
Information Officer follow
One Washington Contract Review contractor invoices by the appropriate state staff,
Managers managing the contract to ensure that: the amounts are correct
(per the contract and budget); the appropriate level of detail is
represented; and the work was completed to the State’s
satisfaction prior to being sent to the budget manager and
business operations manager
One Washington Approves all budget changes of more than 10% of project total,
Executive Steering phase total, biennium total, FY total, gate total
Committee
One Washington Business Approves all budget changes of more than 5% of project total,
Transformation Board phase total, biennium total, FY total, gate total
Qualified personnel: One Washington will leverage experienced financial staff, who are well versed in
both state and industry standard best practices. The program will include a dedicated budget manager
for managing the project budget and expenditures.
Deliverables/milestone-based contracts: Vendor contracts are either (1) fixed price, or (2) hourly rate,
with a “not to exceed” amount with deliverables/milestones. Vendor payments only occur when a
deliverable/milestone is accepted by the State. Payments are commensurate with deliverable/milestone
progress, regardless of the level of effort expended by the vendor.
Regular reporting of budget against actuals: One of the prime responsibilities of the dedicated budget
manager is to produce monthly budget status reports, including financial status, showing actual and
projected expenditures against budget amounts through the reporting period (typically by fiscal year).
The monthly reports cover all project costs, including various contracts and State costs. The report will
also provide a projection of anticipated expenditures including contract impacts.
Formal invoice process: All vendor invoices are reviewed by appropriate State staff managing the
contract to ensure amounts are correct (per the contract), the appropriate level of detail is represented,
and the work was completed to the State’s satisfaction prior to being sent to the budget manager. See
the Vendor Management Plan for more information regarding the vendor invoicing process steps.
1. Resource planning: This process begins with an approved One Washington scope and timeline used to
understand the components and budgeted resources needed to ensure One Washington is successful in
Any potential changes (scope, schedule, or budget) to an approved technology budget will be discussed with the
budget manager prior to those changes being implemented in order to: quantify impact(s) to the One
Washington budget, identify any needed changes to the technology budget(s) and review any changes with the
executive director and/or appropriate governing body.
Examples-
Staffing-any changes to program staffing including: new positions, the timing of hiring, annual salary, etc.
The detailed instructions for submitting a decision package are presented in the OFM budget instructions. During
the development of the OFM budget instructions, the One Washington program will collaborate closely with
OFM Budget for the inclusion of any One Washington-specific instructions.
Once the OFM budget instructions are posted, the One Washington budget manager will coordinate with the
leadership team to identify all components needed for the upcoming funding request and cost estimates,
applying an iterative approach to obtain the information needed for the funding request and all related
projected costs. For example, each component of the funding request will include:
A high-quality narrative description, plus any tables, charts, timelines, or other graphics that can assist
with the justification are strongly encouraged
Detailed assumptions and calculations that support the proposed expenditures
A supplemental budget is an opportunity for One Washington to request changes to the original biennial budget
appropriations. Generally, a supplemental budget represents mid-course corrections to the two-year spending
plans.
2
See A Guide to the Washington State Budget Process
Analysis Excel workbook to support detail calculations and summary information of each item of the
program’s request
OFM staffing model for calculating full-time equivalent (FTE) costs by object
Base funding explanation that identifies the carry-forward funding available for the upcoming biennium,
and the plan for how these funds will be allocated to existing State staff and vendor contracts.
The final approving authority of any One Washington funding request will be the One Washington Program’s
executive sponsor, via the program executive director.
5.6.6 IT Addendum
As outlined within the OFM budget instructions, all DPs with IT costs must include a completed IT addendum.
Therefore, One Washington will be required to submit an IT addendum and a fiscal estimate workbook with any
funding request. The OCIO reviews agency DPs each budget cycle to assess how agency IT requests are aligned
with the Washington State Enterprise Technology Strategy and posts a prioritization ranking to their website
5.6.7 DP Submission
After all reviews and approvals are complete, the decision package and supporting documents are officially
submitted to OFM finance for uploading into the agency budget system.
Work with the assigned OFM budget assistant to prepare for the legislative session
Be responsible for all fiscal details and overall quality of the proposal, including the detailed assumptions
and calculations
Serve as the point of contact for the DP
Review the DP and supporting documentation with legislative fiscal staff, providing the opportunity to
answer legislative members’ questions
The One Washington enterprise business consultant will be responsible for coordinating and integrating the
narrative portion of the DP, including the strategic and performance outcomes
One Washington funding requests and supporting documentation can be viewed externally through a public
repository after the official submission.
After a biennial or supplemental budget has been approved, the budget manager works with OFM budget to
identify the details of the program’s approved funding, including timing (biennial or fiscal year), provisos, etc.
The budget manager compiles potential budget options to review and discuss with One Washington’s leadership.
Depending on the level of funding received, leadership may need to make decisions related to scope, schedule,
staffing and vendor contracts. Depending on the size of the impact appropriated funding has on the scope
and/or schedule, leadership may make decisions internally or use the program’s governance structure.
After One Washington leadership and/or the appropriate governing body makes any necessary budget-impacting
decisions, the budget manager will revise the budget appropriately. At the next OCIO gate, the budget manager
will include these budget updates in technology budget revisions. This budget along with the related, approved
technology budget are used as the program’s cost baseline.
The table below summarizes the One Washington status reports produced on a monthly and quarterly basis that
include budget and cost management status information:
The report, along with the budget manager’s narrative, are provided to the executive director for review and
discussed with the leadership team. The executive director and/or leadership team will identify any areas of
concern that need to be addressed and take appropriate action
Using tools and templates provided by One Washington, these OCM SMEs will support agency-level readiness.
These resources will develop customized OCM plans specific to agencies. The resources will handle the
development, coordination, organization, facilitation and deployment of agency-specific OCM plans in order to
ensure successful adoption of the Workday ERP.
For more information, please refer to the Deloitte OCM Funding Pool Plan (OCM SOW 2 deliverable 7).
The One Washington technology pool is critical for providing agencies the skills, expertise and resources to
modify their systems and interface to the One Washington ERP. This pool will be administered by the One
Washington program, in collaboration with OCIO and OFM Budget, to ensure agencies only use these funds for
the work needed to effectively connect the agency systems to the new ERP and ensure data quality and integrity.
For detailed information on how One Washington plans to administer these funds, see the One Washington
Technology Pool Process Framework document.
• The technology budget must be submitted using the standard template and format. At each gate, the
project will apply to OCIO and OFM to receive funds for the next project stage.
• The investment plan is an OCIO required project document that summarizes the project description,
business benefits, scope, acquisition plan, schedule, project governance and management plan, budget,
dependencies and risks.
• The OCIO IT oversight may also be referred to as the IT Pool, which refers to the information technology
investment revolving account created in RCW 43.41.433, a state fund where allocated money is held
before it is allotted to specific IT projects.
Effective July 1, 2019, state agencies must use the technology budget Excel workbook template that is available
on the OCIO website. When submitting a technology budget, the One Washington program will align with the
approved standard naming convention format: OFM_One Washington_Phase_TechBudget_yyyymmdd
Per OCIO Policy 121: IT Investments – Approval and Oversight Policy and OCIO Policy 121 – Procedures, the One
Washington program is a Level 3 IT investment and considered a major IT project that is subject to OCIO
oversight.
Typically, OCIO oversight IT projects will receive 85% of their funding at the beginning of each gate with the
remaining 15% provided at the end of the gate after the gate and associated deliverables are certified. However,
in the 2020 Operating Budget—Supplemental (ESSB 6168), One Washington’s gate withhold percentage was
changed from 15% to 20%.
• Budgeted resources: Detailed outline of how the project intends to use its’ current funding, including
base funding, for the duration of the project. Includes staff, IT hardware, software, IT services,
professional contracted services and labor. These are typically for resources beyond an agency’s baseline
capability and/or capacity. Therefore, is excludes any in-kind resources.
Once the program receives the OCIO approval letter, the budget manager will coordinate with its’ OFM budget
assistant and OFM finance to allot the approved funding. After the funding has been allotted, the budget
manager will review the program’s expenditures for the applicable gate and make any necessary corrections,
including adjusting chart of accounts coding, via journal voucher and/or payroll forms, for expenditures incurred
during the applicable gate.
A non-material change to an existing posted, OCIO and OFM approved technology budget is used to make
technical corrections only. Corrections may include a change in project point of contact, updates to deliverable
completion dates, updates to target completion dates for upcoming deliverables, corrections to AFRS codes to
reflect costs, etc.
Washington State budgets are based on a two-year (biennial) state fiscal period. The Washington state biennium
runs from July 1 of an odd-numbered year to June 30 of the next odd-numbered year. A fiscal year is the State
12-month period that runs from July 1 through June 30 of the following year and is named for the calendar year
in which it ends. For example, the 2021-23 biennium includes both:
• Fiscal year 2022 that begins July 1, 2021 through June 30, 2022
• Fiscal year 2023 that begins July 1, 2022 through June 30, 2023
One Washington will also provide forecasts for maintenance and operations (M&O) costs. Annual M&O costs
are costs associated with the ongoing support of an IT investment after project closure and/or transition to
operations.
M&O costs are not typically reported within technology budgets, but the One Washington was directed to add
this information as part of the gated funding process.
Contracted Professional Services: the amounts that are planned/budgeted for contracted resources, regardless
of how they are acquired (e.g., request for proposals, direct buy, agency convenience contract, inter-agency
agreement); applies to all planned consulting.
Non-state Employee Staffing Costs: contractor or external labor needed to complete the scope of the project.
Software Licenses and Subscriptions: the amounts expended for purchased software or licenses of commercially
available software with a useful life of one year or less, including upgrades and/or maintenance agreements.
Software licensing includes, but is not limited to, the right to use the software, support for the software and
upgrades.
State Employee Staffing Costs: the full cost to employee state staff. Includes salary, benefits, and other costs
associated with an employee (travel, supplies, indirect costs-IT, HR and Accounting support).
