Smart plus Construction Pvt.

Ltd
Lalitpur
Measurement Sheet
S.N Description Unit No. L B H Qty Remarks

Civil Works

A Formworks 3975.86

Beams ft2 1086.68


i Main Beam ft2
Between C-B grid ft2 5 15.67 1.00 1.00 235.00
Between B and A,extra Grids
Along grid 1 ft2 1 12.60 1.00 1.00 37.80
Along grid 2 ft2 1 13.42 1.00 1.00 40.25
Along grid 3 ft2 1 11.17 1.00 1.00 33.50
Along grid 4 ft2 1 13.33 1.00 1.00 40.00
Along grid 5 ft2 1 8.83 1.00 1.00 26.50
Along grid 6 ft2 1 7.17 1.00 1.00 21.50
Along C&B grid
Between 1-2 ft2 2 9.50 1.00 1.00 57.00
Between 2-3 ft2 2 9.92 1.00 1.00 59.50
Between 3-4 ft2 2 9.92 1.00 1.00 59.50
Between 4-5 ft2 2 10.17 1.00 1.00 61.00
Betwee 5-6 ft2 2 12.50 1.00 1.00 75.00
Along Grid and extra grids
Between 1-2 ft2 1 9.50 1.00 1.00 28.50
Between 2-3 ft2 1 10.92 1.00 1.00 32.75
Between 3-4 ft2 1 10.83 1.00 1.00 32.50
Between 4-5 ft2 1 12.00 1.00 1.00 36.00
Betwee 5-6 ft2 1 14.42 1.00 1.00 43.25
ii Secondary beams
Between grid 1&2 ft2 1 17.67 0.75 1.00 48.58
Between Grid C&B ft2 1 12.50 0.75 0.75 28.13

iii Top Beams


a. Side beams ft2 6 4.00 1.00 1.00 72.00
b. Back Projected ft2 2 4.25 1.00 0.58 18.42

Columns 229.083333
a. 2 beams connected ft2 1 5.33 2.5 13.33
b. 3beams connected ft2 7 4.17 2.5 72.92
c. 4 beams connected ft2 10 3.33 2.5 83.33
d. Backside Columns ft2 2 0.75 1.00 8.5 59.50

Slab 2392.22396
Tops
a. Side ft2 1 67.00 4.00 268.00
b. Back ft2 1 22.92 5.00 114.58
c. Circular Top ft2 1 radius = 2.50 2.45
Supported slab
a. Rectangular ft2 1 62.00 28.33 1756.67
b. Small rectangle ft2 1 24.92 6.25 155.73
c. Triangular ft2 1 37.92 5.00 94.79
Soffits ft2 1 268.92 0.42 112.05

Sraircase 155.833333
Risers ft2 14 4.17 0.58 34.03
Sides ft2 2 10.83 2.00 43.33
Waist Slab ft2 1 10.83 4.17 45.14
Landing ft2 2 4.00 4.17 33.33
Smart plus Construction Pvt.Ltd
Lalitpur
Measurement Sheet
S.N Description Unit No. L B H Qty Remarks

