Professional Documents
Culture Documents
IMPAK1
IMPAK1
IMPAK1
The motors are carefully inspected and individually tested before despatch to ensure that
they comply with the requirements of the relevant specifications in respect of both
electrical and mechanical features, and that they are safe in operation.
This manual covers the installation and maintenance procedures to be adopted for CACA
cage and wound rotor induction motors, and should be read carefully before installing
and commissioning the machine. Additional guidance may be obtained from the following
publications:
IEC Recommendation BS EN 60034-1 : Rating and performance’.
IS325 : 1996 ‘Three Phase Induction Motors – Specification’
The top and bottom bearing assemblies, of motors in storage for two years or more, should be
dismantled immediately prior to installation, as there is a possibility that the Degraded grease will
not be expelled by the grease relief system.
As much as possible of the old grease should be removed by hand. If separation of the oil and the
base has occurred all traces of the old grease must be removed in a degreasing plant, care being
taken to ensure absolute cleanliness.
The dismantling re-greasing and re-assembly procedures are given on pages 33-38 and a copy of
QA4910, which details the squareness and clearance checklist for duplex bearings, is included as
an addendum to page 38.
Care of bearings
Rolling bearings Although stationary vibration should not normally be a
If a motor fitted with rolling bearings is subjected to problem with plain sleeve bearings, precautions should
vibration for long periods while stationary, damage to the still be taken to isolate the motor from any external
rolling elements and races may be caused by fretting vibration, by standing it on rubber blocks, if necessary.
corrosion (commonly called ‘stationary vibration’). The Where lubricant is fed from an external sources, seal
following precautions are to be taken to prevent this : inlet and outlet flanges to prevent ingress of
1. The motor should not be placed on a vibrating contamination.
floor. Bearings housings should then be filled with either one
2. The shaft should be turned through at least a of the recommended oils (see ‘Oils’ pages 12 and 13) or
quarter of a revolution each week. with a turbine oil of any viscosity grade. The method of
filling should follow the procedure detailed for the
3. If storage on a vibrating floor cannot be avoided,
appropriate type of bearing ( see pages 11 and 12).
the motor should be placed on thick blocks of
rubber, cork or felt. In all cases, after filling, the shaft should be turned at
least 10 revolutions. Every 3 months the shaft must be
Grease-lubricated rolling bearings
turned (at least 10 revolutions) to re-establish the
These should be overfilled with an approved grease (see protective film of lubricant.
‘Grease’ page 12). This will prevent moisture entering
the bearings and any surplus grease will be forced out
when the machine is started. Every 12 months inject
fresh grease into the bearing assembly.
Plain bearings
Shaft clamps
Where a shaft clamp has been fitted to prevent axial lubricant. When refitting the shaft clamp use a torque
shaft movement during transit, this should be left in spanner to obtain the following torque values:-
position. The motor should still be placed on rubber M 8 nuts - 2, 6 Nm
blocks if necessary, and the clamp removed every 3
M 10 nuts - 2, 6 Nm
months to allow shaft rotation which will re-distribute the
M 12 nuts - 5, 7 Nm
Windings
Temporary covers should be fitted to all terminal box or The safety precautions and methods of test are
sealing chamber openings. Heaters, if fitted, should be described under ‘Insulation Resistance Testing’ on
energised to prevent condensation if a suitable supply is pages 8 and 9. The associated temperature at the time
available during the storage period. of test should be recorded.
The insulation resistance should be checked at 3 It is important to remember that the winding should be
monthly intervals using a Megger. (For preferred completely discharged by earthing after each insulation
voltages see page 8). Take individual phase valus to test.
earth and measure between phases if permitted by the
winding connection.
Brushgear
On slip-ring machines fitted with a short-circuiting device mechanism at each winding inspection. Check that the
(brush-lifting and /or short-circuiting gear), operate the surface of the rings are fully protected by adhesive tape.