Funding Source(s): the different funds the agency is drawing from to provide financial support for the project,
referring to chart of accounts coding used to identify the source of allocated project funds (e.g., general fund
state, general fund federal, statewide IT system maintenance). This information is available within the Fund
Reference Manual on the OFM website.
Object: a state accounting classification used to categorize expenditures. Objects of expenditure in the State
operating and capital budgets are:
Object C: Contracts
Object E: Goods and services
Object G: Travel
Object J : Equipment
Object T: Intra-agency reimbursements
Sub-object: a refined breakdown of Object of expenditures relating to particular items or item categories.
Section 75.70 of the Statewide Accounting Administrative Manual (SAAM) is the source for object and sub-object
codes.
Carry-forward Level (CFL): a reference point created by calculating the biennialized cost of decisions already
recognized in appropriations by the Legislature.
Maintenance Level (ML): reflects the cost of mandatory caseload, enrollment, inflation and other legally
unavoidable costs not contemplated in the current budget. Expenditure adjustments may be positive or
negative, depending on expected experience in the ensuing biennium.
Policy Level (PL): incremental expenditure changes that do not fall under the definitions of CFL or ML are
considered PL changes. These changes may represent revised strategies or substantial differences in program
direction, and can include proposed program reductions. Each significant change to current policy must be
justified in a DP.
Contingency: events that could affect the execution of the project and impact success, may be accounted for
with a contingency reserve (money allocated in cost baseline for known risks with mitigation strategies).
Cost Aggregation: summarizes lower-level cost estimates associated with various components of the project.
Cost Variance (CV): the amount of budget deficit or surplus at a given point in time, expressed as the difference
between budgeted and actual costs.
Forecast: estimate or prediction of conditions/events in project future, based on information and knowledge
available at the time of the forecast.
Funding Requirements: forecasts project costs to be paid, derived from cost baseline for total or periodic
requirements, including projected expenditures plus anticipated liabilities.
OFM Budget Terms: a glossary of terms related to the OFM Budget that can be found on the OFM website.
Technology Budget Glossary of Terms: a glossary of terms related to Technology Budgets can be found on the
OCIO website. This plan uses standard Washington state enterprise and basic project management terminology.
Threshold: pre-determined value of a measurable variable that represents a limit that will require certain actions
to be taken if it is reached.
(1) Releases: Currently four (4) entries for the One Washington Project:
(2) Teams: Currently eleven (11) entries for the One Washington Project:
(4) Discipline/Threads (i.e., Workstreams): Currently eight (8) entries for the One Washington Project:
All four of these custom fields are optional (not mandatory) per PMC requirements when logging a request/RAID
item. However, selecting a value for each of these custom fields when logging and managing tickets will enable
the One Washington PMO and project leadership to sort and/or filter RAID tickets for reporting in many ways
that would NOT be available otherwise.
Custom One Washington fields in PMC for Release, Team, Phase (Stage) and
Discipline/Threads (Workstreams) are mandatory when creating and managing PMC RAID
tickets.
Roles Responsibilities
All One Washington Identify and log One Washington RAID items into PMC as they are
project team members encountered throughout the project lifecycle
Work with the RAID owners when input is needed to help address
and/or manage a RAID item to closure
Properly manage RAID items assigned to closure in a timely,
appropriate manner, keeping the ticket record for each RAID item
up-to-date and complete
One Washington PMO Continuously monitor and ensure that all appropriate RAID items
are properly logged in PMC as accurately and completely as
possible, depending upon its workflow status and requirements at
each workflow stage
Convene workgroups with the appropriate stakeholders and/or
SMEs to brainstorm resolution steps or risk response strategies and
response plans, as appropriate
Prepare weekly RAID Dashboards for status reporting and
meetings, highlighting delinquent and/or critical priority tickets
Plan and conduct regular reviews of high-priority RAID tickets
Follow Governance Plan guidelines and protocols to escalate
priority RAID items as appropriate
Monitor RAID items and confirm tickets that should be closed or
cancelled as appropriate
Roles Responsibilities
RAID Ticket Owners Work with appropriate team members and the PMO to fully assess
assigned RAID tickets and their impacts, as well as resolution or
mitigation plans
Where appropriate, conduct a root cause analysis of an issue to
understand its source and help define an effective resolution
Analyze risks and their risk scores to determine to the right
response strategy (i.e., avoid, transfer, accept or mitigate) and
response plan
Actively manage all assigned RAID items on a weekly basis, and
keep their PMC information and status as up-to-date and complete
as possible
Provide timely responses to questions or other information
requests on assigned RAID items from other team members,
stakeholders, the PMO or Governance bodies
Inform the PMO when RAID items meet the criteria for escalation
(see the Governance section in this Playbook for more information)
Workstream/Team Leads Monitor and validate respective team RAID tickets
Be responsive and communicate team positions/views on RAID
tickets impacting respective workstream(s)
Work with assigned RAID owners to help assess impacts, causes,
resolutions, risk responses, or feasible decision options, as
appropriate
Assist in the coordination and execution of relevant risk plans if the
risks are realized
Inform the PMO when RAID items meet the criteria for escalation
(see the Governance section in this Playbook for more information)
Business Transformation Advise and provide recommendations for risk mitigations,
Board (BTB) response plans, and status to the program director,
program team leads, project managers, and PMO
Approve or reject RAID analysis and response or resolution
recommendations for all RAID items escalated to the BTB
Determine subject matter experts and gather needed
inputs from them, as required
Determine if and when a RAID item needs to be escalated
to the ESC, in accordance with the Governance Plan
guidelines and protocols
One Washington Program Ensure accountability of all roles within the RAID management process
Director Provide resources and support needed for the development and
implementation of the RAID management processes
Authorize the execution of risk response plans, as required
Escalate priority RAID items that cannot be controlled at the program
level to the appropriate governance body
Work within the governance structure to mitigate
enterprise-wide and external stakeholder risks, as needed
Roles Responsibilities
Executive Steering Advise and provide recommendations for escalated RAID items to the
Committee (ESC) program director, program team leads, project managers, and PMO
Approve or reject RAID analysis and response planning/resolution/decision
recommendations for all RAID items escalated to the ESC
Seek input from subject matter experts, as needed
Work with the executive sponsor to mitigate enterprise-wide or external
stakeholder risks and issues, as needed
Authorize contingencies and communicate actions, as needed
One Washington Advise and provide direction to the ESC and BTB, as required
Executive Director Approve or reject RAID analysis and response planning/resolution/decision
recommendations for all RAID items escalated to the executive sponsor
Seek input from subject matter experts, as needed
Work with the One Washington Executive Director to mitigate enterprise-
wide or external stakeholder risks and issues, as needed
Authorize contingencies and communicate actions, as needed
Project
Management
Plan
No
No
Risks Log
Legend
Inputs / Supporting
Task Outputs Step Output Procedure Decision
Risks are identified during weekly project status meetings, or the bi-weekly or special RAID meetings
organized by the project manager or PMO manager
As risks are identified, the following information will be captured:
Project
Assigned To (“risk owner”) – the project team member responsible to develop and implement the risk
response plan
Status – the status of the risk as it flows through the process (Risk status is assigned automatically within
PMC)
Priority – a subjective assignment of the significance of the risk used by the project manager for
prioritization and status reporting. The priority risk ratings for the project are as follows (Priority can be
used to further prioritize risks in cases where there are multiple “High” severity risks.):
o Critical— the risk response plan must be defined and executed immediately
o High— the risk response plan must be defined and executed as soon as possible
o Medium— the risk response plan can be developed any time before the next risk review meeting
o Low— a risk response plan is not required
Type – a means for categorizing risks (see subsequent section for type options and descriptions defined
in PMC)
Probability – the likelihood of the risk occurring
Impact – the overall impact if the risk does occur
Severity – probability times impact (automatically calculated - see subsequent section for details)
Short Description – a brief description of the risk
Due Date – sometimes referred to as the risk’s trigger date or timeline, this represents the forecasted
date when a risk may be realized or project events may change its probability and/or impact. This date
will be used by PMC to monitor whether the ticket is late, and it will show up in late ticket (called
requests) reports once the current date is > the due date defined for the risk ticket
Long Description – a more detailed description of the risk
Open Issue on Close? – PMC has an option for the workflow to automatically prompt the user to create a
new issue request/ticket when a risk is realized, and will transfer over all relevant information from the
risk ticket to the new issue ticket. The user will have the option of bypassing this new issue trigger (if it’s
no longer valid) when the risk is realized, so the ticket can just be closed and the approved response plan
will be implemented
The objective of the risk analysis is to develop more specific information to aid in decision-making during the
response planning or resolution process. The analysis of risks and issues is a crucial step for determining how
they might impact the program.
The risk owner/assignee may identify additional business and technical subject matter experts to become
workgroup members and set a due date to complete the response plan. An owner may re-assign the risk
probability and impact ratings based upon inputs from the business and technical members of the workgroup,
thereby changing the risk severity score and potentially the risk response plan required.
1) Reduction – identifies ways to minimize or eliminate project risks. The risk owner is overall
responsible for developing options and determining actions to lessen impacts or threats to the
program. Risk reduction strategies include:
Avoid – involves changing the project plan to eliminate the threat posed by the adverse
risk.
Transfer – requires shifting the negative impact of a threat along with the ownership of the
response to a third party. Transferring the risk simply gives another party responsibility for
its management: e.g., insurance is a good example of transferring risk to the insurance
company…for a price.
Mitigate – reduce the probability and/or impact of a risk event to a more acceptable level.
2) Acceptance – risks can be accepted as is or after mitigation steps have been taken. Risks are
typically accepted when a mitigation plan has not eliminated the risk, and/or the cost/benefit of
eliminating the risk is not acceptable.
Contingency reserves may be established for risks, including amounts of time, money or
other resources necessary to respond to a realized risk.
