Professional Documents
Culture Documents
O20361-Q-VIA-CM-ME-35204 (Rev A)
O20361-Q-VIA-CM-ME-35204 (Rev A)
O20361-Q-VIA-CM-ME-35204 (Rev A)
CONTENTS
1 INTRODUCTION 7
2 SCOPE 7
3 TERMS AND DEFINITIONS 8
4 REFERENCES 8
5 ROLES AND RESPONSIBILITIES 9-13
6 MANPOWER 13
7 MATERIAL 13-15
8 FORMWORK METHODOLOGY 16-17
9 QUALITY CONTROL, INSPECTION AND TESTING 17
10 ENVIRONEMNTAL & SAFETY PRECAUTIONS 17-18
11 INSPECTION & TESTING PLAN 18
12 FORMAT & CHECKLIST 18
Page 4 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
Page 5 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
Page 6 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
1. Introduction
The Mumbai – Ahmedabad High Speed Rail (MAHSR) Project is the first High Speed Rail (HSR)
network planned to be constructed in India. The MAHSR Project line connects Mumbai, located
in Maharashtra State with Ahmedabad in Gujarat State, passing through one Union Territory,
Dadra and Nagar Haveli (refer Figure 1). The entire stretch is divided into 8 packages from C1 to
C8.
C4 Package of High Speed Rail Project is awarded to L&T Construction. This package consists
of four stations namely, Vapi, Billimora, Surat and Bharuch and other structures viz viaducts,
SMD, Ramp, etc. C4 package starts from Ch. 156.6 km at Zaroli village to Ch. 393.7 km which
ends near Vadadora. It covers approximately 237.1 km in this package. The alignment of the
MAHSR C4 package is shown in Figure 2.
Page 7 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
4. References
• Clause Nos. 3 and 4 of Division 2000, Technical Specifications of Employer’s Requirement
• IRC 87-2018 – Clause No. 10
• IRC CBC- Clause Nos. 4.5.2, 6.2.5, 6.3 and 6.4.
• For detailed procedure on concreting technology refer the Method Statement on Concrete
Production, Transportation and Placement: (MAHSR/L&T/PKG/C4/QA/QC/CONC/0008)
Page 8 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
Project Director
Section-in-Charge
Production In-
Charge
Shift-In-Charge QA/QC EHS P&M
Engineer Engineer Engineer
5.1 Section-In-Charge:
• Reports to Project Director
• Plan resources in his area and make them available at site
• Monitor the works qualitatively and quantitatively
• Responsible for time cycle & achievement for the days plan
• Responsible to have latest revisions of approved drawings at site
• Responsible to submit, take approval and implement work method statements
• Initiate and apply all safety norms and work practices
• Interact with Customer for approvals
• Responsible for handing over of completed section for next process owner or Customer
• Keep track of Internal/Customer complaints on quality, their compliance, control on repetitions
and guide/support the execution team under him
• Suggest and implement improvements to product quality
Page 9 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
5.2 Shift-In-Charge:
• Reports to Section-In-Charge
• Plan all sub-activities in his area
• Responsible for all activities in his shift and ensure hand over and take over process between
shifts
• Responsible for good industrial practice to place the concrete with a suitable means that will not
segregate the concrete ingredients
• Deliver the work in qualitatively and quantitatively manner
• Responsible for taking over works from process owners of previous works
• Responsible for implementation of approved work method statement
• Raise RFIs and initiate inspections along with Customer
• Coordinate with QA/QC team for field testing of concrete & other construction material
• Ensure sequence of construction is being followed
• Interact with all internal teams to achieve targets
• Apply good industrial practices
• Responsible for adequate curing of concrete
• Responsible to implement safe work practices
• Responsible for preparation and take approval of correction procedures and methods for any
defective members of structure are identified and implement them accordingly
• Responsible for screening of workmen under his purview
• Suggest and implement improvements to product quality
5.3 Production-In-Charge:
• Reports to Project Manager
• Arrange all resources required for production of concrete
• Coordinate and arrange for calibration of concrete batching plant at pre-scribed intervals.
• Coordinate with QA/QC team to implement approved mix design
• Responsible to implement approved methods of production of concrete
• Interact with all internal teams to achieve targets
• Responsible to implement safe work practices
• Responsible for screening of workmen under his purview
Page 10 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
5.6 Surveyor:
• Report to Shift-In-Charge
• Ensure only calibrated survey instruments are used during construction
• Responsible for marking levels and fixing coordinates of the structure
Page 11 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
• Responsible for marking of centre line of piers, abutments, piles and boundaries of foundations
• Responsible to mark alignment
• Responsible for taking levels before and after concrete placement and report to Section-In-
Charge and Shift-In-Charges on achievements and lapses.
