Professional Documents
Culture Documents
Load Flow Analysis
Load Flow Analysis
Why: -
A power system study will ensure that the power system is robust and dependable, with any flaws or
safety risks identified and rectified under all operating conditions.
Why: -
Power system is the most dynamic system in the world. The rate at which process of
converting any form of energy to electrical is same instant of converting electrical energy
to other forms. If it is not obtained, then the system may get collapsed.
To Initialise the transient study.
Equipment rating is suitable for normal operating conditions.
Equipment rating is suitable for abnormal operating conditions with specified time.
As we said earlier, power system is the most dynamic system, we need to find
365*24*60*60(Days*Hours*Minutes*Seconds) 31536000 sec/yr. possible combinations
which may occurs in the year. But practically it is not possible to run all the combinations
so that we can go for worst case conditions (Max/Min/Normal) with few operating
instants.
Why: -
Equipment loading or Circuit Loading – To know the margin available for future. */ explained below /*
Real/Reactive Power Flow. */ explained below /*
Transformer Tap Settings – To find out OLTC/OCTC requirements with Min/Max tap settings.
Steady State Bus Voltage/Angle. */ explained below /*
System Losses – To find out configuration with minimum losses.
Generator Voltage set point – Study about generator set point to improve P.F at PCC.
Performance under Emergency/critical cases.
Swing bus concept assumes that whatever the load demands, it can be compensated by the source. All
the simulation software uses swing/slack bus concept.
All the generators in power system should only supply the real/reactive power within its given
Max/Min range and we need to ensure that one.
Conventional Load Flow It assumes that source, load and network are balanced. It obeys
a) Swing Bus Swing/Slack bus concept. We can run all the possible combinations.
b) Freq. Dep LF
c) Forward reverse Forward reverse sweep algorithm mainly used in weakly distributed
sweep algorithm system or less X/R system.
Like 3*1 ph transformers with different impedance, Traction
Unbalanced Load Flow
connected with two phases, etc.
Time Domain Load Flow At each and every 15 min interval the load and supply are seldom
(Quasi Dynamic Study) concept. LF will be simulated for 365*24*4 = 35040/yr.
Time Domain Unbalanced
Load Flow
It is based on angular difference. Having more than one swing bus in
power system. Nuclear power plants power generation remains
Distributed Slack/Swing
constant through interval but renewable and gas, thermal plants are
Bus
generating power based on availability/demand. So, they are
considered as swing buses.
Secondary Controllers Can be done in Digsilent Power Factory
Optimal Power Flow To Optimize the Load flow/losses/reactive power compensation.
Radial System
Closed Ring
Weak Mesh
Interconnected system.
Radial System:
Each buses are connected to other bus through only
one path.
The power flow can be calculated easily through
vectorial method as the power flows through only one
path. So, load flow for radial system is not required.
Closed Ring:
It is same as the radial system except all the buses are
connected to other in ring form.
If anyone circuit open means it will be become open
circuit system.
Open ring or Weak Mesh:
It is same as the radial system.
If anyone circuit open means it will be become open
circuit system/weak mesh system as the power flow is
interrupted.
Interconnected System:
The most reliable network system.
Each bus/source are connected by more than one path.
So, if the one path breaks, it will continue by other
paths.
The above-mentioned conditions have to be checked for Short/Medium/Long Time intervals because our utility
demand scale varies day by day.
These studies need to be performed precisely for Load Flow and Analysis and Load Forecasting.
If the Load Forecasting is not accurate then the outcome of Load Flow is also not accurate. It is depending upon
Power system engineer who’s performing the Load flow and accuracy of Load forecasting.
These studies are not covered in IEE 399 because that is only for industrial power system and not for
conventional systems.
Available Transfer Capacity (ATC) of T/L:
It plays critical role in Transmission line planning. It is defined as
ATC = TTC-CBM-TRM-Ex TC
Were,
For ex., TTC – 1000 MW; Ex TC – 600 MW; Then the remaining ATC will be 400 MW. But we need to think
about CBM and TRM so we will allocate 50 MW each.
ATC=1000-50-50-600
ATC=300MW.
For radial system it is not necessary to do load flow because it is connected through single bus. But
for interconnected systems it is mandatory to check power flow/voltage level at each bus to ensure
that they are within the tolerance or not.
Angle stability in Bus – The angle difference between one bus to another bus must be within 90º and
if it goes beyond that value, it is not stable itself. In India it is permissible up-to 23º and in other
countries it may goes up-to 30º
If the angle difference goes beyond the limits, we can go for alternative solutions like adding
additional circuit for power flow, other transmission lines if required. If no more extension ways
available due to constraints, then we may use Series Compensation devices like FSC, TCSC, etc.
Real power always flows from higher angle to lower angle bus.
This study includes power factor compensation and reactive power compensation by using capacitor
and inductor.
It also gives information about loop flow system means if the two generators are connected in same
bus with one generating reactive power and other one consumes reactive power. It increases system
losses and rise in temperature around generators.
For Reactive Power Compensation, capacitor bank size needs to be calculated. For example, in the
metro/traction railways during the train running time it consumes more power so thus the power
factor will become lagging and capacitor is required. And if the station is at no load condition the
OHL/Cables inject reactive power to the system so thus it becomes leading and inductor is required to
mitigate it.
Basic Things To know Before Going to do the LFA:
1.Impendance Triangle
2.Power Triangle
3.Types of Bus
1. Impedance Triangle:
2. Power Triangle:
Cosϴ = Adjacent/hypotenuse
Tanϴ = Opposite/Adjacent
3. Types of Bus:
Based on Real/Reactive Power (Pg, Pd and Qg, Qd) & Voltage/Angle
If any reactive power control source like generator, FSC, TCSC and that bus voltage is fixed by
means of regulating reactive power, it is then PV or Voltage Controlled or Generator Bus.
