WHRS Qap
WHRS Qap
FOUNDATION CHECKING
ORIENTATION VISUAL 100% APPROVED DRG. H
DISTANCES ( C/C AND DIAGONALS) MEASUREMENT 100% .+/- 10 MM H
ELEVATION'S W.R.T. MASTER LEVEL MEASUREMENT 100% .+/- 5 MM H
MAIN BOILER BLOCK /
POCKET C/L W.R.T.FOUNDATION MEASUREMENT 100% .+/- 5 MM H
COLUMNS / ROTARY
4 EQUIPMENT /TANK - POCKET DEPTH MEASUREMENT 100% .+ 50 MM & - 5MM H
VESSELS/ AUXILARY DIAGONAL OF POCKETS MEASUREMENT 100% .+/- 5 MM H
FOUNDATION /
CIVIL BLOCK SIZE - WIDTH & LENGTH MEASUREMENT 100% DRG. H
MISC.EQUIPMENT
SURFACE ROUGHNESS & CRACKS VISUAL 100% ROUGH SURFACE WITHOUT CRACKS H
6 STRUCTURAL
IDENTIFICATION VISUAL 100% DRG. H
ERECTION & TIGHTNESS OF ANCHOR BOLTS MEASUREMENT 100% TORQUE VALUE AS PER BOLT SIZE & GRADE H
B) ALIGNMENT OF
COLUMN'S
NO SURFACE DEFFECTS LIKE UNDERCUT,GROUP
POROCITY,CRACKS, EXCESS LUMPS DEFECTS ETC.
WELDING OF GUSSET PLATE/ BEAM CLEAT FILLET SIZE 100% H
Note - Weld reinforcement should not be ground for smooth
weld.
DISTANCES W.R.T. BOILER AXIS / CENTER LINE & DRUM AXIS MEASUREMENT 100% .+/- 8 MM H
GIRDER'S /FABRICATED
C) BEAMS /CONNECTING
NO SURFACE DEFFECTS LIKE UNDERCUT,GROUP
MEMBER'S / BRACINGS
WELDING WITH COLUMN (FOR WELDED STRUCTURE)- IF POROCITY,CRACKS, EXCESS LUMPS DEFECTS ETC.
DPT 10% H
APPLICABLE Note - Weld reinforcement should not be ground for
smooth weld.
CLEAT FIT UP & WELDING ( FOR WELDED STRUCTURE) VISUAL 100% DRG H
PLATFORMS &
7
STAIRCASE'S
NO SURFACE DEFFECTS LIKE UNDERCUT,GROUP
POROCITY,CRACKS, EXCESS LUMPS DEFECTS ETC.
WELDING VISUAL 100% H
Note - Weld reinforcement should not be ground for
smooth weld.
8 PRESSURE PARTS
IDENTIFICATION & CORELATION WITH TEST CERTIFICATES REVIEW 100% LOP / FOBD - WHICHEVER APPLICABLE H
GROUND INSPECTION & CLEARANCE FROM AUTHORITIES REVIEW 100% FOBD - WHICH EVER APPLICABLE H
DISTANCES W.R.T. BOILER AXIS / CENTER LINE & DRUM AXIS MEASUREMENT 100% .+/- 8 MM H
B) HP & LP DRUM
D) Hanger / Clamp Support DISTANCES W.R.T. BOILER AXIS / CENTER LINE & DRUM AXIS MEASUREMENT 100% .+/- 5 MM H
DISTANCE - LENGTH, WIDTH & HEIGHT TILL RDZ MEASUREMENT 100% .+/- 10 MM H
CLEANLINESS BEFORE END CAPS FIT UPS VISUAL 100% NO FOREIGN MATERIAL H
SITSON INDIA PVT LTD Page 10 of 31
W-76, PHASE-II, MIDC, DOMBIVLI WHRB - QAP
H) COILS
AIR BLOW FLUSHING / CLEANING SPONGE TEST 100% NO FOREIGN MATERIAL H
DISTANCES W.R.T. BOILER AXIS / CENTER LINE & DRUM AXIS MEASUREMENT 100% .+/- 15 MM H
DISTANCE OF COIL LOOP FROM THE CASING GAP MEASUREMENT 100% .+/- 5 MM H
CLEARANCE BETWEEN BAFFLE PLATE & COIL (IF APPLICABLE ) MEASUREMENT 100% .+/- 3 MM H
SITSON INDIA PVT LTD Page 12 of 31
W-76, PHASE-II, MIDC, DOMBIVLI WHRB - QAP
III) HP & LP SUPER HEATER COIL ALIGNMENT & LEVELING MEASUREMENT 100% 8 MM MAXIMUM H