Civil Works

B Concreting ft3 1491.153


Beams ft3 351.45
i Main Beam ft3
a. Between C-B grid ft3 5 15.67 1.00 1.00 78.33
b.Between B and A,extra Grids
Along grid 1 ft3 1 12.60 1.00 1.00 12.60
Along grid 2 ft3 1 13.42 1.00 1.00 13.42
Along grid 3 ft3 1 11.50 1.00 1.00 11.50
Along grid 4 ft3 1 10.33 1.00 1.00 10.33
Along grid 5 ft3 1 8.83 1.00 1.00 8.83
Along grid 6 ft3 1 7.17 1.00 1.00 7.17
c. Between C&B grid
Between 1-2 ft3 2 9.50 1.00 1.00 19.00
Between 2-3 ft3 2 9.92 1.00 1.00 19.83
Between 3-4 ft3 2 8.92 1.00 1.00 17.83
Between 4-5 ft3 2 10.17 1.00 1.00 20.33
Betwee 5-6 ft3 2 12.50 1.00 1.00 25.00
d. Along Grid and extra grids
Between 1-2 ft3 1 9.50 1.00 1.00 9.50
Between 2-3 ft3 1 10.92 1.00 1.00 10.92
Between 3-4 ft3 1 10.83 1.00 1.00 10.83
Between 4-5 ft3 1 12.00 1.00 1.00 12.00
Betwee 5-6 ft3 1 14.42 1.00 1.00 14.42
ii Secondary beams
a. Between grid 1&2 ft3 1 17.67 0.75 1.00 13.25
b. Between Grid C&B ft3 1 12.33 0.75 0.58 5.40
iii Top Beams
a. Side beams ft3 6 4.00 1.00 1.00 24.00
b. Back Projected ft3 2 4.25 1.00 0.58 4.96
c. C reinforced beam ft3 1 2.00 1.00 1.00 2.00

Slab 989.36
Tops
a. Side ft3 1 67.00 4.00 0.42 111.67
b. Back ft3 1 18.92 5.00 0.42 39.41
c. Circular Top ft3 1 radius = 2.50 0.42 2.04
Supported slab
a. Rectangular ft3 1 62.00 28.33 0.42 731.94
b. Small rectangle ft3 1 24.92 6.25 0.42 64.89
c. Triangular ft3 1 37.83 5.00 0.42 39.41

Column 106.50
Column Type I (22"*22") ft3 16 1.83 1.83 1.50 80.67
Column Type II (22"*26") ft3 1 1.83 2.17 1.50 5.96
Column Type III (22"*36") ft3 1 1.83 3.00 1.50 8.25
Back Columns 2 0.75 1.00 7.75 11.62

Staircase 43.84
Waist Slab ft3 1 10.83 4.17 0.42 18.81
Landing ft3 2 4.00 4.17 0.42 13.89
Steps ft3 11 4.17 0.58 0.83 11.14
Smart plus Construction Pvt.Ltd
Lalitpur
Measurement Sheet
S.N Description Unit No. L Qty Remarks

