Millennium Erectors Corporation

9445 Retiro St. Guadalupe Nuevo, Makati City


Tel. No. 8882-1537 to 39 Fax No. 882-3329

SIENA
TOWER 2
SUMULONG HIGHWAY, BRGY. STO. NIṄO, MARIKINA CITY

GENERAL CONSTRUCTION WORKS


THE COMPANY
Millennium Erectors Corporation was organized at the birth of the Global Second
Millennium. It was registered on the 3rd day of February 2000 with an authorized capital stock
of ten million pesos. The corporation is the back-up by a nucleus of personnel with extensive
experience proven capabilities in construction High Rise buildings Industrial and Power Plants,
Housing Projects, Construction of Ports, Harbors, Roads and Bridges.

Millennium Erectors Corporation is a Triple “A” Construction firm mainly trading on


General Construction Works. As the years piled up, aside from being a responsive and cost
effective provider of Professional and Engineered Construction Services in the building and
construction industry, MEC has developed and maintained groups of effective and
competitive personnel, thus making the company on of the most sought-after firm in the
construction field.

To date, the corporation has accumulated sufficient stocks of Formworks, Heavy and
Light Equipment to support its operations. The Corporation is likewise adopting the latest trend
in construction technology to be at part with the best industry.
COMPANY PROFILE

Corporate Name: Millennium Erectors Corporation


Business Address: 9445 Retiro St., Guadalupe Nuevo, Makati City
Tel. No. :882-1537 to 39
Fax No. :882-3229
Liaison Office Address: 8 Gertrudes St. Mambungan, Antipolo City
Tax Identification No: 205-173-783-000
SSS ID Number: 03-9147910-4
GENERAL CONSTRUCTION WORKS

CONSTRUCTION EXECUTION PLAN


LOCATION MAP
PROJECT SCHEDULE
ITEM NO.

I. START
DESCRIPTION/ACTIVITIES
1ST
1ST MONTH
2nd 3rd 4th 5th
2nd MONTH
6th 7th 8th 9th
3rd MONTH 4th MONTH 5th MONTH 6th MONTH 7th MONTH 8th MONTH 9th MONTH 10th MONTH 11th MONTH 12th MONTH 13th MONTH 14th MONTH 15th MONTH 16th MONTH 17th MONTH 18th MONTH 19th MONTH 20th MONTH 21st MONTH
10th 11th 12th 13th 14th 15th 16th 17th 18th 19th 20th 21st 22nd 23rd 24th 25th 26th 27th 28th 29th 30th 31st 32nd 33rd 34th 35th 36th 37th 38th 39th 40th 41st 42nd 43rd 44th 45th 46th 47th 48th 49th 50th 51st 52nd 53rd 54th 55th 56th 57th 58th 59th 60th 61st 62nd 63rd 64th 65th 66th 67th 68th 69th 70th 71st 72nd 73rd 74th 75th 76th 77th 78th 79th 80th 81st 82nd 83rd 84th

