12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Method Statement The Method Statement Resources


···
Home » Method Statement for Marble Wall Cladding

Method Statement for Marble


Wall Cladding

This Method Statement for marble wall cladding describes the


steps involved in the installation in accordance with approved shop
drawings, quality, and safety requirements.

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 1/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

···
Table of Contents
Scope of Works
Preparation

Your file is ready

DOWNLOAD
Ad

Wall Cladding System Methodology


Known Hazards and Controls
Health, Safety & Environmental Procedure for Method Statement for Marble
Wall Cladding

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 2/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Your file is ready

Download Now

Plant & Equipment


Tools
FAQ
What is marble cladding?

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 3/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Method of backfilling and plinth filling/Backfilling and plinth fi…

Scope of Works
This method covers the application of marble and granite works as wall
cladding for both exterior and interior areas.

All works shall be done in accordance with the approved Method


Statement and Project Specifications. Request for inspection shall be
submitted for Engineer’s approval prior to the commencement of the work.

···

Preparation
Survey mechanical fixings, backing structure, and grid lines datum against
approved shop drawing. Make sure all are as specified and approved by the
client.

Survey stone against approved drawing, (all correct depth, length, and height
molding specifications approved by client).

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 4/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Every marble will be drilled into four locations at its edges and will be installed
using a cladding fixing system as shown below.

Wall Cladding System Methodology


Ensure to have the correct PPE before accessing the scaffold, e.g. boots, hi-visual
vests/coats,
hard hats and gloves.

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 5/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

···

Access the scaffold under the project safety procedures implemented measures
via access provided e.g. fixed ladders, scaffolding, elevator, etc.

Using the approved drawing, mark the position on the wall where the self-
expanded anchor of the fixing set (as shown above) should be fixed.

Ensure to have the correct PPE prior to drilling the hole.

Ensure that the drilling depth is equal to the length of the specified anchor by
measuring the
length of the required anchor and transferring this to the actual drill bit while
monitoring that the correct diameter of the anchor is applied.

Drill the hole to the required depth.

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 6/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Mechanical fixing of support for marble stone panel / external stone cladding

Place your drill on the scaffold floor or other designated location, away from
walkways in order to eliminate trip hazards and burns.

Using a lump hammer drive the anchor into the drilled hole making sure the nut
is on, prior to inserting the anchor into the hole.

The fixing is now ready to bolt into position. Mount the fixing onto the anchor
and tighten using a torque wrench. Tighten to the required torque as per
specification approved by the engineer and client drawings.

Complete this process until all fixing sets are in location as per the approved
drawings.

Survey the location of the cladding system and measure the distance between
the two fixing
points on the wall.

Move the marble stones into the designated cutting area either by manual

handling or trolley if required, ensuring that any manual handling procedures
https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 7/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

are met and do not lift more than the specified weight of 20 kgs per person,
ensure another competent person assists in the lifting to transport the stone in a
safe manner.

Survey the stone dimensions as per project specification.

Once stones are ready to cut, wearing the correct PPE (gloves, glasses, P2 dust
masks) drill the holes into the stone.

Install the stone into the cladding fixing system by inserting the dowel into the
stone when
positioning the stone into the system.

···

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 8/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

···

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 9/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Marble wall cladding fixing of support bolts

Once the stone is in place check the face line, height, and depth location.

Repeat the process until all pieces have been installed.

Once all marble has been installed clean all areas and stone using clean water
and sponges.

··· ···

If close joints are required apply the grouting as per the project specification.

Use the grouting mix to grout the stonework. Mix as per manufacturers
specification, wearing rubber gloves to prevent injury e.g. cement or lime burns.
Using a grouting tool, grout up the joint and wash with clean water, make sure
to leave the grouting flush with the stonework unless otherwise specified.

···

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 10/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Know n Hazards and Controls


All operatives are to attend a site introduction prior to commencing any work.
The site induction will be carried out by the client.

···

All operatives will receive a RAMS toll box talk prior to any work commencing.

All operatives will receive a shift briefing prior to any work commencing at the
start of each day if required.

Hazard Control

Clear up any waste arising as work proceeds, and at least


Site Tidiness daily, store surplus materials in a designated place and all
rubbish in the skips and bins provided. 

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 11/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

All operatives will comply with client site rules PPE, safety
Personal
footwear, safety helmet, goggles/glasses, gloves class 3 cut
Protective
protection, and high visible coat/vests at all times when in
Equipment
the work areas. Hearing protection and fp2 masks will be
(PPE)
worn for specific tasks as identified in the risk assessments.

All operatives will comply with client site rules PPE, safety
footwear, safety helmet, goggles/glasses, gloves class 3 cut
Working at
protection, and highly visible coat/vests at all times when in
Height
the work areas. Hearing protection and fp2 masks will be
worn for specific tasks as identified in the risk assessments.

The most appropriate access equipment shall be used


depending on the nature of the work e.g. scaffolds, alpha
step podium step. Only competent staff are employed to
work at height. The work will be organized so that possible
falls from height are minimized. Effective fall protection
Members of measures will be taken e.g. guardrails & toe boards are fitted
the Public to all work platforms and staging.
Areas below where work at height is being carried out will
be fenced off, as necessary, to prevent injury from falling
objects. Waste materials will be transferred to ground level
in a controlled safe manner. The work area is isolated from
the staff areas so no contact is to be expected.

Stone is of the smallest size practicable. Operators know


Manual
and follow a safe system of work for the lifting of the
Handling
maximum weight for an individual manual lift.

