Professional Documents
Culture Documents
Logistics Management and Strategy Part 2
Logistics Management and Strategy Part 2
net/publication/273119271
CITATIONS READS
0 151
1 author:
Robert Prieto
Strategic Program Management LLC
296 PUBLICATIONS 163 CITATIONS
SEE PROFILE
All content following this page was uploaded by Robert Prieto on 04 March 2015.
Industry Leader
global experience
proven expertise
i GV20110547012.DOCX
Seminar on Logistics Cooperation for Stabilization
and Reconstruction: Engineering and Reconstruction
Institute for Defense and Business, University of North Carolina at Chapel Hill
Bob Prieto
Senior Vice President
July 28, 2011
Fluor Confidential. No Release Except to Institute of Defense and Business.
©2011 Fluor. All Rights Reserved. GV20110547003.pptx 1-1
Overview
Perspective of presentation
Phases of a disaster and
broad lessons learned
Engineering, procurement,
and construction (EPC)
process and how it changes
post disaster
Logistics-affecting activities
Recommendations and
things to consider
1-2 GV20110547003.pptx
Perspective of Presentation
1-3 GV20110547003.pptx
Personal Perspective
Event Perspective
Gujarat, India earthquake World Economic Forum Engineering Governor
1-4 GV20110547003.pptx
Fluor’s Perspective
LOGCAP II
1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011
GV20110547003.pptx
Contingency Operations Knowledge Packs
1-6 GV20110547003.pptx
Contingency Operations Knowledge Packs:
Project Initiation
1-7 GV20110547003.pptx
Types of Disasters
Human
– War, civil strife, terrorism
Natural
– Regional – wind, water, earthquake, geological
Discrete
– Specific facility
– Human – terrorism, explosion, fire
– Natural – tornado, fire
1-8 GV20110547003.pptx
Phases of a Disaster
Resist (pre-disaster)
Response
Recover and reconstruct
– Enhance resiliency for each phase
1-9 GV20110547003.pptx
Example of Fluor’s Response Capabilities
1-10 GV20110547003.pptx
Example of Fluor’s Response Capabilities
1-11 GV20110547003.pptx
EPC and How it Changes Post Disaster
1-12 GV20110547003.pptx
Simplified Project Model
Project Environment/Setting
Social/Stakeholder Framework
Business Framework
Project Project
Project
Inputs Construction/Activity
Outputs
Economic/Political
Framework
1-13 GV20110547003.pptx
Traditional Construction Site Considerations
1-14 GV20110547003.pptx
Global-Scale Project Supply Chain
1-15 GV20110547003.pptx
Simplified Inputs and Outputs
Project
Social/Stakeholder Framework
Environment/Setting
Business Framework
Project Project
Project
Inputs Construction/Activity
Outputs
Labor Completed
Materials Project
Equipment Construction
Economic/Political Waste
Framework
1-16 GV20110547003.pptx
Major Framework Components
• Project Site
• Geography
• Organized
• Climate
Stakeholders
• Regional
Project • Demographics
Infrastructure
• Cultural/Religious
Environment/Setting
Social/Stakeholder Framework
• Records and
• Ownership Rights
Documentation
• Codes and Standards
Labor Completed
Materials Project
Equipment Construction
Economic/Political Waste
Framework
1-17 GV20110547003.pptx
Site-Based Factors
Project
Construction/Activity
• Site-based factors
• Construction site services
• Esprit de corps/site
culture/sense of purpose
• Know how
1-18 GV20110547003.pptx
Construction Site Services
1-19 GV20110547003.pptx
Construction Site Services
Site
Equipment Services Tools
Equipment and
Repair
Safety
Fuel and and
Lube Consumable
Supplies
\
Parts,
Maintenance,
and Scaffolding
Warehousing
Operator Planning
Training and
Forecasting
1-20 GV20110547003.pptx
Disaster Changes Project Inputs
Project Inputs
1-21 GV20110547003.pptx
Disaster Changes Business Framework
Contract
• Scope includes more unknowns and potentially evolving requirements
