Method statement of Frame

Project Name: Benghazi Four Bridges - Libya

Client:

Consultant:

Main Contractor:
 Orascom Construction (OC)
 Hassan Allam Construction (HAC)
 Rowad Modern Engineering (RME)
 Neom Real Estate Development (NRD)

Project Manager: Mohamed Ghobara

REVISION HISTORY

Rev. Revision information Date

Originated by Reviewed by Reviewed by Approved by

Construction Manager TO Manager QA/QC Manager Project Manager

Date: Date: Date: Date:


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

1. SCOPE

This method statement is intended to outline the activities and the method used for the scope covers the
procedure for installation and inspection of the frame (Cross beam) All activities shall be carried out in
accordance with relevant project specifications and drawings.

2. PURPOSE

The purpose of this method statement is to describe the detailed procedure to follow for frame (cross beam) to
achieve mechanical completions. And to ensure that the concerned persons are familiarized with the sequence
of activities, utilization of resources and relevant documents in compliance with HSE and QA/QC procedures &
requirements.

3. REFERENCES

 Project Specifications
 Project Quality Plan
 Project HSE Plan
 Egyptian Code for Practice

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

4. DEFINITIONS

QA: Quality Assurance


QC: Quality Control
ITP: Inspection and Test Plan
WIR: Work Inspection Request
MS: Material Submittal
MS: Method Statement
RA: Risk Assessment
PQP: Project Quality Plan
PPE: Personal Protective Equipment
DM: Department Manager
CM: Construction Manager
PM: Project Manager

5. RESPONSIBILITIES

I. Project Manager:

1. Determines the various responsibilities and assigned site staff accordingly for accomplishing the
project and controls the team towards efficient and effective utilization of the company’s resources but
not limited to manpower availability, machineries, equipment, and plants and related.

2. Assist PD for regular checking of the job for review, BOQ, bar chart, government requirements,
staffing and all aspects within the department’s productivity and intimate to the management for
information and assistance.

3. Assist PD for to obtain and secures building permits, demarcation, fencing and other pertinent
documents from concerned government and private offices for every new project. Also, to obtain the
completion certificate.

4. Monitors the progress of works and resolve the obstacles, if any.

5. Coordinates and controls subcontract items in an effective manner to achieve the product/process
quality as per the requirements.

6. Coordinates with other department such as but not limited to Engineering, Operations, and Purchase
Departments to ensure smooth flow of the projects.

7. Executes the project within the approved budget and in accordance with the contract specification.

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

8. Updates the cash flow on monthly basis.

9. Ensures that all QA/QC procedures, safety rules, precautions and procedures are strictly implemented
in all project sites.

10. Ensure mobilization of staff material and all concerned items in coordination with PD.

11. Updates DM with all projects transactions towards, authority requirements, approvals, variations, cost
claims, time extensions, payments, project development etc.

12. Maintains copy of all documents required at job site for Municipality/Consultant inspection, i.e., no
objection certificates from telecommunication, electric and water agencies, etc.), affection plan,
building permit, etc.

II. Construction Manager:

1. Ensures all required submittals are made in a timely manner.

2. Ensures that all preparation for work execution is carried out according to contract
specifications/approved shop drawings.

3. Ensures that work progress is carried out according to programmed/project plan and as per
approved method statement.

4. Ensures co-orientation with all the concerned and the implementation of the Consultant’s comments.

5. Ensures that the required plant equipment/tools/material and manpower is available for the timely
execution of work.

6. Controls and makes sure all safety measures have been implemented by the construction team as
specified and as general safety rules.

7. Ensures that all related activities and quality control procedures are practiced and implemented
according to the PQP.

8. Ensures that all drawings (A1 & A3 size) shall be available on site with Project Engineer & Site
Engineer.

9. Should be available/present at the time of work execution and for work progress.

10. Reports to PM.

III. Site Engineer:

1. Site Engineer is responsible to carry out the work as per the approved shop drawings, method
statements. He is also responsible to ensure adequate equipment for the works are in place prior to the
starting of work.