There is no physical bus is available as swing/slack or reference bus. The assumption we make one
bus as swing bus in a system if one or more generating bus available. This bus having capability to
inject or consume infinite amount of real/reactive power in a strong transmission system feeding
weak distribution system.
Step-1: Always beware of file saving location while creating new project in etap.
Step-2: After creation of new project enter information like project name, contract number, location, engineer
name and standards (IEC/ANSI), Frequency, Unit system in the Project Menu.
IEC - International Electrotechnical Commission
Step-3: After above steps, go to the View Gridlines option in the menu and enable it so that we can draw or
insert components with uniformity. After that enable check circuit continuity option that helps us to check all the
components are connected to others. If any component left not connected to the system it shows that particular
element in a dull colour which differs from other elements.
Step-6: Enabling One Line Auto Build which helps us to draw one line diagram more precisely without adding
components one by one manually. Go to enable one line auto build option open auto build rule book editor
Describe the system voltage levels and standard Enter the spacing options between bus and nodes and
branches.
After that we just need to insert the very first component only. For example, first insert power grid and after that
all we need to do is just select the next component like bus and it will automatically draw/connect next to power
grid.
And we need to do alignment like some of the components are not connected properly or slightly away from
vertical/horizontal position, bus and branches are not in proper place. In that stage alignment tab, which
available next to the one-line auto build option helps us to solve all the alignment related issues.
These basic things are useful for modelling of system with basic requirements.
4. Modelling Of Transmission Line:
CATEGORY LINE LENGTH METHODOLOGY
Short ≤ 80 kms Neglected Capacitance (RL)
Medium 80 – 160 kms Nominal Pi/Nominal T/End Condenser
Long ≥ 160 kms Integrated Nominal Pi or Distributed parameters
Let’s find-out Transmission line P loss and Q loss for a 200km long length transmission line having 400kV as a
rated voltage.
R = 0.02339*200 = 4.678 ꭥ
X = 0.39671*200 = 79.342 ꭥ
Y = 2.99052*200 = 598.102 µʊ
Now we need one more resistance value means the above given resistance is for 20º and etap will evaluate
resistance value at 75º and etap itself gives us the resistance value at 75º in parameter section or we can find-out
it by using below formula.
Y = 1/Z
Y = 1/(R+jX)
Y = (1/R) + (1/jX)
Y = G + jB;
And kindly note that etap itself gives admittance value in micro mho but it won’t explain it exclusively to us.
P-loss = 3*I2*R
Q-loss = V2*BC
R – Resistance
Bc – Capacitive Susceptance
To find:
P-loss =?
Qab = V2*BC
= 50196933.468 VAr
= 47848160 VAr
= 50.1969 + 47.848
= 3*(70.7376)2*4.678
= 70223.4422
As we already know that etap will simulate resistance value at 75º but the resistance value we used in
calculation is measured at 20º.
= 84063.9753 W
Now we only created the naming for the different generation category and it doesn’t make any
change in the simulation. For create/editing different generation range select edit study case option
(small red briefcase symbol) in the menu bar and create new three different study case as the same
we named earlier.
And change the generation categories parallelly with respect to the study case (Max/Min/Normal)
For run/generating different output files at the same time add the same three different
categories we seen earlier in output file option. Select output reportsclick promptrun
the load flow and it will as be naming for output file. Repeat the steps again to create
three output files. And we can compare this output files in load flow analyser option.
Adaptive Newton Rapson Both are having same accuracy and less speed.
Newton Rapson
Fast decoupled – Fast but less accurate
This also exports results in Excel format and it gives us to choose whatever the output data
that needed in excel sheet. And Load flow report also available in pdf format also in report
manager menu.
All the output files/excel sheets are stored in Etap system path which we installed it(Disk
C/D).
Select Local Disk CEtap 19.01Load Flow (Project name) and we can find all the files
which we simulated in the project name load flow.
As far we saw above conditions are meant for generation category (voltage variation) but
we need to simulate the voltage with different types of loading category. For that we can
go for below mentioned 9 possible combinations.
Let assume 100MVA load with UPF at 95%/100%/105% voltage levels.
1 Max Load (100 MVA) Max Voltage (105%) We can run all these 9
2 Average Load (70 MVA) Max Voltage (105%) combinations but
3 Minimum Load (40MVA) Max Voltage (105%) logically case 3 and 7 is
4 Max Load (100 MVA) Normal Voltage (100%) more than enough and
5 Average Load (70 MVA) Normal Voltage (100%) it will cover all the
6 Minimum Load (40MVA) Normal Voltage (100%) remaining cases also.
7 Max Load (100 MVA) Minimum Voltage (95%)
8 Average Load (70 MVA) Minimum Voltage (95%) We can go for case 5 if
9 Minimum Load (40MVA) Minimum Voltage (95%) required for end user.
From output report option we have to run each case one by one to get this output. But if
we are going to do 9 combinations means it will take much more time and for that we
have an alternate option called scenario wizard and study wizard.
In Scenario wizard we have to create 9 scenario
total for all cases.
Select a Bus and we can get LDF range which is given as 80% minimum to 125% maximum. If we
set LDF value minimum in study case editor the overall load is multiplied by 80% and if we select
maximum then it will be multiplied by 125%
For example, study case type is maximum load 100MVA and nominal voltage 400kV
LDF @ None = 100MVA
LDF @ Bus minimum = 100MVA*80% = 80MVA
LDF @ Bus maximum = 100MVA*125% = 125MVA
For LDF at Global we need to give
manual value based on Z , I, P load types.
LDF @ Global = 100*10% = 10MVA
Operating P, Q, V:
This Option is available in study case editor under loading section.
