Ebauche Inspection Test Plan (Mangoro)
Ebauche Inspection Test Plan (Mangoro)
Prepared by : M. FILS & M.RICHARD Date : 5/27/2022 Reviwed by : M. FANEVA Date : 5/27/2022
LEGEND H : Hold Point W : Witness Point R : Records Review S : Surveillance
OPERATION STEPS
INSPECTION POINT
Acceptance Verifying Document &
Steps Quality related Activity Frequency Reference document
Criterea Forms CIMELTA AMBATOVY/ VIVO
A IMPLANTATION INSP POINT SIGN DATE INSP POINT SIGN DATE
Allowed tolerances
A.1 Checking the dimensions of the land Beginning of the work As built drawing Inspection check list H R/W
±5cm
Allowed tolerances
A.2 Checking the base level ± 00 Beginning of the work As built drawing Inspection check list H R/W
±2cm
Allowed tolerances
A.3 Verification of compliance for levels Beginning of the work As built drawing Inspection check list H R/W
±1cm
Allowed tolerances
A.4 Putting chairs Beginning of the work As built drawing Inspection check list H R/W
±0.5cm
Allowed tolerances
A.5 Checking Implantation of axes Beginning of the work As built drawing Inspection check list H R/W
±0.5cm
Allowed tolerances
A.6 Squareness control Beginning of the work As built drawing Inspection check list H R/W
± 1°
Allowed tolerances
A.7 Control of axis reports Beginning of the work As built drawing Inspection check list H R/W
±1cm
Name: Name:
Sign: Sign:
Date: Date:
MANGORO PUMPING STATION ADDITIONAL FUEL TANK INSTALLATYION
INSPECTION AND TEST PLAN
Ambatovy
Project N° : P190034
Contractor N° : 1CN000085 Service : CIMELTA-SCB
Page : 2/7 REV : 0
Prepared by : M. FILS & M. RICHARD Date : 5/27/2022 Reviwed by : M. FANEVA Date : 5/27/2022
B.2 Checking alignment and level Starting work As built drawing Inspection check list H R/W
Allowed tolerances
B.3 Levelling and compacting Starting work As built drawing Inspection check list H R/W
±3 cm
B.4 Evacuation of excess soil Starting work As built drawing Inspection check list H R/W
C EXCAVATION
Check excavation
C.1 As built drawing width, depth, Inspection check list H R/W
Check excavation dimension Before excavation
length According
to Drawings
Name: Name:
Sign: Sign:
Date: Date:
MANGORO PUMPING STATION ADDITIONAL FUEL TANK INSTALLATYION
INSPECTION AND TEST PLAN
Project N° : P190034 Ambatovy
Contractor N° : 1CN000085 Service : CIMELTA-SCB
Page : 3/7 REV : 0
Prepared by : M. FILS & M. RICHARD Date : 5/27/2022 Reviwed by : M. FANEVA Date : 5/27/2022
Allowed tolerances
D.4 Leveling check During the work Inspection check list H R/W
±1cm
D.5 Installation of the polyane film During the work Inspection check list H R/W
D.6 Blow away the impurities During the work Drawing of SEPARATEUR Inspection check list H R/W
D'HYDROCARBURE
N° OUV COF FER 01-01-REV
Vérification of the poses of A(19/07/22)
D.7 reinforcements (covering; During the work Inspection check list H R/W
lower/upper layer, coating, etc..) Drawing of AIRE DE
DEPOTAGE.
D.8 Check of overlapping During the work N° OUV COF FER 04-01- REV 0 Allowed tolerances Inspection check list H R/W
±5cm
D.9 Installation of peripheral seal During the work Drawing of AIRE DE Inspection check list H R/W
DEPOTAGE.