Storage after installation
If a motor is first coupled and commissioned and then uncoupled and rubber blocks placed under the feet.
not required for a considerable period the preceding Before lifting the motor, two of the feet should be
conditions still apply, and the machine should be treated dowelled to facilitate replacement. Alignment should be
as though it were in storage. It nust be isolated from all re-checked before starting up. It is essential that the
sources of vibration, excess humidity and atmospheric rotor be turned every 3 months as described previously,
pollution. If vibration is present the motor should after uncoupling if necessary.
Pre-commissioning
General
Remove rust preventative from shaft extensions, holders, and ensure that the tensioning device operates
keyways and half-couplings using petrol or white spirit freely and is set to the correct tension. See page 22.
(observing all relevant safety precautions when using Inspect and operate any brush lifting or short-circuiting
these volatile cleaning agents). All exposed insulated device and lubricate if necessary. Do not over-lubricate.
surfaces such as terminal arrangements or brushgear Turn the rotor by hand to ensure that there are no
should be wiped clean with a lint-free cloth. obstructions, check the condition of sealing gaskets in
Contaminants should be removed with a solvent such as the terminal enclosure, and remove any temporary seals
ICI ‘Genklene’. If the machine is slip-ring version, added for storage purposes.
remove adhesive tape from slip-rings and clean, check
the operation of brushes which should slide freely in their
Insulation resistance
The insulation systems used on the windings of modern Machine voltage d.c. test voltage
machines are designed to give reliable service life under
Up to 660V 500V
the specified operating conditions. Certain basic
precautions must be taken to ensure that the integrity of 661 to 4160V 1000V
the insulation is maintained during periods when the
motor is in storage, under installation, or not operating. 4161 to 6600V 2500V
These precautions have already been outlined in the 6601-110000V 5000V
section ‘Windings’ on page 6. To ensure that insulation
has not degraded due to moisture absorption during long Before carrying out the test, the surface of the windings
outage periods it is essential to check its resistance should be clean and dry. In the case of a new machine,
value. which has been properly stored, contamination should
not be present, but for re-built motors that have been in
Insulation resistance tests are carried out normally using service for some years the windings should be cleaned
a d.c. tester or ‘Megger’. For polarisation index values to in accordance with the instructions given under
be taken, the equipment must be capable of supplying a ‘Cleaning’ page 20.
steady voltage for 10 minutes.
Auxiliary circuits
The insulation resistance of all auxiliary circuits other temperature detector circuits must be made at a voltage
than bearing temperature detectors must be measured less than 100V e.g. by use of an AVO.
with a 500V Megger. Measurements on bearings
Safety precautions
Before attempting any insulation resistance test it is parts of the winding not being tested, including all
essential to earth the frame of the machine and any auxiliary circuits.
Dry insulation with a high resistance is capable of For reasons of both safety and accuracy it is essential
holding an electrical charge for several hours after that the winding under test is adequately earthed both
removal of the applied voltage. before and after the application of the test potential. 15
minutes is the recommended minimum time.
Methods of test
On low voltage machines (up to 660V) disconnect all is not possible to separate individual phases then the
supply cables, and terminal links where fitted, from the formula must be applied directly.
machine before carrying out the test, to eliminate the The duration of each test is one minute at the end of
possibility of false readings. which resistance reading R1 is taken. If resistance
On high voltage machines (above 660) the insulation reading R! is below the recommended medium value.
resistance can be measured at the control gear. If the
recommended minimum values are not obtained the
supply cables must be disconnected and the test
repeated.
Rw = Pt (kV + 1) Megohms
The polarisation index of a winding is defined as the ratio below the recommended minimum Rw, then the winding
of the insulation resistance after 10 minutes (R10) to the can only be considered acceptable provided that the
insulation resistance after one minute (R1). resistance value R10 is greater than the recommended
minimum. If neither of these conditions is satisfied then
i.e. Polarisation index (P.I.) = R10/R1 the windings should be dried out in accordance with the
following procedure.
On a clean dry winding the index value should not be
less than 1,5. Where a winding has a satisfactory
polarisation index but a value of insulation resistance R1
Drying out
General Once the maximum temperature is reached it should be
maintained throughout the dry-out period. To ensure that
When the results of the insulation resistance and
the moisture is effectively removed there must be free
polarisation index tests indicate that a dry-out is
circulation of air around the windings. On totally-
necessary then the moisture should be removed by one
enclosed machines covers must be opened to allow
of the methods specified in ‘Methods of drying out’.
continuous interchange of air.