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

2. Site Engineer is responsible to ensure work has been done as per the specification and drawings;
inspections are done as per QC procedure and the ITP and offer works for Consultant’s inspection.

3. Site Engineer is responsible to ensure that all Safety precautions are in place, and that all personal on
site are using the required Personal Protective Equipment’s like – Helmet, Gloves, Shoes, and
Coveralls. We will also ensure all relevant permissions are available for the works.

4. Reports to Sr. Project Engineer.

5. Conducts MS/RA training to the workforce.

IV. QA/QC Engineer

1. Ensures work is being carried out as per approved Method Statement, ITP, approved shop drawings &
project specifications.

2. Monitors related works according to requirements of this procedure.

3. Advises Project Engineer/Supervisor of the specific requirements related to work quality and
requirement of Consultant/Client and approvals at different stages as site preparation and setting out.

4. Shall receive internal inspection form requests from Site Engineer and organizes inspection requests as
per required.

5. Inform Consultant/Client representative by the official inspection request as and when their presence is
required to carry out inspections.

6. Conducts MS training to the project/site engineers.

V. Safety Officer

1. Ensures safe and sound implementation of all safety procedures and measures specific to this work
procedure.

2. Ensures that all project personnel/site execution team is fully aware of their responsibilities and has
full understanding of the related safety rules and procedures.

3. Should conduct toolbox meeting before the execution of work.

4. Keeps PM, CM and Consultant/CLIENT updated about the adopted safety measures at site and
ensuring their adequacy.

5. Reports to the HSE Manager.

VI. Foreman

1. Continuous coordination and following Project/Site engineer instructions.

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

2. Controlling disposal of waste material and keeping a good housekeeping to keep good access to
working area.

3. Coordinate with the surveyor to carry out the correct levels.

4. Coordination with site safety officer for maintaining a safe working place and educating site workers
for the required safety instructions.

5. Reports to the Site engineer.

6. GENERAL REQURIEMENT
6.1 Tools & Equipment

a) Mobile crane.
b) Welding machine.
c) Air compressor
d) Scaffolding.
e) Fork lift.
f) Use Safety belts.

6.2 PPE List

High visibility Safety Shoes Protective Dust Mask Safety goggles, Safety
safety vest Helmets if necessary signs

6.3 MANPOWER
Manpower requirements such as Project Manager, Construction Manager, Project Engineer, Forman, and
Skilled labor/helper will be available at site upon the requirements.

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

7. CONSTRUCTION PROGRAM

 Based on the program of works, CM and the Planning Engineer shall jointly develop a Weekly Plan.
This plan will also be made available to the Engineer/Client, PM, Project Engineer, Safety
Officer and QA/QC Engineer.
 Based on the above weekly program, the Project Engineer shall prepare materials/equipment
requirement schedule for the week and shall coordinate with supplier for delivery.
 It is the responsibility of the Project Engineer to ensure that areas are ready for work.

8. PROCEDURE FOR INSTALLATION


A. GENERAL
 Prior to installation, the foreman will verify and ensure that the work area is clean and safe for
carrying out the activities and proper clearance is available from civil side before commencement of
works.
 Verify that all relevant approved latest revisions of shop drawings, technical submittals, inspection,
and test plans for installation reference.
 The foreman will inspect all the materials delivered to the workplace and ensures that these are
approved materials and for damage or defect. Materials found not to be as per requirement or with
damage or defect will be set aside.
 The foreman will orient and familiarize all the technicians and labors involved in the installations
regarding the relevant approved shop drawings, technical submittals, installation procedures and
details, acceptance criteria and safety requirements.
 The designs and execution to be followed as per the approved code of practice.

