RATE ANALYS

ITEM NAME : EXCAVATION FOR FOUNDATION (30 m LEA


(A) Labour Cost Analysis

SR.NO LABOUR NUMBERS RATE


RS/-

1 MALE COOLIE 2 200


2 FEMALE COOLIE 2 180
3 SUNDRIES - -
Total Cos

(B) Equipment Cost Analysis


SR.NO Equipment Name

1 -
2 -
3 -
TOTAL COST
RATE ANALYSIS SHEET
ON FOR FOUNDATION (30 m LEAD AND 1.5 m LIFT ) (QUANTITY 10 CUBIC METER)

RATE PER AMOUNT


Ps RS/- Ps

0 Day 400 20
0 Day 360 0
- - 20 0
Total Cost 780.2

(A) LABOUR COST 780.2


HIRE CHARGES (B) EQUIPMENT COST 0
RS/- Ps.
0 0 TOTAL COST OF LABOUR & EQUIPMENT
0 0 1 A+B 780.2
0 0 2 1.5% WATER CHARGE 11.703
0 3 10% CONTRACTOR'S PROFIT 78.02
TOTAL COST RS/- 869.923
FOR 10 CUBIC METER RS/- 869.923
FOR 1 CUBIC METER RS/- 86.9923