Professional Documents
Culture Documents
RSIP - Risk Informed Decision Support - Appendix-D-Wg-4-Report
RSIP - Risk Informed Decision Support - Appendix-D-Wg-4-Report
Report for:
RISP Participants, att: Equinor Energy AS
• Safety premises: Identified aspects presumed to be true and therefore used as a basis for the
management of MAH. This can typically be presumption made in the HAZAN as a basis for
concluding that the design is within the validity envelope of the RISP models. It can also
cover other aspects such as operational restrictions. Safety premises typically needs to be
verified at a later stage.
• Safety program: The safety program is a high-level plan describing the goals, means
(resources), activities and analyses planned to manage MAH in a development project.
Responsibilities, organisation and interaction arenas related to implementation of MAH
design in the development project should be described.
• Safety strategy: The safety strategy is a high-level plan giving the link between the safety
program and the design development with respect to MAH. The strategy describes how the
end goals will be achieved. The safety strategy should also cover the needs related to fire and
explosion strategy (FES) and escape, evacuation and rescue strategy (EERS). The safety
strategy should outline applicable overall principles for design, layout, arrangements,
philosophies and other high-level design and operational aspects related to barriers, e.g.:
o Describing MAH relevant for the development (e.g. area by area) and describing key
design measures and safety premises.
o Describing how specific MAH are managed by the use of barrier functions, systems and
elements. Typically, this should include a reference to standard requirements (e.g.
NORSOK S-001) and whether there are special solutions required not covered by the
standards.
• Proven design: Design or concepts that are considered prequalified through operational
experience and/or previous engineering documentation and analyses to such a degree that
the RISP methodology and models can be applied.
• RISP methodology: The principles that has been used to establish methods and models in the
JIP. The term is also applied as the totality of RISP methods and RISP models.
• RISP methods: The work steps and procedures proposed to be used for risk-based decision
support in development projects
• RISP models: The assessment tools proposed to be applied for risk-based decision support in
development projects
Workgroups (WG):
1. Risk 5.
3. Fires (heat 4. Other
management, incl. 2. Explosions Regulatory
and smoke) accidents
decision process framework
3.2 Context
The applicability for RISP will be assessed in the HAZAN (see Section 3.3.1). During the HAZAN
the following should be assessed to verify applicability for RISP:
• Regulatory requirements
• GOMO guidelines
• Overall layout and plans.
The RISP method is developed for oil and gas operations on the Norwegian Continental Shelf, and
comply with Norwegian regulations for petroleum activities, and based on procedures and
operating practices which are considered industry practice on the Norwegian Continental Shelf.
1 This is a Lloyd’s Register best estimate based on experience and is not consolidated by a detailed review of
platforms. However, the context of which the estimate is used in RISP does not depend significantly on
having a more accurate number.
Impact energy from a dropped object will depend on terminal velocity at the point of impact. The
impact velocity will vary significantly, particularly for pipes or slender objects. Due to variation in
terminal velocities one can expect conditional probabilities for various energy bands as shown in
Table 3. The conditional probabilities are proposed for a close to horizontal pipeline with normal
protection requirement, and a normal distribution of the impact energies.
Middle zone
Drop (33% hit
point probability)
Inner zone
(33% hit
probability)
Figure 3 – Drop zones applied in RISP model for each object that can be dropped
Three drop zones (inner, middle and outer) are defined for all object types defined in Table 2
(with their given Angular deviation). The three drop zones for each object type will be different
due to the different Angular deviation.
The average likelihood of hitting one pipeline within each drop zone is estimated by assuming
that the pipeline is hit if the dropped objects lands closer than 2,5 m from the pipeline on each
side (i.e. critical drop width of 5 m). The likelihood of hitting a pipeline in each drop zone can
hence be found by
5𝑚
𝐻𝑖𝑡 𝑝𝑟𝑜𝑏𝑎𝑏𝑖𝑙𝑖𝑡𝑦 =
2𝜋𝑋𝑀𝐸𝐴𝑁
Where XMEAN is the mean radial distance from the drop point for each drop zone.
