Submission of Revised Method Staterment Survey Setting Out For Foundations and Piers
Submission of Revised Method Staterment Survey Setting Out For Foundations and Piers
CONTENTS
1 INTRODUCTION 6
2 SCOPE 6
3 REFERENCES 7
4 ORGANIZATION CHART 7
5 ROLE AND RESPONSIBILITIES 8
6 RESOURCE 9
7 DEFINITION AND ABBREVATION 10
8 PROCESS 10
9 WEATHER LIMITATION 15
10 SAFETY ASPECT 16
11 TRAINING AND EDUCATION 16
12 INSPECTION PLAN 17
13 TEST PLAN 18
14 ANNEXURE 19
Annexure A- Work record Formats and Checklist Formats
Annexure B- EHS Formats and Documents
Annexure C- Incident Flow Chart
Annexure D-Tolerances of the Finished Structures
Organization Chart
Fig.3 7
Table 1 Material 9
Table 2 Manpower 9
Table 3 Machine, equipment, Tools and Tackles 9
Table 4 Weather Limitations 14
1. INTRODUCTION
The Mumbai – Ahmedabad High Speed Rail (MAHSR) Project is the first High Speed Rail (HSR) network
planned to be constructed in India. The MAHSR Project line connects Mumbai, located in Maharashtra State
with Ahmedabad in Gujarat State, passing through one Union Territory, Dadra and Nagar Haveli (refer Figure
1). The entire stretch is divided into 8 packages from C1 to C8.
The Package C4 of High-Speed Rail Project is awarded to L&T Construction. This package consists of Design
and Construction of Viaduct and Bridges, Tunnels, Earth Structures, Building works for four stations namely,
Vapi, Billimora, Surat and Bharuch and other structures viz SMD, & Ramp, etc. The scope of workfor this
package starts from Ch. 156.6 km at Zaroli village at Maharastra -Gujrat Border to Ch. 393.7 km which ends
near Vadadora. The MAHSR Project line covers length of 237.100 km in this package. The alignment of the
MAHSR C4 package is shown in Figure 2.
2. SCOPE
The Scope of work of this Method Statement covers Survey Setting Out for Foundations, Piers and Pier Caps
from the established control points as per “Method Statement of Establishing the Horizontal and Vertical
Control System and Topographic Survey” & “Method Statement for HSR Benchmark Establishment Plan”.
Reference points shall be protected during construction and should be handed over all the points back to the
Engineer after completion of work, as per requirement. The purpose of this document is to prepare a system for
execution and control on the survey activities which is to be performed sequentially to achieve the specified
product. This Procedure is applicable for setting out of survey for foundations, Piers, Pier Caps and other sub-
structures including marking the center line of alignment on Pier cap for superstructure works of Via-ducts,
Stations, Depots, TSS and other structures.
3. REFERENCE
Latest revisions of the following Method Statements / Drawings shall be applicable for execution:
a. Method Statement for Establishing the Horizontal and Vertical Control System and Topographic
Survey with NONO issued vide letter NHSRCL/ST/MA/04/NHSRCL-MAHSR-C-4:
Correspondence/88/.1/2446 dated 24.12.2020
b. Method Statement for HSR Benchmark Establishment Plan with NONO issued vide letter
NHSRCL/ST/MA/04/NHSRCL-MAHSR-C-4: Correspondence/88/.1/2447 dated 24.12.2020
c. GNSS Benchmark & Control Points
d. Alignment “Plan and Profile” Drawing
• Sec-I ‐ XX‐XXX-XXX-XX (Sheet XX to XX)
• Sec-2 ‐ XX‐XXX-XXX-XX (Sheet XX to XX)
• Sec-3 ‐ XX‐XXX-XXX-XX (Sheet XX to XX)
• Sec-4 ‐ XX‐XXX-XXX-XX (Sheet XX to XX)
• Sec-5 ‐ XX‐XXX-XXX-XX (Sheet XX to XX)
e. General specification requirements in Contract Clause 6 & Clause 7 of Division 06020 of General
Specifications.
4. ORGANISATION CHART
TFL HEAD
G. VINOD
TECHNICAL HEAD
N. KAUL
PROJECT DIRECTORS
(6 Nos)
CHIEF
QA HEAD SURVEYOR
S. MANI
I. Chief Surveyor
o Reports to the Technical Head.
o Interacts with the Engineer’s Representatives and Internal departments.
o Reviews program and progress along with the Section Heads / Project Directors (6 no’s).
o Liaison with internal departments like Planning, Quality control, Plant & Machinery, Safety
and Stores for achieving the set targets.
o Ensures safe working condition and safe acts of all work men, machineries etc.
o Prepares daily, weekly & monthly program.
o Monitors progress as per the set program.
o Ensures preparation of process related reports as per this procedure.
o Responsible for implementation of all EHS requirements related to this procedure.
o Responsible for maintaining and updating of calibration certificates of all survey instruments.
o Responsible for correctness of X,Y,Z values of Survey Control points and to circulate the list of
survey control points once in three months to all concerned Site Representatives.
