IMPAK1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 32

Installation and maintenance manual for Impak cage

and wound rotor induction motors


Frames 355, 400 and 450
Electric motors produced by MARATHON ELECTRIC comply with all Indian Standard
requirements relating to such machines, and to specific customer requirements.

The motors are carefully inspected and individually tested before despatch to ensure that
they comply with the requirements of the relevant specifications in respect of both
electrical and mechanical features, and that they are safe in operation.
This manual covers the installation and maintenance procedures to be adopted for CACA
cage and wound rotor induction motors, and should be read carefully before installing
and commissioning the machine. Additional guidance may be obtained from the following
publications:
IEC Recommendation BS EN 60034-1 : Rating and performance’.
IS325 : 1996 ‘Three Phase Induction Motors – Specification’

MARATHON ELECTRIC MOTORS (INDIA) LIMITED


DHQ
58,Taratala Road, Kolkata – 700024
Tel : 24695560/61/65/66
Fax : 2469 8530/24695369
Contact for Service – Ananda Majumdar, Cell 09903900891
ADDENDUM TO PAGE 10 OF PUBLTCATTON C51 F11

GREASE LUBRICATED BEARINGS –VERTICALLY MOUNTED MOTORS.

The top and bottom bearing assemblies, of motors in storage for two years or more, should be
dismantled immediately prior to installation, as there is a possibility that the Degraded grease will
not be expelled by the grease relief system.

As much as possible of the old grease should be removed by hand. If separation of the oil and the
base has occurred all traces of the old grease must be removed in a degreasing plant, care being
taken to ensure absolute cleanliness.

The dismantling re-greasing and re-assembly procedures are given on pages 33-38 and a copy of
QA4910, which details the squareness and clearance checklist for duplex bearings, is included as
an addendum to page 38.

ADDENDUM TO PAGE 38 OF PUBLICATION C51F11

MARATHON ELECTRIC MACHINES


QA4910 (10/82)

SQUARENESS AND CLEARANCE CHECKLIST FOR DUPLEX BEARINGS


Index
Page
Receipt and storage..................................................................................................................................... 5
Lifting and handling ..........................................................................................................................................5
Conditions of storage ........................................................................................................................................5
Preparation for storage ......................................................................................................................................6
Care of bearings.................................................................................................................................................6
Shaft clamps ......................................................................................................................................................6
Windings ............................................................................................................................................................6
Brushgear ..........................................................................................................................................................7
Storage after installation ....................................................................................................................................7
Pre-commissioning....................................................................................................................................... 8
General..............................................................................................................................................................8
Insulation resistance testing...........................................................................................................................8
Auxiliary circuits .................................................................................................................................................8
Safety precautions .............................................................................................................................................8
Methods of test...................................................................................................................................................8
Recommended minimum value (Rw) .................................................................................................................9
Polarisation index...............................................................................................................................................9
Drying out .........................................................................................................................................................9
General ..............................................................................................................................................................9
Methods of drying out.........................................................................................................................................10
Grease-lubricated bearings-horizontal and vertical mounting machines...................................................10
Oil-lubricated bearings-horizontal mounting machines ...............................................................................10
Oil-lubricated bearings-vertical mounting machines....................................................................................10
Recommended lubricants and capacities...........................................................................................................10
Installation ..................................................................................................................................................... 14
Location .............................................................................................................................................................14
Foundations .......................................................................................................................................................14
Alignment-horizontal mounting machines ..........................................................................................................14
Pulley drives.......................................................................................................................................................14
Direct-coupled drives .........................................................................................................................................14
Belt and coupling guards....................................................................................................................................15
Alignment-vertical mounting machines...............................................................................................................15
Dowelling of machines .......................................................................................................................................15
Connection to supply-cage motors.....................................................................................................................16
Connection to supply-wound rotor motors..........................................................................................................19
Desiccators units................................................................................................................................................19
Methods of starting.............................................................................................................................................19
Routine maintenance.................................................................................................................................... 20
General ..............................................................................................................................................................20
Cleaning.............................................................................................................................................................20
Grease-lubricated rolling bearings .....................................................................................................................20
Oil-lubricated rolling bearings.............................................................................................................................20
Disc-lubricated plain bearings-horizontal machines only....................................................................................21
Terminal Box ......................................................................................................................................................21
Drying out desiccators........................................................................................................................................21
Brush gear, brushes & slip-rings ........................................................................................................................22
Summary of routine maintenance ......................................................................................................................22
Overhaul – dismantling and reassembly .................................................................................................... 23
General..............................................................................................................................................................23
Terminal Box ....................................................................................................................................................23
Bearings and end brackets-horizontal foot mounting machines.................................................................25
Grease lubricated bearings ................................................................................................................................25
Oil-lubricated rolling bearings with CIRCON system ..........................................................................................28
Disc-lubricated plain bearings ............................................................................................................................31
Bearings and end brackets-vertical mounting machines.............................................................................32
Removal of top bearing and bracket (non-drive end) .........................................................................................33
Removal of bottom bearing and bracket (drive end) ..........................................................................................35
Removal of rotor.................................................................................................................................................37
Reassembly of bearings and brackets ...............................................................................................................37
Brushgear ......................................................................................................................................... 39
General ..............................................................................................................................................................39
Number 3 brushgear ..........................................................................................................................................39
Number 4 brushgear ..........................................................................................................................................40

Receipt and storage


The following general instructions should be read in may however occur during transit and the machine
conjunction with any specific data applicable to a should be inspected on receipt. Any damage or defect
particular order. Each machine is thoroughly inspected should immediately be reported to both the carrier and
and tested before leaving the works and every care is supplier.
taken to ensure safe transit to its destination. Damage
Lifting and handling

All impak motors are provided with lifting lugs or


trunnions, suitably positioned to allow safe lifting of the
machine.
Vertical mounting machines should be lifted using a
beam and vertical chains or ropes to each of the two
trunnions as shown.
Horizontal mounting machines should be lifted using four
chains, one to each lifting lug. Must machines will be
fitted with a top cover, which must be protected from
damage, during lifting, by fitting load spreaders between
the chains and the cover.

Table 1. Approximate standard motor mass (net kg)


Foot mounting – rolling bearings
MARATH Cage motors Wound rotor motors
ON
ELECTRI
C
Style IP22S IP44 IP22S IP44
IC01 IC0161 IC01 IC0161
355-6B -- 1520 -- --
355-7B 1500 1660 - --
355-8A -- -- 1875 2065
355-8B 1950 2100 2055 2245
355-9B 2110 2420 2225 2580
400-3A 2840 3160 3000 3370
400-3B 3020 3340 3180 3555
400-3C -- -- 3265 3635
450-3A 3600 3840 3845 4150
450-3B 3860 4100 4025 4335
450-3C 3950 4190 4110 4415
450-4A 5850 6500 6200 6890
450-4B 5850 6500 6200 6890
Conditions of storage
Motors should be stored in a plain, dry, well-ventilated 20°C and 75% respectively. They should not be
store with temperature and humidity not in excess of subjected to contamination form dust, dirt, or oil.
Preparation for storage
Project all shaft extensions, exposed keyways, half- Inspect all exterior paintwork and touch-up where
couplings, jacking screws and any other unpainted necessary. Lift the brushes on slip-ring machines and
surfaces with an anti-rust preparation. Where a shaft- apply self adhesive tape to the rings.
locking device has been fitted, this must be left in Stand vertical machines on substantial stable packing
position until the motor is installed, apart from its with the shaft axis vertical and shaft extension clear of
temporary removal in order to rotate the shaft as the ground.
indicated later.