Apart from the Gen/Loading category which we used/assigned for load flow what if we needed some
other loading/generating values and in that case this option will be helpful.
So first we have to enable this option in Edit Study CaseLoadingclick Operating P, Q, V.
And then go to the lumped load/generatorNameplate and enter values whatever the additional
load/generation required correspondingly.
After entering load/generation values in operating P Q V section run the load flow and we will get the output as
the same we entered in those P, Q, V values.
Now we will run load flow at two different conditions.
1 – Normal Voltage(400kV)/Max Load(100MW) without Operating P/Q/V option.
2 – Normal Voltage(400kV)/Max Load(100MW) with Operating P/Q/V as 40MW/10MVAr in motor
load and 15MW/5MVAr as static load in Lumped load editor.
1 2
From here we can understand that operating P/Q/V will give output despite of whatever loading
category we simulated in Loading/Generating category.
Adjustment in study case editor:
This option is used to add some parameters which we already used in load flow. For example, if we
are having trans. Line length of 200 kms and if we need to add or reduce some changes mean we
will put that tolerance level about 10 or 20% whatever required.
Except short circuit study all other remaining studies will consider positive tolerance and short
circuit will take negative tolerance because lesser impedance means higher short circuit current.
After manually entering tolerance value make sure that the tolerance adjustment is enabled in study
case editor. If it is not enabled, then we won’t get any changes in output.
This option is used during construction phase of projects. Because after commissioning/charging of
Trans. Line or transformer their parameters can’t be changeable means impedance or line length
remains same after project execution.
Branch Connection in Load Flow report:
In the Load Flow Report, we may have seen a page that contains a topic named Branch Connection.
It’s nothing but etap internally calculate and gives us the parameters value in terms of %Z.
ZPU = ZACT/ZBASE
= 1600 ꭥ
Let consider 2MVAr, 12.1kV rated capacitor connected to 11kV system. What will be the capacitor generated
reactive power when capacitor terminal voltage is 10.75kV
Vr = 11kV Q = 2*(10.75/12.1)2
From the above picture we can see the configuration manager mode is in normal condition
means CB1 is in open condition with lump load 5 is out if service
By using configuration editor option now, we can transfer the lump load 3 directly to lump
load 5 by closing CB1 which is shown in following steps.
By using the base editor option, we can change the parameters of elements but we are not
allowed to add or edit the parameters in existing project. To create a new, click on the data
manager option besides Base menu and create a new one.
Applications:
Step up or step down
Isolation
Inverter transformers
Conversion of 3 phase 3 wire to 3 phase 4 wire system
To limit a short circuit current (Unit ratio and lighting transformers)
Phase shifting to control the power flow
To supress few harmonics (3rd harmonics and multiples of 3rd harmonic)
Impedance matching transformers
To convert ungrounded system to grounded system
Instrumentation transformers
12 pulse rectifier application (Two different winding configuration
Centre tapped transformers (single phase full wave rectifier)
Cathodic protection
There are so many IEC standards available for transformer study. But few important topics are given below
Here, R1 and X1 represents Primary resistance and reactance while I1 is the current flow through the
primary. Similarly, R2 and X2 are secondary winding resistance and reactance respectively with I 2
current flow in it.
Primary winding having magnetizing components Rc and Xm and Rc core loss or hysteresis loss or eddy
current loss resistance or iron loss and Xm is the magnetizing reactance.
During no load condition Ic is the working current or core loss current and Im is the magnetizing current
flowing through Rc and Xm respectively. The vectorial sum of this current will give us the no load
current(Io) value.
I1’ = I1 + I0
No load loss current(I0) is chiefly inductive and this is not inclusive in etap and so the output results of
etap may not exactly match with field values.
Transformer rated value given in MVA is the full load value including losses that occurs during energy
transfer. So, we need to consider the losses also during transformer load study.
The transformer load study not only depends on real power but we need to evaluate the load flow with
respect to current capacity also.
For example, let consider a Two winding transformer with following parameters.
Rating in MVA 50
Primary Voltage in kV 220 and 131.2 FLA
Secondary Voltage in kV 33 and 874.8
%Impedance 12.5
X/R ratio 45
Vector Group Dyn11
Now it is connected to a load which has a capacity of 50MVA through Bus 5.
We run a load flow and results will shows that a 50MVA load is flowing through the transformer. It
may be a full load (100%) with respect to real power (MVA) rating even though if we look into it by
a current rating, we will get another scenario shown below.
From picture 1 we can identify that the transformer is in full load condition not over loaded but still
it shown red alert (overload caution) in SLD. Because the transformer full load current (FLA) is
reached out of its max value 131.2A in HV and 874.8A in LV side shown in picture 2 and that’s the
reason behind transformer over loading caution in SLD. So, logically current value determines the
loading/thermal capacity of equipment.
Voltage Tolerance in Transformer:
Voltage tolerance value of a transformer will be provided in a transformer data sheet. If it is not
provided, we need to ensure that if it is designed at 0% from the end client.
For example, transformer tolerance is given as 0% it is only managed by current rating 131.2A in
HV and 874.8A in LV.
P = √3*V*I
P = √3*220*131.2
P = √3*198*131.2
In case of voltage tolerance (±10%) provided then the transformer has a capability to transfer more
current (additional 10%) to compensate the voltage drop. Let consider grid voltage increased by 5%
and we have voltage tolerance of ±10% in transformer.
P = √3*231*131.2
P = 52493.61 = 52.493 MVA @ 231kV (+5% voltage level)
Things to remember:
We can conclude that the current rating of transformer plays vital role in power rating and losses and
also in thermal characteristics also.
The thermal losses of a transformer depend on ambient temperature and heat generated inside
transformer or I2 R losses mainly caused by current flow. And temperature rating of transformer
varies with different class.