N° OUV COF FER 04-02- REV 0
Formwork reservations and
D.10 During the work Inspection check list H R/W
expansion joints
D.11 Concrete Pouring and Vibration During the work Inspection check list H R/W
D.12 Ruler level adjustment During the work Inspection check list H R/W
D.13 Manual or mechanical troweling During the work Inspection check list H R/W
Application of curing or
D.14 End of work Inspection check list H R/W
sanding product
Name: Name:
Sign: Sign:
Date: Date:
MANGORO PUMPING STATION ADDITIONAL FUEL TANK INSTALLATYION
INSPECTION AND TEST PLAN
Ambatovy
Project N° : P190034
Contractor N° : 1CN000085 Service : CIMELTA-SCB
Page : 4/7 REV : 0
Prepared by : M. FILS & M.RICHARD Date : 5/27/2022 Reviwed by : M. FANEVA Date : 5/27/2022
E.1 Ground tracing Starting work As built drawing Inspection check list H R/W
Allowed tolerances
E.2 Check cumulates coasts During the work As built drawing Inspection check list H R/W
± 0,5cm
Allowed tolerances
E.3 Baseline trait During the work As built drawing Inspection check list H R/W
± 0,5cm
Allowed tolerances
E.4 Checking of plumbs and squares During the work As built drawing Inspection check list H R/W
± 0,5cm
Allowed tolerances
E.5 Installation of openings During the work As built drawing Inspection check list H R/W
± 0,5cm
E.6 Sill level During the work As built drawing Inspection check list H R/W
E.7 Implantation of reservations During the work As built drawing Inspection check list H R/W
Allowed tolerances
E.9 Lintel level During the work As built drawing Inspection check list H R/W
± 0,5cm
E.10 Installation of rods for coatings During the work As built drawing Inspection check list H R/W
E.11 Plastering gobtis During the work As built drawing Inspection check list H R/W
E.12 End of work During the work As built drawing Inspection check list H R/W
Name: Name:
Sign: Sign:
Date: Date:
MANGORO PUMPING STATION ADDITIONAL FUEL TANK INSTALLATYION
INSPECTION AND TEST PLAN
Ambatovy
Project N° : P190034
Contractor N° : 1CN000085 Service : CIMELTA-SCB
Page : 5/7 REV : 0
Prepared by : M. FILS & M.RICHARD Date : 5/27/2022 Reviwed by : M. FANEVA Date : 5/27/2022
F.1 Plan of the design office Starting work Inspection check list H R/W
F.2 Lists of steels During the work Inspection check list H R/W
F.3 Steel cutting During the work Inspection check list H R/W
F.7 Verification after assembly End of the work Inspection check list H R/W
G FORMWORK INSTALLATION
Allowed tolerances
G.1 Planing Starting work Inspection check list H R/W
±5mm
Allowed tolerances
G.2 Cutting During the work Inspection check list H R/W
±1mm
G.3 mounting and assembly During the work Inspection check list H R/W
as built drawings
Allowed tolerances
G.4 Fitting During the work Inspection check list H R/W
±1mm
Allowed tolerances
G.5 Checking dimensions During the work Inspection check list H R/W
±1mm
G.6 Verification of squarences End of the work Inspection check list H R/W
Name: Name:
Sign: Sign:
Date: Date:
Prepared by : M. FILS & M.RICHARD Date : 5/27/2022 Reviwed by : M. FANEVA Date : 5/27/2022
Allowed tolerances
H.2 Laying the formwork During the work Inspection check list H R/W
±1cm
H.3 Laying Rebar During the work Inspection check list H R/W
H.4 Installation of the concrete wegde During the work Inspection check list H R/W
H.7 Verification after pouring During the work Inspection check list H R/W
Name: Name:
Sign: Sign:
Date: Date:
Prepared by : M. FILS & M. RICHARD Date : 5/27/2022 Reviwed by : M. FANEVA Date : 5/27/2022
Name: Name:
Sign: Sign:
Date: Date:
1 Modification of the contents of the form
0 5/18/2022 Creation of document MICKAEL ANDRY BAUMANN