Procedure for Installation of Cross Beams in Bridges with


Steel Formwork System
i. Preparation:
 Review design documents: Ensure thorough understanding of cross beam specifications,
location, and connection details.
 Inspect steel formwork system: Verify its integrity, cleanliness, and proper alignment.
 Gather necessary equipment and materials: This includes lifting equipment (crane, hoist),
temporary bracing, and tools.
 After finishing the pier stem the next step will be the frame
 Chipping the surface of the top pier stem
 Field tests (sand cone , PLT ) for determine the compaction ration not less than 95% &
determine the bearing capacity not less than 3KG/cm2
 Start installing for the scaffolding (blocks, base plate, cross head, standards , pipes ,etc.)
 Starting RFT by fixing the steel chairs for bottom & top steel
 Finishing the RFT of frame by fixing the pedestal steel of elastomeric bearings

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

ii. Lifting and Positioning:


 Attach slings securely to designated lifting points on the cross beam. Use slings of appropriate
capacity and ensure proper balance.
 Lift the cross beam using the appropriate equipment. Maintain control and avoid sudden
movements.
 Guide the cross beam into its designated position within the steel formwork system. Use
positioning guides or temporary supports for precise placement.
iii. Alignment and Connection:
 Verify the cross beam's alignment with the surrounding formwork and bridge structure. Use
measuring instruments and adjust as necessary.
 Connect the cross beam to the formwork and adjacent beams. Utilize pre-drilled holes and
approved fasteners according to the design specifications.
 Tighten all connections to the required torque values. Use calibrated torque wrenches to ensure
proper tension and securement.
iv. Temporary Bracing and Inspection:
 Install temporary bracing to stabilize the cross beam and prevent movement during concrete
placement.
 Inspect all connections and ensure they are secure and meet the specified requirements.
 Re-check the alignment and adjust any discrepancies before proceeding with concrete pouring.
v. Concrete Placement and Curing:
 Place concrete around the cross beam, ensuring proper consolidation to eliminate voids and air
pockets.
 Follow designated curing procedures to allow the concrete to gain sufficient strength before
removing the formwork and temporary supports.
vi. Removal of Formwork and Temporary Bracing:
 Once the concrete has reached the required strength, carefully remove the formwork panels.
 Remove temporary bracing in a controlled manner, ensuring the stability of the bridge
structure.
vii. Finishing and Inspection:
 Inspect the exposed concrete surfaces for any defects and perform necessary finishing work.
 Conduct a final inspection of all connections and components to ensure adherence to design
specifications and safety standards.

9. QUALITY ASSURANCE AND QUALITY CONTROL


 Quality assurance measures must be taken into consideration during execution in compliance with the
quality requirements of the contract and according to the technical specifications and approved ITP.
 All works requiring inspection and testing to demonstrate conformity with requirements will be
undertaken in accordance with relevant inspection and test plan.

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

 The quality control activities associated with the works will be conveyed to all personnel involved in
the execution of the works by the project QA/QC prior to the commencement of works.

 INSPECTION & TESTING


 In process works shall be monitored for quality of workmanship and installation as per approved
construction drawings and approved ITP by the relevant Site Engineer, Supervisor and QA/QC
Engineer.
 All works shall be inspected for quality of workmanship and conformance to specification.

 HOUSE KEEPING
All workplaces will be cleaned from waste materials & ensuring clean & healthy work environment as well as
maintain free access & egress in the event of Emergency.

 SAFETY
All works shall be controlled as per safety procedures & as per manufacturer Safety Data Sheet (MSDS).
Safety equipment’s will be always worn. Safety procedure are to be considered before, during & after the
completion of the work to avoid any Possibility of danger to humans or the construction

 References

1. BOQ
2. project specifications
3. ITP.

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

RISK ASSESSMENT

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

F-P-QD-07-05 Cover + 27 Pages


Doc. no.:00
METHOD STATEMENT

Frame (Cross beam) Date:

F-P-QD-07-05 Cover + 27 Pages