Accepted risks are monitored and if realized, outcomes will be addressed by the project
team.
3) Contingency planning: defines a back-up or “Plan B” for a realized risk if the approved response
plan does not work or reduce the impact as much as expected.
Once the risk owner completes his/her risk assessment and proposed risk response strategy and response plan,
the PMO will determine who needs to review and approve the response plan, and arrange a meeting to review
if/when required: e.g., the risk’s severity score and/or priority is “Critical” or “High” and the appropriate
Governance body will need to review and finalize the risk strategy, response plan, and contingency (i.e.,
“backup”) plan for the risk.
The PMO will also work with the risk owner, when needed, to convene a workgroup to explore mitigation
strategies and recommendations. The PMO is responsible for working with the risk owner and other
stakeholders to ensure that the risk assessment is complete and well documented.
Risks at this workflow stage will be designated as “In Progress” status in PMC during this process. When
necessary, the PMO manager will escalate to the appropriate governance level for review and analysis, per the
process defined in the Governance Plan section this Project Management Playbook.
Determine the appropriate new risk owner(s) if the risk assignment needs to change
Where necessary, update the risk score, assessment, response, or other details
For realized risks, follow the risk realization steps included in the approved risk response plan (where
applicable), and log a new issue in PMC for the realized risk, where appropriate.
o As mentioned above, this create issue option can be bypassed if it is not relevant
Once the issue record is created, cross-reference the new Issue # in the old risk record before closing the
risk record.
If the risk has not been realized, continue monitoring it throughout the project, for as long as the risk is
active or “In Progress.”
The determination of severity will be estimated by the risk creator and analyzed/verified by the risk owner, who
may need to bring in relevant subject matter experts or business owners to help with the analysis and
assessment. Formal, properly vetted risk response plans are required for risks determined to be High severity,
and recommended for most Medium severity risks. Other risks will be monitored and reviewed, but will not
necessarily require a formal risk response plans, particularly if the risk response strategy is “Accept” the risk.
Proper risk response planning and monitoring will be done by the PMO.
If the risk or issue solution or remediation has an impact to project scope, budget, quality, or schedule, a change
request may be generated. Please refer to the Scope Management and Change Control Plan section for the
change request process. Risks with high and medium severity should also have a contingency plan as a back-up
to the risk response plan.
Impact Probability
1-Low 2-Low/Medium 3-Medium 4-Medium/High 5-High
5-High Low (5) Medium (10) High (15) High (20) High (25)
4-Medium/High Low (4) Medium (8) Medium (12) High (16) High (20)
3-Medium Low (3) Medium (6) Medium (9) Medium (12) High (15)
2-Low/Medium Low (2) Low (4) Medium (6) Medium (8) Medium (10)
1-Low Low (1) Low (2) Low (3) Low (4) Low (5)
Score Severity
1-5 Low
6-12 Medium
13-25 High
A realized risk will: (1) Initiate the approved response plan defined for the risk (where applicable); and (2) may
create a new issue in PMC, to follow the issue management process described in a subsequent section. If the
realized risk does not become an issue, it can be closed after its response and/or contingency plan is fully
implemented and completed.
The following risk measurements are default risk status metrics offered in the standard PMC risk manager
dashboard and will be used to monitor and control One Washington project risks:
Risks by status
Risks by priority and status
Active risks by priority
Active risk aging by priority
The next section further delineates when an action item should be logged and tracked in PMC.
Project
Management
Plan
No
Legend
Inputs / Supporting
Task Outputs Step Output Procedure Decision
Critical - the action item must be addressed immediately in order to protect the project's objectives
High - the action item must be addressed as soon as possible in order to prevent significant negative
impacts to the project (for example, cost overruns or milestone delays)
Medium - the action item will be addressed, monitored, and controlled following regular project action
item management processes
Low - the action item will be addressed as cost and schedule permits
These priorities and descriptions are provided in PMC as online Help for action items.
Project
Management
Plan
4. Manage
3. Change
1. Create Issue 2. Resolve Issue Yes Change
Request?
Requests
No
5. Close Issue
Issues Log
Legend
Inputs / Supporting
Task Outputs Step Output Procedure Decision
The person identifying and logging the issue needs to provide as much information as possible on the new issue.
Required fields include:
Project
Assigned To
Priority
Type
Description
Detailed Description
The issue status tracks the status of an issue as it flows through the process. The PMO will review and validate
“New” issue status records from the project team, canceling any new issue entries that are not valid. The PMO
will also confirm or re-assign valid issues to the appropriate project team member(s) (issue owners) for detailed
analysis and resolution planning.
Priority – the priority issue ratings for the project are as follows:
o Critical – the issue is jeopardizing overall project objectives and must be addressed immediately
o High – the issue is negatively impacting the project significantly (for example, cost overruns or
milestone delays) and must be addressed as soon as possible
o Medium – the issue is negatively impacting the project and should be addressed, monitored, and
controlled using regular project issue management processes
o Low – the issue has minimal impact and should be addressed as cost and schedule permits
Type – Issue types are defined in a table below
Project areas and stakeholders impacted: Release, Team, Phase, Thread, Stakeholder(s)
Resolution, including:
o Escalation Level
o Resolution
o Whether a change request (CR) needs to be created to close the issue
o Other closure criteria
For “Critical” or “High” priority issues, the PMO managers should review and approve the proposed issue
resolution for each.
If an issue’s resolution actions require work outside the defined scope for the project or changes to
signed-off project documents, the issue owner needs to create a change request to resolve the issue.
No work on the issue resolution steps can be performed until the associated change request (CR) for the
issue is approved by the PMO and appropriate governance body.
Issue CRs that are not approved will need to be set to “Closed” or “Cancelled” status, as appropriate.
The appropriate stakeholder(s) identified for the issue should help confirm the issue resolution.
For issues where resolution is confirmed, click on the “Resolve Issue” button in PMC to set the issue to
“closed” status.
Issues where the resolution results were not confirmed will remain in “In Progress” status until they can
be successfully confirmed.
Issues by status
Issues by priority and status
Active issues by priority
Active issue aging by priority
Managing project decisions includes identifying, documenting, prioritizing, assigning, and tracking the results of
decisions throughout the phases of the project. This section documents the process and tools the project will use
to log and manage day-to-day decisions, as well as formal, high-impact project decisions.
Day-to-day decisions are decisions that the PMO deems necessary to document and track for future reference.
Formal decisions are decisions that meet the criteria defined below and require a more structured process for
analyzing alternatives for potential solutions. The decision criteria for making a formal decision versus a day-to-
day decision must be understood by all One Washington project team members.
Project
Management
Plan
No
No
6. Proposed 7. Communicate
4. Assess 5. Make
Recommendation Yes and Implement
Alternatives Recommendations Approved ? Decision
Decisions Log
Legend
Inputs / Supporting
Task Outputs Step Output Procedure Decision
The person identifying and logging the decision needs to provide as much information as possible on the new
decision. Required fields include:
Project
Assigned To
Priority
Type
Description
Detailed Description
The decision tracks the status of a decision as it flows through the process. The PMO will review and validate
“New” decision status records from the project team, canceling any new decision entries that are not valid. The
PMO will also confirm or re-assign valid decisions to the appropriate project team member(s) (decision owners)
for detailed analysis and decision recommendations.
The assigned team member(s) will confirm or define the following fields for a decision record after completing
the necessary due diligence and analysis on the decision:
Priority – the priority decision ratings for the project are as follows:
o Critical – The decision has overall project outcome ramifications and must be addressed
immediately.
o High – The decision has significant project ramifications (for example, impacts project budget,
quality, or milestones) and must be addressed as soon as possible.
o Medium – The decision has project ramifications and should be addressed, monitored, and
controlled using regular project decision management processes.
o Low – The decision will have minimal impact and can be addressed as cost and schedule permits.
Type – Decision types are defined in a table below
Project areas and stakeholders impacted: Release, Team, Phase, Thread, Stakeholder(s)
Escalation level
The formal decision-making process allows the project team to analyze possible critical decisions using a formal
evaluation process that evaluates identified alternatives against established criteria. The formal decision process
results in a recommended solution and rationale that are provided to key stakeholders for review and approval
before it is considered final.
Making decisions using qualitative and quantitative feedback based on established solution criteria at
the appropriate level of authority
Driving timely decision-making
Documenting and communicating formal decisions made
Preventing formal decisions from being revisited
The table below lists some examples of the types of project decisions where the formal decision-making process
should be used, and includes the approval authorities for each decision type. In addition to these types of
decisions, the project should consider using the formal decision process in scenarios where the outcome may
significantly impact the ability of the project to meet its commitments or established objectives.
The Formal Decision Alternative Evaluation Tool allows decision reviewers a structured template to rate, score
and compare decision alternatives against defined criteria, thereby enabling both qualitative and quantitative
analysis. The tool can be used to help generate a recommended solution with backing rationale to present to key
stakeholders for final review and approval of the recommended decision.
For “Critical” or “High” priority decisions, the PMO managers should review and approve the proposed decision
recommendation and rationale, as well as the decision approver, before taking the decision to the appropriate
Governance body.
The Prioritization Criteria Framework shown below is a helpful way to organize and categorize project decisions
against key program criteria highlighting the mission and goals of the One Washington initiative: high impact
toward initiative objectives with low/reasonable difficulty in implementing.
After each RAID review meeting, the PMO has the following responsibilities:
Term Definition
Risk An uncertain event or condition that, if occurs, has a .negative effect on one or more of the
program’s objectives.
Action Item An assignment to do some work or address a question that requires cross-workstream/team
input and be accomplished in eight hours or less total effort.
Issue An event or situation that has occurred, was not planned, and requires action. Issues may also
be referenced as problems, gaps, or conflicts. Additionally, a risk that is realized can also
become an issue.
Decision A project situation where a team lead or management has two or more options when
determining a project approach or choice that will impact future work and/or outcomes for
the project.
Issue priority The importance of the issue severity, ranked low, medium or high.