III. Surveyor
o Reports to the Sr. Surveyor
o Study drawing before setting out any survey work
o Responsible for survey work at site as per site requirement.
o Responsible for accuracy of survey work at site.
o Responsible for executing the EHS requirements of this procedure while setting out.
o SURVEY ASSITANT
o Reports to the Surveyor and help him to do survey work at site with accuracy and safety.
6. RESOURCES
6.1 Materials for Each Survey Team
6.3 Machines, Equipment’s, Tools & Tackles (for each Survey Team)
8. PROCESS
8.1 Sequence of Activities
i) Follow the Definitions and Abbreviations in surveying activities.
ii) Keeping the list of Benchmarks and Control points- Horizontal and Vertical control points.
iii) Quarterly validation of above control points and circulating them
iv) Marking for foundation excavation area on ground.
v) Marking for centerline (X & Y) of foundation on PCC
Sensitivity: LNT Construction Internal Use
Page 10 of 37
LARSEN & TOUBRO LIMITED SITE QUALITY MANAGEMENT PLAN
HCI IC METHOD STATEMENT- Survey Setting Out for
Mumbai-Ahmedabad High Speed Rail Foundations, Piers and Pier Caps
(Package No. MAHSR –C-4) MAHSR-L&T/PKG/C4/QAQC/SUR/0036
Rev.01
vi) Marking the centerline (X & Y) on foundation for pier starter / kicker
vii) Marking the centerline (X, Y, Z) on top of pier cap
viii) Reporting and submission of survey records.
8.2 GNSS Benchmarks and Control points - (Procedure for starting the work) Control of Global
Navigation Satellite System (GNSS)
Refer Method Statement for Establishing the horizontal & Vertical Control system and
Topographic Survey (Document no – 020361-S-ALL-00-MS-90000 Rev 02) and Method
Statement for HSR Benchmark Establishment Plan (Document no – 020361-S-ALL-00-MS-90001
Rev 01)
Total Station
Distance Accuracy 1mm+1.5ppm
Angle accuracy 1”
Level Instrument
Accuracy 1 mm
8.4.1 General
• Survey data shall be read out from approved drawings, specifications, or other documents
approved by the Employer / the Engineer OR their representative.
• The Surveyor shall keep his drawings updated and well organized. He obliges to completely
understand the contents given by the drawings.
• Dimensions and measurements given on drawings shall be checked by the Surveyor, and if
there is some indistinctness, it shall be clarified before the Surveyor uses the drawings for
survey works.
• The Chief Surveyor shall be responsible for the correctness of survey reference data.
stations, GNSS Benchmarks and control points, pegs, profiles, rails, marks, etc., are protected.
The markings shall be regularly inspected for damage or dislocation. The markings shall be
re‐set out if found displaced. The Surveyor should keep his instrument data‐memory updated,
and after the day’s work these should be downloaded and printed out. These files should be
used for the survey works. The printout should correspond to the survey documentation under.
It should be ensured by Chief surveyor that all surveying and setting out records are identifiable
and rectified if required and kept at the site office. All records should clearly identify the works
that has been carried out.
Survey Documentation:
Record sheet should be prepared by the surveyor for all his work. Record sheets should carry
the following information as applicable:
Work description.
Date of survey work.
Name of surveyor responsible.
Instrument used.
Referenced drawing number.
Referenced survey stations.
Instrument memory files print out (Day survey work).
These field documents should be available for the reference of client representative.
Setting Out
The Surveyor shall be obliged to learn and completely understand the functions of his
instrument and the software accompanied with the instrument.
8.5 Procedure for Establishment of straight section of alignment using NSCP pillar (until TSBM
establishment):
Part A – Construction of control pillar
1. Stacking of the designed TS & ST points on ground by RTK method with fixing the base on
nearest NSCP pillar.
2. Stacking out of the control pillar near the proposed construction location at every 250 m approx. on
the ground by RTK method with fixing the base on nearest NSCP pillar. The control points shall be
on the straight alignment in between TS & ST.
3. Casting the centerline pillar of “TS”, “ST” and the “control point near the proposed construction
location on stack out location:, with steel plate centrally fixed on the top surface of the pillar.
