GR Master Programme - Mahalla

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024

Mode M J J A S O N D J
1 CONSTRUCTION OF 700m3 GROUND 205 days Mon 05/06/23 Tue 26/12/23
RESERVOIR - MAHALLA SITE
2 Preliminaries 164 days Tue 20/06/23 Thu 30/11/23
3 Access road preparation(considering 162 days Thu 22/06/23 Thu 30/11/23
the periodical repair of road)
4 Preparation of Site office and Site Yard 24 days Mon 26/06/23 Wed 19/07/23 3SS+4 days

5 Reinforcement cleaning work 18 days Tue 20/06/23 Fri 07/07/23


6 Sorting re bar 2 days Sat 08/07/23 Sun 09/07/23 5
7 Initial surveying works 1 day Sat 08/07/23 Sat 08/07/23 6SS
8 Documentation works 16 days Fri 30/06/23 Sat 15/07/23
9 Construction of Ground Reservoir 150 days Mon 05/06/23 Wed 01/11/23
10 Construction of Base 42 days Mon 05/06/23 Sun 16/07/23
11 Setting out work 1 day Mon 05/06/23 Mon 05/06/23
12 Completion of balance excavation 2 days Tue 06/06/23 Wed 07/06/23 11
13 Completion of screed concrete 1 day Thu 08/06/23 Thu 08/06/23 12
14 Setting out work 1 day Fri 09/06/23 Fri 09/06/23 13
15 Fabrication and installation of 20 days Wed 14/06/23 Mon 03/07/23 13FS+5 days
reinforcement includeing wall re bar

16 Fabrication and installation of 9 days Fri 30/06/23 Sat 08/07/23 15SS+16 days
formwork
17 inspection 1 day Sat 08/07/23 Sat 08/07/23 16FF
18 Base Concrete 2 days Sat 08/07/23 Sun 09/07/23 17SS
19 Curing 7 days Mon 10/07/23 Sun 16/07/23 18
20 Removing formwork 2 days Thu 13/07/23 Fri 14/07/23 19SS+3 days
21 Construction of Walls 77 days Sat 15/07/23 Fri 29/09/23
22 Outer Wall - First lift - Along Grid A 24 days Sat 15/07/23 Mon 07/08/23
to E / 1 to 6
23 Fabrication and installation of 8 days Sat 15/07/23 Sat 22/07/23 19SS+5 days
reinforcements (including the
rebar cleaning work)
24 Scaffolding work and platform 3 days Mon 17/07/23 Wed 19/07/23 23SS+2 days
preparation work (Including the
inner side)
25 Fabrication and erection of 10 days Fri 21/07/23 Sun 30/07/23 23SS+6 days
formwork
26 inspection 1 day Mon 31/07/23 Mon 31/07/23 25
27 Concrete wall first lift 1 day Mon 31/07/23 Mon 31/07/23 26SS
28 Curing 7 days Tue 01/08/23 Mon 07/08/23 27
29 Formwork removing & Surface 3 days Thu 03/08/23 Sat 05/08/23 28SS+2 days
finishing

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: mahalla gr
Milestone Inactive Summary Start-only Critical
Date: Thu 27/07/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
30 Outer Wall - Second lift - Along Grid 30 days Fri 04/08/23 Sat 02/09/23
A to E / 1 to 6
31 Scaffoding work and platform 2 days Fri 04/08/23 Sat 05/08/23 28SS+3 days
preparation work (including the
inner side)
32 Fabrication and installation of 10 days Sun 06/08/23 Tue 15/08/23 31
reinforcements (Including the
rebar cleaning work)
33 Fabrication and erection of 12 days Fri 11/08/23 Tue 22/08/23 32SS+5 days
formwork
34 inspection 1 day Wed 23/08/23 Wed 23/08/23 33
35 Concrete wall second lift 1 day Wed 23/08/23 Wed 23/08/23 34SS
36 Curing 7 days Wed 23/08/23 Tue 29/08/23 35SS
37 Formwork removing and surface 2 days Fri 01/09/23 Sat 02/09/23 36FS+2 days
preperation
38 Inner Wall,Baffer wall and column - 15 days Sun 03/09/23 Sun 17/09/23
first lift - 6nrs
39 Fabrication and installation of 4 days Sun 03/09/23 Wed 06/09/23 37
reinforcement (Including the rebar
cleaning work)
40 Fabrication and erection of 4 days Wed 06/09/23 Sat 09/09/23 39SS+3 days
formwork
41 inspection 1 day Sun 10/09/23 Sun 10/09/23 40
42 Concrete pouring for wall first lift 1 day Sun 10/09/23 Sun 10/09/23 41SS

