Professional Documents
Culture Documents
Project Execution Plan
Project Execution Plan
SIENA
TOWER 2
SUMULONG HIGHWAY, BRGY. STO. NIṄO, MARIKINA CITY
To date, the corporation has accumulated sufficient stocks of Formworks, Heavy and
Light Equipment to support its operations. The Corporation is likewise adopting the latest trend
in construction technology to be at part with the best industry.
COMPANY PROFILE
I. START
DESCRIPTION/ACTIVITIES
1ST
1ST MONTH
2nd 3rd 4th 5th
2nd MONTH
6th 7th 8th 9th
3rd MONTH 4th MONTH 5th MONTH 6th MONTH 7th MONTH 8th MONTH 9th MONTH 10th MONTH 11th MONTH 12th MONTH 13th MONTH 14th MONTH 15th MONTH 16th MONTH 17th MONTH 18th MONTH 19th MONTH 20th MONTH 21st MONTH
10th 11th 12th 13th 14th 15th 16th 17th 18th 19th 20th 21st 22nd 23rd 24th 25th 26th 27th 28th 29th 30th 31st 32nd 33rd 34th 35th 36th 37th 38th 39th 40th 41st 42nd 43rd 44th 45th 46th 47th 48th 49th 50th 51st 52nd 53rd 54th 55th 56th 57th 58th 59th 60th 61st 62nd 63rd 64th 65th 66th 67th 68th 69th 70th 71st 72nd 73rd 74th 75th 76th 77th 78th 79th 80th 81st 82nd 83rd 84th
MILESTONE
MILLENNIUM ERECTORS CORPORATION SUMMARY ENGR. ARVIN B. PADILLA ENGR. RONALD PERAL
SIENA TOWER 2-PROJECT SCHEDULE
ACTUAL WORK Project-In-Charge Project Manager
EXTERIOR TOWER CRANE LOCATION
EXTERIOR
CRANE
LOCATION
STRUCTURAL BLOCK-OUT LOCATION
TOWER CRANE
LOCATION
TOWER CRANE LOCATION
GENERAL CONSTRUCTION WORKS
8. Shoring will be maintained on two (2) strong floors to support weak floor.
SEQUENCE OF WORK PER SEGMENT
Note:
The above sequence of work will progress gradually on
succeeding floors up to roofdeck level simultaneously with
concrete pouring of the respective columns, slab,
beams/girders and stairs until reaching the roofdeck level.
INTRODUCTION
The Ringlocked formworks is a modular scaffold which is
more safe and convenient, it can be divided into 48mm system
and 60mm system. Ringlock system is constitute of standard,
ledger, diagonal brace, base jack, U-head and other
components. Standard is welded by rosette with eight hole at four
small holes to connect the ledger and another four big holes to
connect diagonal brace. This scaffold system is reasonable design
make the system force by there point that can resist bending and
anti-skating.
When you hammer down and fix the wedge pin, the joints
will be connected with standard closely and make the vibration
from the ledger pass down to the ground, it can make the wedge
pin get the vibration less and will not be bounced off.
PROPOSED RINGLOCKED SCAFFOLDING
SYSTEM
Advantages of Ringlock Scaffolding System
1. Advance technology, reasonable joint design and stable
connection.
2. Assembling easily and quickly, greatly reduced the time
and labor cost.
3. Upgrade the raw materials by low-alloy steel.
4. High zinc coating and long life to use, clean and
beautiful.
5. Automatic welding, high precision and superior quality.
6. Stable Structure, high bearing capacity safe and durable.
RINGLOCK SCAFFOLDING SYSTEM
RINGLOCK SCAFFOLDING SYSTEM
FORMWORKS SECTION PLAN
PROPOSED SAFETY PROTECTION PLAN
PROPOSED SAFETY PROTECTION PLAN
PROPOSED SAFETY PROTECTION PLAN
PROPOSED SAFETY PROTECTION PLAN
CONCRETING LAY-OUT PLAN
STAFF
WORKER’S BARRACKS
HOUSE PANDA EXPRESS
FABRICATION AREA
POURING OF CONCRETE AT
TOWER AREA USING LINE
PUMP AND BOOM SETUP
TOWER 2 AREA
CONCRETING PLAN
SAFETY, HEALTH AND
ENVIRONMENT PROCEDURES
MILLENNIUM ERECTOR CORPORATION
ENGR. ELMER T. ROMERO
QUALITY CONTROL PLAN
MILLENNIUM ERECTOR CORPORATION
Purpose
To provide a plan that outlines the construction quality checks to
be performed during the Project. This plan defines the roles and
responsibilities of Project Management Team and the Contractor with
respect to construction quality.
END OF PRESENTATION.
THANK YOU!