• Schedule based on potential continuing risk events, degraded labor
Business Framework
Risk Framework
• Significantly changed risk profile must be reflected in terms and conditions
Owners
• External funding agencies may assume de facto owner’s role
Labor Organizations and Agreements
• Existing agreements may create barriers to recovery
• Potential for labor strife as external workforce mobilized
1-22 GV20110547003.pptx
Disaster Changes Project and Environmental
Setting Framework
Project Environment/Setting
Project Site Climate Regional Infrastructure Social Records and
• Constrained access • Adverse climactic • Widespread Infrastructures Documentation
• Denied access conditions impact destruction of regional Disrupted or • Lost records
response activities infrastructures Destroyed • As-builts no longer
• Uncertain
ownership or other (continuing important to response • Housing, medical, meaningful
property rights hurricane season, and reconstruction police, fire, • Property rights not
seasonal extremes (roads and rails sanitation well documented or
Geography of temperature or • Banking and other
washed away, bridges inconsistent with
• Modified precipitation) severely damaged or financial institutions social realities
topography (floods, • Event of scale destroyed, airports (squatter
landslides, or necessitates rendered unusable, populations)
mudslides; construction in destroyed power
earthquake non-traditional time Codes and
generation and
displacement; lava periods (monsoon, Standards
transmission capability,
fields; aftermath of depth of winter, destroyed or degraded • Evolving as a result
military action) peak of summer) potable water of event of scale
• Terrain limits rate of treatment and • Variable – affected
response or distribution capability, by donor/funder
reconstruction degraded wastewater requirements
• Accessibility capability, constrained
constrains available telecom services from
options facility damage)
• Regional infrastructure
inadequate for level
and nature of response
and rebuilding
activities
1-23 GV20110547003.pptx
Disaster Changes Social and
Stakeholder Framework
Organized Stakeholders
• Traditional stakeholder groups dysfunctional
Social/Stakeholder Framework
• Stakeholder objectives evolving
• New stakeholder groups emerging
• National or international stakeholders gain roles to enable or Intervene
Demographics
• Loss and displacement of populations
• Impact of relief, response, and reconstruction populations
• Constraints on construction labor
Cultural/Religious
• Transitional roles often played by cultural or religious groups
• Cultural and religious sensitivities often elevated
• Tribal issues and prerogatives may resurface
Ownership Rights
• Lack of documentation and records
• Conflicting claims
• Formal versus informal rights
• Confiscation in the absence of the rule of law
• Corruption
1-24 GV20110547003.pptx
Disaster Changes Economic and
Political Framework
Economic/Political Framework
1-25 GV20110547003.pptx
Post-Disaster Project and Construction Activity
Changed Project
Framework
Special Challenges
1-26 GV20110547003.pptx
Post-Disaster Construction Outputs
Project Outputs
Completed Project
• Temporary
• Transitional
• Permanent
Construction Waste
• Linkage to debris considerations (disposal and
reuse in construction)
• Recycling drivers
Sustainability
• Capacity building
• Economic development
• New industry creation
• Enhanced resiliency
• Lessons learned and best practices
1-27 GV20110547003.pptx
Logistics-Affecting Activities
1-28 GV20110547003.pptx
1-29 GV20110547003.pptx
1-30 GV20110547003.pptx
1-31 GV20110547003.pptx
Logistics-Affecting Activities
1-32 GV20110547003.pptx
Logistics-Affecting Activities (Cont.)