In order to ensure that a satisfactory final result is
A convenient method of following the progress of the
achieved the most important factors to watch are:
dry-out is to take insulation resistance readings (R1 and
(a) The rate of temperature rise during the initial heating R10) at regular intervals and to plot them, along with the
period when moisture may be trapped inside the calculated value of polarisation index and winding
winding, and temperatures, on a chart as shown on Fig. 2. For damp
windings readings should be taken every 1 or 2 hours.
(b) The maximum temperature of the dry-out. On grossly contaminated windings the dry-out will be
Where a winding has been allowed to get damp due to slower and the intervals may be increased to 4 to 8
moisture pick-up from a highly humid atmosphere, then hours.
the rate of temperature rise should be limited to The dry-out process should be continued beyond the
approximately 10K per hour. time of which the insulation resistance has started to
Where a winding has been soaked thoroughly with water increase, and heat should be maintained until the
then the rate of temperature rise should be limited to 5K insulation resistance is above the minimum acceptable
per hour, otherwise damage to the insulation can occur. value obtained from Fig. 1 for the temperature at which
the dry-out is being carried out, and preferably until three
In general when using direct heating of the winding by consecutive measurements indicate that R1 has reached
passing current, the temperature should be raised to a steady value. Polarization index is not substantially
approximately 85°C, as measured by thermometers affected by temperature and hence a value of 1,5 would
attached to the end-windings, or 90/95°C when be achieved.
measured by embedded temperature detectors (ETDs)
located in the slot separators between coil sides in the
core.
Grease
The standard lubricating grease used in rolling bearing
machines is:
Shell Alvania RA
This is a lithium-base grease and contains oxidation and
corrosion inhibitors. We also approve the use of the
Table 2 Grease to be added at each re-greasing interval
lithium-base greases given below* for machines not
exceeding kW output and speeds not exceeding 1500 ( See Table 5, page 21, for regreasing intervals )
r/min.
BP Energrease LS3 MARATH
Castrol Companies Spheerol AP3 ON Up to 751-1200 1201-1800 Over 1800
Esso Beacon 3 ELECTRI 750 r/min r/min r/min r/min
Mobile Mobilux 3 C style
Shell Alvania 3 355-6
If a change from one approved grease to another is 355-7 15 20 40 35
comtemplated, try to remove as much of the existing
355-8
grease as possible before applying the new grease.
355-9 20 30 60 35
355-6 Not
20 30 60
355-7 applicable
Horizontal mounting- CIRCON® system, rolling bearings Horizontal mounting- Disc-lubricated plain bearings
( natural or water cooling )
Bearing Size Litres per bearing Bearing size
Oil capacity per ‘es bearing
RRM080 1.0 BRM080 Bearing size (inches/mm)
(litres)
RRM090 1.2 BRM090
2.5 / 64 2.0
RRM100 1.5 BRM100
3.0 / 76 2.0
RRM120 1.8 BRM120
3.5 / 89 3.0
4.0 / 102 3.0
4.5 / 114 4.5
5.0 / 127 4.5
Top bearing sizes Oil Capacity Bottom bearing size Oil capacity
Lower Upper (litres) ( litres )
98350-98788 78250-78551 3.0
EE197045-197100 98350-98788 3.5 RRM090 3.5
EE195500x-195116x 98400-98788 4.0
Installation
Location
The machine should be installed in a well ventilated 4. If the machine is water-cooled, ensure that an
location, as the total temperature and hence the adequate supply of clean water is available, in
permissible output depends on the temperature and accordance with the details specified on the general
hence the permissible output depends on the arrangement drawing appropriate to the machine.
temperature of the surrounding air. The following points Piping must be installed in such a way that it does
should be borne in mind. not exert any restraint on the motor, and incorporate
1. Ensure that the motor enclosure is correct for flexible sections if necessary. Adequate precautions
service at the site selected. must be taken to guard against water leakage or
loss of supply.