Risk response The process of developing strategic options, and determining actions, to reduce threats to the
strategy project's objectives. Risk response strategies can include: (1) accept (2) avoid (3) mitigate and
(4) transfer.
Risk impact Assesses the impact on the program should the risk be realized.
Risk timeframe Defines when risk is most likely to occur and is used to determine when the risk management
activities must begin.
Risk register A critical document that contains information about identified risks, issues, analysis and
evaluations of risks severity, the probability and the possible mitigation options.
Risk statement Approach to distinguish the risk from its cause(s) and effect(s), by utilizing a three-part
statement in the form: “As a result of [CAUSE], [RISK] may occur, which would lead to
[EFFECT].”
7.1 Introduction
This section describes the process for handling changes to any One Washington project baseline, defined by the
approved scope, schedule, and cost (i.e., the “triple constraint”). The One Washington change control process is
defined for how the project will capture, evaluate and make decisions related to any requested changes.
A baseline is the approved version of a work product that can be changed only through formal change
control procedures.
Scope: the approved scope document describes the products, services, and results to be provided by the
One Washington program
Schedule: the master project plan is the representation of the plan for executing all One Washington
program releases and activities, including durations, dependencies, and milestones
Budget: the current approved One Washington technology budget, as well as the Cost Management
section of this Playbook, outlines the One Washington spend plan for authorized expenditures and cost
allocations
A change to any one of the above baselined components may necessitate a change to the others. The change
control process, therefore, must include an assessment of all three baseline planning artifacts. This assessment is
conducted as a part of the impact analysis completed once a change request (CR) is received by the One
Washington PMO. In addition, other dependencies and impacts should always be considered during this
assessment of a submitted CR.
The purpose of this document is to define the One Washington standard process for:
Roles Responsibilities
Executive Sponsor Provides approval or rejection of all escalated CRs from the ESC
Executive Steering Reviews CRs and validates viability, estimates, and evaluations
Committee (ESC)
Works with PMO to determine whether CR should be approved, deferred,
rejected, or escalated to Executive Sponsor
Business Transformation Reviews CRs and validates viability, estimates, and evaluations
Board (BTB)
Works with PMO to determine whether CR should be approved, deferred,
rejected, or escalated to ESC; and if so, provides CR recommendation
Advisory Committees Review CRs and determine viability
Provide SMEs to perform impact analysis of the CR in collaboration with the
PMO
Verify and validate business requirements, perform estimation, including size,
schedule, and cost (in term of labor and other resources), and provide
recommendations
Works with PMO to determine whether CR should be approved, deferred,
rejected, or escalated to BTB; and if so, provides CR recommendation
Project Management Reviews CRs and determines viability, estimates, and evaluations
Office (PMO)
Determines if CR should be approved, deferred, rejected, or whether CR
needs to be escalated
Coordinates CR decisions and oversees the analysis, facilitating coordination
of additional resources as needed to complete the CR
Reviews all open CRs, updates status, facilitates the approval process, and
ensures that CRs are documented properly in the CR log
Determines how the approved changes have impacted the baselines (re-
baselining is generally done after a major gate, budgeting or other major
program event)
Coordinates or manages the completion of action items necessary to
incorporate changes into the program, including monitoring the approved CRs
activities and reporting status until all work to implement the change is
completed
Coordinates with other stakeholders, as necessary
Vendors For vendor-initiated CRs:
Develop justification for change and perform impact analysis of the CR
Complete estimations, including size, schedule and cost (in terms of labor and
other resources)
Confirms requirement verifications
Reviews CR proposal and provide recommendation to contract manager (refer
to Vendor Management Plan )
Roles Responsibilities
Stakeholders As assigned:
Work collaboratively to validate CR requirements
Verify business requirements associated with CR
Perform impact analysis of the CR, including assistance in development of
impact analysis and CR overview
Develop justification for change
Perform estimation, including size, schedule and cost (in terms of labor and
other resources)
Recommend CR decision (i.e., approve, reject or defer) with rationale details
Any change to an approved scope, schedule, or budget baseline requires a change request (CR). The
PMO encourages that all change requests go through this process, even if they have zero or minimal
impact to scope, schedule, or budget. This provides transparency and helps facilitate communication.
Changes are normal part of project delivery.
The One Washington PMO will handle all logistics and tracking of CRs, including the change request form
and change control log. All CRs, their status and any associated documentation will be maintained by the
PMO in the Change Request Log on SharePoint: Change Request Log
All CRs will be assessed by the PMO to determine the appropriate authorities to approve the request.
The approach is to enable decision-making on CRs at the lowest level possible, while recognizing that a
CR may need to be escalated to the ESC for final decision.
An approved change request that impacts the work of any contractor may result in an amendment to a
contract. The contract amendment process is described in the Vendor Management Plan.
Amendments to contracts usually result in impacts to the budget and it is therefore critical that contract
managers follow both the change management processes outlined in this section of the Playbook, as
well as the processes outlined in the vendor management plan.
Documents >
Documents >
The assigned team member, with assistance as described above, will proceed with completing an impact
analysis, to include schedule and cost estimation impacts. Along with the impact analysis, the individuals will
determine what any high-level actions needed to incorporate the change into the program. This may include
changes to the schedule, budget documents, contract amendments, charter, resource lists, etc.
The PMO will update the status of the CR to ‘prepared’ in the change log when the CR is ready to proceed to step
7.4.3. Perform initial CR review.
A CR that has been deferred and reached its re-review date reenters the process starting at this step.
During the initial review of the CR, the governance body will determine whether the CR is valid and determine
whether the CR needs to be escalated to the ESC and/or the executive sponsor.
If determined not to be valid, the status is updated to ‘rejected’ and the reason for rejection is documented on
the form (step 7.4.5. Record change request outcome and communicate results) and the CR status is ‘closed’
within the change log.
CRs requiring additional information and/or analysis following the initial development of the CR impact analysis
and overview will be re-routed back to the previous step for more refined CR analysis and/or impact analysis.
Decision Action
Deferred For valid changes, the reviewing governance body first determines whether or not
to defer the decision on the CR. If they determine it should be deferred, the PMO
will perform the following:
o Update the status to ‘deferred’ within the change log
o Document the date for which the PMO will reconsider the CR and describe
the reason for the deferral is documented on the form.
The governance body formalizes the decision. The CR is then sent back to Step 2 of
the CR process: Prepare CR Overview and Impact Analysis; when the deferral date is
reached, the CR owner updates the CR with current information in preparation for
PMO review
Escalated If the CR is escalated by the reviewing governance body, it will be sent back to Step
2 to prepare the CR for the next escalation governance body review, and the PMO
will determine how to proceed
The PMO sets the CR status to ‘reviewed by’ in the change log and completes the
process by communicating the results to the change requester
Accepted The CR is approved by the reviewing governance body and the PMO will develop a
recommended action plan to implement the CR
The PMO sets the CR status to ‘approved’ in the change log and it then goes to Step
6: Create Action Plan to Implement Approved Change
Rejected The CR is rejected by the reviewing governance body, and they formalize the
decision through proper documentation
The PMO sets the CR status to ‘rejected’ in the change log and completes the
process by communicating the results to the change requester
If the requesting party disagrees with a CR decision, they may appeal the decision or create a new CR that
provides more information in support of the requested change.
For approved CRs, the PMO will coordinate the completion of all necessary action items to incorporate the
approved changes into the program. These action items may include modifications to the program schedule,
budget, and/or charter and could include amending vendor contracts. Upon approval of the CR action plan by
the PMO, the change control process will conclude.
ID
Date Logged
Status
Originator
Date Submitted
Change Description
Reason for Change
Date Required
Summary of Impacts
Approval Authority (Governance Level Required)
Decision
Date of Decision
Notes
Documents >
Decision Action
New A new CR has been opened and is currently under review
Reviewed by A CR that has been through the initial governance review, and was not
rejected or deferred
Analyzed A CR that has been analyzed for potential changes to scope, schedule, staffing,
costs, quality and/or risks awaiting review and decision by the reviewing
governance party
Escalated A CR that has been escalated to the next governance tier for action
The PMO Manager, in conjunction with the project manager and appropriate Team Lead(s) will determine the
status of scope (i.e., red, yellow, or green) in weekly project status reports, based on the quantity and impact of
the open CRs in the Change Control Log, as part of weekly status report preparation and analysis. When the
total open and approved CRs amount to more than 5% of the baseline scope, scope status will typically be in
yellow status, and possibly red when it surpasses 7.5% and/or starts impacting schedule milestones and the
critical path.
As One Washington SaaS requirements are reviewed, validated and prioritized, they will be mapped to the
solution during Process Design and Discovery workshops conducted with the appropriate SMEs and business
owners in order to define User Personas and Moments that Matter for the end-users of the new solution. New
requirements may also be identified and documented that cover the “out-of-the-box” functionality that One
Washington Workday solution end-users will enjoy as part of the Workday transformation.
As these design elements evolve into One Washington Process Maps and User Stories, the confirmed and
prioritized One Washington requirements will all be traced and referenced to appropriate User Stories,
establishing the traceability relationship that will continue throughout the rest of the project until the solution is
implemented.
The traceability relationships will remain important references for the deployed system during the Sustainment
Phase, allowing the support team to understand the scope and impact of any changes to the production solution
by tracing them through their associated test scenarios/cases to their respective User Story(ies) and
requirements.