Winding configuration
Ambient temperature
Voltage tolerance
Cooling type
Altitude
Winding material – Cu/AL
Altitude Derating/uprating:
The rating of equipment affected by some external factors like altitude, ambient temperature, wind
velocity, etc. is known as derating.
Transformer derating level is same up-to 1000m mean sea level. And after 1000m it will increase 2%
for every 100m altitude variation.
If the ambient temperature is 31°C then the transformer is derated by 1% and if it goes down to 29°C
then transformer is uprated by 1% and normally we don’t change temperature in etap.
Types of Cooling:
i. Liquid Fill
ii. Dry type
ODAF – Oil Direct Air Forced Transformer construction itself direct the oil towards the hotspot.
By using anyone method we can go up-to 20-33% of rated MVA.
Let consider a 220/33kV Transformer with rating of 75/100 MVA ONAN/ONAF and impedance given
as 12.1% on ONAN.
Now we have an impedance value for ONAN (75 MVA) but not for 100 MVA. But regrettably etap
will consider highest value as Zbase and we need to find out impedance value at ONAF (100 MVA).
= 12.1*(220/220)2 * (100/75)
= 16.133
But the increase in the impedance results in a huge power loss across transformer and if the power
factor is rated around 0.85. So, we can load the transformer maximum by 80-82% when the power
factor is 0.85.
The transformer impedance has the huge impact on effective loading of transformer.
Increase in impedance increases the X/R ratio and reduction in RMS short circuit current. But the Peak
short circuit will be high due to increased X/R ratio.
If FAT is completed
Use impedance from FAT report or name plate – Don’t use it from data sheet.
No optimisation is possible because its already manufactured and FAT completed.
Z tolerance is used for accounting the tolerance in transformer impedance only when the transformer
is not FAT tested and it is yet to procured.
While %Z variation used for accounting impedance adjustment at different tap position of
transformer because impedance will vary for every tap increases or decreases from normal tap.
%Z variation is used all the studies except short circuit because we already considering C factor and
Kt factor for impedance variation at short circuit.
Importance of %Z variation:
Let consider two transformers with same parameters except that one transformer(T3) having %Z
variation and other one(T2) has no %Z variation.
And before running load flow ensure that the LTC upgrade is enabled in Load Flow Study case
editor to showcase the tap value in SLD.
Trafo 2
Trafo 3
At grid voltage 100% and full load condition, both the transformers are having 229kW+10.3MVAr
load losses. 220kV and 33kV Bus voltages are within the limits.
In picture-2 we intentionally reduced the grid voltage to 90% so thus the bus voltage level went
down to 90% at 220kV level. To accommodate the voltage reduction both the transformer reduces
the tap level and it helped to maintain the voltage level at 33kV within the margin. But if we look
into the transformer load losses, Transformer T2 is having more losses( comparing with
T3.(229kW+10.3MVAr) comparing with T3 (173kW+7.78MVAr).
Because T2 is having %Z variation as zero and we didn’t consider the tolerance. So, whenever the
tap increases or decreases impedance remains the same i.e., 12.5%
We assigned %Z variation as ±12% for T3 so it automatically adjusts the impedance level depends
on tap setting.
Transformer Paralleling:
i.) Why?
Now we consider a transformer which connected to a 50MW load on LV side and after few
months the load demand on feeder increases and that time, we can segregate the load flow
equally by adding one more transformer in parallel or we can go of higher rating of
transformer to replace the existing one.
Redundancy purpose – consider two transformers are in parallel and connected as 2*100%
or 3*50% load and in that case bus coupler is in open. If any one transformer went out of
service the other transformer can transfer the load using bus coupler.
ii.) Conditions?
Vector group
Transformer impedance
Voltage
Tap ratio and X/R ratio
Transformer rating
Before simulating parallel operation make sure that the transformer phase shift
option is enabled in study case editor option. Otherwise, if we run a load flow it
won’t consider phase shift or vector group mismatch in transformer.
Both HV and LV winding transformers must be connected to a common bus
Case 1
In case (2) change the vector group of T6 by Dyn11(HV lags LV) and T5, T7 remains the
same vector group i.e., Dyn1(LV leads HV).
Case 2
Transformer T6 LV current went to huge that almost made a short circuit current due to that
Bus 18 also got overloaded even in no load condition (load is still out of service).
The amount of current generated by T6 is equally distributed to T5 and T7 also so the all
three transformers went to unbalanced condition.
It is mainly happened due to the phase shift difference in T6 (-30º) to T5 and T7 (30º) so the
overall phase shift of 60º in R phase led to the short circuit. So, connecting two or more
transformers with a contradictory vector group is not possible.
What happens (case 3) if we parallelly connects two or more transformer with the same
phase shift means Dyn0 with Ynyn0 or Dd0 (at load in service).
Case 3
The three transformers are sharing load equally without any discrepancy because as long as
voltage, phase angle and frequency remains same at circled points there will be no impact on
power flow but the issue may arise due to the one-point earthing on transformers.
We may have one more option (case 4) as the T5 having Dyn1 and T6 is Ynd1 and T7 is Dd1
and still the transformers can share the loads equally irrespective of different HV/LV
configuration but the most important thing is phase shift of all three transformers are same
(LV leads HV).
Case 4
From the above cases we can conclude that transformer paralleling with different vector groups
can’t possible unless the voltage, phase angle and frequency matches irrespective of HV/LV
configuration.
II.) Impedance:
It is practically not possible to make transformers with same impedance. If we insist the
transformer manufacturer to make three transformers with same impedance from the same
manufacturer still there will be some marginal variations.
Now we will change the T6 impedance value within marginal variation of 7.5% by IEC
60076.
