GR Master Programme - Mahalla
GR Master Programme - Mahalla
GR Master Programme - Mahalla
Mode M J J A S O N D J
1 CONSTRUCTION OF 700m3 GROUND 205 days Mon 05/06/23 Tue 26/12/23
RESERVOIR - MAHALLA SITE
2 Preliminaries 164 days Tue 20/06/23 Thu 30/11/23
3 Access road preparation(considering 162 days Thu 22/06/23 Thu 30/11/23
the periodical repair of road)
4 Preparation of Site office and Site Yard 24 days Mon 26/06/23 Wed 19/07/23 3SS+4 days
16 Fabrication and installation of 9 days Fri 30/06/23 Sat 08/07/23 15SS+16 days
formwork
17 inspection 1 day Sat 08/07/23 Sat 08/07/23 16FF
18 Base Concrete 2 days Sat 08/07/23 Sun 09/07/23 17SS
19 Curing 7 days Mon 10/07/23 Sun 16/07/23 18
20 Removing formwork 2 days Thu 13/07/23 Fri 14/07/23 19SS+3 days
21 Construction of Walls 77 days Sat 15/07/23 Fri 29/09/23
22 Outer Wall - First lift - Along Grid A 24 days Sat 15/07/23 Mon 07/08/23
to E / 1 to 6
23 Fabrication and installation of 8 days Sat 15/07/23 Sat 22/07/23 19SS+5 days
reinforcements (including the
rebar cleaning work)
24 Scaffolding work and platform 3 days Mon 17/07/23 Wed 19/07/23 23SS+2 days
preparation work (Including the
inner side)
25 Fabrication and erection of 10 days Fri 21/07/23 Sun 30/07/23 23SS+6 days
formwork
26 inspection 1 day Mon 31/07/23 Mon 31/07/23 25
27 Concrete wall first lift 1 day Mon 31/07/23 Mon 31/07/23 26SS
28 Curing 7 days Tue 01/08/23 Mon 07/08/23 27
29 Formwork removing & Surface 3 days Thu 03/08/23 Sat 05/08/23 28SS+2 days
finishing
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 1
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
30 Outer Wall - Second lift - Along Grid 30 days Fri 04/08/23 Sat 02/09/23
A to E / 1 to 6
31 Scaffoding work and platform 2 days Fri 04/08/23 Sat 05/08/23 28SS+3 days
preparation work (including the
inner side)
32 Fabrication and installation of 10 days Sun 06/08/23 Tue 15/08/23 31
reinforcements (Including the
rebar cleaning work)
33 Fabrication and erection of 12 days Fri 11/08/23 Tue 22/08/23 32SS+5 days
formwork
34 inspection 1 day Wed 23/08/23 Wed 23/08/23 33
35 Concrete wall second lift 1 day Wed 23/08/23 Wed 23/08/23 34SS
36 Curing 7 days Wed 23/08/23 Tue 29/08/23 35SS
37 Formwork removing and surface 2 days Fri 01/09/23 Sat 02/09/23 36FS+2 days
preperation
38 Inner Wall,Baffer wall and column - 15 days Sun 03/09/23 Sun 17/09/23
first lift - 6nrs
39 Fabrication and installation of 4 days Sun 03/09/23 Wed 06/09/23 37
reinforcement (Including the rebar
cleaning work)
40 Fabrication and erection of 4 days Wed 06/09/23 Sat 09/09/23 39SS+3 days
formwork
41 inspection 1 day Sun 10/09/23 Sun 10/09/23 40
42 Concrete pouring for wall first lift 1 day Sun 10/09/23 Sun 10/09/23 41SS
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 2
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
54 Fabrication and installation of 6 days Wed 04/10/23 Mon 09/10/23 53SS+8 days
reinforcement including manhole and
slab wall re bar(Including the rebar
cleaning work)
55 inspection 1 day Tue 10/10/23 Tue 10/10/23 54
56 Concrete of slab 1 day Tue 10/10/23 Tue 10/10/23 55SS
57 Curing 21 days Tue 10/10/23 Mon 30/10/23 56SS
58 Removing formwork 2 days Tue 31/10/23 Wed 01/11/23 57
59 Construction of slab wall and man 13 days Wed 18/10/23 Mon 30/10/23
holes
60 Formwork and Reinforcement 5 days Wed 18/10/23 Sun 22/10/23 56FS+7 days
61 Inspection 1 day Mon 23/10/23 Mon 23/10/23 60
62 Concrete 2 days Tue 24/10/23 Wed 25/10/23 61
63 Curing 7 days Tue 24/10/23 Mon 30/10/23 62SS
64 Removing formwork 2 days Thu 26/10/23 Fri 27/10/23 62
65 Puddle Pipe installation and 34 days Sat 30/09/23 Thu 02/11/23
Miscellaneous metal work
66 Puddle pipe installation and Concreting 5 days Sat 30/09/23 Wed 04/10/23 21
67 Ladder and penstock gate installation 7 days Sat 30/09/23 Fri 06/10/23 66SS
68 Heavy duty Cover Installation 3 days Tue 31/10/23 Thu 02/11/23 62FS+5 days
69 Air Went Installation 2 days Tue 31/10/23 Wed 01/11/23 62FS+5 days
70 Water Tightness Test 42 days Wed 25/10/23 Tue 05/12/23
71 Deshuttering / Cleaning / Rectification 7 days Wed 25/10/23 Tue 31/10/23 55FS+14 days
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 3
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
86 Construction of toe wall 46 days Sat 30/09/23 Tue 14/11/23
87 Ground Preparation and Levelling 7 days Sat 30/09/23 Fri 06/10/23 21
concrete for base
88 Construction of retaining wall 25 days Sat 07/10/23 Tue 31/10/23 87
89 Backfilling and ground preperation 14 days Wed 01/11/23 Tue 14/11/23 88
90 Type 3 drain construction 46 days Sat 30/09/23 Tue 14/11/23
91 Ground preparation 25 days Sat 30/09/23 Tue 24/10/23 87SS
92 Drain Construction 30 days Mon 02/10/23 Tue 31/10/23 91SS+2 days
93 Catchpit construction 14 days Wed 01/11/23 Tue 14/11/23 92
94 Landscaping and Boundary Fence 52 days Fri 03/11/23 Sun 24/12/23
Construction
95 Construction of boundary fence. 35 days Fri 03/11/23 Thu 07/12/23 75
96 Ground leveling 14 days Fri 17/11/23 Thu 30/11/23 95SS+14 days
97 Gate construction 10 days Fri 08/12/23 Sun 17/12/23 95
98 Turfing 10 days Fri 01/12/23 Sun 10/12/23 96
99 Interlock paving 10 days Fri 01/12/23 Sun 10/12/23 96
100 Painting works 7 days Mon 18/12/23 Sun 24/12/23 97
101 Finishing work 21 days Wed 06/12/23 Tue 26/12/23
102 Applying Water proofing for GR Slab 5 days Wed 06/12/23 Sun 10/12/23 74
and walls
103 Placing Chip concrete in the GR slab 2 days Mon 11/12/23 Tue 12/12/23 102
104 Laying Pebbles on GR Slab 5 days Wed 20/12/23 Sun 24/12/23 103FS+7 days
105 External Painting works 5 days Wed 20/12/23 Sun 24/12/23 104SS
106 Cleaning and Remove all the debris 2 days Mon 25/12/23 Tue 26/12/23 105
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 4
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 5
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 6
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 7
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 8
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 9
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 10
ID Task Task Name Duration Start Half 1, 2023 Finish Predecessors Half 2, 2023 Half 1, 2024
Mode M J J A S O N D J
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 11