The total energy that the dropped object protection must be able to absorb without resulting in a
rupture to the pipeline can then be found by assuming that given a drop in one drop zone, the
pipeline must have 95% probability of surviving. Consequently. if the hit probability is less than
5% in a drop zone, then there is no need for additional protection. If the hit probability is above
5% the pipeline must be protected with sufficient strength to provide total survivability of 95%
E.g. if the hit probability is 50% then the pipe must be protected to survive 90% of the hits to
have a total survivability of 95%:
(0.95−(1−0.5))
= 0.90
0.5
From Table 3 the cumulative collision energy for each object type can be estimated. Combining
the hit energy with the hit rate and the target total survivability of 95% the required protection
energy can be estimated for all dropped object types in all drop zones.
In the RISP model it is assumed that all object types of Table 2 will be lifted, and by following the
process described above for all objects and applying the highest calculated protection energy for
each radial distance, the dimensioning protection energy can be produced for all radial distances
from the drop point. The capacity of the pipeline (typically 20 kJ) can be subtracted from the
800
700
Protection energy [kJ]
600
500
400
300
200
100
0
0 2.5 5 7.5 10 12.5 15 17.5 20 22.5 25 27.5 30 32.5
Horizontal distance from drop point [m]
700
600
Protection energy [kJ]
500
400
300
200
100
0
0 2.5 5 7.5 10 12.5 15 17.5 20 22.5 25 27.5 30 32.5 35 37.5 40 42.5 45 47.5 50 52.5 55 57.5 60 62.5 65
Horizontal distance from drop point [m]
600
500
Protection energy [kJ]
400
300
200
100
0
0
5
2.5
15
80
7.5
10
20
25
30
35
40
45
50
55
60
65
70
75
85
90
95
12.5
17.5
22.5
27.5
32.5
37.5
42.5
47.5
52.5
57.5
62.5
67.5
72.5
77.5
82.5
87.5
92.5
97.5
100
102.5
105
107.5
110
112.5
115
117.5
120
122.5
125
Horizontal distance from drop point [m]
Figure 6 – Required protection energy – water depth 200m or more (95% survivability)
Table 6 – Tabulated protection energies – water depth 200m or more (95% survivability)
Other equipment that may be hit by dropped objects on the seabed or on the way down to the
seabed (such as risers, anchor lines and structures) are not covered by the RISP methodology and
special studies of these arrangements must be performed to assess robustness against collision
with dropped objects.
Δh
Critical area
Platform topside
Step 1:
Identify what you potentially will be lifting where
Step 2:
Chose what you will design against vs. and what will require a
shutdown/depressurization of the exposed equipment
Step 3:
Understand the consequences of the choices (what it may cause in terms of
downtime/shutdown etc.)
Step 4:
Establish the loads, and design accordingly
Geometric
shielding
Pipeline
Platform topside
Drop
point
Operational shielding is when the operational procedures ensures that lifting over the side with
pipelines is reduced to a minimum. In Figure 11 this is illustrated with ensuring that lifts over sea
(and hence drop points) are located on the opposite side of the platform from where the pipelines
are located. This means that in the case of a drop to sea, the pipeline is shielded by the jacket
structure. This type of shielding can be provided by any gravity-based substructure. For floating
substructures, this shielding is limited (but can be partly applied e.g. for SPAR FPSO concepts). If
the design is dependent on operational shielding, this must be clearly communicated to the
operations management to be included in the operation strategy, e.g. by lifting maps or no lifting
zones.
Operational
shielding
Drop
point
Platform topside
Pipeline
Figure 11 – Operational shielding by ensuring lifting over sea is done on the opposite side of the platform
from where the pipelines are located
When planning for operational shielding in an early phase development projects one must assess
possible consequences for all major accident risks. As an example, one can perform a trade-off
assessment between ship collision strength and need for protection of pipelines; if one decides to
RISP radial
distance origin
Possible drop
point area
Crane
pedestal Platform topside
Jacket structure
Figure 12 – Radial distance origin for pipeline protection by the RISP model
If a template or other important structure (containing hazardous material) is located within the
radial distances requiring protection as defined by RISP, they must be protected against the same
energies as indicated by RISP for subsea arrangements. If these templates are especially
vulnerable, e.g. if being a main barrier towards the reservoir, one must consider additional
protection by special studies (this case will be outside RISP).
An illustration of the RISP method is given in Figure 13.