Civil Works

C Reinforcements Tons 5.957


Beams
Along Grid C
i. Between Grid 1-5
a. 20mm dia. kg 4 55.67 167.22
b. 16mm dia. kg 1 55.67 26.72
c. 20mm dia. Extra kg 2 42.33 63.58
d. 12mm dia. Extra kg 2 9.67 5.22
e. Stirrups kg 135 4.50 72.90
ii. Between 5-6
a. 20mm dia. kg 4 24.17 72.60
b. 16mm dia. kg 1 24.17 11.60
c. 20mm dia. Extra kg 2 6.33 9.51
d. 12mm dia. Extra kg 2 9.67 5.22
e. Stirrups kg 34 4.50 18.36
iii. Top Beam
a. 20mm dia. kg 4 7.00 21.03
b. 16mm dia. kg 1 7.00 3.36
c. 20mm dia. Extra kg 2 3.50 5.26
d. Stirrups kg 13 4.50 7.02
Along Grid B
i. Between Grid 1-6 & back
a. 20mm dia. kg 4 72.00 216.29
b. 16mm dia. kg 1 72.00 34.56
c. 20mm dia. Extra kg 2 42.33 63.58
d. 12mm dia. Extra kg 2 34.17 18.45
e. Stirrups
- 1'*17" Beam kg 174 4.50 93.96
- 1'*1' Beam kg 20 4.17 10.00
Along Grid A
a. 20mm dia. kg 4 78.00 234.31
b. 16mm dia. kg 1 78.00 37.44
c. 20mm dia. Extra kg 2 42.33 63.58
d. 12mm dia. Extra kg 2 10.67 5.76
e. Stirrups kg 174 4.50 93.96
Along Grid 1
i. Top Beam kg
a. 20mm dia. kg 4 7.50 22.53
b. 16mm dia. kg 2 7.50 7.20
c. 20mm dia. Extra kg 2 5.83 8.76
d. Stirrups kg 15 4.50 8.10
ii. Between Grid C to A
a. 20mm dia. kg 4 46.33 139.19
b. 16mm dia. kg 2 46.33 44.48
c. 25mm dia. Extra kg 2 29.33 68.87
d. Stirrups kg 88 4.50 47.52
Along Grid 2
a. 20mm dia. kg 4 42.27 126.98
b. 16mm dia. kg 2 42.27 40.58
c. 25mm dia. Extra kg 2 26.67 62.61
d. Stirrups kg 114 4.50 61.56
Along Grid 3
a. 20mm dia. kg 4 39.67 119.16
b. 16mm dia. kg 2 39.67 38.08
c. 25mm dia. Extra kg 2 26.67 62.61
d. 16mm dia. Extra kg 2 14.67 14.08
e. Stirrups kg 103 4.50 55.62
Along Grid 4
a. 20mm dia. kg 4 41.50 124.67
b. 16mm dia. kg 2 41.50 39.84
c. 25mm dia. Extra kg 2 26.67 62.61
d. 16mm dia. Extra kg 2 28.17 27.04
e. Stirrups kg 99 4.50 53.46
Along Grid 5
a. 20mm dia. kg 4 37.00 111.15
b. 16mm dia. kg 2 37.00 35.52
c. 25mm dia. Extra kg 2 26.67 62.61
d. 16mm dia. Extra kg 2 28.17 27.04
e. Stirrups kg 95 4.50 51.30
Along Grid 6
a. 20mm dia. kg 4 35.33 106.14
b. 16mm dia. kg 2 35.33 33.92
c. 25mm dia. Extra kg 2 26.67 62.61
d. 16mm dia. Extra kg 2 14.67 14.08
e. Stirrups kg 81 4.50 43.74
Secondary Beams
Between Grid1-2
a. 16mm dia. kg 4 21.75 41.76
b. Stirrups kg 45 4.50 24.30
Between Grid C - B
a. 16mm dia. kg 1 16.17 7.76
b. Stirrups kg 45 4.50 24.30
Slab
Top Slab
a. Front
8mm dia Through kg 18 47.67 102.96
8mm lower bar upto downslab kg 12 5.00 7.20
10 mm Top
->upto downslab kg 12 5.50 12.41
->Along the length kg 35 8.08 53.19
b. Back
8mm dia through kg 22 23.50 62.04
8mm lower/ main bars upto staircase kg 68 6.50 53.04
Downslab
a. Front
8mm Main bars / Lower Bars kg 74 5.00 44.40
8mm Distribution Bars/ Top Bars kg 20 18.50 44.40
b. Back
8mm Main bars / Lower Bars kg 54 5.00 32.40
8mm Distribution Bars/ Top Bars kg 18 13.50 29.16
Other Remaining Slabs Portions
Bottom Rebars (all 8mm)
a. Along Numeric Grid ->
Between Grid 1-4 kg 56 39.00 262.08
Between Grid 4-5 kg 25 34.50 103.50
Between Grid 5-6 kg 14 17.50 29.40
Between Grid 6-5 kg 14 16.00 26.88
Between B1-B2-C1-C2 Room kg 19 15.50 35.34
b. Along Alphabetic Grid ^ drxn
Between Grid C & B
> shorter kg 22 40.83 107.80
> Longer kg 11 54.42 71.83
Between Grid B & A kg
> Through kg 32 60.17 231.04
> subtraction at triangular edge kg 15 13.17 23.70
Through Top Rebars Lower Bar (all 8mm)
a. Along Numeric Grid ->
Between Grid 1-4 kg 35 39.00 163.80
Between Grid 4-5 kg 14 34.50 57.96
Between Grid 5-6 kg 9 17.50 18.90
Between Grid 6-5 kg 5 16.00 9.60
b. Along Alphabetic Grid ^ drxn
Between Grid C & & B
> shorter kg 6 40.83 29.40
> Longer kg 18 54.42 117.54
Between Grid B & A
> Through kg 4 65.00 31.20
Cuttail Top Bars (all 10mm)
a. Along Numeric Grid ->
Between Grid 1-2
> near downslab kg 5 27.50 25.85
Inside B1-B2-C1-C2 Room
> at side of DW slab along B grid kg 9 5.00 8.46
> along grid 1 kg 18 2.00 6.77
> along grid A kg 14 2.50 6.58
Along Grid 2
> Between C & B kg 21 9.75 38.49
> Between B & A kg 19 8.00 28.58
Along Grid 3
> Between C & B kg 20 7.42 27.89
> Between B & A kg 20 7.42 27.89
Along Grid 4
> Between C & B kg 20 7.58 28.51
> Between B & A kg 14 7.58 19.96
Along Grid 5
> Between C & B kg 20 4.67 17.55
> Between B & A kg 13 9.00 22.00
Along Grid 6
> Between C & B kg 11 23.50 48.60
> Between B & A kg 10 3.58 6.74
b. Along Alphabetic Grid ^ drxn
Along Grid B
> Between 2 &3 kg 11 10.50 21.71
> Between 3 & 4 kg 11 10.00 20.68
> Between 4&5 kg 12 9.50 21.43
> Between 5&6 kg 18 9.00 30.46
Along Grid other extra grids
> Between 2 &3 kg 11 3.00 6.20
> Between 3 & 4 kg 11 2.75 5.69
> Between 4&5 kg 12 2.50 5.64
> Between 5&6 kg 18 2.50 8.46