1-33 GV20110547003.pptx
Comparative Description of Select
Logistics-Affecting Activities
1-34 GV20110547003.pptx
Let’s Go to the Handout…
1-35 GV20110547003.pptx
Client Capabilities and Resources
1-36 GV20110547003.pptx
Client-Contractor Alignment and Contract
1-37 GV20110547003.pptx
Mobilization
1-38 GV20110547003.pptx
Execution Plans
1-39 GV20110547003.pptx
Project Management Manual
1-40 GV20110547003.pptx
Workshare
1-41 GV20110547003.pptx
Design Basis
1-42 GV20110547003.pptx
Degree of Design Standardization
1-43 GV20110547003.pptx
Labor
1-44 GV20110547003.pptx
Typical Stabilization and Post-Disaster Labor
Requirements
Fluor Subcontract
Time Personnel Personnel
Contracts/Task Orders Period Mobilized Mobilized
BP MC 252 Incident Response <70 days 8,447 0
1-45 GV20110547003.pptx
Prefabrication
1-46 GV20110547003.pptx
Pre-assembly
1-47 GV20110547003.pptx
Modularization
1-48 GV20110547003.pptx
1-49 GV20110547003.pptx
1-50 GV20110547003.pptx
1-51 GV20110547003.pptx
Degree of Client-Furnished Materials
and Equipment
1-52 GV20110547003.pptx
Supplier Relationship Agreements (SRAs)
1-53 GV20110547003.pptx
Cost of Labor and Building Materials in Aceh
Late 2004 to Late 2006
Early Change
Resource Unit (RP) End 2004 Mid-2005 2006 Oct 2006 (%)
Labor 000/day 30 40 50 50 67
1-54 GV20110547003.pptx
Cost of Labor and Building Materials in Sichuan
Mid 2008 to Mid 2009
1-55 GV20110547003.pptx
Global Sourcing
1-56 GV20110547003.pptx
Post-Disaster Construction Material Volumes
1-57 GV20110547003.pptx
Supplier Stratification
1-58 GV20110547003.pptx
Sourcing Integrity
1-59 GV20110547003.pptx
Mission-Critical, Unique Equipment Sourcing
1-60 GV20110547003.pptx
Mission-Critical, Unique Equipment Sourcing
1-61 GV20110547003.pptx
Quality of Locally Procured Material
1-62 GV20110547003.pptx
Expediting
1-63 GV20110547003.pptx
Traffic Routing and Logistics Plan
1-64 GV20110547003.pptx
Building Permits and Consents for Temporary
Construction and Logistical Facilities
1-65 GV20110547003.pptx
Warehousing
1-66 GV20110547003.pptx
Material Security
1-67 GV20110547003.pptx
Trafficking
1-68 GV20110547003.pptx
Logistical Contract Forms
1-69 GV20110547003.pptx
Construction Waste
1-70 GV20110547003.pptx
Less-Than-Full Truckload Shipments
1-71 GV20110547003.pptx
Staging Areas
1-72 GV20110547003.pptx
Road and Bridge Transport
1-73 GV20110547003.pptx
Oversized Shipments
1-74 GV20110547003.pptx
Ocean Freight
1-75 GV20110547003.pptx
Transportation Insurance
1-76 GV20110547003.pptx
Port Capacity and Operations
1-77 GV20110547003.pptx
Construction Equipment
1-78 GV20110547003.pptx
Construction Fleet Maintenance
1-79 GV20110547003.pptx
Non-Process Infrastructure (NPI)
1-80 GV20110547003.pptx
1-81 GV20110547003.pptx
Craft Training
1-82 GV20110547003.pptx
Small Tools
1-83 GV20110547003.pptx
Vehicle Safety
1-84 GV20110547003.pptx
Human Remains
1-85 GV20110547003.pptx
Communication
1-86 GV20110547003.pptx
In-Country Logistical Institutional Infrastructure
1-87 GV20110547003.pptx
Site Transport
1-88 GV20110547003.pptx
Cash Flow
1-89 GV20110547003.pptx
Anticorruption and Transparency
1-90 GV20110547003.pptx
Stakeholder Engagement
1-91 GV20110547003.pptx
Change Management
1-92 GV20110547003.pptx
What is Possible
1-93 GV20110547003.pptx
Milliken Fire Rebuild
1-94 GV20110547003.pptx
Confidential Chemical Client
2011 Tornado Rebuild
1-95 GV20110547003.pptx
FEMA Individual Assistance Hurricane Katrina
Response
1-96 GV20110547003.pptx
FEMA Individual Assistance Hurricane Katrina
Response
1-97 GV20110547003.pptx
FEMA Public Assistance Technical Assistance
Contract
1-98 GV20110547003.pptx
LOGCAP
1-99 GV20110547003.pptx
LOGCAP
1-100 GV20110547003.pptx
LOGCAP TO2 Overview
Services
Construction of force providers
Design-build and minor construction
Facilities management and O&M
Bagram
Roads and grounds Joyce
1-101 GV20110547003.pptx
LOGCAP TO4 Overview
Services
Construction of force providers and
Harvest Falcons