Care of bearings
Rolling bearings Although stationary vibration should not normally be a
If a motor fitted with rolling bearings is subjected to problem with plain sleeve bearings, precautions should
vibration for long periods while stationary, damage to the still be taken to isolate the motor from any external
rolling elements and races may be caused by fretting vibration, by standing it on rubber blocks, if necessary.
corrosion (commonly called ‘stationary vibration’). The Where lubricant is fed from an external sources, seal
following precautions are to be taken to prevent this : inlet and outlet flanges to prevent ingress of
1. The motor should not be placed on a vibrating contamination.
floor. Bearings housings should then be filled with either one
2. The shaft should be turned through at least a of the recommended oils (see ‘Oils’ pages 12 and 13) or
quarter of a revolution each week. with a turbine oil of any viscosity grade. The method of
filling should follow the procedure detailed for the
3. If storage on a vibrating floor cannot be avoided,
appropriate type of bearing ( see pages 11 and 12).
the motor should be placed on thick blocks of
rubber, cork or felt. In all cases, after filling, the shaft should be turned at
least 10 revolutions. Every 3 months the shaft must be
Grease-lubricated rolling bearings
turned (at least 10 revolutions) to re-establish the
These should be overfilled with an approved grease (see protective film of lubricant.
‘Grease’ page 12). This will prevent moisture entering
the bearings and any surplus grease will be forced out
when the machine is started. Every 12 months inject
fresh grease into the bearing assembly.
Plain bearings

Shaft clamps
Where a shaft clamp has been fitted to prevent axial lubricant. When refitting the shaft clamp use a torque
shaft movement during transit, this should be left in spanner to obtain the following torque values:-
position. The motor should still be placed on rubber M 8 nuts - 2, 6 Nm
blocks if necessary, and the clamp removed every 3
M 10 nuts - 2, 6 Nm
months to allow shaft rotation which will re-distribute the
M 12 nuts - 5, 7 Nm

Windings
Temporary covers should be fitted to all terminal box or The safety precautions and methods of test are
sealing chamber openings. Heaters, if fitted, should be described under ‘Insulation Resistance Testing’ on
energised to prevent condensation if a suitable supply is pages 8 and 9. The associated temperature at the time
available during the storage period. of test should be recorded.
The insulation resistance should be checked at 3 It is important to remember that the winding should be
monthly intervals using a Megger. (For preferred completely discharged by earthing after each insulation
voltages see page 8). Take individual phase valus to test.
earth and measure between phases if permitted by the
winding connection.

Brushgear
On slip-ring machines fitted with a short-circuiting device mechanism at each winding inspection. Check that the
(brush-lifting and /or short-circuiting gear), operate the surface of the rings are fully protected by adhesive tape.
Storage after installation
If a motor is first coupled and commissioned and then uncoupled and rubber blocks placed under the feet.
not required for a considerable period the preceding Before lifting the motor, two of the feet should be
conditions still apply, and the machine should be treated dowelled to facilitate replacement. Alignment should be
as though it were in storage. It nust be isolated from all re-checked before starting up. It is essential that the
sources of vibration, excess humidity and atmospheric rotor be turned every 3 months as described previously,
pollution. If vibration is present the motor should after uncoupling if necessary.
Pre-commissioning
General
Remove rust preventative from shaft extensions, holders, and ensure that the tensioning device operates
keyways and half-couplings using petrol or white spirit freely and is set to the correct tension. See page 22.
(observing all relevant safety precautions when using Inspect and operate any brush lifting or short-circuiting
these volatile cleaning agents). All exposed insulated device and lubricate if necessary. Do not over-lubricate.
surfaces such as terminal arrangements or brushgear Turn the rotor by hand to ensure that there are no
should be wiped clean with a lint-free cloth. obstructions, check the condition of sealing gaskets in
Contaminants should be removed with a solvent such as the terminal enclosure, and remove any temporary seals
ICI ‘Genklene’. If the machine is slip-ring version, added for storage purposes.
remove adhesive tape from slip-rings and clean, check
the operation of brushes which should slide freely in their

Insulation resistance

The insulation systems used on the windings of modern Machine voltage d.c. test voltage
machines are designed to give reliable service life under
Up to 660V 500V
the specified operating conditions. Certain basic
precautions must be taken to ensure that the integrity of 661 to 4160V 1000V
the insulation is maintained during periods when the
motor is in storage, under installation, or not operating. 4161 to 6600V 2500V
These precautions have already been outlined in the 6601-110000V 5000V
section ‘Windings’ on page 6. To ensure that insulation
has not degraded due to moisture absorption during long Before carrying out the test, the surface of the windings
outage periods it is essential to check its resistance should be clean and dry. In the case of a new machine,
value. which has been properly stored, contamination should
not be present, but for re-built motors that have been in
Insulation resistance tests are carried out normally using service for some years the windings should be cleaned
a d.c. tester or ‘Megger’. For polarisation index values to in accordance with the instructions given under
be taken, the equipment must be capable of supplying a ‘Cleaning’ page 20.
steady voltage for 10 minutes.

The preferred d.c. test voltages for machines of various


voltages are given below:

Auxiliary circuits
The insulation resistance of all auxiliary circuits other temperature detector circuits must be made at a voltage
than bearing temperature detectors must be measured less than 100V e.g. by use of an AVO.
with a 500V Megger. Measurements on bearings
Safety precautions
Before attempting any insulation resistance test it is parts of the winding not being tested, including all
essential to earth the frame of the machine and any auxiliary circuits.
Dry insulation with a high resistance is capable of For reasons of both safety and accuracy it is essential
holding an electrical charge for several hours after that the winding under test is adequately earthed both
removal of the applied voltage. before and after the application of the test potential. 15
minutes is the recommended minimum time.
Methods of test
On low voltage machines (up to 660V) disconnect all is not possible to separate individual phases then the
supply cables, and terminal links where fitted, from the formula must be applied directly.
machine before carrying out the test, to eliminate the The duration of each test is one minute at the end of
possibility of false readings. which resistance reading R1 is taken. If resistance
On high voltage machines (above 660) the insulation reading R! is below the recommended medium value.
resistance can be measured at the control gear. If the
recommended minimum values are not obtained the
supply cables must be disconnected and the test
repeated.