With load
If we compare the impedance of all three transformers, T6 having more impedance than T5
and T7 due to that Power flow through the T6 is lesser than T5 & T7.
We can check this by applying current
division rule
= 32.55 MVA
So, we can’t really design/procure transformers with same impedance and instead of that we
can reduce the marginal difference to a tiny variation so that all transformers can be loaded
almost equal.
III.) Voltage:
In this case the transformer T6 LV voltage differs from T5 & T7.
Let consider T6 having 220/33.5kV and T5 & T7 has 220/3kV.
T5 – 220/33kV
T6 – 220/33.5kV
T7 – 220/33kV
There is a circulating current flow between T6 & T5 & T7 because T6 is connected with
33.5kV LV while T5 & T7 are trying to maintain 33kV LV voltage. Due to this there is a
reactive power flow to T5 & T7 from T6 because it flows from higher voltage (T6) to the
lower voltage (T5 & T7).
So, we can’t connect transformers with different voltage level if it so then there may be a
huge current circulation and reactive power flow in-between them.
What if we have same rated transformers but in different tap positions?
T5 – 0% tap
T6 – 5% tap
T7 – 0% tap
Due to the increased tap position in T6 the power flow through the transformer becomes
comparatively low with T5 & T7.
This can be avoided by using AVR in all three transformers but it must be a master-slave
combination. If all AVR’s are working independently then it results to uncontrollable
reactive power flow in the system.
Here T5 having 0.278 %R and 12.497 %X while we changed the T6 values as 0.50 %R and
12.49 %X.
The lesser X value (in T6) more amount of real power flowing and on other hand lesser R value
(in T5) more reactive power will flow.
V.) Transformer rating:
From the picture we can see that the load is equally balanced to all transformers depends on
rating of individuals.
But in practical we can’t model a 90MVA transformer and 50MVA transformer with same
parameters.
IEC 60076 allows to make paralleling of transformer more than 30% of its rating.
Can we parallel two transformer which connected to different grid system? (Answer – NO)
Consider two transformers with a rating of 50 MVA at 220/33kV and connected to two
different grids on HV and 50 MVA load on LV with a common bus.
Generator – stepping up to the grid and feeding auxiliary supply also (HV/MV/LV)
If your LV winding current rating is too high then we can use three winding transformer
(HV/LV1/LV2) and we can go for multi windings also up-to n-number of LV windings based on
rating.
Two different generators using common transformer.
Two LV windings with different voltage rating.
OLTC modelling:
Ideal device used to regulate voltage during fluctuations.
But not an alternate for SVC/STATCOM/FACTS.
23% failures in power transformers occurred due to OLTC.
Used In Load centre and power plant.
Consider a 100MVA rated 220/33kV power transformer having grid fluctuations around
+12.5% to -17.5% and the load varies from 10 MW to 35 MW.
Now we need to identify OLTC range to regulate voltage within ±5%
Let assume two different conditions namely higher grid voltage with minimum load and lower
voltage with maximum load.
Here we need to improve grid voltage within a limit of ±5% from normal value.
Step
Selection of Generators:
In-case of selecting generators, always go to the low power
factor.
Because if motor or any other load higher power factor is better because lower the power factor,
they will consume more reactive power which is no use – higher the power factor lowers the
reactive power (reactive power demand by end equipment is less).
In this generator case – we need to evacuate higher reactive power which required for regulating
voltage at generator terminal – higher the power factor generates less reactive power and may
leads to loess access to regulate voltage at generator terminal.
So technically low power factor generator helps us to regulate the voltage more precisely by
injecting or consuming more reactive power.
But commercially higher power factor generators are cheaper around 85% cost of low power
factor generators. If we think to optimize the cost of generator, we may go for higher power factor
one but it has less reactive power capability.
Technically diesel generators are designed in lower power factor to maintain the reactive power
requirements of load which connected to the system during stand-alone operation or grid failure.
It is possible to go for DG with power factor <0.8 likely 0.5, 0.6, 0.7 but standard design not
allowed to go below 0.8 P.F.
On other hand Synchronous condenser which having 0 P.F only capable of generating reactive
power not real power.
Whenever a Small capacity generator <50 MW (5,10,15 MW) are connected to LV or MV voltage
level (11,33,66 kV) where the power factor of system is low or peak, it is advised to go with power
factor of 0.8 generator.
When high-capacity generator from 50-500 MW which are connected to MV or HV voltage range
(110-400 kV) where the system is very strong and low voltage fluctuations with loess reactive
power requirements. This case we can move up to higher power factor generators like 0.85 or 0.9
PF range where low reactive power capability required. It is fully based on study where the
generator is used and voltage fluctuations around that point which is sufficient to regulate
generator terminal voltage and supports an inter-connected grid in a state or country transmission
line not for momentarily but for the next 10-12 years.
In selection of suitable voltage range for generator – it is recommended to go for higher rating to
reduce the full load current rating. For example, let consider 500 MW generator connected at
different voltage levels
Rating (MW) Power factor Voltage rating (kV) Full load current (FLA) MVA Qmax
500 0.8 11 32803.993 625.000 375
500 0.8 33 10934.664 625.000 375
500 0.8 66 5467.332 625.000 375
500 0.8 220 1640.200 625.000 375
500 0.8 400 902.110 625.000 375
Low voltage (11kV) – less insulation cost; high current & more conductor size results higher cost.
High voltage (400kV) – more insulation cost; reduced current results lower conductor cost.
Load flow won’t tell us how much real power generator generates. The amount of real power
generation required is given as input to the load flow.
Only one exemption if we have only one generator feeding loads in islanded system and in these
case load flow will tell how much real power is generated.