The figure below summarizes the Workday Momentum lifecycle that will be used to design, configure, test, and
deploy the One Washington solution:
Roles Responsibilities
Facilitator Coordinates meeting setup / prep
Presents material during PDD workshops
Orchestrates PDD workshops
Engages One Washington SMEs to get their inputs and buy-in
Co-facilitator Supports presentation technology (monitors, presentation software, demos, white
boards, easels, etc.) during PDD workshops
Captures white board/easel contents digitally (taking pictures) at the end of each PDD
workshop
Scribe Documents meeting minutes
Documents proposed requirement edits, priorities, and clarifications
Documents action items
Documents parking lot items
Documents risks, issues, assumptions, decisions, and change requests that occur
during PDD workshops
Monitors PDD working session timing and agendas to keep workshops on track
Roles Responsibilities
State Identifies participants for PDD workshop prep, production and follow-up
Workstream Oversees content development needed for PDD workshops and reviews
Leads
The ownership of specific development areas will be shared by the State and Deloitte. Deloitte will be the
primary owner for the majority of the project scope. See sections 4.3 Responsibility Matrix: Configuration
Components and Design Updates, 7.2 Responsibility Matrix: Integration and Interface, 8.2. Responsibility Matrix:
Data Conversion, and 9.5.Responsibility Matrix: Reports, Dashboards and BIRT Development in the Statement of
Work.
Guidelines that will be followed as One Washington user stories are defined, configured, tested and integrated
into the Workday solution are listed below:
Confirm that all solution functional and technical requirements are properly documented and prioritized:
the prioritization and ranking of user stories early in the process will be a key success factor
Estimate the user story size (in story points) and implementation effort (in hours)
Document acceptance criteria (definition of done) for each user story
Update user stories as more information becomes available to accurately reflect the functional and
technical requirements for the project
Prioritize and sequence user stories; priorities may be adjusted as new information becomes available,
or new user stories emerge from configuration reviews
Once prioritized, allocate user stories into appropriate configuration cycles
Perform proper change control, as defined in Section 7 of the Project Management Playbook
Roles Responsibilities
Integration Lead Oversee the Workday integration process and confirm timely, incremental
deliveries
Responsible for the design, build, and unit testing of the interfaces connecting the
One Washington Workday solution
Communicate timeline and dependencies with the system owners and functional
team
Work with the Technical Architect Lead and Security Lead to design and deliver
an effective, secure solution
Manage the Workday software builds and integration management processes
Plan and manage the various test cycles, code migrations, and deployment
milestones defined in the project schedule
Roles Responsibilities
Workstream Direct design/configuration review meetings
Leads Manage the Workday configuration development staff who interact with the quality
and testing teams; manage the Workday solution build and configuration
management processes
Provide weekly status of development activities and accomplishments to the PMO
Validate key activities such as code review, requirements traceability and unit
testing
Validate that the configuration team adhered to configuration standards
Lead the development and functional teams to meet delivery dates, tracking
progress against the project schedule
Analyze the business requirements provided by the application team to confirm
functional requirements
Assist the reporting team in identifying report specifications and the configuration
of setup data required for report development and testing
Configuration Provide estimates for configuration of features and functionality
Team Configure and unit test Workday objects
Adhere to design and configuration standards
Conduct peer reviews
Participate in design/configuration review meetings
Establish configuration in Workday that will enable interfaces to work as expected
Maintain source code
Coordinate activities with other developers in preparing the task list for Check
Point/Quality Builds
Analyze/correct defects discovered during testing of the solution
Define and maintain traceability of detailed application design and configuration
artifacts
Define/maintain the solution detailed application design artifacts
State SMEs and Provide and confirm integration design requirements
Business Owners Assist with setup configuration and connectivity from the external systems which
will be integrated with Informatica/Workday
Ensure that the data is in the correct format, as defined in the functional
specifications
Ensure the proper availability of resources and systems during the various test
phases
Confirm requirements of the reports in the Imagine phase, and test them during
the Deliver phase
Contribute to sprint planning and execution for report development
Test and confirm reports for production readiness
Specific planning for 1A configuration, data conversion and integration work will begin once the brunt of the
Discovery and Design session work is complete and the primary Workday 1A User Stories are defined.
The technical team will define the authentication approach in the Solution Architecture deliverable and work
with the State to build and configure the appropriate identity and access management components that the
Workday solution will use for user access authentication.
Workday role-based security definitions will be created during Process Design and Discovery sessions, with
validation occurring during customer confirmation sessions, as well as in the testing phase. During integration
design, the security requirements will be identified and documented in the Integration Design deliverable.
Deloitte will support the State in defining and configuring security for the integrations being implemented by the
State.
One
Deloitte
Activity Milestone/Deliverable Washington
Responsibility
Responsibility
Complete Workday Deliverable: Project Team Workday Training Support Primary
Security training Plan and Training
Create Solution Deliverable: Solution Architecture Primary Support
Architecture
Create and define Deliverable: Configuration Security Primary Support
Configuration Security Framework
Framework
Develop mobile usage Deliverable: Mobile Usage Deployment Primary Support
deployment Requirements
requirements
Conduct authentication N/A Primary Support
design sessions
Update SAW N/A Support Primary
authentication
components as required
to support the Workday
implementation
One
Deloitte
Activity Milestone/Deliverable Washington
Responsibility
Responsibility
Configure authentication Milestone: Configuration 1 Tenant Build Primary Support
process in Workday
tenant
Test authorization Milestone: Configuration 1 Tenant Build Primary Support
authentication process in
Workday tenant
Conduct Discovery and Deliverable: Configuration Security Primary Support
Design Sessions Framework
Conduct Integration Deliverable: Integration Design Primary Support
Design Sessions
Conduct Integration Deliverable: Integration Design – State Support Primary
Design Sessions – State
Configure role-based Milestone: Configuration 1 Tenant Build Primary Support
security and unit test
Review roles-based Milestone: Customer Confirmation Sessions Primary Support
security
Test role-based security Deliverable: End-to-End Test Results Support Primary
The figure below illustrates the high-level framework that will be used to plan, execute and deliver the solution
integration work required for the One Washington Workday solution:
Establish and maintain the project Document Management Plan (i.e., this section) of the Project
Management Playbook
Establish and manage the One Washington SharePoint project document management system
Manage, maintain, and control project documents on the SharePoint site
Work with the PMO to update any baselined documents under change control that need to change as a
result of an approved Change Request (CR)
o Please see Section 7 for more details about the One Washington Change Control process
The library is called Approved Deliverables and will house both approved Deliverable Expectation Documents
(DEDs) and deliverable documents. One Washington project leadership and team leads will have read-only
access to this library, but only a small group of team members managing change control for the project will have
write/delete access in this Library. This select group currently includes the following five (5) individuals:
Once an approved deliverable document is archived in the Approved Deliverables library, it cannot be updated
or edited without an approved change request (please see Section 7) – it is under change control.
Team leads may also want to post/publish/share final versions of work products (i.e., documents that are NOT
deliverables requiring formal sign-off) with the PMO, so that those documents can also be archived in
appropriate Final Work Products folders separate from the controlled Approved Deliverables library for record-
keeping. These final work product documents are NOT under change control and can be updated without an
approved CR, but best practices require that the Document/Version Control section in the front of every project
work product document be kept up-to-date with any document revision or updates.
Please see Section 14.6.2 Deliverable Management Process of the Quality Management Plan in this Playbook for
more information regarding the standard One Washington project deliverable management process.
The DED and DEL number (“###”) must correspond to the number of the deliverable designated in the One
Washington project Deliverables Log (i.e., <OneWa-005DEL-Deliverables Log.xlsx>).
Please Note: Software file naming conventions are addressed and maintained in the <One Washington Workday
Configuration and Naming Standards.docx> document.
Note: As a general rule, all One Washington deliverables and work product documents should NOT contain a
version number or date in their filename: those details will be maintained in the Version Control table at the
front of every document, as well as the versioning and tracking capabilities provided by SharePoint.
10.5.3 Document Naming Standards for All One Washington Project Documents
Regardless of whether the document is a team working document posted in Microsoft Teams, or a deliverable
being prepared for formal review and approval in the SharePoint site, the following Do’s and Don’ts apply to ALL
One Washington project documents:
Do’s
From a labor perspective, it provides a staffing model, as well as plans and processes for managing and
controlling human resources and their activities within the One Washington program, including:
This plan is considered a living document and will be updated periodically. Specific events that maytrigger
updates to this plan include:
Review of the resource requirements by the ERP procurement assistance consultant, ERPexpert advisor
and system integrator (Deloitte)
Finalization of maintenance and operations plans at each implementation stage
Final funding approval at the end of each budget cycle
Other updates to the plan may be necessary throughout the program’s duration and will be made at thedirection
of either the business operations manager, PMO manager, program director or the executive director.
The One Washington program includes four (4) core projects or workstreams for solution implementation:
Please see Section 2 – Project Organization and Section 3 – Project Governance for details about the organization
of the implementation project team and the program governance structure and escalation procedures.
In addition, bluecrane has been contracted as the program’s quality assurance consultant, to provide
independent assessments of the health of the One Washington program, as required by OCIO Policy 132. The
program also benefits from having OCIO consultants assigned as oversight to the program. This oversight will
help to ensure the program stays on track and follows applicable external guidelines.
Technical Lead This role is responsible for providing sound Single point of authority and
technical guidance in all aspects ofthe One technical responsibility for
Washington program and providing technical statewide ERP solution
leadership for the implementation of the ERP Provide leadership, mentoring
solution. and leads technical teams in
executing project deliverables
The technical lead reports to the chief Establish priorities for
technology officer. developers, configurators, or
testers based on business
owner priority and feedback
Align ERP software
implementation with OFM IT
strategy
Work with teams to implement
processes and technology that
support business value and
improve efficiencies across
business and technical functions
Business Functional These roles serve as One Washington's lead Facilitate and lead the work and
Area Leads (Finance, subject matter experts on state enterprise stakeholder sessions with
Procurement, business process and systems (finance, business stakeholders to identify
Budget, HR and procurement, budget, HR and payroll); and document enterprise
Payroll) supporting the ongoing use and development business capabilities, business
of the state's new ERP system. Additionally, outcomes and user stories, to
they work to transform business operations understand and define business
and solve business problems by analyzing processes, policies and
business processes, determining business application specifications
needs and communicating clearly to Produce project documentation
stakeholders, technology developers, and such as use cases, business
vendors. rules, functional requirements,
andnon-functional
The business functional leads report to the requirements
PMO manager. Effectively translate business
problems and solutions to
technical staff
Lead and support other staff on
the One Washington business
functional teams to meet
deliverables and understand tasks
and directionto ensure program
efforts are aligned with program
goals, and objectives are met
timely with quality work products
Assist with future business line
training endeavors
Business Owners These roles serve as the lead for the Collaborates with OneWa and its
functional areas of finance, procurement, associated governing bodiesto
budget, HR and payroll. Business owners will identify business process areas
define and champion the implementation of for improvement
business process needs and requirements Reports status to the program
related to theirrespective areas. This effort director and the business
will be in collaboration with program staff, transformation board
advisory committees and the business Assess and decide software and
transformation board. system integrator that best fits
their functional areas
The business owners provide updates tothe
Review and provide feedbackon
program director and do not report directly to
SI request for proposal
program staff.