Insulation resistance should be measured between each


individual phase and earthed with the remaining phases
earthed. The insulation resistance (Rph) of one phase to
earth on a three-phase winding is approximately twice
that of the complete winding, therefore the measured
value must be divided by two to obtain a figure for
comparison with the value Rw recommended. Where it

Recommended minimum value

The recommended minimum value Rw for the winding


can be calculated from the following formula:

Rw = Pt (kV + 1) Megohms

Where kV = Line voltage (in kilovolts)

Pt is a factor dependent on the condition of the winding


and on the ambient temperature at which the test is
carried out, but for reasons of safety the pity factor itself
should be limited to a minimum value of 1.

Values of Pt are shown in Fig 1.

The value of Pt must be decided by considering the age


and amount of contamination on the machine end-
windings, condition (A) should be adhered to for all new
machines whereas condition (C) should be considered
as the minimum value for an old machine.
Polarisation index

The polarisation index of a winding is defined as the ratio below the recommended minimum Rw, then the winding
of the insulation resistance after 10 minutes (R10) to the can only be considered acceptable provided that the
insulation resistance after one minute (R1). resistance value R10 is greater than the recommended
minimum. If neither of these conditions is satisfied then
i.e. Polarisation index (P.I.) = R10/R1 the windings should be dried out in accordance with the
following procedure.
On a clean dry winding the index value should not be
less than 1,5. Where a winding has a satisfactory
polarisation index but a value of insulation resistance R1
Drying out
General Once the maximum temperature is reached it should be
maintained throughout the dry-out period. To ensure that
When the results of the insulation resistance and
the moisture is effectively removed there must be free
polarisation index tests indicate that a dry-out is
circulation of air around the windings. On totally-
necessary then the moisture should be removed by one
enclosed machines covers must be opened to allow
of the methods specified in ‘Methods of drying out’.
continuous interchange of air.
In order to ensure that a satisfactory final result is
A convenient method of following the progress of the
achieved the most important factors to watch are:
dry-out is to take insulation resistance readings (R1 and
(a) The rate of temperature rise during the initial heating R10) at regular intervals and to plot them, along with the
period when moisture may be trapped inside the calculated value of polarisation index and winding
winding, and temperatures, on a chart as shown on Fig. 2. For damp
windings readings should be taken every 1 or 2 hours.
(b) The maximum temperature of the dry-out. On grossly contaminated windings the dry-out will be
Where a winding has been allowed to get damp due to slower and the intervals may be increased to 4 to 8
moisture pick-up from a highly humid atmosphere, then hours.
the rate of temperature rise should be limited to The dry-out process should be continued beyond the
approximately 10K per hour. time of which the insulation resistance has started to
Where a winding has been soaked thoroughly with water increase, and heat should be maintained until the
then the rate of temperature rise should be limited to 5K insulation resistance is above the minimum acceptable
per hour, otherwise damage to the insulation can occur. value obtained from Fig. 1 for the temperature at which
the dry-out is being carried out, and preferably until three
In general when using direct heating of the winding by consecutive measurements indicate that R1 has reached
passing current, the temperature should be raised to a steady value. Polarization index is not substantially
approximately 85°C, as measured by thermometers affected by temperature and hence a value of 1,5 would
attached to the end-windings, or 90/95°C when be achieved.
measured by embedded temperature detectors (ETDs)
located in the slot separators between coil sides in the
core.

With machines which have been immersed in water, a


careful watch should be kept on the winding --
particularly at the positions where the leads enter the coil
-- to see if amy actual drops of water come out. If these
are observed before the maximum temperature is
reached, then the rate of temperature rise should be
reduced to approximately 2K per hour to permit the
moisture to evaporate without ‘blowing’ the insulation.
Methods of drying out
Space heater Where possible all phases should be connected in series
using copper strip or cable of adequate section to carry
Electric space heaters may be useful for drying out
the full-load current.
windings where the moisture is on or close to the surface
of the outer layer of insulation. However, if the moisture Initially the value of current should be set at
has penetrated the winding, especially on old machines, approximately 15% of the full-load rating and adjusted as
then the method is unlikely to be successful on its own. the temperature rises to follow the heating schedule. The
supply and any external cables must be disconnected
Heaters should be located in the air spaces under the
before any insulation resistance readings are taken.
machine end windings and sited so as to allow even
distribution of heat throughout the end windings and MARATHON ELECTRIC Ltd. have facilities available for
core. A clearance of not less than 300 mm must be overhaul, drying out and testing of rotating electrical
allowed between any high temperature heater and the machines, either on or off site in accordance with the
nearest part of the winding, otherwise scorching may principles set out in this section.
occur. The machine should be lagged with temporary
covers to limit convection and give more uniform
heating.

Low voltage heating

Where a controllable low-voltage a.c. or d.c. supply is


available then this may be used for drying out stator
windings (with or without the rotor in position).

Grease-lubricated bearings – horizontal and vertical mounting machines


Machines will already have been over-filled with grease
prior to storage, but further grease should be added as
soon as possible after the machine is started. Surplus
grease will be expelled into the grease tray on horizontal
machines or the excess grease chamber on vertical
machines.
Fig.5 A general view of a duplex bearing on an IP22
vertical mounting motor showing lubrication point.(Right-
hand side looking at non-drive end). The lubrication point
is also accessible on IP44 motors.

Oil-lubricated bearings – horizontal mounting machines


Rolling bearings using the CIRCON® system 7. Check that the indicated oil level is at the centre line
On horizontal machines, the constant-level lubricator is of the sight glass, if the level is too high drain off
mounted adjacent to, but separate from, the bearing excess oil by removing the overflow plug.
housing assembly. See Fig. 6. To fill the assembly 8. Replace the filler pipe cap.
proceed as follows: Disc-lubricated plain bearings
1. Remove the overflow plug from the overflow pipe or Disc-lubricated plain bearing assemblies are filled via
bearing housings. either of the two filling plugs on the top half bearing
2. Remove the filler pipe cap and clean out the end of housing. If the bearing has been filled with oil for storage
the pipe. purposes it should be drained, or flushed with lubricating
oil if the bearing is empty as shipped from MARATHON
ELECTRIC Ltd. Pour in oil slowly until it reaches the
indicated limit shown on the ‘standing’ oil level
indicators, situated on each side of the lower half
bearing housing. Take care not to introduce any oil into
the top reservoir as this could result in the bearing
housing being overfilled.

3. Remove the oil reservoir by depressing and turning


the protective cover to release the bayonet-type
fixing.
4. Pour oil steadily down the filler pipe until the
indicated oil level is slightly below the horizontal When the motor is started the level of oil in the ‘standing’
centre line of the sight glass (located on oil reservoir oil level gauges will fall, indicating that rotation of the oil
base). Allow time for the oil wetted surfaces of the disc is raising oil from the lower to the upper reservoirs
bearing housing to drain. Check that the oil level is where the oil level will be seen to rise above the
still below the centre line of the sight glass. minimum indicated level on the ‘running’ oil level
5. Replace the plug in the overflow pipe or bearing gauges.
housing. This circulation of oil will be maintained while the motor
6. Fill the oil reservoir and replace, taking care that oil is running. When the motor is stopped the oil will slowly
from the bottle does not escape into the bearing drain back to the lower reservoir and the oil level will rise
housing before the reservoir is finally assembled. back to the original ‘standing’ level. This could take
There is an integral flap valve designed to retain the several hours.
oil when the glass reservoir is inverted. Do not attempt to fill to the ‘standing’ level while the
motor is running or flooding and leakage will occur.
These instructions apply to standard bearings with available for bearings with oil-flow cooling from an
natural or water cooling. Special instructions are external source.