Consider a 250 MW generator connected to a system through 400/28kV Generator Step-up
Transformer and a power factor 0.80
The generator generates 250 MW real power because we insisted to generate 250MW and it gives
250 MW with 7.48 MVAr also. This is because generator is set at voltage control mode and thus it
requires some amount of reactive power to maintain 100% voltage at generator terminal point.
The reactive power 7.48 MVAr is depends on various factors includes amount of real power
generated, transformer impedance, grid voltage, etc.
All three cases are explained below and one thing is common that generator is continuously
regulating the bus voltage at 100% as we given input V as 100%.
Change in Real Power generation Change in Transformer Impedance Change in Grid Voltage
The important one is generator terminal set voltage – if we change the voltage then the reactive
power generation also varies with it.
The changes in generator voltage terminal also affects the voltage at grid side also because grid is
connected to a swing/slack bus through trans. line and we are insisting the generator to maintain
the voltage level which we given as input.
Here grid voltage is down to 92% and all the remaining parameters are same except generator
power factor namely 0.80, 0.85, 0.95.
The generator with low P.F produces more reactive power (187.5 MVAr) hence the generator
terminal voltage almost near to 100% even if grid voltage dropped to 92%. On other hand the
same generator with 0.95 capability produces less reactive power (82.2 MVAr) and due to that it
unable to maintain generator terminal voltage (only 95.23%).
Hence if we keep the operating mode in voltage control it automatically adjusts reactive power as
per requirement to regulate terminal voltage at 100%.
To avoid unnecessary frequent change of reactive power, we can set a voltage dead-band around
0.3, 0.4 or 0.5%. For example, if dead-band is ±0.5% and then the reactive power won’t change
unless voltage variation goes beyond 99.5 to 100.5. If voltage goes beyond 100.5 then the
generator will adjust reactive power to regulate terminal voltage at 100%.
Rating (MW) Power factor Voltage rating (kV) Full load current (FLA) MVA Qmax
250 0.95 28 5426.224 263.158 82.17103
250 0.9 28 5727.681 277.778 121.0805
250 0.85 28 6064.604 294.118 154.9361
250 0.8 28 6443.641 312.500 187.5
MVAr Control/Load Bus/PQ Bus Mode:
Consider three generators are operating in MVAr mode and reactive power as same as above case.
Drop down the grid voltage namely from 95, 100, 105%.
The above-mentioned case already simulated in voltage control mode. In that mode generator tried
to regulate terminal voltage by means of automatically adjusting reactive power.
But when we change the mode to MVAr – it starts to inject the reactive power (Qmax) and not
really looks to regulate the terminal voltage whatever it may be.
Is it suggested to keep generator in MVAr mode and the answer is no because generator will go out
of step and it nor generates output power if it goes out of fail/failure to run.
Generators are ideally designed to operate voltage tolerance of ±5% only.
Swing Mode:
The swing mode only contribute when the generator is left stand-alone or island system.
Consider a 50MW load is fed by generator and grid where both of them contributes parallelly.
When the grid fails then the generator must contribute the load requirement means voltage and
frequency because the demand is not going to be constant and it changes time to time. So, the
generator must adjust its output power regarding to change in load demand and this mode is also
known as isochronous mode or V/F mode.
In normal condition grid supplies the load demand and generator will be in out of service and we
can bring generator to service if we need to met the requirement of demand by adjusting output
power of generator.
Normally generators with isochronous mode are not connected to grid because load variation
momentarily changes in power system and generators are not capable to switch that much respect
to load variation
But I practical the cost of grid supply is much lower than the cost of generator supply and that’s
why generators are used in emergency cases to meet the load demand and in-terms of cost
reduction.
parallel
Gen alone
MVAr control and power factor control are almost same unless the power factor is not unity and
change in real power.
Case 1 Case 2
In case-1, the load demand is 250MW and generators are running on MVAr and PF mode. The
both generators are not regulating terminal voltage and instead of that they’re regulating reactive
power and PF given as input to them.
In case-2, the demand reduced to 150MW and all other parameters are same. Now generator 4 still
gives 187.5 MVAr reactive power output even at 150 MW and it overlooked about terminal
voltage and real power output.
On other hand generator-5 reduces its real power and reactive power output also to maintain the
PF setpoint of 0.80.
The important cons of this mode is it failed to regulate terminal voltage within ±5% which is
mandatory for high capacity generators.
This mode is useful only when power grid or utility insist us to inject reactive power in system.
(*) Constant power mode – Generates constant output power despite of change in frequency.
(*) Droop mode – Change in % frequency makes the output power change by 100%. In other
terms – the power output of generator reduces as the line frequency increases.
So, Droop is a phenomenon helps whenever a reduction in terminal frequency it increases power
output and on other hand whenever a terminal frequency increases it reduces the power output.
A stand-alone generator can’t be operated at droop mode because the load and frequency changes
momentarily and generator should adjust its output load and frequency.
Droop is typically maintained at 4-5%
A 500MW generator running in full load 100% at 50 HZ and it reduces the output to 0% (0 MW) hence
frequency increased to 52 HZ.
Now all generators are generating equal real power but not same reactive power. Lets change the
operating mode into reactive power for gen-6,7,8 and set MW as 0.8 with 0.6 MVAr reactive
power and gen-5 as swing source.
This mode also works well until changes in load demand. If we increase the load demand to 7 MW
and after increase in demand, the all generators are still generating 0.8MW with 0.6MVAr because
we insisted it to do it and gen-5 is generating 3.2MW with 2.4MVAr because it is operating in a
swing mode.
So, if a swing source generator (Isochronous mode) connected with other generators with different
operating modes or droop mode results in an unequal load sharing. This can be eliminated by use
of secondary controllers which gives continuous feedback to AVR and Governor about load
demand but it can’t be modelled in etap.
9. Modelling Of Load:
What Is Load?
Load – Device which converts electrical energy to some other form of energy is a Load.