43 Curing 7 days Mon 11/09/23 Sun 17/09/23 42


44 formwork removing and surface 3 days Thu 14/09/23 Sat 16/09/23 43SS+3 days
preparation work
45 Inner wall,Baffer wall and column - 16 days Thu 14/09/23 Fri 29/09/23
second lift - 6nrs
46 Fabrication and installation of 6 days Thu 14/09/23 Tue 19/09/23 43SS+3 days
reinforcement (Including the rebar
cleaning work)
47 Fabrication and erection of 6 days Sun 17/09/23 Fri 22/09/23 46SS+3 days
formwork
48 inspection 1 day Sat 23/09/23 Sat 23/09/23 47
49 Concrete pouring for wall first lift 1 day Sat 23/09/23 Sat 23/09/23 48SS

50 Curing 7 days Sat 23/09/23 Fri 29/09/23 49SS


51 Removing formwork 1 day Sun 24/09/23 Sun 24/09/23 49
52 Construction of Roof Slab 37 days Tue 26/09/23 Wed 01/11/23
53 Fabrication and erection of formwork 14 days Tue 26/09/23 Mon 09/10/23 50SS+3 days

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: mahalla gr
Milestone Inactive Summary Start-only Critical
Date: Thu 27/07/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 2
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
54 Fabrication and installation of 6 days Wed 04/10/23 Mon 09/10/23 53SS+8 days
reinforcement including manhole and
slab wall re bar(Including the rebar
cleaning work)
55 inspection 1 day Tue 10/10/23 Tue 10/10/23 54
56 Concrete of slab 1 day Tue 10/10/23 Tue 10/10/23 55SS
57 Curing 21 days Tue 10/10/23 Mon 30/10/23 56SS
58 Removing formwork 2 days Tue 31/10/23 Wed 01/11/23 57
59 Construction of slab wall and man 13 days Wed 18/10/23 Mon 30/10/23
holes
60 Formwork and Reinforcement 5 days Wed 18/10/23 Sun 22/10/23 56FS+7 days
61 Inspection 1 day Mon 23/10/23 Mon 23/10/23 60
62 Concrete 2 days Tue 24/10/23 Wed 25/10/23 61
63 Curing 7 days Tue 24/10/23 Mon 30/10/23 62SS
64 Removing formwork 2 days Thu 26/10/23 Fri 27/10/23 62
65 Puddle Pipe installation and 34 days Sat 30/09/23 Thu 02/11/23
Miscellaneous metal work
66 Puddle pipe installation and Concreting 5 days Sat 30/09/23 Wed 04/10/23 21

67 Ladder and penstock gate installation 7 days Sat 30/09/23 Fri 06/10/23 66SS

68 Heavy duty Cover Installation 3 days Tue 31/10/23 Thu 02/11/23 62FS+5 days
69 Air Went Installation 2 days Tue 31/10/23 Wed 01/11/23 62FS+5 days
70 Water Tightness Test 42 days Wed 25/10/23 Tue 05/12/23
71 Deshuttering / Cleaning / Rectification 7 days Wed 25/10/23 Tue 31/10/23 55FS+14 days