2. Ensure that air circulation around the machine is not
restricted due to close proximity to walls etc. it is 5. Sufficient space should be allowed round the
important to guad against the possibility of re- machine for routine maintenance to be carried out.
circulation taking place i.e. hot outlet air being drawn 6. The location should be such as to along suitable
back into the machine. lifting equipment to be used, with adequate access.
3. The trunking connected to pipe-ventilated machines Only the eyebolts or lifting hooks provided on the
should not exceed 15m in length and there should machine must be used. Read carefully any
should not be more than two right-angle bends. The instruction plates fitted to the motor which may refer
cross-sectional area of the trunking must not be less to lifting or handling, particularly where fabricated
than 150% of the area of the inlet opening of the enclosures are fitted to the top of the machine.
machine.
Foundations
In any foundation, the essential qualities are rigidity and Machines Ltd. will advice on suitable mounting
freedom from transmitted vibration. Concrete provides arrangements, including the provision of bed plates on
the best foundation materials with bolts securely grouted slide rails Alignment – horizontal mounting machines.
in position. If required MARATHON ELECTRIC
Alignment- horizontal mounting machines
It is essential that the motor and its driven machine be motor by the drive system do not exceed are
correctly aligned, and that any forces imposed on the recommended figures. See publication C51A01.
Pulley drives
Overhung pulleys on all two-bearings motors must be hours of running. It is therefore advisable to check the
fitted so that the effective centre of the drive is as near tension after 1 hour’s running and again after 1 hour’s
as possible to the motor drive-end bearing and within the running and again after 2 day’s running.
shaft extension length. If a pulley is tight on the shaft the
pulley bore should be checked, and if correct it should be
heated in an oil bath before fitting. Damage to bearings
can result from imposed shock loads when a fitment is
forced on the shaft.
When installing a set of V-belts ensure that all belts in
the set are matched in length and cross-section.
Pulley centre distances should not be less than four
Slide rails are generally required with belt drives . The
times the diameter of the large pulley, unless an idler
correct method of mounting slide rails and aligning the
pulley is used. V-belts should be tensioned in
two pulleys is shown in Fig. 11. If the and driven pulleys
accordance with BS 1440, and with belt manufacturer’s
are not of identical widths, allowance must be made for
recommendations. Belts should only be sufficiently tight
this to ensure that the pulley grooves are aligned.
to prevent slip. V-belts may stretch during the first few
Direct-coupled drives
Correct alignment of direct drive can be achieved by Fig. 12 shows a suitable method of checking a parallel
following the instructions given below, in conjunction with misalignment using a dial indicator gauge. The couplings
the coupling manufacturer’s recommendations. BS3170 : half should be loosely connected together with a driving
1972 (Flexible couplings for power transmission) is also pin and readings taken at 90° intervals. This will indicate
recommended for consultations. whether vertical and / or lateral adjustment is required. It
General is worth noting that errors may be introduced with any
method of alignment involving relative rotation of the two
Where a coupling is large or heavy, ensure that the
coupling halves.
machine ventilation is not impaired and that shaft and
bearing permitted loads are not exceeded (see Angular alignment
publication C51A01 for allowable loads ). Undue force
should not be applied when fitting half couplings to motor
shafts. The method alignment should not rely on the
accuracy of machining or mounting of individual half-
coupling.
Special care must be taken when ‘inching ‘ a motor into
its final position, to avoid damaging the feet.
Parallel alignment
Axial alignment motor. (this is the approximate frame temperature rise
On rolling bearing machines, the rotor is located axially for a standard Class B insulated Impak).
within the confines of the ball bearing clearance, and If class F insulation has been specified and the full
care must be taken to ensure that the axial component of output temperature limit is 100k, the figure will be 0, 6
coupling load is within the capacity of the locating ball mm per metre. Table 4 shows the increase in centre
bearing on the motor. Thrust capacities of ball bearings height in mm for each frame size. Guards should be
on horizontal foot mounting machines are shown in designed so that they do not restrict the cooling of the
publication C51A11. motor or its bearings.