Oil-lubricated bearings – vertical mounting machines


On vertical mounting machines, the oil reservoir is Recommended lubricants and capacities
integral with the housing assembly, (see Figs. 8, 9 and The branded lubricants referred to below have been approved
10) and the filling procedure is as follows:- after consideration of their manufacturer’s specifications and,
1. Remove filler plug and clean. where desirable, after laboratory and rig testing. The omission
of a lubricant does not imply that it has been tested and found
2. Pour in oil steadily until the level is in line with the
unsuitable.
mark on the sight glass.
3. Replace filler plug. The use of a non-approved lubricant, provided it had been
recommended by a reputable supplier after full consideration of
Approved lubricants and capacities are shown below and
the application, would not normally be regarded as invalidating
on page 12.
our guarantee.

Grease
The standard lubricating grease used in rolling bearing
machines is:
Shell Alvania RA
This is a lithium-base grease and contains oxidation and
corrosion inhibitors. We also approve the use of the
Table 2 Grease to be added at each re-greasing interval
lithium-base greases given below* for machines not
exceeding kW output and speeds not exceeding 1500 ( See Table 5, page 21, for regreasing intervals )
r/min.
BP Energrease LS3 MARATH
Castrol Companies Spheerol AP3 ON Up to 751-1200 1201-1800 Over 1800
Esso Beacon 3 ELECTRI 750 r/min r/min r/min r/min
Mobile Mobilux 3 C style
Shell Alvania 3 355-6
If a change from one approved grease to another is 355-7 15 20 40 35
comtemplated, try to remove as much of the existing
355-8
grease as possible before applying the new grease.
355-9 20 30 60 35
355-6 Not
20 30 60
355-7 applicable

The above figures for grease quantity are strokes of an


average hand-operated grease gun, (approx 11/2 grams)
and apply to both horizontal and vertical mounting
machines. They are approximate figures only to be used
as a guide for standard motor operating in a – 40°C to
+40°C ambient, lubricated with Shel Alvania RA.

Oils Fina Hydran 31 Fina Hydran 32


Gulf Harmony 44 Gulf Harmony 47
We recommend the use of light and medium grade turbine oils Mobil DTE Oil Light Mobil DTE Oil Medium
to BS489.1955. The light grade oils should be used for rolling Shell Turbo T32 Shell Turbo T46
bearing machines, and either light or medium grade oils for Total
plain bearing machines. *Note: The order of listing is alphabetical and does not
imply any order of preference.
If the ambient temperature exceeds 30°C or heavy
Among the oils which have been approved*, the following are shock loads are likely, always use the medium grade for
widely obtainable: plain bearing machines.

Light oils Medium oils


When a motor must start in an ambient temperature
BP Energol THB32 BP Energol THB46
Caltex/Texaco Turbine EE32 Caltex/Texaco Turbine EE46 below 5°C, the specialized advice of the oil supplier must
Burmah Castrol Perfecto T32 Burmah Castrol Perfecto T46 be sought to ensure that an oil with suitable low-
Esso Teresso 43 Esso teresso 32
temperature properties is selected.
Table 3 Approximate oil capacities

Horizontal mounting- CIRCON® system, rolling bearings Horizontal mounting- Disc-lubricated plain bearings
( natural or water cooling )
Bearing Size Litres per bearing Bearing size
Oil capacity per ‘es bearing
RRM080 1.0 BRM080 Bearing size (inches/mm)
(litres)
RRM090 1.2 BRM090
2.5 / 64 2.0
RRM100 1.5 BRM100
3.0 / 76 2.0
RRM120 1.8 BRM120
3.5 / 89 3.0
4.0 / 102 3.0
4.5 / 114 4.5
5.0 / 127 4.5

Vertical mounting- Top bearing taper roller


Bottom bearing roller

Top bearing sizes Oil Capacity Bottom bearing size Oil capacity
Lower Upper (litres) ( litres )
98350-98788 78250-78551 3.0
EE197045-197100 98350-98788 3.5 RRM090 3.5
EE195500x-195116x 98400-98788 4.0
Installation
Location

The machine should be installed in a well ventilated 4. If the machine is water-cooled, ensure that an
location, as the total temperature and hence the adequate supply of clean water is available, in
permissible output depends on the temperature and accordance with the details specified on the general
hence the permissible output depends on the arrangement drawing appropriate to the machine.
temperature of the surrounding air. The following points Piping must be installed in such a way that it does
should be borne in mind. not exert any restraint on the motor, and incorporate
1. Ensure that the motor enclosure is correct for flexible sections if necessary. Adequate precautions
service at the site selected. must be taken to guard against water leakage or
loss of supply.
2. Ensure that air circulation around the machine is not
restricted due to close proximity to walls etc. it is 5. Sufficient space should be allowed round the
important to guad against the possibility of re- machine for routine maintenance to be carried out.
circulation taking place i.e. hot outlet air being drawn 6. The location should be such as to along suitable
back into the machine. lifting equipment to be used, with adequate access.
3. The trunking connected to pipe-ventilated machines Only the eyebolts or lifting hooks provided on the
should not exceed 15m in length and there should machine must be used. Read carefully any
should not be more than two right-angle bends. The instruction plates fitted to the motor which may refer
cross-sectional area of the trunking must not be less to lifting or handling, particularly where fabricated
than 150% of the area of the inlet opening of the enclosures are fitted to the top of the machine.
machine.