72 Water Filling 5 days Wed 01/11/23 Sun 05/11/23 71


73 Saturation and Observation 28 days Mon 06/11/23 Sun 03/12/23 72
74 Dewatering / Flushing / Disinfection 2 days Mon 04/12/23 Tue 05/12/23 73
75 Chamber Construction works 34 days Sat 30/09/23 Thu 02/11/23
76 Excavation / Levelling Concrete for 14 days Sat 30/09/23 Fri 13/10/23 21
Chamber bases
77 Base Construction 14 days Mon 02/10/23 Sun 15/10/23 76SS+2 days
78 Wall Construction 14 days Mon 09/10/23 Sun 22/10/23 77SS+7 days
79 Cover slab construction 14 days Mon 16/10/23 Sun 29/10/23 78SS+7 days
80 Heavy duty cover placing 4 days Mon 30/10/23 Thu 02/11/23 79
81 Yard Pipe laying 47 days Fri 03/11/23 Tue 19/12/23
82 Excavation (soil and rock) and Pipe 30 days Fri 03/11/23 Sat 02/12/23 75
Laying
83 Pressure testing 10 days Sun 03/12/23 Tue 12/12/23 82
84 Disinfection 7 days Wed 13/12/23 Tue 19/12/23 83
85 Panel room construction work 14 days Tue 14/11/23 Mon 27/11/23

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: mahalla gr
Milestone Inactive Summary Start-only Critical
Date: Thu 27/07/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 3
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
86 Construction of toe wall 46 days Sat 30/09/23 Tue 14/11/23
87 Ground Preparation and Levelling 7 days Sat 30/09/23 Fri 06/10/23 21
concrete for base
88 Construction of retaining wall 25 days Sat 07/10/23 Tue 31/10/23 87
89 Backfilling and ground preperation 14 days Wed 01/11/23 Tue 14/11/23 88
90 Type 3 drain construction 46 days Sat 30/09/23 Tue 14/11/23
91 Ground preparation 25 days Sat 30/09/23 Tue 24/10/23 87SS
92 Drain Construction 30 days Mon 02/10/23 Tue 31/10/23 91SS+2 days
93 Catchpit construction 14 days Wed 01/11/23 Tue 14/11/23 92
94 Landscaping and Boundary Fence 52 days Fri 03/11/23 Sun 24/12/23
Construction
95 Construction of boundary fence. 35 days Fri 03/11/23 Thu 07/12/23 75
96 Ground leveling 14 days Fri 17/11/23 Thu 30/11/23 95SS+14 days
97 Gate construction 10 days Fri 08/12/23 Sun 17/12/23 95
98 Turfing 10 days Fri 01/12/23 Sun 10/12/23 96
99 Interlock paving 10 days Fri 01/12/23 Sun 10/12/23 96
100 Painting works 7 days Mon 18/12/23 Sun 24/12/23 97
101 Finishing work 21 days Wed 06/12/23 Tue 26/12/23
102 Applying Water proofing for GR Slab 5 days Wed 06/12/23 Sun 10/12/23 74
and walls
103 Placing Chip concrete in the GR slab 2 days Mon 11/12/23 Tue 12/12/23 102
104 Laying Pebbles on GR Slab 5 days Wed 20/12/23 Sun 24/12/23 103FS+7 days
105 External Painting works 5 days Wed 20/12/23 Sun 24/12/23 104SS
106 Cleaning and Remove all the debris 2 days Mon 25/12/23 Tue 26/12/23 105

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: mahalla gr
Milestone Inactive Summary Start-only Critical
Date: Thu 27/07/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 4
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: mahalla gr
Milestone Inactive Summary Start-only Critical
Date: Thu 27/07/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 5
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: mahalla gr
Milestone Inactive Summary Start-only Critical
Date: Thu 27/07/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 6
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: mahalla gr
Milestone Inactive Summary Start-only Critical
Date: Thu 27/07/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 7
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: mahalla gr
Milestone Inactive Summary Start-only Critical
Date: Thu 27/07/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 8
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: mahalla gr
Milestone Inactive Summary Start-only Critical
Date: Thu 27/07/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 9
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: mahalla gr
Milestone Inactive Summary Start-only Critical
Date: Thu 27/07/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 10
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline


Project: mahalla gr
Milestone Inactive Summary Start-only Critical
Date: Thu 27/07/23
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 11