ROAD PROGRESS IN-HOUSE (L&T) Date: Oct 26, 2023

S No Description Road Type Location Scope (M) Previous (M) Today (M) Cummulative (M) Remaining (M) Progress in %age REMARKS

1 Subgrade Preparation with Surface Miner Type D IHR - 03 3698.48 2990 2990 708.48 80.84% Surface Miner is Broken

2 Subgrade Preparation with Bulldozer Type B PR - 01 3202.12 3202.12 0 100.00%

3 Subgrade Preparation with Bulldozer Type B PR - 02 111.0994 111.0994 0 100.00%

BULLDOZER started working at


4 Subgrade Preparation with Bulldozer Type B PR - 03 1896.821 1200 600 1800 96.821 94.90%
9:30 AM

ROAD SURVEY PROGRESS IN-HOUSE (L&T) Date: Oct 26, 2023

S No Description Road Type Location Length (M) REMARKS

1 Survey Progress Type D IVR - 21 1010.9881 Today Survey Marking was not done

2 Survey Progress Type D IVR - 26 1010.9845

EXCAVATED MATERIALS SHIFTING PROGRESS IN-HOUSE (L&T) Date: Oct 26, 2023

Today Quantity Cummulative Number of Dump


S No Description Road Type Location Previous Quantity M3 Number of Trips REMARKS
M3 Quantity M3 Trucks
Excavated Materials/Boulders/Loose Sand
1 Type B PR - 01 984 504 1488 2 21
Shifting from both sides of the road