Foundations
In any foundation, the essential qualities are rigidity and Machines Ltd. will advice on suitable mounting
freedom from transmitted vibration. Concrete provides arrangements, including the provision of bed plates on
the best foundation materials with bolts securely grouted slide rails Alignment – horizontal mounting machines.
in position. If required MARATHON ELECTRIC
Alignment- horizontal mounting machines
It is essential that the motor and its driven machine be motor by the drive system do not exceed are
correctly aligned, and that any forces imposed on the recommended figures. See publication C51A01.
Pulley drives
Overhung pulleys on all two-bearings motors must be hours of running. It is therefore advisable to check the
fitted so that the effective centre of the drive is as near tension after 1 hour’s running and again after 1 hour’s
as possible to the motor drive-end bearing and within the running and again after 2 day’s running.
shaft extension length. If a pulley is tight on the shaft the
pulley bore should be checked, and if correct it should be
heated in an oil bath before fitting. Damage to bearings
can result from imposed shock loads when a fitment is
forced on the shaft.
When installing a set of V-belts ensure that all belts in
the set are matched in length and cross-section.
Pulley centre distances should not be less than four
Slide rails are generally required with belt drives . The
times the diameter of the large pulley, unless an idler
correct method of mounting slide rails and aligning the
pulley is used. V-belts should be tensioned in
two pulleys is shown in Fig. 11. If the and driven pulleys
accordance with BS 1440, and with belt manufacturer’s
are not of identical widths, allowance must be made for
recommendations. Belts should only be sufficiently tight
this to ensure that the pulley grooves are aligned.
to prevent slip. V-belts may stretch during the first few
Direct-coupled drives
Correct alignment of direct drive can be achieved by Fig. 12 shows a suitable method of checking a parallel
following the instructions given below, in conjunction with misalignment using a dial indicator gauge. The couplings
the coupling manufacturer’s recommendations. BS3170 : half should be loosely connected together with a driving
1972 (Flexible couplings for power transmission) is also pin and readings taken at 90° intervals. This will indicate
recommended for consultations. whether vertical and / or lateral adjustment is required. It
General is worth noting that errors may be introduced with any
method of alignment involving relative rotation of the two
Where a coupling is large or heavy, ensure that the
coupling halves.
machine ventilation is not impaired and that shaft and
bearing permitted loads are not exceeded (see Angular alignment
publication C51A01 for allowable loads ). Undue force
should not be applied when fitting half couplings to motor
shafts. The method alignment should not rely on the
accuracy of machining or mounting of individual half-
coupling.
Special care must be taken when ‘inching ‘ a motor into
its final position, to avoid damaging the feet.
Parallel alignment
Axial alignment motor. (this is the approximate frame temperature rise
On rolling bearing machines, the rotor is located axially for a standard Class B insulated Impak).
within the confines of the ball bearing clearance, and If class F insulation has been specified and the full
care must be taken to ensure that the axial component of output temperature limit is 100k, the figure will be 0, 6
coupling load is within the capacity of the locating ball mm per metre. Table 4 shows the increase in centre
bearing on the motor. Thrust capacities of ball bearings height in mm for each frame size. Guards should be
on horizontal foot mounting machines are shown in designed so that they do not restrict the cooling of the
publication C51A11. motor or its bearings.
On plain sleeve bearing motors, the rotor is allowed to Table 4
float +5mm either side of it’s mean position, and the MARATHON Class B Class F
thrust faces fitted to either end of the bearing bushes are ELECTRIC
only suitable for accepting the inherent thrust of the style
motor during uncoupled test running (which will rarely
exceed 250 Newtons ). It is essential that the coupling 355 0.18 0.21
between the motor and driven equipment should be of 400 0.20 0.24
the limited, end float type thus ensuring the motor shaft 450 0.25 0.27
runs within the limits marked on it.The burden of axially
locating the shaft the system of motor and drive is thus
placed on the driven equipment. Limits of accuracy
Thermal expansion These will normally be specified by the coupling
manufacturer, but it is usual to allow a difference in
Final tests for alignment should be preferably be carried
reading of 0,.5mm, when measuring either parallel
out with the motor and driven equipment at normal
alignment as shown in Fig. 12 or angular alignment as
running temperature.
shown in Fig. 12a for coupling up to 400mm diameter.
Where that is not possible allowance should be made for For larger couplings the permissible tolerance is 0,
differential thermal expansion. It can be assumed that 13mm per metre of coupling diameter.
the centre height
Of a motor will increase by 0.5mm per metre for a
temperature rise of 50° measured on the frame of the
Belt and coupling guards
Adequate guards must be provided to cover all types of couplings’. For machines installed in the UK it is
drive systems. Reference may be made to the necessary to meet the requirements of the Factory
recommendations of the British Standard Code of Inspectorate with regard to the protection of personnel
Practice 3004, BS 1649 : 1950 ‘Guards for shaft against accidental contact with rotating machinery.
Alignment – vertical mounting machines
During manufacture every care is taken to ensure a as for a horizontal mounting machine (shown in Figs. 12
close degree of accuracy between the mounting flange and 12a).
and recess of the skirt base (if fitted) and the shaft.
As a precautionary measure, the alignment of the driving
and driven shafts should be checked with dial indicators
Dowelling of machines
When the alignment is correct and performance are mounted. This will facilitate future re-positioning. Use
satisfactory, all machines pedestals etc, should be the terminal marking and connection diagram in
dowelled to the bed-plate or base plate on which they conjunction with the controller or starter diagram when
making connections to the machine. Ensure that the removed, and all safety precautions have been
supply voltage and frequency are in line with those observed.
quoted on the motor rating plate and that the incoming The method of connection inside the terminal box will
cable section is suitable for the motor full load current depend upon the particular box fitted, which will normally
and any other limitations such as system fault level. be one of the following types:
Check that the supply is isolated, that line fuses are
Connection to supply – cage motors
Use the terminal marking and connection diagram in cable section is suitable for the motor full load current
conjunction with the controller or starter diagram when and any other limitations such as system fault level.
making connections to the machine. Ensure that the Check that the supply is isolated, that line fuses are
supply voltage and frequency are in line with those removed, and all safety precautions have been
quoted on the motor rating plate and that the incoming observed.

Standard terminal box

Standard terminal boxes, which may be of cast iron terminal provided, and any auxiliary connections made. It
fabricated steel, are fitted with a blanking plate drilled is important to ensure that continuity of the earth circuit
and tapped to receive the incoming cable gland or between the motor frame and the terminal box is
adaptor. Remove the front terminal box cover plate to maintained. Finally, re-check all connections and test the
expose the terminals, which are marked for easy installation, replace loose covers and line fuses, tighten
identification, and feed the supply cable through the cable gland, and check motor for correct rotation (see
sealing chamber gland and into the box. Connection can ‘Methods of starting’ page 19). Coupling and pulley
then be made using the cable lugs supplied. The guards must be in position before starting.
machine must be earthed in a manner which is both
electrically and mechanically sound, using the earth
Phase insulated BEAMA/CEGB box
The BEAMA/CEGB box contains a separate sealing termination made at the terminal studs, and a short
chamber through which the cables are taken before length of flexible cable 11 taken through into a deep
connection to the terminal studs. On some applications sealing chamber for connection to customer’s cable 12
the machine may be supplied with the complete (see Fig. 16). More commonly, however, the customer’s
cable will be taken straight through a shallow sealing
chamber to the terminal stud 6. Where this is the case
the terminations are made as shown on following page:

1. Remove steel cover 1 and integral flash plate. crutch and working up to the terminal, to
2. Remove sealing chamber from terminal box, accommodate axial contraction.
where this has not already been done. (A 4. Attach cable lugs to terminal studs, and secure
protective cover will have been fitted to the with two outer nuts 5.
aperture to seal the terminal box during transit. 5. Slide rubber terminal caps and cable seals into
This should be removed and discarded). position, and place cable spacing block 9 in
3. Feed incoming supply cable through gland, position.
connect to cable lugs 7 supplied, fit heat-shrink
sleeves 10 to each phase lead and fit neoprene
Note: Make sure the phase sequence selected will give
rubber terminal caps 3 and cable seals 4. Apply
the required direction of rotation. For full installation and
gentle heat to sleeves, starting at the cable
maintenance instructions for the BEAMA/CEGB box, see Sealing chambers can only be filled correctly when they
BEAMA publication No. 203, available from BEAMA, 36 are in a vertical attitude, with the cable entry at the
Kingsway, London WC2. bottom.
To fill the sealing chamber with insulating compound, If the specified mounting position for the terminal box
tighten the cable gland, replace the cover plate 8, and places the sealing chamber in any other position, the
pour compound into the chamber via the top aperture. chamber should be unbolted from the terminal box
Access to this can be gained through the terminal box (complete with cables), twisted into a vertical position
front opening. The chamber is correctly filled when the and filled. (If this is not possible a sealing plate is
compound level reaches the indicated mark inside the supplied to seal the aperture between terminal box and
sealing chamber. chamber, which can then be filled from the gland end).
Recommended sealing compounds Ensure that the relative positions of the phase leads in
the sealing chamber are not disturbed during filling.
Maximum Softening
Manufacturer’s Replace sealing chamber.
pouring temperature
List No. The motor must then be earthed in a manner, which is
temperature (°C) (°C)
both electrically, and mechanically sound, using the
AEI 57046 140 / 175* 59 earth terminal provided, and any auxiliary connections
AEI 57017 Cold pouring 56 made. Finally, re-check all connections and test the
BICC G8 145 / 155* 84 # installation, replace loose covers and fuses and fit
desiccators unit to terminal box. The motor is then ready
BICC G93 Cold pouring 60
for starting, when pulley and coupling guards are in
position (see ‘Methods of starting’ page 19).
Note: Sealing compounds usually shrink on cooling to * Must not exceed 150°C for PVC insulated cables.
ambient temperature. Topping-up may therefore be # For use in ambient temperatures above 30°C.
required. The quantity of material required for the
shallow sealing chamber is approx 10kg (9 litres), and
for the deep chamber 14kg (12 litres).
Phase –segregated terminal box (PSTBs)
On high voltage machines, a phase-segregated terminal
box may be fitted. These units are supplied with the
terminal connections already made within the terminal
To fill the sealing chamber with insulating compound
box. A short length of cable 5 is taken through into the
(required in case tail cables are used which is NOT a
sealing chamber, where the connections are made to the
recommended practice as on date), tighten the cable
incoming supply cable (see Fig. 18).
gland, replace the cover plate and pour compound
The procedure for connecting to this type of box is as through each of the two filling holes provided. The level
follows:- is correct when sealing compound reaches the
1 If the sealing chamber is not already fitted to the underside of the filling plugs.
terminal box, remove protective covering from the The recommended sealing compounds are those
cable tails and terminal box aperture, and bolt already listed on page 17(required in case tail cables
chamber into position. are used which is NOT a recommended practice as
2 Feed supply cable through gland and connect to on date). The quantity of material required to fill the
incoming cable tails 5 in the sealing chamber. This chamber is approximately 18kg (15 litres).
are marked for easy identification. If the mounting position of the terminal box is such that
Note: make sure the phase sequence selected will give the sealing chamber cannot be filled via the holes
the required direction of rotation. provided, e.g., it may be at 90° to the vertical, the
chamber should be removed and turned into a an upright (See Fig. 18.).
position before filing
This involves disconnecting inside the phase
compartments as follows.

1. Unbolt and remove the steel covers 1 with their


glass reinforced plastic linings 2.
2. Unbolt and remove the cable clamps 3 which couple
the incoming cable tails 5 to the respective motor
winding cables 4.
3. Unscrew and remove the larger of the nylon gland
nuts from both the bottom and the back of each
phase compartment. A light blow, with a flat-ended
bar located in one of the slots, is all that is required
to lock or unlock these nuts.
4. Remove the twelve nylon fixing screws, and
withdraw the three glass-reinforced plastic phase
compartments 6 leaving the nylon glands attached to
the cables.
5. Remove the bolts which secure the sealing chamber
7 to the terminal box, and remove the sealing
TAIL
chamber and cable assembly. Take care not to
disturb the relative position of the phase leads within
the chamber.
(If the sealing chamber cannot be turned into a n upright
position prior to filling, a sealing plate is provided to seal
the aperture between terminal box and chamber, which
can then be filled from the gland end).

When the sealing chamber has been filled and cooled to


ambient temperature, it may be re-assembled to the
terminal box, and an earth connection made which is
both electrically and mechanically sound. An earth
terminal is provided for this purpose. Connections to
auxiliary terminals can be made at this stage.

Finally, re-check all connections and test the


installations, fit loose covers, desiccator units and line
fuses. When pulley and coupling guards are in position
the motor is ready for starting (see ‘Methods of starting’,
page 19).
Connection to supply – wound for motors
Stator windings of slip-ring machines are connected in be connected to the starter in a similar manner to the
exactly the same manner as described previously for stator windings.
cage machines, on page 16 to 18.
Connectors to the rotor slip-rings are brought from the
brushgear to a separate terminal box, which should then
Desiccator units
For terminal boxes fitted with desiccators, these units are so, the units should be screwed into the threaded
supplied loose in sealed tins. Only after cable jointing bushes provided on the terminal box.
and compound sealing has been completed, and all If the 6mm diameter portion of the indicator head is pink
covers replaced, should the desiccator units be removed in colour, contrasting sharply with the blue outer ring, it
from their containers. will be necessary to dry out the desiccators before fitting
An examination of the front face of each unit should, if them into the terminal box. The procedure for drying out
the desiccator is dry, shoe the 6mm diameter portion of desiccators in given on page 21.
the indicator head to be coloured blue. Providing this is
Methods of starting
Instructions for starting will normally be supplied by the 3. Check also that all holding-down bolts, cabling and
starter manufacturer, whose manual should be consulted cleaning and secure. Safety guards must be in
for the detailed procedure. Certain precautions are, position.
however, applicable to any motor/starter combination, 4. Check that all fuses are in position, and are of the
and the following points should be noted: correct rating.
1. Before main switches are closed, ensure that the
starter is in the ‘off’ position, and that brush lifting
If all is correct switch on the motor and check that it runs
and short-circuiting gear on slip-ring machines is in
up to full speed.
the ‘START’ position.
2. Check overload release settings, and that any
dashpots fitted to the overload trips are correctly
filled with oil.
ROUTINE MAINTENANCE
General
It is strongly recommended that a system of regular 3. Ensure that the windings and bearings are not
maintenance be adopted ,as the efficient operation of overheating and that the motor runs quietly and
any machine depends on correct installation and the smoothly. Bearings usually operate with a
care which it subsequently receives in service. temperature rise above ambient between 20 K and
It is also recommended that a maintenance record card 40 K measured on the outside surface.
be prepared on which to record dates and details of all 4. Check the security of all fixing bolts, couplings,
maintenance and repair work carried out. This card is coupling guards etc. check that all air vents are
useful not only to the maintenance engineer but also to unobstructed and filters, if fitted, are clean.
the manufacture should the machine ever be returned to 5. Compare the actual load current with the full load
the works. current given on the rating plate.
During the first few weeks of service a new machine 6. Check that there is no sparking between brushes
should receive particular attention. Faulty installation is and slip-rings on wound rotor motors.
more likely to cause trouble during this period in which
Note: Should any fault occur which cannot be
the moving parts are settling down to working surfaces
diagnosed, please communicate with out nearest office
and temperature. Careful attention to the following,
or agent or with the works. A staff of experienced
shortly after commissioning, may help prevent serious
engineers is available who can assist or advise
trouble developing later.
customers on the rectification of any fault or breakdown.
1. Ensure that all external cables are adequately
cleated and are secure and that there is no evidence
of chafing.
2. Check that all terminals are clean and tight.