On plain sleeve bearing motors, the rotor is allowed to Table 4
float +5mm either side of it’s mean position, and the MARATHON Class B Class F
thrust faces fitted to either end of the bearing bushes are ELECTRIC
only suitable for accepting the inherent thrust of the style
motor during uncoupled test running (which will rarely
exceed 250 Newtons ). It is essential that the coupling 355 0.18 0.21
between the motor and driven equipment should be of 400 0.20 0.24
the limited, end float type thus ensuring the motor shaft 450 0.25 0.27
runs within the limits marked on it.The burden of axially
locating the shaft the system of motor and drive is thus
placed on the driven equipment. Limits of accuracy
Thermal expansion These will normally be specified by the coupling
manufacturer, but it is usual to allow a difference in
Final tests for alignment should be preferably be carried
reading of 0,.5mm, when measuring either parallel
out with the motor and driven equipment at normal
alignment as shown in Fig. 12 or angular alignment as
running temperature.
shown in Fig. 12a for coupling up to 400mm diameter.
Where that is not possible allowance should be made for For larger couplings the permissible tolerance is 0,
differential thermal expansion. It can be assumed that 13mm per metre of coupling diameter.
the centre height
Of a motor will increase by 0.5mm per metre for a
temperature rise of 50° measured on the frame of the
Belt and coupling guards
Adequate guards must be provided to cover all types of couplings’. For machines installed in the UK it is
drive systems. Reference may be made to the necessary to meet the requirements of the Factory
recommendations of the British Standard Code of Inspectorate with regard to the protection of personnel
Practice 3004, BS 1649 : 1950 ‘Guards for shaft against accidental contact with rotating machinery.
Alignment – vertical mounting machines
During manufacture every care is taken to ensure a as for a horizontal mounting machine (shown in Figs. 12
close degree of accuracy between the mounting flange and 12a).
and recess of the skirt base (if fitted) and the shaft.
As a precautionary measure, the alignment of the driving
and driven shafts should be checked with dial indicators
Dowelling of machines
When the alignment is correct and performance are mounted. This will facilitate future re-positioning. Use
satisfactory, all machines pedestals etc, should be the terminal marking and connection diagram in
dowelled to the bed-plate or base plate on which they conjunction with the controller or starter diagram when
making connections to the machine. Ensure that the removed, and all safety precautions have been
supply voltage and frequency are in line with those observed.
quoted on the motor rating plate and that the incoming The method of connection inside the terminal box will
cable section is suitable for the motor full load current depend upon the particular box fitted, which will normally
and any other limitations such as system fault level. be one of the following types:
Check that the supply is isolated, that line fuses are
Connection to supply – cage motors
Use the terminal marking and connection diagram in cable section is suitable for the motor full load current
conjunction with the controller or starter diagram when and any other limitations such as system fault level.
making connections to the machine. Ensure that the Check that the supply is isolated, that line fuses are
supply voltage and frequency are in line with those removed, and all safety precautions have been
quoted on the motor rating plate and that the incoming observed.
Standard terminal boxes, which may be of cast iron terminal provided, and any auxiliary connections made. It
fabricated steel, are fitted with a blanking plate drilled is important to ensure that continuity of the earth circuit
and tapped to receive the incoming cable gland or between the motor frame and the terminal box is
adaptor. Remove the front terminal box cover plate to maintained. Finally, re-check all connections and test the
expose the terminals, which are marked for easy installation, replace loose covers and line fuses, tighten
identification, and feed the supply cable through the cable gland, and check motor for correct rotation (see
sealing chamber gland and into the box. Connection can ‘Methods of starting’ page 19). Coupling and pulley
then be made using the cable lugs supplied. The guards must be in position before starting.
machine must be earthed in a manner which is both
electrically and mechanically sound, using the earth
Phase insulated BEAMA/CEGB box
The BEAMA/CEGB box contains a separate sealing termination made at the terminal studs, and a short
chamber through which the cables are taken before length of flexible cable 11 taken through into a deep
connection to the terminal studs. On some applications sealing chamber for connection to customer’s cable 12
the machine may be supplied with the complete (see Fig. 16). More commonly, however, the customer’s
cable will be taken straight through a shallow sealing
chamber to the terminal stud 6. Where this is the case
the terminations are made as shown on following page:
1. Remove steel cover 1 and integral flash plate. crutch and working up to the terminal, to
2. Remove sealing chamber from terminal box, accommodate axial contraction.
where this has not already been done. (A 4. Attach cable lugs to terminal studs, and secure
protective cover will have been fitted to the with two outer nuts 5.