Communicate externally to
function constituencies –
business processes, benefits
Assist in resolution of
resistance
Collaborate with partner
agencies to implement
business process
improvements
One Washington advocate
Decides on the system design
direction for their functional
area
Assist with future business line
training endeavors
Where specific technical knowledge is required, or where State resources are unavailable, the program will
rely on contracted consulting resources. Where vendors are responsible for the development, and
implementation of contracted deliverables, state and contracted staff will work with the vendors to develop
deliverables and transfer knowledge so that State staff have the skills needed to provide ongoing
maintenance and operations of the solution.
The following table identifies the staff that have been assigned to the One Washington program, by their
specific roles. It does NOT include the ERP (i.e., Workday) vendor staff responsible for the configuration and
implementation of the Workday solution. For a more detailed view of the overall staffing plan, please <
Resource Management and Staffing Plan>.
State Resources
Role Name
Executive Director Vann Smiley
Program Director Matthew Meacham
Executive Assistant Susanne McLemore
PMO Manager Lizzy Drown (OOO); PMO Co-Managers are John Cook and
Liz Colón
Project Manager - Operations Matthew Toney
Project Manager - Technical Charlene Bane
Project Coordinator Vacant
Subject Matter Expert – Finance Lead Mike Schaub
General Ledger Lead Steve Nielson
General Ledger SME Jayda Williams
Accounts Receivable Lead Laura Lopez
Asset Management Lead Keri Smith
Cost Allocation Lead Stacy Crawford
Grants Project Accounting SME Vacant
Subject Matter Expert – Finance Specialist Trinh Bui
Subject Matter Expert – Procurement Lead Vacant
Subject Matter Expert – Procurement Specialist Teri Lund
Chief Technology Officer Ann Bruner
Technical Lead Vacant
The program director, in consultation with the business operations manager, will be responsible for
identifying and assigning resources in accordance with the program’s organizational structure. All resources
must be approved by the executive director before the resource can begin any program work. The project
teams will likely be split between multiple locations, to include working remotely, and thus need flexibility in
terms of work location, facilities and space limitations.
Version: 0.9 Page 136 of 169
03/10/2021
One Washington (System Integrator K3298 SOW_1A)
Project Management Playbook
11.2.3.1 State Resource Acquisition
The One Washington PMO, with guidance from the executive director, program director, and business
operations manager, developed and maintains a staffing plan based on the requisite knowledge, skills and
experience needed for the positions required to support the program. Most of the program roles were
presented in the Roles and Responsibilities table shared in Section 11.2.1. Many of the positions require in-
depth knowledge of the state’s core business processes, as well as the systems that support those processes.
The program has and will continue to recruit for State staff with the requisite experience into program
positions. Additionally, based on program funding, these positions may change to better ensure project
completion.
Where appropriate, positions may be filled with contracted vendors that have the experience necessary to
fill the roles and responsibilities of the position. Contractors will be hired through a competitive
procurement process. The program director and business operations manager will define the requirements
for program resources, and the program must find resources with the requisite knowledge, skill, and
experience that can effectively perform their roles to achieve the goals and objectives of the program. The
program director and business operations manager will escalate any resource risks or issues to the executive
director, as needed.
In addition to program staff and partner agency resources, the program has completed seven of eight
procurements to fill various vendor roles. Deloitte was chosen as the system integrator vendor and the 1A
release of the Workday implementation project that officially kicked off in January 2021.
Resource Onboarding/Ramp-up
The One Washington program employs full-time State staff and contractors. This does not include the
executive sponsor, executive steering committee, business transformation board,or advisory committees.
The staffing table presented in Section 11.2.2 does not include additional staff that have been requested in
the program’s 2021-2023 decision package request. If that funding is approved, an update will be made to
this document highlighting new positions that will be part of the program.
Onboarding for positions included in the 2021 – 2023 decision package will begin in July 2021 and are
expected to occur in waves, based upon priority as determined by the program director and business
As the program evolves and implementation work begins, additional resources and/or modified roles may be
identified. When this occurs, first-line supervisors will be responsible for initiating a resource request to the
program director and business operations manager. This request will need to include an overview of how the
position will support the program’s overall mission, as well as the necessary skill sets and timeframes. The
program director and the business operations manager will be responsible for monitoring and prioritizing all
resource requests. Given the fluidity of staffing on projects of this size and the occasional need to ramp up
quickly, the State will strive to provide new contractors with laptops, badges, email, and other items
essential to their work within 10 business days of the initial request.
New resources that join the program will be provided a formal onboarding process, including project
orientation. The first-line supervisor (or contract manager for contractor resources) will be responsible for
delivering the project orientation. The orientation will include the following:
As the program reaches key milestones and/or stages in the project, staff will need to be reduced or
transitioned to operational positions. For example, after the go-live of the core finance and purchase-to-pay
functionality, the program will transfer the finance team (to include subject matter experts and project
managers) into maintenance and operations, which may require a different organizational structure to
provide ongoing system support.
For consultants, the program will align the contract lengths and needs with the program’s staffing
requirements. This will enable an easy transition of contracted staff out of the program. As staff transition
off the program, the program director will coordinate appropriate roll-off steps with the business operations
manager. An Offboarding Checklist will be used to facilitate efficient off-boarding. This template is housed on
the program’s SharePoint site here.
Identify any remaining duties and transition these responsibilities to other staff
Transition electronic files to the program’s document repository in accordance with state retention
laws and agency policies
Return building security/access card
Complete off-boarding form provided by the business operations section:
Remove access rights to program documents and repositories
A transition document will be created identifying the timing of the transition from a program position to an
operational position and will also include training and other requirements necessary for transitioning staff to
be successful in their new positions.
Vendor resources are replaced in accordance with the procedures established within their contract or
through established competitive procurement processes (please see the vendor management plan). Any
replacement of a contract position must meet the original minimum qualifications for the position andmay
be subject to an interview in addition to a review of their resume and qualifications. Prior work references
may be checked as part of the hiring process. Where possible, the replacement staff will begin work prior to
the original staff’s departure to help ensure appropriate transition of responsibilities and knowledge.
Individual training and program organizational development (e.g., formal training, on-the-job, coaching,
mentoring, team skills, etc.) will be provided as needed to educate the individual on program-specific items
or job-specific tasks. The program is also creating an organization development program aimed at providing
long-term team skills that will contribute to each employee’s role within the program and help retention.
General
o One Washington program overview
o Program governance and organizational structure
o Program meeting schedules
Presentation/meeting
On-the-job training/intern program
Coaching/mentorship program
Learning Management System (LMS)
Specific discipline self-study
LinkedIn Learning
Periodic performance reviews will also be conducted of contracted staff, and a recommendation for
replacement will be made for those staff unable to meet the requirements of their role: please see the
Vendor Management Plan for further information. This recommendation will be followed by the necessary
steps outlined in their contract to release them and onboard replacement staff if required.
Training plans and a log of their execution are maintained in the “Project Team Training Log” that is
documented for each specific training class. The living “Project Team Training Log” will be posted and
maintained in the PMO folder on the One Washington SharePoint site.
The Resource Plan is a dynamic document used to facilitate the planning, acquisition, and management of
the project’s staffing needs. Because it is frequently updated to reflect progress and forecasts, the Resource
Plan is maintained outside of the Project Management Playbook and will be stored in the PMO folder in
SharePoint.
The Project Tools Strategy took into consideration the One Washington project Workday implementation
approach, as well as the State’s existing project tool suite and long-term vision for project tools supporting
the solution, as well as the overall integration requirements for the project tools that will be used.
Project Deloitte PMO – Our standard project management Web based tool hosed by Contractor. Access No OFM Records and Data will be No
Management Individual TBD information system (PMIS) for managing is provided by Contractor and is secured with stored in PMC.
Center (PMC) risks, action items, issues, and decisions MFA also.
State: (RAID) items for an implementation project One Washington project RAID items.
Mistyjean within the PMO. Access is for the State and Deloitte project
Brown and Dan teams. and possibly a few Agency SMEs
Ward Based upon the MicroFocus Project and needing access.
Portfolio Management (PPM) tool, PMC
facilitates consistent, accurate RAID
management and reporting. It can also
facilitate work plan and CR management
for a project, but these items are out-of-
scope for the One Washington project.
ALM - Deloitte Finance Octane is a cloud-based application Web-based tool hosed by Deloitte. Access is No OFM Records and Data is stored in No
Octane Team – lifecycle management (ALM) platform that provided by Deloitte and secured with MFA Octane.
Individual TBD will enable the One Washington also.
workstreams to collaborate on ** As part of a user story/test case, an
State: configuration, integration development, Access is for the State project team and employee ID or some other reference
Mistyjean reporting and other project tasks. Agency key users involved in testing may be made to OFM Records and
Brown and Dan activities. Data.
Ward Octane will also be used to plan, execute
and manage all Workday testing activities.
The POCs for all State project tools will be the following Technical Team members:
Any additional software will be agreed upon between the State and Deloitte as needed throughout this
project.