Chairs (all 8mm Except mentioned)


a. slab between B-A
> and 1-2 kg 12 3.33 7.52
> and 2-3 kg 10 3.33 6.27
> and 3-4 kg 9 3.33 5.64
> and 4-5 kg 7 3.33 4.39
> and 5-6 kg 16 3.33 10.03
> and 6-back portion kg 2 3.33 1.25
b. Slab between C-A
> and 1-2
Down Slab
- 10mm dia kg 8 3.33 5.01
- 16mm dia kg 2 3.33 1.25
Normal Slab kg 1 3.33 0.63
> and 2-3 kg 12 3.33 7.52
> and 3-4 kg 12 3.33 7.52
> and 4-5 kg 13 3.33 8.15
> and 5-6 kg 9 3.33 5.64
> and 6-back portion kg 9 3.33 5.64
c. Slab along side Top
> and 1-2 kg 2 3.33 1.25
> and 2-3 kg 3 3.33 1.88
> and 3-4 kg 4 3.33 2.51
> and 4-5 kg 4 3.33 2.51
> Downslab kg 7 3.33 4.39
> and 6-back portion kg 2 3.33 1.25

Staicase kg
Middle Section with 2 landings
a. Longitudinal bars kg
Through kg 8 18.00 69.12
Cuttailed kg 24 7.00 80.64
b. Transverse bar kg 14 4.00 10.53
Down Part kg
a. Longitudinal bars kg 18 11.00 95.04
b. Transverse bar kg 23 4.00 17.30
Upper Part kg
a. Longitudinal bars kg 18 11.00 95.04
b. Transverse bar kg 23 4.00 17.30
Landing Beam at Starting kg
16mm bars kg 4 6.00 11.52
Stirrups kg 12 2.50 3.60
Z- Beam kg
16mm bars kg 4 11.00 21.12
Stirrups kg 23 2.50 6.90

Binding Wires kg
1% of total Rebars kg 59.57
Smart plus Construction Pvt.Ltd
Lalitpur
Project
Swyambhu Building
Location Swyambhu
Date Baisakh

Item. Current Bill of Current Bill of


Description Unit Rate NRs. Remarks
No. Quantities Amount

1 Formwork sq.ft. 3975.86 -


2 Concreting cu.ft. 1491.15 -
3 Reinforcement / Rebars quintal 5.96 -
4 Binding Wires Kg. 59.57 -

Total= -