• Responsible for safeguarding TBMs and centerline pegs/spikes
• Responsible for calibrating and recalibrate TBMs and centerline pegs/spikes.
Page 12 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
• Ensure lock-out and tag-out system while attending breakdown and/or maintenance
• Suggest and implement, improvements to product quality
6. Manpower
• The project will be divided into 5 sections and each section will have a project director.
• Manpower shall be deployed as per requirement.
• A safety steward will be available at every work location, so as to monitor all the working
machineries at a location.
• The total availability of manpower shall be submitted separately.
7 Materials
7.1 Reinforcement Steel
• High strength deformed steel bars for concrete reinforcement used in the works shall be
Fe500D/Fe550D TMT, conforming to IS 1786 and manufactured by SAIL/TATA
STEEL/JINDAL/JSW STEEL/RINL/IISCO.
• No rerolled steel shall be used.
• Reinforcement steel shall be stored as per IS 4082.
• The reinforcement bars shall be bent to conform to the dimensions and shape shown in the drawings
and Appendix -7, Division 2000, Technical Specifications of Employer’s Requirement. However,
Page 13 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
any change in bar bending to suit construction feasibility will be followed as per approval from the
engineer.
• Bars shall be bent cold and any bent reinforcement shall not be re-bent. However, when it is
unavoidable to re-bend the reinforcement, the same shall have approval from the engineer.
• Placement of reinforcement shall conform to the provisions laid down in IRS - CBC (CL. 7.1.3)
(Refer Appendix-1). Cover and spacing of steel shall be uniform and as specified in the
specifications and as shown in the drawings.
• Uncoated reinforcement steel shall be protected from rusting or chloride contamination.
Reinforcements shall be free of rust, mortar, loose mill scale, grease, oil or paint.
• Cover blocks shall be firmly placed at appropriate intervals to maintain specified concrete cover to
the reinforcement. The number of cover blocks to be provided shall generally be 4 pieces per square
meter for the bottom surface of the member and about 2 to 4 pieces per square meter for the side
surface of the member. Cover blocks shall be made of concrete or mortar having quality equal to or
superior than that that of the parent concrete.
• Procurement of reinforcement steel shall be so phased by the contractor that the storage period
before its actual use in the works is limited to the bare minimum as directed by the Engineer.
• All reinforcement bars are properly tagged for easy identification.
• Tolerances & Criteria:
Tolerances and criteria for reinforcement work shall be as specified in Table 2.
Page 14 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
• Lapped splices - Standard design drawings indicate the locations of splicing of bars. Other than
those, no splicing of bars shall be permitted without prior approval of the Engineer. Lengths of
splice, wherever required, shall be as indicated on the Standard Design drawings and/or shop
drawings subject to a minimum length of 40d for rebar diameter ‘d’ less than 25mm and 50d for ‘d’
greater than or equal to 25mm and 50d for 'd' greater than or equal to 25mm, approved by the
Engineer. Lapped splices shall be staggered and located at points along the span where stresses are
low, unless otherwise indicated in Standard Design drawings, other parts of the Technical
Specifications or approved by the Engineer.
• Mechanical Joints - Standard Design drawings indicate the locations of jointing of bars. Other than
those, no jointing of bars shall be permitted without obtaining approval of the Engineer. Quality
control of mechanical joints shall be as per IS 16172.
• Design Adjustment - Where the diameter of the reinforcement bar is not greater than 32mm, lapped
splice may be changed to mechanical joint or vice-versa, subject to the Engineer’s approval.
• GI Binding wire shall conform to the provisions laid down in IS 280 and IS 2502.
Page 15 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
8. Formwork (Methodology)
General-
• Formwork shall be designed in consideration of appropriate raising (camber) against sinking and
deformation due to the weight of the concrete during construction and after completion.
• Ties shall not be welded to the reinforcement bars with the exception of distribution reinforcement
and other reinforcements which do not contribute to structural performance. Clear cover to the end
of the ties shall not be less than 25 mm. Filling of tie locations after removal of formwork shall be
carried out with dry pack cement mortar.
Design-
• The foundation of all supports shall be designed to suit the bearing capacity of soil to support the
designed loads without settlement.