Deloitte personnel may conduct work on the project using devices issued to them by the State, both on-site
in Olympia and offsite at Deloitte or home offices. The State will provide reasonable access to State assets
required to fulfill the requirements of the project, including the sFTP server for conversion and shared
document repositories.
Any OFM Records and Data in Deloitte tools that will be decommissioned at the end of the project will be:
(1) Exported to the State for retention at the conclusion each tool’s project use or end of the SOW,
following the State’s instructions
(2) Cleared and sanitized from all such tools, employing sanitization and clearing processes acceptable
to comply with the National Institute of Standards and Technologies Guidelines for Media
Sanitization (NIST 800-88 Revision 2)
This section covers three key components needed for a successful One Washington project:
Weekly Monday Workstream meetings include the workstreams conducting planning and execution work
and depend upon the stage/phase of the project. For example, during the Plan/Imagine phase, Monday
workstream meetings are being conducted by the PMO, Functional, and Architecture and Security teams.
Since the One Washington transformation is statewide, success of the program relies heavily upon all
stakeholder groups being thoroughly engaged and prepared for change. The Stakeholder Engagement Plan,
along with the Communications Plan, provides the One Washington program with a strategic and proactive
approach to communicate key messages with stakeholders to align during the transformation. It provides
key messaging for stakeholder groups based on their unique high-level impacts, attributes, concerns, and
information needs, and it recommends tailored engagement activities for impacted stakeholders.
Another key component of the One Washington Stakeholder Engagement Plan is the design and
implementation of the High Impact Agency Approach. Based on an analysis of people, process, and
technology impacts included in Phase 1a, the program team has identified three tiers of agencies that are
considered “high impact” and require more frequent planning meetings and coordination based on size,
complexity, influence, and other unique characteristics. The program is engaging them through a series of
high impact meetings and the use of “relationship managers” to guide the activities of Tier 1 agencies.
Planning and managing stakeholder involvement for the project is vital to meeting project goals and
objectives, particularly when external resources can influence the direction or outcome of project results.
Please see the One Washington Organizational Change Management (OCM) Plan for overall stakeholder
management plan for specific stakeholder management activities of the Workday Phase 1A project.
Chairperson/
# Communication Description Audience Frequency
Responsibility of
1 Project Status Meeting Regularly scheduled Program Director Weekly Deloitte Project
meeting to update PMO Leads (Tuesdays), Manager
project leadership on Team Leads through
project progress and project
status. Information closure
presented:
Schedule
performance
Milestone progress
Deliverable status
RAID items that need
attention
Version: 0.9 Page 150 of 169
03/10/2021
One Washington (System Integrator K3298 SOW_1A)
Project Management Playbook
Chairperson/
# Communication Description Audience Frequency
Responsibility of
CR updates
2 Project Status Distribute standard Project leadership Weekly PMO
Distributions status report after the
Team Leads
weekly status
meeting, and/or post
in the appropriate
folder on the
SharePoint site
3 Project Phase Kick-off Formal kick-off of next All project team TBD PMO with
Meetings project stage members sponsorship from
leadership
The following criteria determine when a One Washington meeting requires planning, an agenda and meeting
minutes following the standard One Washington project meeting minutes template: <provide SharePoint link
to One Washington standard meeting minutes template>
Roles Responsibilities
Meeting Leader Plans, prepares, and conducts meeting
Assigns a meeting scribe
Ensures the meeting starts and ends on time
Reviews and approves meeting minutes
Reviews risks and issues
Ensures risks, issues, and action items are documented in PMC and assigned with
agreed upon due dates
Summarizes outcome of the meeting
Meeting Attendee Prepares for and participates in the meeting
Determines the topics to cover and the best format to discuss each of them
Creates an agenda
Delegates a suitable person to conduct the meeting if unable to attend on the scheduled day or
reschedules the meeting
Defines the objectives and desired outcomes in preparation for the meeting
Ensures meeting starts on time
Facilitates the meeting, follows the agenda, and manages the time for each topic
Reviews action items from the last meeting and validates completion
Identifies risks and issues and validates the information with attendees
Clarifies and paraphrases key ideas and decisions
Identifies next steps and assigns roles and responsibilities for each
Identifies action items, action owner, and due date for each
Reviews action items, next steps, decisions, issues, and risks raised at the meeting with the team
For a non-recurring meeting, sets a tentative date for the next meeting, as needed
Guidelines:
The following checklist is provided on the upper right corner of the Meeting Agenda Template to assist the
Meeting Leader, as needed.
Start on time
Review agenda
State meeting purpose and objective(s)
Solicit risks and issues
Record all RAID items in PMC (or capture in notes for entry into PMC later)
Summarize key points and takeaways from the meeting
End on time and thank participants
Attendance
Key points of the meeting in summary bullets
Key RAID items identified, updated or closed during the meeting (in either PMC directly, or in
minutes for PMC entry/updates later)
Key lessons learned and next steps
Sends the minutes for review to the leader within 24 hours after the meeting
Step 6: Review and approve minutes
Incorporates inputs received from meeting attendees and leader and updates the minutes as needed
Posts the final minutes to SharePoint
Updates action items on SharePoint
Notifies the team about the updates and posting of minutes on SharePoint
Define the One Washington project quality objectives, roles and responsibilities
Define the plans for formal Quality Assurance (QA) reviews for the One Washington project
Define the approach to verify that the methods, processes, templates and tools developed for the
One Washington project are being consistently used by the project team properly, and they are
effective
Define the approach to verify that One Washington project deliverables are meeting project
standards and quality expectations
Describe how quality will be monitored, controlled and reported on the One Washington project
Describe the plans for continuous improvement and capturing lessons learned from the One
Washington project
Validation is a quality process for confirming that a work product or service satisfies its intended
requirements upon migration to the production environment. It is usually confirmed by different types of
pre-migration testing (e.g., parallel testing, user acceptance testing or UAT, and readiness testing). The One
Washington project Testing Strategy deliverable details the types of testing planned for the project.
Quality Quality
Assurance Control
Definition A set of activities for ensuring quality in the A set of activities for ensuring quality in
processes by which products are developed. products. The activities focus on identifying
defects in the actual products produced.
Focus PROACTIVE REACTIVE
Customer focus: Organizations can establish this focus by trying to understand, meet or exceed their
customers’ current and future requirements and expectations.
Leadership: Organizations succeed when leaders establish and maintain the internal environment in
which employees can become fully involved in achieving the organization’s unified objectives.
Involvement of people: Organizations succeed by retaining competent employees, encouraging
continuous enhancement of their knowledge and skills, empowering them, encouraging engagement
and recognizing achievements.
Process approach: Organizations enhance their performance when leaders manage and control their
processes, as well as the inputs and outputs that tie these processes together.
System approach to management: Organizations sustain success when processes are managed as
one coherent quality management system.
Continuous improvement: Organizations maintain current levels of performance, respond to
changing conditions, and identify, create and exploit new opportunities when they establish and
sustain an ongoing focus on improvement.
Factual, metrics-based approach to decision-making: Organizations succeed when they have
established an evidence-based decision-making process that entails gathering input from multiple
sources, identifying facts, objectively analyzing data, examining cause/effect, and considering
potential consequences.
Mutually beneficial vendor and partner relationships: Organizations that carefully manage their
relationships with vendors and partners can nurture positive and productive involvement, support
and feedback from those entities.
One Washington has established a number of processes and best practices that focus on these principles.
These include inclusive governance groups and processes, project management processes to establish
monitor, and control scope, schedule and budget, risk and issue management processes, and the
establishment of a PMO to cohesively manage these processes.
Version: 0.9 Page 156 of 169
03/10/2021
One Washington (System Integrator K3298 SOW_1A)
Project Management Playbook
Roles Responsibilities
Project Manager Review and approve the Quality Management Plan section of the Playbook
Review quality and Deloitte engagement review findings
Assign project team members to appropriate action items resulting from
quality assurance reviews, quality reviews, and other adviser
recommendations; monitor and manage those action items to closure
Track engagement review and quality action items to closure
PMO Maintain the Quality Management Plan section of the Playbook
Develop and maintain the quality review schedule for the One Washington
project
Track quality improvement action items for the One Washington to closure
Team Members Prepare for and participate in quality assurance reviews and Deloitte
quality reviews
Implement action items resulting from quality reviews and Deloitte quality
reviews
Deloitte Quality Perform engagement quality reviews
Reviewer Review the findings with the project leadership team
Follow up on action items from previous reviews
Workday Delivery Plan and perform Workday DA reviews: Plan Stage, Integration, FDM,
Assurance (DA) Authentication, Configuration, Cutover, Operate
Reviewer Review the findings with the project leadership and technical teams
Follow up on action items from previous reviews
Oversight bluecrane independent QA reviews
OCIO Oversight
Throughout the project, the PMO will implement required revisions to the project’s Quality Management
Plan to keep it current and relevant throughout the One Washington project lifecycle.
This section of the QMP describes how One Washington project quality is evaluated through QA reviews
performed to confirm that the project is making steady progress to deliver a high-quality solution on budget
and schedule.
Project Governance
Schedule Management
Cost Management
RAID Management
Risk Management
Action Item Management
Issue Management
Decision Management
Scope Management and Change Control
Requirements Management
Development Management
Solution Development
Document Management
Resource Management
Project Status Reporting
Communications Management
Meeting Management
Quality Management
Quality Control
Personally Identifiable Information Handling
The PMO will check compliance with the defined processes as part of each of the:
Regular PMO meeting to review key risks, issues, schedule, upcoming activities and late tasks
Weekly schedule updates from vendors, and program leadership team members
Risk and issue review meetings
Governance preparation meetings to prepare proposed change requests and coordinate requests
across governance committees.
Program management plan reviews to apply lessons learned and refine processes
As quality assessments are performed, it is up to project leadership to evaluate the results and determine
what, if any, corrective actions should be taken. Corrective actions might include (a) additional training, (b)
stronger process enforcement, or (c) process refinements. It is important to weigh the cost of process
changes versus their expected benefits before implementing them.