Cleaning
Moisture, oil, dirt, grease and carbon or metallic dust are If the windings are contaminated but in a dry state the
the principal causes of electrical breakdown. As far as is contaminant can be removed by hand brushing, dry
practicable, machines should be kept clean and dry both compressed air blowing or by vacuum cleaning. Great
internally and externally. The tubes of heat exchangers care must be taken not to damage the windings. The
can be cleaned using compressed air or a non-metallic windings may be washed with a hot detergent solution
tube brush. It may be necessary to remove air deflectors and rinsed with clean hot water. This must be followed
or silencers from the body of the heat exchanger to gain by drying out and an insulation resistance check (see
access to the tubes. Ensure that debris is not blown into page 8).
the machine, and gasket seals are not damaged.

Grease-lubricated rolling bearings


Horizontal and vertical machines relied system. Surplus grease is ejected from the
All grease-lubricated rolling bearings fitted to Impak bearing, during running, into a tray on horizontal
machines are protected from overgreasing by a pressure machiens, or into a chamber on vertical mounting
machines. It is not possible to cause damage by expressed as strokes of a normal hand-operated grease
overgreasing, although it should be noted that up to 24 gun.
hours may be required for all excess grease to be Grease should preferably be added whilst the machine is
expelled, and some rise in operating temperature may running, and it should be free from contamination by dirt
occur during this period. or water. The importance of ensuring cleanliness of
Every 12 months or at intervals shown in Table 5, grease fittings before and after lubrication cannot be
whichever is the most frequent, grease should be added over-emphasized. Expelled grease should be removed
to the bearings. from the tray after lubrication.
For location of greasing points see Figs. 3, 4 and 5
pages 10 and 11. The quantity varies with motor size
and running speed, and is given in Table 2, page 12,
Oil-lubricated rolling bearings
Horizontal and vertical machines On vertical mounting machines the minimum oil level is
Every 12 months the oil system should be drained, marked on the sight glass. Oil should be added to the
flushed out and refilled with clean new oil of an approved system when the level reaches the lowest mark.
grade. See ‘Oils’ pages 12 and 13. This period can be It is not possible to give any fixed periods between
extended providing regular checks are carried out on oil normal replenishments as so much depends on
acidity and sludging. circumstances. If, however, oil is being lost at such a
Regularly, the level of oil in the constant-level lubricator rate that attention is required more than once a month,
or reservoir should be checked. The position of the oil- as attempt should be made to find and rectify the leak
level indicator is shown in ‘Pre-commissioning’ pages 11 which probably exists. The procedure for refilling a
and 12. On horizontal mounting machines a graduated bearing housing and reservoir is given on pages 11 and
mark on the glass reservoir shows the minimum oil level. 12.
Table – 5 : Suggested lubricating intervals
For standard motors operating in a 40°C (max.) ambient on a 50 Hz supply.
MARATHO Horizontal mounting Vertical mounting
N Running Size of bearing (mm) Running Size of bearing (mm)
Poles
ELECTRIC
hours Drive end Non drive end hours Drive end Non drive end
style
2 2000 080 080 -- -- --
355-6
4-12 8000 080 080 -- -- --
2 2000 080 080 2000* 080 --
355-7 4 8000 080 080 4000 080 100
6-12 8000 080 080 8000 080 100
2 2000 080 080 -- -- --
355-8 4 4000 120 120 -- -- --
6-12 8000 120 120 -- -- --
2 2000 080 120 -- -- --
355-9 4 8000 120 120 4000 120 100
6-12 8000 120 120 8000 120 100
4 4000 120 120 4000 120 100
400
6-12 8000 120 120 8000 120 120
4 4000 120 120 4000 * 120 --
450
6-12 8000 120 120 8000 120 120
When adding oil to a machine, great care must be taken transporting oil must be clean, and filters and the
to ensure that dirt and other foreign matter does not surrounding areas should be cleaned to prevent dirt
contaminate the oil. Containers used for handling and being dislodged and falling into housings, reservoirs etc.
Disc-lubricated plain bearings – horizontal machines only
Every 12 months – or at longer intervals if these have is stationary, the oil level is that shown on the oil-level
been established by periodic checks of oil acidity and indicator (standing) on the lower half bearing housing.
sludging – the oil system should be drained, flushed with Oil should not be added when the machine is stationary
normal lubricating oil and refilled with clean oil of an until the upper reservoir has emptied. This may take
approved grade. ( See ‘Oils’ page 13, Table 3). The several hours. No attempt should be made to restore the
position of filling plugs and the method of filling is ‘standing’ oil level when the machine is running, as this
outlined in ‘Disc-lubricated plain bearings’, page 11. could lead to flooding on shut-down.
Regularly check the level of oil in the bearing housing, A plain bearing is usually safe if it operates at a
and top up if necessary. This can be done with the motor temperature below 90°C, but a rapid change towards
running or stationary. If the machine is running, the this limit is a danger signal calling for prompt attention.
minimum level of oil is shown in the oil-level indicator This figure applies where the temperature is measured
(running) on the upper half bearing housing. If the motor by thermometer in the top reservoir.
Terminal box
It is necessary to make a regular check on the security of should be checked regularly. If the units have become
connections. The interior of the box should be wiped with damp, the 6mm diameter inner portion of the indicator
a clean lint-free cloth and vacuum cleaned if necessary. head will be coloured pink and the desiccator must be
Where phase-segregated or phase-insulated dried out as follows:
BEAMA/CEGB type boxes are fitted, the desiccator
Drying out desiccators
Unscrew the indicating head from the body of the activated and the unit ready for use. This will be shown
desiccator and place the body only in an oven by the colour change of the desiccator head, which have
maintained at 120°C for two or three hours. Take care returned to its original blue.
during handling to avoid damage to the unit. Remove If the presence of moisture has been indicated by a
from the oven and replace the indicating head on the colour change in the desiccator the winding insulation
body. Place the complete unit in a sealed air tight resistance should be checked and the enclosure
container while still hot and allow the unit to cool down to examined for sources of leaks. The procedure is
normal temperature. The desiccator will now be re- described in ‘Insulation resistance testing’, page 8.