MOBILIZATION & DEMOBILIZATION


LAYOUT AND STAKING
II. STRUCTURAL WORKS
A. FORMWORKS
5TH FLOOR
6th FLOOR
7th FLOOR
8th FLOOR
9th FLOOR
10th FLOOR
11th FLOOR
12th FLOOR
15th FLOOR
16th FLOOR
17th FLOOR
18th FLOOR
19th FLOOR
20th FLOOR
21st FLOOR
22nd FLOOR
RD LEVEL
B. REBARS
5TH FLOOR
6th FLOOR
7th FLOOR
8th FLOOR
9th FLOOR
10th FLOOR
11th FLOOR
12th FLOOR
15th FLOOR
16th FLOOR
17th FLOOR
18th FLOOR
19th FLOOR
20th FLOOR
21st FLOOR
22nd FLOOR
RD LEVEL
C. CONCRETE POURING
5TH FLOOR
6th FLOOR
7th FLOOR
8th FLOOR
9th FLOOR
10th FLOOR
11th FLOOR
12th FLOOR
15th FLOOR
16th FLOOR
17th FLOOR
18th FLOOR
19th FLOOR
20th FLOOR
21st FLOOR
22nd FLOOR
RD LEVEL
III. ARCHITECTURAL WORKS
A. MASONRY WORKS
1A. 150mm CHB LAYING
2A. 100mm CHB LAYING
3A. INTERIOR PLASTERING
4A. EXTERIOR PLASTERING
B. WATERPROOFING
1B. TOILET & BATH AREA
2B. BALCONY AREA
3B. ROOF DECK AREA
C. CEILING / BULKHEAD
1C. TOILET & BATH AREA
2C. KITCHEN AREA
3C. HALLWAY AREA
D. DRYWALL PARTITION
E. TILE WORKS
1E. TOILET & BATH AREA
2E. BALCONY AREA
3E. LIVING AND KITCHEN AREA
4E. HALLWAY AND ELEV. LOBBY
F. FLOOR TOPPING
G. VINYL INSTALLATION
H. WOOD & PLASTIC DOORS AND FRAMES
1H. DOOR JAMB INSTALLATION
2H. DOOR PANEL INSTALLATION
3H. DOOR CASING
4H. BASEBOARD
5H. PLASTIC DOORS AND FRAMES (T&B's)
I. METAL WORKS
1I. STAIR RAILING
2I. BALCONY RAILING
3I. STAIR NOSING
4I. METAL DOORS AND FRAMES INSTALLATION
5I. WATER METER DOOR INSTALLATION
J. PAINTING WORKS
1J. INTERIOR PAINTING
2J. EXTERIOR PAINTING
3J. AUTOMOTIVE LACQUER PAINT (FOR WOOD DOORS AND FRAMES)
4J. METAL PAINT (ON STEEL DOORS, STAIR RAILING, BALCONY, ETC)
K. EPOXY FLOOR FINISHES
1K. EE ROOM AND AUX. ROOM
2K. STAIRS
3K. ROOF DECK AREA
L. PRECAST ARCHITECTURAL CONCRETE
1L. HORIZONTAL FINS AND DRIP MOLD
2L. PRECAST LEDGES
3L. 100mm THK PRECAST WALLS
M. OTHERS
1M. SOAP DISH INSTALLATION
2M. ROLL PAPER HOLDER
3M. MIRRORS INSTALLATION
4M. LOCKSET ON DOORS (WOOD, PLASTIC, AND METAL DOORS)
5M. DOOR STOPPER AND DOOR VIEWER
IV. FINAL PUNCHLIST
V. FINISH

CONTRACTOR: LEGEND: TITLE: PREPARED BY: NOTED BY:

MILESTONE

MILLENNIUM ERECTORS CORPORATION SUMMARY ENGR. ARVIN B. PADILLA ENGR. RONALD PERAL
SIENA TOWER 2-PROJECT SCHEDULE
ACTUAL WORK Project-In-Charge Project Manager
EXTERIOR TOWER CRANE LOCATION

EXTERIOR
CRANE
LOCATION
STRUCTURAL BLOCK-OUT LOCATION

TOWER CRANE
LOCATION
TOWER CRANE LOCATION
GENERAL CONSTRUCTION WORKS

PROPOSED SEQUENCE OF WORK


STRUCTURAL WORKS
SITE INSPECTION

 Joint Inspection with Project Manager/Construction


Manager & others.
 Site clearing (Removal of all possible obstruction).
 Check and Verify the reference point and elevation.
 Turnover of site and reference.
SEGMENTAL WORK
The primary purpose of dividing the work into segmental are intended
for a laddered-type of construction to be done in sequence starting
from segment 1 and continued towards segment 2.

