Professional Documents
Culture Documents
Concrete Floor Slab Construction Process
Concrete Floor Slab Construction Process
Poor or lack of formwork examination during and after concrete placement to identify
uncommon deflections or other indications of possible failure that could be corrected
Inadequate nailing, bolting, welding, or fastening
Improper lateral bracing
Construct formwork that does not comply with form drawings
Lack of proper field inspection to ensure that form design has been properly interpreted by
form builders
Use of damaged or inferior lumber having lower strength than needed.
Also Read: Formwork (Shuttering) for Different Structural Members -Beams, Slabs, Columns,
Footings
2. Prepare and Place Reinforcement for Slab
Prior to the placement of reinforcement for concrete floor slab construction, inspect and check forms
to confirm that the dimensions and the location of the concrete members conform to the structural
plans. Added to that, the forms shall be properly cleaned and oiled but not in such amount as to run
onto bars or concrete construction joints. Design drawings provides necessary reinforcement details,
so it only needs understanding to use designated bar size, cutting required length, and make
necessary hooks and bents. After preparation is completed, steel bars are placed into their positions
with the provision of specified spacings and concrete cover. The concrete cover and spacing for floor
slabs can be maintained by introducing spacers and bars supporters. Wires are used to tie main
reinforcement and shrinkage and temperature reinforcement (distribution reinforcement).
Fig. 2: wires used to tie reinforcement and supporters used to maintain concrete cover
It should be known that incorrect reinforcing steel placement can lead to serious concrete structural
failures. Improper concrete cover exposes reinforcement bars to danger and jeopardize concrete-steel
bond. Finally, after all requirements of reinforcement placements (positions, concrete cover, spacing,
and correct bars size; length; hooks; and bending) are finalized, then site engineer can order
concreting.
Fig. 3: Provision of concrete cover for reinforcement bars in slab
Also Read: Reinforcement Detailing of Reinforced Concrete Slabs
3. Pour, Compact and Finishing Concrete Floor Slab
Mixing, transporting, and handling of concrete shall be properly coordinated with placing and
finishing works. In floor slab, begin concrete placing along the perimeter at one end of the work with
each batch placed against previously dispatched concrete.
Fig. 9: Wire used to bind main and shrinkage and temperature reinforcement (Detail 'A')