11 WELDING - WELDER'S PERFORMANCE QUALIFICATION (WPQ) IS MANDATORY BEFORE COMMENCEMENT OF WELDING WORK - (WELDER TEST )
IDENTIFICATION VISUAL 100% AS PER WELD MAP / SCHEDULE H
CLEANLINESS VISUAL 100% 50 MM - BOTH ENDS
FIT UP'S MEASUREMENT 100% DRG. H
WELDER QUALIFICATION REVIEW 100% QUALIFICATION RECORDS H
WELDING PROCESS REVIEW 100% WPS H
WELDING CONSUMABLES REVIEW 100% APPROVED CONSUMABLE LIST & WPS H
WELDING SCHEDULE REVIEW 100% SCOPE OF WELD JOINT IN PRESSURE PARTS H
HARDNESS VALUE ONLY FOR P 91 / T 91 GRADE HARDNESS IN BHN 100% AS PER CODE H
SITSON INDIA PVT LTD Page 16 of 31
W-76, PHASE-II, MIDC, DOMBIVLI WHRB - QAP
FIT UP'S MEASUREMENT 100% 1 MM CLERANCE BETWEEN PIPE END AND SOCKET H
HARDNESS VALUE ONLY FOR P 91 / T 91 GRADE HARDNESS IN BHN 100% AS PER CODE H
FILLET WELD JOINTS FOR WELDING CONSUMABLES REVIEW 100% APPROVED CONSUMABLE LIST & WPS H
E)
STUCTURAL
FILLET WELDING SIZE OF GIRDER'S AND MAIN LOAD CARRYING
VISUAL 100% AS PER DRG. H
MEMBER'S
HYDROSTATIC TESTING - HYDRO TESTING TO BE CONDUCTED ONLY AFTER COMPLETION OF NDE,PWHT AS PER ATTACHED ANNEXURE - I & II RESPECTIVELY.ATTCHEMENT
12
WELDING WITH PRESSURE PARTS TO BE 100 % COMPLETE.
BOILER WATER FLUSHING CLEANING OF DIRT / METAL BURRS / METAL CHIPS / ANY FOREIGN NO DIRT/METAL BURRS/CHIPS & FREE FROM FOREIGN
A) VISUAL 100% H
(BEFORE HYDRO TEST) MATERIAL MATERIAL
WATER QUALITY & TEMPRATURE MEAUREMENT SAMPLE PH 8.5 TO 9.0 & TEMPRATURE -20 DEG C TO 45 DEG.C H
3O MINUTES AT TEST PRESSURE & -
HOLDING TIME MEASUREMENT 100% SUFFICIENT TIME FOR INSPECTION AT MAXIMUM H
ALLOWABLE WORKING PRESSURE
SOUNDNESS OF JOINTS VISUAL 100% NO LEAKAGE'S / NO PRESSURE DROP H
WATER QUALITY POTABLE WATER 100% PH 8.5 TO 9.0 & TEMPRATURE -20 TO 45 DEG.C H
13 ROTARY EQUIPMENT
FLANGE CONCENTRICITY WITH DUCT & EXPANSION BELLOW MEASUREMENT 100% .+/- 5 MM H
DEAREATOR TANK,BLOW
DOWN TANK, HP & LP
18
DOSING SKID ,Air FIT UP'S MEASUREMENT 100% .+/- 1 MM H
receiver Tank
SURFACE CLEANILINESS VISUAL 100% FREE FROM DIRT / GREASE / OIL / MOISTURE ETC. H
VISUAL &
21 PAINTING MIXING RANDOM MANUFACTURE'S PROCEDURE H
MEASUREMENT
INTIMATION TO BE GIVEN FOR WITNESSING THE STAGE / OPERATION. IN THE ABSENCE OF THE VISIT,VENDOR / TECC MAY PROCEED WITH
W WITNESS
THE NEXT STAGE / OPERATION AFTER SELF INSPECTION & RECORD
INTIMATION TO BE GIVEN FOR WITNESSING THE STAGE / OPERATION. VENDOR / TECC SHALL NOT PROCEED FURTHER UNLESS WITNESS OR
H HOLD
WIAVER IS GRANTED.
SW SPOT WITNESS FURTHER WORK CAN PROCEED WITH OUT INSPECTION BUT PARTIAL INSPECTION TO BE DONE AT APPROPRIATE TIME
NOTES :
A) (*) APPLICABLE FOR ONLY COMPONENTS DESIGNED,MANUFACTURED & INSPECTE UNDER ASMS CODE.
B) SCOPE OF INSPCETION SHALL BE ONLY FOR THE COMPONENTS / EQUIPMENTS SUPPLIED BY THERMAX AS PER PURCHASE ORDER
4.0) RECORD OF REVISION :
REV. DATE CHANGES
0 01-06-2023 FIRST ISSUE