aperture to seal the terminal box during transit. 5. Slide rubber terminal caps and cable seals into
This should be removed and discarded). position, and place cable spacing block 9 in
3. Feed incoming supply cable through gland, position.
connect to cable lugs 7 supplied, fit heat-shrink
sleeves 10 to each phase lead and fit neoprene
Note: Make sure the phase sequence selected will give
rubber terminal caps 3 and cable seals 4. Apply
the required direction of rotation. For full installation and
gentle heat to sleeves, starting at the cable
maintenance instructions for the BEAMA/CEGB box, see Sealing chambers can only be filled correctly when they
BEAMA publication No. 203, available from BEAMA, 36 are in a vertical attitude, with the cable entry at the
Kingsway, London WC2. bottom.
To fill the sealing chamber with insulating compound, If the specified mounting position for the terminal box
tighten the cable gland, replace the cover plate 8, and places the sealing chamber in any other position, the
pour compound into the chamber via the top aperture. chamber should be unbolted from the terminal box
Access to this can be gained through the terminal box (complete with cables), twisted into a vertical position
front opening. The chamber is correctly filled when the and filled. (If this is not possible a sealing plate is
compound level reaches the indicated mark inside the supplied to seal the aperture between terminal box and
sealing chamber. chamber, which can then be filled from the gland end).
Recommended sealing compounds Ensure that the relative positions of the phase leads in
the sealing chamber are not disturbed during filling.
Maximum Softening
Manufacturer’s Replace sealing chamber.
pouring temperature
List No. The motor must then be earthed in a manner, which is
temperature (°C) (°C)
both electrically, and mechanically sound, using the
AEI 57046 140 / 175* 59 earth terminal provided, and any auxiliary connections
AEI 57017 Cold pouring 56 made. Finally, re-check all connections and test the
BICC G8 145 / 155* 84 # installation, replace loose covers and fuses and fit
desiccators unit to terminal box. The motor is then ready
BICC G93 Cold pouring 60
for starting, when pulley and coupling guards are in
position (see ‘Methods of starting’ page 19).
Note: Sealing compounds usually shrink on cooling to * Must not exceed 150°C for PVC insulated cables.
ambient temperature. Topping-up may therefore be # For use in ambient temperatures above 30°C.
required. The quantity of material required for the
shallow sealing chamber is approx 10kg (9 litres), and
for the deep chamber 14kg (12 litres).
Phase –segregated terminal box (PSTBs)
On high voltage machines, a phase-segregated terminal
box may be fitted. These units are supplied with the
terminal connections already made within the terminal
To fill the sealing chamber with insulating compound
box. A short length of cable 5 is taken through into the
(required in case tail cables are used which is NOT a
sealing chamber, where the connections are made to the
recommended practice as on date), tighten the cable
incoming supply cable (see Fig. 18).
gland, replace the cover plate and pour compound
The procedure for connecting to this type of box is as through each of the two filling holes provided. The level
follows:- is correct when sealing compound reaches the
1 If the sealing chamber is not already fitted to the underside of the filling plugs.
terminal box, remove protective covering from the The recommended sealing compounds are those
cable tails and terminal box aperture, and bolt already listed on page 17(required in case tail cables
chamber into position. are used which is NOT a recommended practice as
2 Feed supply cable through gland and connect to on date). The quantity of material required to fill the
incoming cable tails 5 in the sealing chamber. This chamber is approximately 18kg (15 litres).
are marked for easy identification. If the mounting position of the terminal box is such that
Note: make sure the phase sequence selected will give the sealing chamber cannot be filled via the holes
the required direction of rotation. provided, e.g., it may be at 90° to the vertical, the
chamber should be removed and turned into a an upright (See Fig. 18.).
position before filing
This involves disconnecting inside the phase
compartments as follows.