Source – Device which converts some other form of energy to electrical energy is a Source.
Types:
Based on power consumption changes respect to voltage:
Constant Impedance(Z)
Constant Current(I)
Constant Power(P)
@etap:
Static Load – pure static load doesn’t have an inductive or motor load.
Constant Impedance(Z):
To understand better let have a system rated voltage of 11/0.415kV having 1.5MVA transformer. Now we will
connect a static load of 1MVA with same parameters on each HV and LV buses of transformer.
As we said earlier, both loads having same parameters but the consumption of load is varying from load-1 to
load-2 in picture-1. What happens if we change the voltage on grid from 100% to 95% then the load
consumption also gets deviated shown in picture-2.
P = P0*(V/V0)^2 P = P0*(V/V0)^2
@LV BUS side = 985.595 W @HV BUS side = 1000 W
P = P0*(V/V0) ^a
a-"1" P = P0*(V/V0) ^1
a-"2" P = P0*(V/V0) ^2
Note:
This is known as frequency dependant factor which used to simulate load with different frequency. As
we know if the frequency changes it will affect the power also and power also change linearly.
But etap is not capable/convertible the frequency dependant function. Because etap uses a swing bus
concept which connects strong feed system with a weak feed system and the power flow in the swing
or slack bus will vary and it adjusts the voltage and frequency level with requirement of power flow.
So if we need to simulate frequency dependant factor we have to use transient stability which simulates
different frequencies with respect to change in power.
To find P: To Find Q:
P = P0*(V/V0) ^a Q = Q0*(V/V0) ^b
For Polynomial loads
𝑉 1 𝑉
𝑃 = 𝑃0 ∗ {𝐴 + 𝐵 ∗ ( ) + 𝐶 ∗ ( )2 } were, A Constant power load
𝑉0 𝑉0
B Constant Current load
𝑉 1 𝑉
𝑄 = 𝑄0 ∗ {𝐴 + 𝐵 ∗ ( ) + 𝐶 ∗ ( )2 } C Constant Impedance load
𝑉0 𝑉0
So, for the polynomial loads, power consumption calculation will be vectorial summation of P and Q
values.
𝑉 1 𝑉 𝑉 1 𝑉
𝑃 + 𝑗𝑄 = 𝑃0 ∗ {𝐴 + 𝐵 ∗ ( ) + 𝐶 ∗ ( )2 } + 𝑄0 ∗ {𝐴 + 𝐵 ∗ ( ) + 𝐶 ∗ ( )2 }
𝑉0 𝑉0 𝑉0 𝑉0
An incandescent lamp of 100W running at 230 V. Find the power consumption of lamp at 210V.
Solution:
We know that constant current sources (ex- mobile charger) internally alter resistance itself to
achieve constant current regardless of voltage which is fed to it and so the power will vary.
In other words, it will draw same amount of current despite of change in voltage or other
impedance in circuit.
An incandescent lamp of 100W running at 230 V. Find the power consumption of lamp at 210V.
Solution:
Constant power load means it will maintain constant power irrespective of voltage.
An incandescent lamp of 100W running at 230 V. Find the power consumption of lamp at 210V.
Sungrow - China
SMA – Germany
FIMER (Formerly ABB) – Italy
Huawei – China
Eaton
Growatt – China
Power Electronics – Spain
Sineng
Inverters are mainly classified as String and Central Inverters.
Inverter data are available in data sheet of corresponding manufacturer and model. Also, we need to
ensure that the given PV array/PV panel output with inverter input to minimize the overloading of
inverter.
Inverter have a capable of controlling the output power by controlling DC output voltage.
There is an always slight mismatch between inverter output and etap simulated results because
irradiation level changes time to time.
From above SLD, we can see that inverter is generating 248.3kVA power only though PV array rated
output is 254.8kVA.
This mismatch is due to irradiation level occurs in PV panels.
All the inverter must obey IEEE-1547 Anti Islanding standard.
This anti-islanding is nothing but if grid supply fails then the inverter must cut-off its output power and
goes to inhibit mode to prevent continuous injection of power into grid connected system.
Due to this inhibit mode we can’t run solar inverters on swing/slack mode because voltage and phase
angle can’t be set as a reference value in inverter. It always needs reference voltage from grid.
For Voltage Control mode – Solar inverter load flow didn’t get converge if the irradiation level is
100%. It is due to that 100% irradiation will deliver full load with zero reactive power. So, if we need
to run the solar inverter in voltage control, we must reduce the irradiation level of inverter. Reduction
in irradiation will help to reduce real power generation and increase reactive power generation.
And solar inverter is not like synchronous generators. For example, if we set Qmax and Qmin value in
the generator it generates only whatever the possible P, Q power within given limits. But in solar
inverter it doesn’t obey the Qmax and Qmin criteria and it continue to generate P, Q that are not in
limit. So, it is our responsibility to ensure the outcome of solar inverter is matching the real time
values.
During Case study and simulation of solar power plants – it is suggested to do it with Digsilent Power-
factory which have secondary controller option because etap doesn’t have or support secondary
controllers (PPC) and we may face severe issue if we need to adjust power output/irradiation level at
inverter point for a power plant which have hundreds of inverters.
Cut-in wind speed Minimum wind speed required to generate power. And below cut-in speed
generator won’t be able to generate any power and instead it will act as a motor. So, below cut-in speed
we must turn off the generator (Approx.2-3.5m/seconds).
Anemo-meter Used in WTG to determine speed of wind and helps to identify cut-in speed level so
we can turn on the generator.
Wind vane Used to identify direction of wind.
Yaw motor/drive Used to rotate the WTG nacelle to face against direction of wind that helps to
generate more power.
