Buying Process Tracker-V.1
Buying Process Tracker-V.1
Buying Process Tracker-V.1
Date: 21-Nov-2022
A standard SOCH model from Procurement to Inward Goods. The steps have been created after the discussion with Buying, QC, IT, SCM & Planning team.
Page 1 of 6
Company: Soch Apparels Pvt. Ltd. Date: 21-Nov-2022
Page 2 of 6
Company: Soch Apparels Pvt. Ltd. Date: 21-Nov-2022
Page 3 of 6
Company: Soch Apparels Pvt. Ltd. Date: 21-Nov-2022
PO tracker / TNA file / SCM To freeze the format of PO tracker file /TNA file /
Step No 6 tracker file format to be SCM tracker file with all the expected date & IT IT
finalised quantity with actual date & quantity columns.
The PO tracker to be a system automated tracker
Linking of TNA file & SCM
pulling data from Ginesys for PO details, QC details
Step No 7 tracker file to PO tracker IT IT
from TNA file & pickup, Gate entry details from SCM
file
tracker file.
First update for the PO Tracker will in the TNA file by
Step No 8 QC Date the QC team once the QC is done. To update QC
quantities & date of QC Done.
Contd…
Page 4 of 6
Company: Soch Apparels Pvt. Ltd. Date: 21-Nov-2022
Contd…
Page 5 of 6
Company: Soch Apparels Pvt. Ltd. Date: 21-Nov-2022
Source of data/Information/Ownership
Frequency of
Source Ownership Destination of file upload to Ginesys Remarks
Fileserver/Cloud-
Allocation file.xls Planning Gdrive/sharepoint "
Final automated tracker IT System "