Part B – Establishment of grid coordinates on control pillars
1. Repeat the point 1 & 2 of Part A and temporarily mark the point on the steel plates on all pillars.
2. Place the DGPS on temporary marked point and observe the coordinates by static survey method.
3. All the observed coordinates of TS, ST and control points shall be marked in the AutoCAD
drawing. Straight line shall be drawn on between TS and ST. The position of control points shall
be observed w.r.t. the straight line marked between TS and ST. If any control point is deviated
beyond +/-3mm from the straight line, then the same shall be noted and corrected at site
accordingly.
4. The static survey (steps 1, 2 and 3 of Part B) shall be repeated till all the control points fall with +/-
3mm of straight line.
Part C – Establishment of Total Station / Ground Control Points
1. Since bearing of line in between TS and ST is fixed by above method, therefore ground coordinate
should be generated by total station by measuring distance and correcting it (if required) by scaling
(grid to ground).
2. Cross verification of bearing should be done by static survey.
3. Setting out of foundation, pier and pier cap shall be done accordingly by these ground coordinates.
The above method shall be complied only till the establishment of TSBM.
205km 472m
206km 059m
1 206km 480m
204km 753m
205P1
204P1
206P1
2
988 m
205km 447m
206km 435m
1022 m
204km 425m
Procedure of setting Out of Foundation Layout for Excavation using NSCP pillar (until TSBM establishment):
Project Alignment
References Lines (Ref-01- Ref-03 along the alignment; and Ref.-02 – Ref.-04 across the alignment)
shall be established defined by the Ref. points on the ground as in sketch above at a distance not
less than 2 m. from the edge of excavation / structure.
Each of these References Line shall be extended further by setting Extension points on each of
these lines, at least 10 m. from the reference points above.
The co-ordinates of these Reference points and Extension points shall be preserved so as to re-
establish them from the nearest control points, in the event of any damage to them.
The centre lines from these pair of Reference-Extension points shall be used to give the Centreline
of the structure in both directions for setting out the works on ground and raising the structure.
8.6 Procedure of Setting Out of Center Line on Top of PCC using NSCP pillar (until TSBM
establishment):
After excavation completed, and a safe access provided as per the Construction work procedure for
foundation, marking for center line (X,Y) on top of PCC for foundation shall be done from the
Ground Control Points established as per 8.5 above.
The foundation center should be marked in form of butterfly shape on top of PCC with red colour
paint.
8.7 Procedure of setting out of Foundation Centerline using NSCP pillar (until TSBM
establishment):
After pier foundation cast, marking for Foundation centerline (X,Y) on top of concrete should be
done from the Ground Control Points established as per 8.5 above. The foundation center should
be marked in form of butterfly shape on top of foundation concrete with yellow colour paint. This
marking should also be used as reference for the starter / kicker of pier.
8.8 Procedure of setting out of Pier Centerline using NSCP pillar (until TSBM establishment):
After pier cap concrete completed, and a safe access provided to the top of pier cap as per the
Construction work procedure for pier & pier cap, marking for center line (X,Y) on top of pier cap
should be done similar to procedure mentioned above (from the Ground Control Points established
as per 8.5 above). The pier center should be marked in form of butterfly shape on top with red
colour paint.
8.9 Procedure of setting Out of Bearing Pedestal Centerline on Pier Cap using NSCP pillar (until
TSBM establishment):
After pier cap concrete completed, and a safe access provided to the top of pier cap as per the
Construction work procedure for pier & pier cap, marking for center line (X,Y) for bearing
pedestals on top of pier cap should be done similar to procedure mentioned above (from the Ground
Control Points established as per 8.5 above). The pedestal center should be marked in form of
butterfly shape on top with red colour paint.
8.10 Procedure of setting Out of Alignment, Foundation, Pier, Pier Cap, Bearing Pedestal using
TSBM pillars (post TSBM establishment)
Once the TSBM pillars are established, the same (along with other established Bench Marks / Check
Points) will be used to setting out of the structures. Min 3 nos of established benchmarks (in the near
vicinity of the structure), will be used for any setting out activity.
including checks on mapping, survey stations, co‐ordinates and setting out, updated topographic
survey and survey drawings should be prepared and submitted to the Engineer. The following
records should be retained for entire duration of project at project document control room.
Control Record: GNSS Benchmarks and Control Points.
Request for Inspection / Survey Control forms
Please refer Annexure A for all work record Formats and Checklist Formats. These formats are
prepared for checking and monitoring purposed and can be further modified as desired.
8.14 Clearances
Structures shall not infringe the clearances specified in the Contract – Schedule of Dimensions
9. WEATHER LIMITATIONS
Rainy The total station instrument is very The Total station should be protected
sensitive which may have adverse effect immediately by shading with umbrella and the
in drizzling or Raining. ongoing activity should be suspended if rain
starts.