Brushgear, brushes and slip-rings


The slip-rings of wound rotor machines should be Minimum diameter shown in the table
smooth, burnished and free from oil and dirt. if Brushgear Diameter when Minimum
roughened, they should be cleaned with fine glass reference No. new (mm) diameter (mm)
3 203 193
paper mounted on a wooden block shaped to their
4.4A
curvature. Emery cloth must not be used. Should the 222 210
4M
roughness be due to sparking, the cause should be
investigated, i.e., vibration, excessive load ,spring
Examine brushes regularly to ensure that they are free in
pressure to low, brushes worn down, etc. If ridged or
their boxes and bedding properly on the rings. Brush
eccentric, e.g., more than 0,1 mm TIR for 999r/min
pressure can be checked by attaching a spring balance
machines or slower and 0,05 mm TIR for 1000r/min plus
to the brush tail and placing a piece of paper between
machines, the ring should be or turned in a situ on a
the slip-ring and brush surface. Pull gently on the spring
lathe, concentric with the bearing seatings, until a
balance in line with the brush axis until the paper just
smooth, true surface is restored.
slides between the brush and the slip-ring. The pressure
Slip-rings must not be turned below the
is correct at approximately 0,21kgf/cm2 of brush cross- slip-ring. This can be achieved by placing a strip of fine
section for brush grade CM 3H. Our engineers will glass paper (not Emery paper) round the periphery of the
advise on pressure settings for brush grades other than slip-ring, with the pressure spring holding the brush in
CM 3H. contact with the paper. Work the strip backwards and
If the brushes are worn, they should be replaced with forwards until the brush face has acquired the curvature
brushes of the same size and grade. The safe limit of of the ring. Ensure that the glass paper does not lift away
wear is up to 50% of the original length of the brush. from the ring at the brush edges. Carefully remove
New brushes are usually 35 to 45mm in length, and deposits of dust and carbon.
replacement should be considered when brush length Brush lifting and short-circuiting gear, which may be
reaches 20mm. fitted to some machines, should be lightly lubricated at
To renew a brush, disconnect the tail, lift the pressure pivot and bearing points, and short-circuiting contacts
spring and remove the brush from its box. Place the new cleaned.
brush in the box and bed it down to the surface of the
Summary of routine maintenance

Regular checks
See page

1. Check bearing oil levels 20, 21

2. Check desiccators 21

3. Check bearing temperatures 20, 21

Every 12 months or at each re-greasing interval, whichever is most frequent (see Table 5, page 21)

1. Re-grease bearings 20

2. Check desiccators 21

3. Check bearing temperatures 20, 21

4. Check brush length and pressure 22

5. Check condition of slip-rings 22

Every 12 months

1. Check security of terminals, cables, fixing 20


bolts, couplings and guards

2. Clean air vents and filters 20

3. Drain and refill oil lubricated 20, 21

4. Lubricate brush gear 22

5. Clean motor 20
Overhaul - dismantling
And re-assembly
General

Wherever possible the complete machine should be correct angular relationship. After removal of dowels and
removed from its site to a dry and dust-free location. This securing bolts, the machine can be lifted from its site.
particularly important for machines mounted out of Observe the safety precautions and procedures outlined
doors. Dowelling should be checked to ensure accurate on page 5, “Lifting and Handling”.
re-location after overhaul. Any shims which have been used should be identified
Before attempting to carry out any work on the machine, and carefully retained. Use load spreaders when lifting
it should be isolated from its electrical supplies, both machines fitted with fabricated top covers, such as heat
main and auxiliary. It is important that all necessary exchangers or silencers, to avoid damage to these
safety precautions are taken. Disconnection at the items. If the machine is vertical mounting version with oil-
terminal box can be achieved by reversing the procedure lubricated rolling bearings it should be placed vertically
described on pages 16 to 18. Identify all leads. Where a on substantially packing pieces, with the shaft extension
phase isolated insulated, phase-segregated or any type well clear of the floor. Sufficient space should be allowed
of terminal box with a compound filled sealing chamber under the shaft extensions for a jack or packing piece to
is fitted, disconnection will have to be made inside the be placed to support the weight of the rotor during
terminal box, and the sealing chamber unbolted and left removal of the top bearing assembly.
attached to the mains supply cabin. (As an alternative If the machine is vertical mounting version with grease-
the compound may be removed if preferred ). Protect lubricated bearings, it can be laid on its side for
any exposed cabin, or open sealing chamber apertures, dismantling. If the top bearing only is to be removed, this
to prevent the ingress of dirt or moisture and support the can be done with the motor in a vertical attitude, with the
sealing chamber to prevent damage to the main cable. shaft jacked up to support the rotor weight.
Auxiliary connections, and those to slip-ring brushes, in
Where a non-standard assembly has been fitted to a
the case of wound rotor machines, should be removed
vertical motor, such as tilting pad-type bearing, the
and carefully identified to aid future re-connection.
machine must be placed in a vertical attitude only.
Remove pulley or coupling guards, external cooling Special instruction are available for dismantling
ducts, water/oil supplies an uncouple the motor from its machines with non-standard bearing arrangements, and
drive system. If a coupling is fitted, do not forget to mark application should be made to MARATHON ELECTRIC
the two halves so that they can be reassembled in their Machines Ltd. or their agents.

Terminal Box

Disconnection of the motor from its mains supply, by dismantled state. To remove the box completely from the
reversing the procedure outlined on pages 24-30 will machine, proceed as follows:
have already left the main terminal box in a partially
Standard terminal box

Disconnect the motor cables from the terminal support Remove the securing bolts attaching the terminal box to
bar, by pulling the cables through their grommets until the motor frame and remove the box, complete with the
the cables eyes are free from their respective terminal terminal support bar.
studs. Avoid unnecessary strain on the cables, which
may caused damage. On low voltage application, there
may be additional auxiliary connections within the main
box, which should also be disconnected.

To re fit the box, reverse the procedure outlined above.

Phase-insulated (BEAMA/CEGB) terminal box

Removal of the BEAMA/CEGB box can be achieved by


removing the bolts securing the terminal box to its
adaptor, and lifting the box clear. The terminal base and
stud assembly can be left attached to the terminal box
adaptor face. If it is necessary to dismantle the terminal
base and stud assembly proceed as follows:
1. Remove the two locknuts from each terminal stud. A
hexagon on the stud, which locates in the terminal
base, will prevent it from rotating.
2. Remove the bolts securing the terminal base to the
terminal box adaptor.
3. Carefully ease the terminal base over the terminal
studs, noting the position of the sealing rings fitted
between base and stud assembly.
Re-fitting the terminal box is a reversal of the above procedure.
Replace any damaged gaskets or sealing rings, check the
condition the pressure relief diaphragm, and clean the interior of the terminal box, particularly the terminal base.
Phase-segregated terminal box

To remove the phase-segregated terminal the following


procedure should be followed: Before re-assembling the terminal box , check the
1. Remove the glands from the motor cables by condition of the gland packings and all gaskets and
unscrewing the remaining gland nuts and easing the grommets. Clean the interior of the box and check that
gland body and its packing off the end of the cable. the pressure relief disc is in good condition.
2. Remove the bolts securing the terminal box to the When re-fitting glands, the gland nuts should be hand
motor frame and ease the box free of the motor tightened only, to avoid damaging the threads.
cables.

Re-connection

Re-connection to the main supply is described on pages 16 to 18.


Bearings and endbrackets – horizontal foot mounting machines

You might also like