PROJECT COST ESTIMATE AZUCENA PROJECT

Model: 2 STOREY
Gross Wall Area : 17.98 sq. meter

ITEM CLASS ACTIVITY MATERIALS QTY U/M UNIT COST MATERIAL COST LABOR COST TOTAL COST
MODULE FINISHING WORKS (DRYWALL PARTITION)
11 ARCHITECTURAL INSTALLATION OF 2F DRYWALL PARTITION 17.98 sqm
11 ARCHITECTURAL GYPSUM BOARD (120 cm x 245 cm x 9 mm) 6.00 pcs 488.00 2,928.00
11 ARCHITECTURAL METAL STUDS (2" x 3" x 0.4") 12.00 pcs 145.00 1,740.00
11 ARCHITECTURAL BLACK SCREW (1.5") 250.00 pcs 1.50 375.00
11 ARCHITECTURAL CONCRETE NAIL (1.5") 0.50 kg 30.00 15.00
11 ARCHITECTURAL SKIMCOAT (20 kg) 1.00 bags 530.00 530.00
Subtotal 5,588.00 2,794.00 8,382.00