Table 4
Please refer Annexure B for RISK ASSESSMENT SUMMARY SHEET and RISK
ASSESSMENT FORM SAF‐20 and Matrix for Risk Assessment.
1. Daily safety Tool-Box talk should be given by Managers to the staff and workmen.
17 OF 37
Remarks: List of calibration of GNSS Bench mark and Control Points shall be circulated to NHSRCL
Test type Relevant Format As per IS Code Frequency Specification requirements Remarks
Sl. of practice of testing
No
Manufacturer’s
Leveling instrument Calibration certificate IRC/IRS Yearly / As per specification of instrument
1 calibration
six months
Manufacturer’s
Total station Calibration certificate IRC/IRS Yearly / As per specification of instrument
2 calibration
six months
(Control Points
In house
Horizontal HMRP/VD/SURVEY/ IRC/IRS Quarterly 1 in 20000
4 calibration
calibration) 01
(Control points
In house
Vertical HMRP/VD/SURVEY/ IRC/IRS Quarterly Accuracy 2mm / Km
5. calibration
calibration) 03
18 OF 37
ANNEXURE- A
20 OF 37
PROJECT : MAHSR-C4
CLIENT : NHSRCL
ENGINEER : XXXX
CONTRACTOR : Larsen & Toubro limited
Date:
Drawing Number:
Instrument and its number: Date of next calibration:
21 OF 37
PROJECT : MAHSR-C4
CLIENT : NHSRCL
ENGINEER : XXXX
CONTRACTOR : Larsen & Toubro limited
Drawing No………………………….
DIFF NORTHING
DIFF EASTING
Distance
Co-ordinate as per Co-ordinate as per Error distribute in Co-ordinate as per
Station between two
Engineer Observation Traverse Length Adjustments REMARKS
station
From To Meter Meter Northing Easting Northing Easting Northing Easting Northing Easting
22 OF 37
Survey instrument ID
Drawing No.
Theoritica Difference
Point Theoritical Actual (N) Actual Difference
l (N)
ID (N) (E) (E)
(E)
ALLIGNMENT CENTRE
LINE
PERMANENT BARICADE
LINE
PCC CENTER LINE
FOUNDATION CENTER
LINE
KICKER/ STARTER CENTER
LINE
PIER CAP CENTER LINE
Note : Measuring units of all Easting (E), Northing (N) are in Meter (M)
23 OF 37
Date : Date :
Time : Time :
Signature: Signature:
Details of inspection :
1. Inspection completed, the contractor may proceed with the works. Yes No
2. Remedial works required as below but further inspection not required. Yes No
3. Remedial works required as below and re-inspection is required. Yes No
Remarks by Engineer:
24 OF 37
Response of workmen :
25 OF 37
PROJECT : MAHSR-C4
CLIENT : NHSRCL
ENGINEER : XXXX
CONTRACTOR : Larsen & Toubro limited
Area / Location : Date:
Nature of the job to be done:
Sl. Not
Points are Checked Done Reqd.
No.
26 OF 37
ANNEXURE B
27 OF 37
CONTRACTOR NAME: Larsen & Toubro Limited RISK ASSESSMENT FOR: SURVEY WORKS
Originator Name: XXXX Date: XX/XX/XXXX
KEY L = Likelihood S = Severity R = Risk (Likelihood x Severity)
L = Low priority to be
M = Medium priority to be scheduled as H = High priority to be acted
RISK RANKING: implemented when resources
soon as practicable. on immediately.
allow.
Population Risk Rating Revised Rating
Task/Element Potential Hazards
at Risk Follow‐up Checklist / Report
L S R L S R
Work below HT or LT live line Ref: IM‐12‐A Rev 00
Setup for survey at
– Electrocution due to Surveyors / Survey Ref. Drawing: Sur ‐
proposed area/ location/ 2 3 M 1 2 L
accidental Asst. / Helpers. 001 Ref: IC‐10 Rev:
points.
contact of levelling staff with 00
HT/LT line.
Fall of loose material & fall of
Surveying work at height
person from top of excavated Ref: IM‐12‐A Rev
close to excavated area Surveyors / Survey
ground to the excavated 3 4 M 00 1 2 L
and on top of Pier Cap & Asst.
bottom and from pier cap to Ref: IC‐10 Rev:
Pedestal
existing ground level. 00
28 OF 37
30 OF 37
Specification
32 OF 37
Severity (S)
1 2 3 4
1 1 2 3 4
Probability(P)
2 2 4 6 8
3 3 6 9 12
4 4 8 12 16
33 OF 37
ANNEXURE-C
34 OF 37
35 OF 37
Discuss in Discuss in
12
weekly review meeting weekly review meeting
37 OF 37