• Shop drawing showing the arrangement of formwork for structural members including shoring
system, horizontal and diagonal bracing system, details of foundation shall be prepared. The sizes
of individual members shall be as per the design calculations.
• If proprietary system of formwork (L&T Formwork system, Doka formwork system, etc.) is used
to overcome practical issues due to site / structure to be cast, detailed drawing and design shall be
submitted to the engineer for approval.
Finishing of Formwork-
• Finishing shall conform to IRS: CBC (CL. 6.2.4 and CL. 6.2.5) (Refer Appendix-1).
Cleaning and Treatment of Forms-
• Cleaning and treatment of forms shall conform to IRS: CBC (CL. 6.3) (Refer Appendix-1).
Specialized Formwork (Slip Form)-
• For slip form, the rate of slipping the formwork shall be designed for each individual case
considering various parameters including the grade of concrete, concrete strength, concrete
temperature, ambient temperature and concrete admixtures.
• In order to verify the time and sequence of striking or removal of specialized formwork, routine
field tests for the consistency of concrete and strength development are mandatory and shall be
carried out before adoption.
Stripping and Removal of Formwork-
• Stripping time shall confirm to provisions laid down in IRS: CBC (CL. 6.4) (Refer Appendix-1).
Page 16 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
• The scheme for removal of formwork (i.e., de-shuttering and decentring) shall be planned in
advance.
• The formwork shall be removed in such a manner that does not cause any damage to concrete.
Centring shall be gradually and uniformly lowered in such a manner that it permits the concrete to
take stresses due to its own weight uniformly and gradually to avoid any shock or vibration.
• Where there are re-entrant angles in the concrete sections, the formwork shall be removed at these
sections as soon as possible after the concrete has set to avoid cracking due to shrinkage of
concrete.
Page 17 of 18
Sensitivity: LNT Construction Internal Use
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Formwork &
Mumbai-Ahmedabad High Speed Rail Reinforcement
(Package No. MAHSR –C-4) O20361-Q-VIA-CM-ME-35204, Rev. A
• Check for the working condition of safety valves of air compressors, if compressed air is being
used for cleaning.
• Necessary safety signboards and precautionary boards shall be placed near working locations.
• Safety stewards shall conduct daily checking to ensure the working areas are safe.
• Daily pep-talks shall be conducted to all workers at site to create awareness and to follow
safe working practices.
• Drinking water, toilet and rest place shall be suitably located for the easy access to
workers. All the facilities shall be properly cleaned and maintained during the entire period
of operation.
Page 18 of 18
Sensitivity: LNT Construction Internal Use
APPENDIX- 1
SITE QUALITY MANAGEMENT PLAN
LARSEN & TOUBRO LIMITED
METHOD STATEMENT- Formwork & Reinforcement
HCI IC
Mumbai-Ahmedabad High Speed Rail (Package No. MAHSR –C-4)
O20361-Q-VIA-CM-ME-35204, Rev.A
Independent test check on quality of steel from each lot (each heat number) shall be conducted. All reinforcement
Independent test on steel 4.5.2 of IRC CBC
shall be free form loose small scales, rust and coats of paints, oil, mud etc.
1
Moulds for pretension works shall be sufficiently strong and rigid to withstand, without distortion, the effects of
Finishing of Formwork 6.2.5 of IRS CBC placing and compacting concrete as well as those prestressing in case of manufacture by the individual mould
2 process where the prestressing tendon is supported by the mould before transfer.
1. All rubbish particularly chippings, shavings and sawdust shall be removed from the interior of the forms before
3
Cleaning and treatment of the concrete is placed and the formwork in contact with the concrete shall be cleaned and thoroughly wetted or
6.3 of IRC CBC
forms treated with an approved release agent.
2. Care shall be taken that such approved release agent is kept out of contact with the reinforcement.
1. Forms shall not be struck until the concrete has reached a strength at least twice the stress to which the concrete
may be subjected at the time of removal of formwork.
2. The strength referred to shall be that of concrete using the same cement and aggregates, with the same
Stripping time of propositions and cured under conditions of temperature and moisture similar to those existing on the work. Where
4
Formwork 6.4 of IRC CBC possible, the formwork shall be left longer as it would assist the curing.
3. In normal circumstances and where ordinary Portland cement is used, forms may generally be removed after the
expiry of the following periods:
1. Crossing bars should not be tack-welded for assembly of reinforcement unless permitted by the engineer.
At all intersections, reinforcing bars shall be securely bound together with 1.6mm dia mild steel wire in
accordance with IS:280 or with approved reinforcement clips. The free ends of the binding wire shall be
bent inwards. For aggressive environment, galvanized binding wire shall be used.