Cleaning
Moisture, oil, dirt, grease and carbon or metallic dust are If the windings are contaminated but in a dry state the
the principal causes of electrical breakdown. As far as is contaminant can be removed by hand brushing, dry
practicable, machines should be kept clean and dry both compressed air blowing or by vacuum cleaning. Great
internally and externally. The tubes of heat exchangers care must be taken not to damage the windings. The
can be cleaned using compressed air or a non-metallic windings may be washed with a hot detergent solution
tube brush. It may be necessary to remove air deflectors and rinsed with clean hot water. This must be followed
or silencers from the body of the heat exchanger to gain by drying out and an insulation resistance check (see
access to the tubes. Ensure that debris is not blown into page 8).
the machine, and gasket seals are not damaged.
Regular checks
See page
2. Check desiccators 21
Every 12 months or at each re-greasing interval, whichever is most frequent (see Table 5, page 21)
1. Re-grease bearings 20
2. Check desiccators 21
Every 12 months
5. Clean motor 20
Overhaul - dismantling
And re-assembly
General
Wherever possible the complete machine should be correct angular relationship. After removal of dowels and
removed from its site to a dry and dust-free location. This securing bolts, the machine can be lifted from its site.
particularly important for machines mounted out of Observe the safety precautions and procedures outlined
doors. Dowelling should be checked to ensure accurate on page 5, “Lifting and Handling”.
re-location after overhaul. Any shims which have been used should be identified
Before attempting to carry out any work on the machine, and carefully retained. Use load spreaders when lifting
it should be isolated from its electrical supplies, both machines fitted with fabricated top covers, such as heat
main and auxiliary. It is important that all necessary exchangers or silencers, to avoid damage to these
safety precautions are taken. Disconnection at the items. If the machine is vertical mounting version with oil-
terminal box can be achieved by reversing the procedure lubricated rolling bearings it should be placed vertically
described on pages 16 to 18. Identify all leads. Where a on substantially packing pieces, with the shaft extension
phase isolated insulated, phase-segregated or any type well clear of the floor. Sufficient space should be allowed
of terminal box with a compound filled sealing chamber under the shaft extensions for a jack or packing piece to
is fitted, disconnection will have to be made inside the be placed to support the weight of the rotor during
terminal box, and the sealing chamber unbolted and left removal of the top bearing assembly.
attached to the mains supply cabin. (As an alternative If the machine is vertical mounting version with grease-
the compound may be removed if preferred ). Protect lubricated bearings, it can be laid on its side for
any exposed cabin, or open sealing chamber apertures, dismantling. If the top bearing only is to be removed, this
to prevent the ingress of dirt or moisture and support the can be done with the motor in a vertical attitude, with the
sealing chamber to prevent damage to the main cable. shaft jacked up to support the rotor weight.
Auxiliary connections, and those to slip-ring brushes, in
Where a non-standard assembly has been fitted to a
the case of wound rotor machines, should be removed
vertical motor, such as tilting pad-type bearing, the
and carefully identified to aid future re-connection.
machine must be placed in a vertical attitude only.
Remove pulley or coupling guards, external cooling Special instruction are available for dismantling
ducts, water/oil supplies an uncouple the motor from its machines with non-standard bearing arrangements, and
drive system. If a coupling is fitted, do not forget to mark application should be made to MARATHON ELECTRIC
the two halves so that they can be reassembled in their Machines Ltd. or their agents.
Terminal Box
Disconnection of the motor from its mains supply, by dismantled state. To remove the box completely from the
reversing the procedure outlined on pages 24-30 will machine, proceed as follows:
have already left the main terminal box in a partially
Standard terminal box
Disconnect the motor cables from the terminal support Remove the securing bolts attaching the terminal box to
bar, by pulling the cables through their grommets until the motor frame and remove the box, complete with the
the cables eyes are free from their respective terminal terminal support bar.
studs. Avoid unnecessary strain on the cables, which
may caused damage. On low voltage application, there
may be additional auxiliary connections within the main
box, which should also be disconnected.
Re-connection