Pitch factor Important thing in WTG which controls the speed of blade rotation. When the wind
speed goes beyond the limit that time it senses the value and adjust the position of blades into slightly
horizontal level so the impact of wind speed towards blade will get reduced.
Power output of wind turbine is proportional to cube of wind velocity (V 3 ).
Cut-out wind speed After some range of wind speed (typically rated wind speed is 12-14m/seconds)
the safety of WTG is highly concerned. So, to ensure the safety of WTG cut-out speed has required to
automatically cut-off rotation to prevent damages. Cut-off wind speed will be approx. 25m/seconds.
The most important thing is Wind Turbine Generator and Synchronous Generator are not the
same. Practically we can control the input to the generator in Thermal, Hydro plants but WTG
input is not controllable.
So, the input to the WTG is not controllable because it is designed to extract as much as power from
Wind speed.
Speed and Frequency of the WTG will vary time to time so Ns=120f/P won’t be applicable for WTG
that’s why we can’t use synchronous generator here.
Squirrel cage Induction Motor are used in Type 1 & 2 WTG. Normally it’s start as a Squirrel Cage
Induction motor but after reaching cut-in speed it will extract power from and works as a Generator.
If its working as a squirrel cage induction motor, it consumes real and reactive power from grid.
Types of WTG:
Type 1
Type 2
Type 3
Type 4
Type-1 WTG:
These are also called as Squirrel Cage Induction Motor.
It normally starts as a motor and after reaching cut-in speed it starts to extract power and
becomes a generator.
During motor position it consumes real and reactive power from grid. And after turns into a
generator it extracts real power from wind speed but still consumes reactive power from the grid
because it requires flux to rotate as why consuming reactive power.
Maximum Capacity of type1 WTG is 250kW and it is obsolete now (no longer used in market
due to drawbacks).
Reactive power consumption of type1 WTG varies with slip and speed of Induction Generator.
In squirrel cage induction motor, it is not possible to add any external resistance. But in slip ring
induction motor we can add external resistance basically known as type-2 WTG.
Type-2 WTG:
It is a slip/wound ring type induction motor cum generator which allows us to add external
resistance to increase the starting torque.
It is also having a maximum capacity around 250kW and obsolete in the market (no longer used
due to its drawbacks).
This is also called semi controllable WTG because we can adjust the speed slightly using
external resistance.
Type-3 WTG:
Its commonly known as doubly fed induction generator.
It generates electricity from stator (70%) and also from rotor (30%)
The maximum rated capacity available is 15MW offshore and 7.5MW onshore.
This type WTG can be operated in voltage control and MVAr control mode.
But MVAr control mode is limited up-to ±0.95 PF value.
Crow bar circuit is provided in WTG to protect the rotor after fault and fault recovery by shorting
the rotor windings.
The following simulation shows the working principle of WTG-3 model
When grid voltage is 100%, it consumes reactive power in order to maintain voltage at point of
connection (bus voltage where the WTG is connected).
When grid voltage reduced to 95%, it generates reactive power to maintain voltage at point of
connection (bus voltage where the WTG is connected).
Type-4 WTG:
And major difference is the maximum real and reactive power extraction from WTG is 100%
where type-3 only offers about 30% by using rotor.
All the 4 types of WTG are capable of running approximately ±10% voltage tolerance.
Important facts about reactive power consumption/injection:
Depends on the grid code of country – The injection/consumption of reactive power is scaled
around 33% which will vary based on county code requirements.
If Grid voltage is 100% - the system must capable of injecting or consuming ±33% reactive
power to maintain power factor and voltage.
If grid voltage is 110% - the system should not inject more reactive power but allowed to
consume reactive power to reduce the voltage level.
If grid voltage is 90% - the system must inject reactive power in order to increase voltage and
maintain power factor but consumption of reactive power is not advisable.
To improve bus voltage and reduce losses further let’s add a
1 Max Load (100 MVA) Max Voltage (105%) We can run all these 9
2 Average Load (70 MVA) Max Voltage (105%) combinations but
3 Minimum Load (40MVA) Max Voltage (105%) logically case 3 and 7 is
4 Max Load (100 MVA) Normal Voltage (100%) more than enough and
5 Average Load (70 MVA) Normal Voltage (100%) it will cover all the
6 Minimum Load (40MVA) Normal Voltage (100%) remaining cases also.
7 Max Load (100 MVA) Minimum Voltage (95%)
8 Average Load (70 MVA) Minimum Voltage (95%) We can go for case 5 if
9 Minimum Load (40MVA) Minimum Voltage (95%) required for end user.
Operating P/Q/V will give output despite of whatever loading category we simulated in
Loading/Generating category.
For IEC it will consider Higher MVA for Zbase while ANSI considers lower MVA rating in transformer
modelling.
We can conclude that the current rating of transformer plays vital role in power rating and losses and
also in thermal characteristics also.
Increase in impedance increases the X/R ratio and reduction in RMS short circuit current. But the Peak
short circuit will be high due to increased X/R ratio
Z tolerance is used for accounting the tolerance in transformer impedance only when the transformer is
not FAT tested and it is yet to procured.
While %Z variation used for accounting impedance adjustment at different tap position of transformer
because impedance will vary for every tap increases or decreases from normal tap.
In-case of selecting generators, always go to the low power factor.
Because if motor or any other load higher power factor is better because lower the power factor, they
will consume more reactive power which is no use – higher the power factor lowers the reactive power
(reactive power demand by end equipment is less).
In this generator case – we need to evacuate higher reactive power which required for regulating
voltage at generator terminal – higher the power factor generates less reactive power and may leads to
loess access to regulate voltage at generator terminal.
The most important thing is Wind Turbine Generator and Synchronous Generator are not the
same. Practically we can control the input to the generator in Thermal, Hydro plants but WTG
input is not controllable.