2. All steel fabrics shall be lapped two meshes unless otherwise shown on the drawing and securely bound to
the supporting bars with 1.6mm dia mild steel wire (IS:280) or approved reinforcement clips. The free ends
of the binding wire shall be bent inwards. Proper cutting pliers shall be used and the wire binding and tying
shall be done as tightly as possible.
3. Unless otherwise specified by the engineer, reinforcement shall be placed within the following tolerances:
(a) For over all depth 200 mm or less : ± 10mm
(b) For over all depth more than 200mm : ± 15mm
Placement of 7.1.3 of IRS CBC
5 The cover shall, in no case, be reduced by more than onethird of specified cover or 5mm whichever is less.
Reinforcement
4. Spacers should be of such material and designs as will be durable, will not lead to the corrosion of
reinforcement and will not cause spalling of the concrete cover. Spacer block made from cement, sand and
small aggregates should match the mix proportion of the concrete as far as is practicable with a view to
being comparable in strength, durability and appearance. The use of the pieces of wood, tile or porous
material will not be allowed for this purpose.
SITE QUALITY MANAGEMENT PLAN
LARSEN & TOUBRO LIMITED
HCI IC INSPECTION & TEST PLAN
Mumbai-Ahmedabad High Speed Rail (Package No. MAHSR –C-4)
O20361-Q-VIA-CM-ME-35204
APPENDIX-2 (Inspection & Test Plan)
Reinforcement
Carbon, Sulphur,
8 Steel- Chemical TPT -do- -do- -do- -do- MTC/TPR R R
Phosphorus Content
Analysis
Review of MTC of Each Lot
9 Tensile Strength TPT IS 1608 and Third Party Testing once Clause no. 9.1 of IS 280- 2006 Shall conform to Table-2 of IS 280-2006 MTC/TPR R R
per source
Wrapping Test (for wire The wire shall withstand without breaking or splitting being
10 smaller than 5mm TPT IS 1755- 2018 -do- Clause no. 9.2 of IS 280- 2006 wrapped eight times round its own diameter & subsequently MTC/TPR R R
diameter) straightened
The wire shall withstand being bent through an angle of 90 0
Bend Test (for wire of 5mm
11 Binding Wire TPT IS 280- 2006 -do- Clause no. 9.3 of IS 280- 2006 round a former of diameter equal to twice its own diameter MTC/TPR R R
diameter & over)
without breaking or splitting.
1. Galvanized coating of steel wire shall conform to the
requirements for any of the type of coatings given in IS
4826- 1979.
12 Coating Test TPT -do- -do- Clause no. 11 of IS 280- 2006 MTC/TPR R R
2. Coating requirement of electro galvanized wires shall
conform to the requirements for any of the type of coating
given in IS 12753-1989.
#
Format No.:
LARSEN & TOUBRO LIMITED MAHSR-C4/CF-01
HCI IC
APPENDIX-3 (FORMATS AND CHECKLISTS) Rev.No. A
Not Satisfactory
S.No. Description Satisfactory (Ok)
(Not Ok)
REMARKS : : ………………………………………………………………………………………………………
………………………………………………………………………………………………………
Name: Name:
Date: Date:
Signature: Signature:
Format No.:
LARSEN & TOUBRO LIMITED
MAHSR-C4/CF-01
HCI IC
Rev. No. A
REMARKS : : ………………………………………………………………………………………………………
………………………………………………………………………………………………………
Name: Name:
Date: Date:
Signature: Signature:
Environment, Health and Safety
Integrated Management System Manual
1 Barricading done for the work area with one entry/exit point
Workers transported from camp to work site in disinfected company
2
exclusive vehicle
3 Workers only from Labour camp deployed for work
11 Medical check-up for all people present in site at least once in a week
16 Posters with Do’s & Don’ts during this situation displayed in worksite
Tool box meeting to be done covering general guide lines for workers
such as
(a)Wearing of face cover/mask (b) Avoid shaking of hands (c) consumption
of Liquor, Gutkha, Tambaku, Paan etc is strictly prohibited (d) Spitting in
17 public places is prohibited (e) gathering in groups to be avoided (f) clean
their hands with soap/hand sanitizer frequently (g) Avoid touching mouth,
eyes and nose (h)Avoid sharing of food, water, utensils, mobile phones etc
(i) Maintain social distancing while travelling inside the vehicle (j) maintain
safe distance from each other