Step 1:
Identify RISP radial distance origin (see Figure 4-10)
Step 2:
Assess operational and geometric shielding
Step 3:
Identify need for seabed protection as function of distance from drop origin
Step 4:
Assess if there are special conditions that allows for reduction in seabed protection
Figure 14 – Model explosion loads for transformer explosions (low and high flashpoint)
8.3.2 Layout
In the design phase the most important decision is to locate the helideck at a safe and operable
location.
In addition to minimising interference with operation of the facility (exhaust, flaring and venting)
the location of the helideck must meet the requirement from NORSOK S-001 that the layout must
facilitate effective emergency response and provide for adequate arrangements for escape and
evacuation.
Operability must also be discussed and facilitated. Special challenges must be addressed, e.g. in
the case of weather vaning facilities the landing approach may be affected by the lighting
conditions in unfavourable direction relative to the wind direction (landing in front of facility
with wind from the front and process lighting from aft).
9.2.2 Concept
The chosen concept for main load bearing, floating and position keeping must be standard and
previously applied in the North Sea.
9.2.4 Waves
Impairment of main safety functions due to extreme weather can be assumed to be dominated by
extreme waves. A wave return frequency of 1E-04 must be used as design case.
When applying standards to design against wave loads one must consider whether subsidence
could cause problems with the air gap throughout the installation lifetime and/or related to
sudden movements of the formation. Subsidence up to maximum 1 m shall be added to initial
water depth for gravity-based facilities. Additional creep must be measured and assessed during
operation.
12.2 Context
• The potential for MAH are related to:
o Maloperation or technical failure of ballasting system or cargo systems
o Anchor system failures
o Structural failures, local explosions or collision impact causing compartment filling and
accidental heel.
• The design is primarily governed by regulations and standards. Key design standards
include:
o Norsok S-001 – Chapter 9 and 24
o Norsok N-001 – Chapter 7.10, 7.11 and 7.12.
o Norsok N-003
o Norsok N-004
o Norsok P-002 Chapter 28.
o DNVGL – OS – D101
o DNVGL-OS-C104
12.3 HAZAN
• The Guide words presented in Z-013, Annex C can be used as a starting point
/1/ Norsk Olje & Gass (NOROG): Prosjekt «Formålstjenlige risikoanalyser» Resultater og
forslag til videreføring, Versjon: 6. februar 2017.
/2/ ISO 17776: “Petroleum and natural gas industries – Offshore production installations –
Major accident hazard “, Second edition dated 15.12.2016.
/3/ JIP report (LR/DNVGL/Safetec): “JIP visiting vessel collision risk assessment
methodology”, Report no: 106074/R1, Rev. Final B, dated 07.05.2019.
/6/ Aasta Hansteen as-built TRA, TN-10: Other accidents, Appendix C: Dropped crane boom
frequency evaluation, Report no: 107046/TN-10 Rev: Draft A, Date: 08 July 2019.
/8/ Lilleaker Consulting report: TRA for Johan Sverdrup P2 EPC, Appendix I, Transformer
accidents”. Lilleaker Consulting report no LA-2018-R-077, Rev. 02, dated 17.12.2018.
/9/ “Power Transformer Tank Rupture and Mitigation—A Summary of Current State of
Practice and Knowledge by the Task Force of IEEE Power Transformer Subcommittee.
IEEE TRANSACTIONS ON POWER DELIVERY, VOL. 24, NO. 4, OCTOBER 2009”.
/10/ Combustion Physics", C.K. Law, Princeton University, Cambridge University Press.
/11/ SINTEF, Helicopter Safety Study 3, rapport nr.: SINTEF A 14973, 22.03.2010,
http://www.sintef.no/Teknologi-og-samfunn/Sikkerhet/Rapporter--
Reports/Helikoptersikkerhetsstudie-3-HSS-3/.
/12/ Civil Aviation Authority, “Standards for offshore helicopter landing areas CAP 437”,
Edition 8, 2016.
/13/ Total risk analysis - Johan Sverdrup Field Centre - P1 platform - As-built Phase 1, TN-8:
Other accidents, Lloyd’s report No. 105584-02-P1/TN-8, Final, Dated June 1, 2018.
/14/ OGP Risk Assessment Data Directory: "Structural risk for offshore installations", Report
No. 434 – 13, March 2010.
/15/ Inge Lotsberg et. al: "Risk Assessment of loss of structural integrity of a floating
production platform due to gross errors", published in Marine Structures 17 (2004) 551-
573, 16 March 2005.