Slips & Trips All operatives wear safety boots. Good housekeeping is
ensured eg debris is put in skips and brush is available to
keep the work area clear. All trailing cables in the work area

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 12/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

are hung up or otherwise kept out of harm’s way. Safe route


to job agreed with site manager based on site H&S plan.

Agreement with site manager that staff may use site welfare
Welfare facilities – toilets, washing facilities with hot & cold water,
and mess room/kitchen.

Health, Safety & Environmental


Procedure for Method Statement for
Marble Wall Cladding
Emergency Procedures
The details of any accident on site shall be entered into the accident book in the
site manager’s office.

···

All reportable accidents/incidents will be investigated and copies of our formal


investigation reports including relevant support documentation, conclusions, 

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 13/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

and recommendations will be provided by the client.

All accidents/incidents reported to the client and report form completed. An


investigation report will be compiled for client records.

Ensure that employees are aware of the location of the fire-fighting equipment,
means of escape, assembly point, and means of raising the alarm.

Environmental Information
Exposure to stone dust – Stone dust will be cleared up using a suitable vacuum
cleaner, fitted with an appropriate filter. Suitable respiratory protective
equipment, as well as LEV for very dusty jobs, and staff, trained in how to use it.

Staff does health surveillance questionnaires before starting, then annually.


Any affected staff referred to a medical professional.
Noise – Noisy works to be kept to a minimum.

Communication w ith Site Workers


The operatives on-site will receive a full RAMS briefing and start of shift briefing,
prior to any works being carried out. A trained and competent working
supervisor will ensure that the work is carried out as detailed in the method
statement.

···

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 14/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

All contractors working on-site will attend client site inductions prior to
commencing work on-site, they will also be given site induction, and records of
inductions will be kept in the site manual.

Our workers will attend any Tool Box Talks or Safety Committee meetings and
will suffer no loss of earnings as a result of their involvement.

Welfare: The welfare facilities will be located within the work area with existing
toilets and rooms for rest and change will be used.

···

Water facilities and electrical power are to be provided by the client.

Operatives will not travel through any public areas with dirty/dusty PPE on.
Changing facilities are available within the site to enable this to be achieved.

Plant & Equipment


All portable electrical equipment on site will be 110 volts coming from either a 
transformer or a generator. All hand and power tools and cables/hoses will be
https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 15/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

maintained, and be in good condition and routine inspections will identify no


split insulation, bad connections, homemade repairs, etc.

All cables should be kept as short as possible across the site and be kept as tidily
as possible to avoid causing a tripping hazard or any damage to the cable
occurring due to site conditions.

Hand and power tools will be properly maintained by:

Formal visual inspections


Checks by user
Power tool checks will be carried out weekly and submitted to the client if
required.

All tools/sharps will under no circumstances be left unattended. After use, they
will be removed from the site & locked away in a secure storage safe within the
site which is to be provided by the client.

···

Tools

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 16/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Battery operated drills


Hand tools
Power tools

FAQ
What is marble cladding?
Marble cladding is a way to add the value of beauty and aesthetics both in the
interior and exterior of any space. With cladding, the existing structure is
covered with layers of marble to give it the appearance of being entirely made
of real stone.
tags: method statement for marble wall cladding, wall cladding, approved shop drawings, method
statement, stone flooring, approved method statement, mechanical fixing, marble flooring installation,
safety procedures, site engineer, access and interface requirements, mechanical method statement,
floor slab, uniform lump free consistency, stone panel, bed mortar method, foreign materials, grout
residue, plastic covers, sand mixture, flat trowel, required format, locations marked, inspection plan,
expansion shell

        

Method Statement of Sanitary Wares, Method Statement for Curtain Wall-


Fittings & Accessories Installation Glazed Installation

Related Post

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 17/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Method Statement for Erecting Sandwich Panels

GRC Method Statement

Method Statement for Wooden Door Installation

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 18/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Se arch

Search

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 19/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

themethodstatement.com recommends this! QA/QC Templates Fully Customizable-


Download Now!

Recent Posts

How to Write an ITP Inspection and Test Plan for Construction?

Method Statement for Erecting Sandwich Panels

Method Statement for Transmission Line Conductor Installation

Method Statement for General Pumps

Method Statement of Static Load Pile Testing


https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 20/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Categories

Method Statement for Architectural Discipline

Method Statement for Electrical Discipline

Method Statement for HVAC

Method Statement for Mechanical

Method Statement Knowledge

Method Statements for Civil Discipline

Risk Assessment

Testing and Commissioning

Archives

November 2023

October 2023

September 2023

August 2023

July 2023

June 2023

May 2023 

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 21/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

April 2023

March 2023

···

This Might Interest You

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 22/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

Method Statement Knowledge

How to Write an ITP Inspection and Test Plan for Construction?

Method Statement for Architectural Discipline

Method Statement for Erecting Sandwich Panels

Method Statement for Electrical Discipline

Method Statement for Transmission Line Conductor Installation

Method Statement for Mechanical

Method Statement for General Pumps

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 23/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

··· ···

Me t h o d St at e m e n t
The Method Statement Resources

    

2023 Copyright © All rights reserved | Blogus by Themeansar.


Privacy Policy Disclaimer Terms and Conditions About Us Contact Us

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 24/25
12/9/23, 7:55 AM Method Statement for Marble Wall Cladding

https://themethodstatement.com/method-statement-for-marble-wall-cladding/ 25/25