Three (3) formal QA review types are planned for the One Washington project:
Each monthly assessment report includes observations, findings, recommendations and a risk rating in
specific program areas. The PMO is responsible for responding monthly to each of the recommendations.
The QA assessment report and PMO response report are posted to the One Washington Program’s OCIO IT
Dashboard and is available for public review.
bluecrane will conduct a readiness assessment at the beginning of each phase. For each assessment area,
bluecrane reports their assessment results and any issues and/or risks assessed over the last month, as well
as high-level recommendations for addressing the risks. They perform the following assessment:
Deloitte project leadership will meet with bluecrane to discuss any observations or findings from their
reviews of the project, and will address any Deloitte action items or follow-ups, as appropriate. Deloitte will
support the audit of any One Washington Workday production release performed by bluecrane, by allowing
access to processes, data, deliverables, staff, resources and tools to verify that as-built functionality and
configuration meet contractual requirements. In addition, Deloitte will also make staff, resources, processes,
data, tools, and deliverables available to bluecrane for reviews, walkthroughs, audits and inspections, as
appropriate.
Deloitte Quality Reviews are formal, objective, onsite reviews (if possible, with Covid; otherwise it will be
virtual) conducted by a seasoned Deloitte executive outside of the immediate One Washington project
leadership team who evaluates the status of the project in six categories:
An initial Deloitte Quality Review Plan is defined in the table below; this plan will be approved and
maintained with One Washington program State leadership:
Type of Project
# Reviewers Frequency Objectives
Review
1 Initial Quality Quality Review Within 3 months of Define the project quality review schedule
Review (QR) executive project kickoff per major project milestone dates and
phase transitions
Introduce project Quality Review executive
and purpose of reviews to client leadership
Review the project per the six quality
review categories as they relate to project
mobilization
2 Regular Quality Quality Review Every 3 months, or Follow up on all previous concerns and
Review schedule executive at major project recommendations
milestones Assess the project against the six quality
review categories as they relate to the
current project phase
The Deloitte Quality Review executive for the One Washington project will be:
Christina Dorfhuber
cdorfhuber@deloitte.com
303-312-4105
The term ”deliverable” applies to a formal output of an activity defined in the Statement of Work on which a
payment depends. Deliverables are distinguished from “work products” which are activity outputs that do
not require formal review nor approval.
Role Responsibilities
Deliverable Owner Review and approve the Deliverable Expectation Document (DED)
Act as central point of contact during deliverable development/review
process for vendor and One Washington resources
Complete assessment of deliverable readiness for walk-through
Attend walk-through
Review deliverable/prepare written comments (along with other
Reviewers)
Consolidate/Reconcile Reviewer and contributor comments and submit a
single set of comments to the vendor
Return individual comment forms with resolution noted to Reviewers;
Forward final comment form with resolution from the vendor
Indicate acceptance, acceptance with conditions or rejection of deliverable
by signing the Deliverable Acceptance Document.
Verify conditions have been satisfied when a deliverable has been accepted
with conditions.
Verify deficiencies are corrected and acceptance criteria met with
approvers when a deliverable is non-accepted
Notify Reviewers when deliverable is ready for review and Approver when
deliverable is ready for acceptance
Consult with producer during deliverable preparation process to avoid
concerns/issues late in the process
Producer Develop initial and final DED orientation session
Coordinate deliverable development with Deliverable Owner
Conduct content development sessions
Develop initial and final deliverable
Conduct walk-through
Submit deliverable for formal review and acceptance
Format The format of the deliverable, as stipulated in the Statement of Work; that
is, Microsoft Word (.docx), Excel (.xlsx), PowerPoint (.pptx), etc.
Constraints A statement on whether and how the deliverable is subject to the change
control process
Acceptance Criteria Criteria that if met determine the One Washington acceptance of a
deliverable
Review and The schedule for the deliverable production, review and acceptance process
Acceptance
Timeframes
Roles and The roles associated with deliverable production, review and acceptance;
Responsibilities same table as the one above
Just prior to releasing the deliverable for formal review, the deliverable coordinator schedules a walk-
through. The walk-through provides an opportunity to orient reviewers to the deliverable, thus familiarizing
all attendees with the subject matter and facilitating/streamlining the overall review time. At the walk-
through, the producer will provide attendees with a high-level review of the deliverable, remind consumer
and reviewers of the acceptance criteria, and answer any questions.
After the walk-through, the producer will submit the draft deliverable for formal review to the consumer.
The deliverable coordinator logs the updated status in the project repository and releases the deliverable to
the consumer and reviewers for review. The deliverable is reviewed based on the acceptance criteria. For
contract deliverables, reviewers will have the time, designated within the DED, to complete the initial formal
review and to submit comments back to the consumer.
The producer will then consolidate and resolve each reviewer’s comments and submit a single set of
comments to the owner. The consolidation/reconciliation process may require the consumer to follow-up
with reviewers to resolve conflicting comments and to meet to discuss and resolve conflicts, when
comments are substantive.
During this final review and acceptance cycle, reviewers should limit their comments to previously identified
comments. The intent is to encourage reviewers to identify all comments or issues in the first review cycle
and not to identify new material within the final review cycle. Consumers are encouraged to work closely
with the deliverable owner to ensure there are no additional concerns identified at this late stage. However,
if a substantive deficiency that does not meet the defined deliverable acceptance criteria is identified,
reviewers should include that in their final comments which could necessitate another revision to the
deliverable before submitting for acceptance.
All program artifacts are published under the auspices of the Office of Financial Management and subject to
public disclosure and therefore, must meet quality standards as defined by the One Washington program.
2. Reject deliverable (some or all of the acceptance criteria have not been met)
If accepted, the deliverable coordinator will prepare a deliverable acceptance form and send it to the
contract manager and deliverable owner, for signature. Once signed, the deliverable coordinator will then
deliver it to the producer. The deliverable coordinator is responsible for ensuring that an electronic version
of the final, accepted deliverable and its supporting documentation is maintained in the project repository.
In the event that a deliverable is rejected, the specific deficiencies that do not meet acceptance criteria must
be included in the deliverable rejection form. The deliverable coordinator, working with the owner, will
prepare the notice of deliverable rejection and send it to the deliverable owner for signature. The
deliverable coordinator will then deliver the signed notice to the producer. The deliverable owner will follow
remediation steps to resolve the rejection.
1. Peer review
Team member peer review
Version: 0.9 Page 165 of 169
03/10/2021
One Washington (System Integrator K3298 SOW_1A)
Project Management Playbook
Author revises draft
2. Deloitte PMO leadership review
PMO team and/or appropriate team lead reviews document for quality and State readiness
Author revises draft and submits final draft to PMO for formal submission to the State
For integration and reporting solution components, peer reviews are part of the development process,
including checks for alignment to the naming conventions and established standards for the One Washington
Workday solution. Please see the Integration Approach and Reporting Strategy and Approach deliverables,
as well as the <One Washington Workday Configuration and Naming Standards.docx> document for more
information.
System testing will focus on ensuring that the installed software components and their unique
configuration for Washington state are functioning per the requirements;
Integration testing will ensure the components are all working together as a single installed unit;
Interface testing will verify that the inputs from external systems and outputs to external systems
are functioning per requirements;
Performance testing ensures that the system will perform (on-line response time, report generation
response time, etc.) according to requirements; and
End-to-end testing will test specific use cases or user stories from beginning of a business process to
the end of the process.
End-user testing, where users verify that the functionality is acceptable based on the requirements
and their use cases.
Prior to the system integrator testing phase, the state and vendor will agree on entrance and exit criteria for
each testing phase.
The Requirements Traceability Matrix (RTM) provides another means of checking solution quality, by
capturing the mapping of test scripts, test cases, and test scenarios to the One Washington requirements.
The RTM provides the means to verify that all of the requirements are covered by test scripts: 100 percent
coverage is the goal.
Quality status will certainly factor into the weekly status reporting process: yellow or red status indicators
(on scope, schedule, RAID, or overall, for example) may be caused by a quality issue when root cause analysis
is applied. Thus project quality will be monitored, controlled, and reported on through weekly status
reporting. Please see Section 13 of this Playbook for more details.
In summary, to efficiently implement the lessons learned approach, the Deloitte team evaluates all activities
in each phase to evaluate:
Version: 0.9 Page 167 of 169
03/10/2021
One Washington (System Integrator K3298 SOW_1A)
Project Management Playbook
1. QA/QC
Activities
2. Review
5. Apply
Current
Process
What went well Improvements
Quality
Processes
What did not go well
What needs to change
4. Capture 3. Perform
Lessons Root Cause
Learned Analysis
For example, extra quality/peer review checklist items may be defined as a result of comments from the
State or other project stakeholders regarding deliverable development. Then, during the next round of
deliverable submissions, the PMO will monitor whether the number of similar issues/comments have gone
down in number as part of continuous improvement measurement procedures.
Personal information or personally identifiable information (PII) is any information relating to an identifiable
person. PII is Information which can be used to distinguish or trace the identity of an individual (e.g., name,
social security number, biometric records, etc.) alone, or when combined with other personal or identifying
information which is linked or linkable to a specific individual (e.g., date and place of birth, mother’s maiden
name, etc.).
The One Washington/Vendors Technical Requirements matrix in the Contract states that the PII data will be
covered by ISO 270018 and NIST800-53 for handling PII in the Cloud, through the Data Processing Exhibit,
controls in the SOC2 report, and formal mapping to GDPR.
The State will limit sensitive information, such as PII, trade secrets and other information that it considers
sensitive or highly confidential, it provides to Contractor (or otherwise makes available to Contractor) to only
that which is reasonably necessary to allow Contractor to provide the Services. Any PII security breach
notification statue as referenced from RCW 19.255.010 will comply with the incidents response process as
stated in this workbook, as well as processes and requirements defined in the Information Security and Risk
Management Plan (ISRMP).