FLOOR AREA=417.4 sq.m FLOOR AREA=375.5 sq.m


VOLUME = 117.2 cu.m VOLUME = 106.9 cu.m
SEQUENCE OF WORK PER SEGMENT
The following shall be the sequence:
1. Prior to start work, all required set up point shall be in
place.
2. Installation of formworks.
3. Installation of reinforcement bars for slabs, columns,
beams and RC walls.
4. Installation of embedded items.
5. Inspection/checking of reinforcement bars, embedded
items and cleaning.
6. Placing of concrete.
7. Simultaneous with the above are the following:
SEQUENCE OF WORK PER SEGMENT
a. Erection of Scaffolding for suspended beams/girders and slab.
b. Installation of beams/girders and slab reinforcement.
c. Check plumpness/levelness, elevation and alignment.
d. Schedule of pouring of concrete after all trades had completed
their works.
e. Concrete placing: first pouring the beam/column’s intersection
the beams and slabs using pump crete.
f. Curing and stripping:
Vertical forms after One (1) day.
Horizontal forms after Eight (8) days

8. Shoring will be maintained on two (2) strong floors to support weak floor.
SEQUENCE OF WORK PER SEGMENT

Note:
The above sequence of work will progress gradually on
succeeding floors up to roofdeck level simultaneously with
concrete pouring of the respective columns, slab,
beams/girders and stairs until reaching the roofdeck level.

Correspondingly, on lower floors where the structural works


was finished already, the Trade works can be started at once
and as well as the finishing works involved.
SEGMENTAL SEQUENCE OF WORKS
SEGMENTAL SEQUENCE OF WORKS

When the structural


works complete on at
8th floor, Architectural
work will start onwards.
PROPOSED RING LOCKED SYSTEM
(ZHEJIANG SUZIN CONSTRUCTION EQUIPMENT CO.,LTD)
RINGLOCK SCAFFOLD AND FORMWORKS SYSTEM

 INTRODUCTION
The Ringlocked formworks is a modular scaffold which is
more safe and convenient, it can be divided into 48mm system
and 60mm system. Ringlock system is constitute of standard,
ledger, diagonal brace, base jack, U-head and other
components. Standard is welded by rosette with eight hole at four
small holes to connect the ledger and another four big holes to
connect diagonal brace. This scaffold system is reasonable design
make the system force by there point that can resist bending and
anti-skating.

When you hammer down and fix the wedge pin, the joints
will be connected with standard closely and make the vibration
from the ledger pass down to the ground, it can make the wedge
pin get the vibration less and will not be bounced off.
PROPOSED RINGLOCKED SCAFFOLDING
SYSTEM
Advantages of Ringlock Scaffolding System
1. Advance technology, reasonable joint design and stable
connection.
2. Assembling easily and quickly, greatly reduced the time
and labor cost.
3. Upgrade the raw materials by low-alloy steel.
4. High zinc coating and long life to use, clean and
beautiful.
5. Automatic welding, high precision and superior quality.
6. Stable Structure, high bearing capacity safe and durable.
RINGLOCK SCAFFOLDING SYSTEM
RINGLOCK SCAFFOLDING SYSTEM
FORMWORKS SECTION PLAN
PROPOSED SAFETY PROTECTION PLAN
PROPOSED SAFETY PROTECTION PLAN
PROPOSED SAFETY PROTECTION PLAN
PROPOSED SAFETY PROTECTION PLAN
CONCRETING LAY-OUT PLAN

STAFF
WORKER’S BARRACKS
HOUSE PANDA EXPRESS

FABRICATION AREA

POURING OF CONCRETE AT
TOWER AREA USING LINE
PUMP AND BOOM SETUP

TOWER 2 AREA
CONCRETING PLAN
SAFETY, HEALTH AND
ENVIRONMENT PROCEDURES
MILLENNIUM ERECTOR CORPORATION
ENGR. ELMER T. ROMERO
QUALITY CONTROL PLAN
MILLENNIUM ERECTOR CORPORATION
Purpose
To provide a plan that outlines the construction quality checks to
be performed during the Project. This plan defines the roles and
responsibilities of Project Management Team and the Contractor with
respect to construction quality.

All construction activities associated with this Project will be


completed under this quality program. Only controlled products will be
delivered to Construction Management Team. Elements will be built with
skilled craftsmen, following approved drawings, using proper materials
and equipment. Inspections and tests will be performed as outlined in
this Plan to document that the construction method is proper and meets
Project requirements. Periodically, the process will be refined based on
worker-identified quality problems, test data, inspection results, audits,
and Construction Management Team’s satisfaction with the Project.
GENERAL CONSTRUCTION WORKS

END OF PRESENTATION.
THANK YOU!