Design-build and minor construction
FOB Leatherneck
Facilities management and O&M
FOB Frontenac FOB Wolverine Transportation services and vehicle fleet
FOB support
Leatherneck FOB Kandahar
FOB Ramrod Housing accommodations and office
FOB Spin Boldak units
FOB Dwyer
Food and laundry service
Security
IT support
Site Locations Satellite (SAT) and local network cell
Kandahar—CSO FOB Ramrod phones
FOB Tarin Kowt FOB Wolverine Insect, rodent, and feral animal control
1-102 GV20110547003.pptx
LOGCAP TO5 Overview
1-103 GV20110547003.pptx
Kuwait Oil Company Fire Rebuild
April 2003
Fire destroyed 80 percent of the
facilities of an oil gathering and
processing center
– During preparation and invasion
of Iraq
1-104 GV20110547003.pptx
American Sugar Refining (Domino)
Flood Response
1-105 GV20110547003.pptx
Recommendations and Things to Consider
1-106 GV20110547003.pptx
Recommendations and Things to Consider
1-107 GV20110547003.pptx
Recommendations and Things to Consider
1-108 GV20110547003.pptx
Logistics-Affecting Activities are Modified Post Disaster
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Client Client organization is appropriately Client organization may be lacking Client organizations must recognize
capabilities and resourced or program manager resources that understand EPC that the linkage between end use
resources engaged processes and how they change in a and shipping and other logistical
Combined team brings necessary post-disaster environment activities grows in importance in a
understanding of EPC activities and Impacts and importance of logistics post disaster situation
how they interact with necessary in a post-disaster situation may not Prepositioned contracts with
logistics considerations be sufficiently understood in client experienced post-disaster
organization or required resources construction contractors that have
have not been engaged strong logistics capabilities provide
Client lack of appreciation for nature owner organizations with the
or scale of logistical challenges may capability to efficiently respond and
adversely impact overall engineering recover
and construction effort
Client- Pre-established contractual basis Private sector efforts typically in Prepositioned contracts allow for
contractor reflective of overall procurement and support of major customers, with pre-disaster alignment around basic
alignment and construction strategy flexibility to quickly execute work processes, allocation of
contract Alignment with owner organization risk-appropriate contracts responsibilities, and delegated and
Public sector efforts effective where retained authorities and approvals
prior contract vehicles exist and Supply chain and logistical strategies
alignment activities have previously can be discussed, and the new first
occurred (FEMA and LOGCAP IV) responder in today's built
Lack of a prior contract impacts environment can participate in select
efficiency of logistical commitments tabletop exercises
being made
Lack of well-defined responsibilities
and authorities in post-disaster
organization may delay completion
of required RACI charts, creating
uncertainties in approval process for
crucial logistics-affecting activities
2-1 GV20110547005.DOCX
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Mobilization Typically recognized and funded Certain government or aid agency Create a limited mobilization task in
activity contracts are task order-based with prepositioned contracts to accelerate
no provision for mobilization costs, response timeframes
delaying activities and commitments
to create an efficient logistics
operation
Execution Scope-driven baseline Funding-driven baseline shaped by Clearly identify any
plans donor community or “color of funding-source-linked requirements
money" at earliest possible stage
Select major donor organization
requirements can be pre-identified in
prepositioned contracts (examples:
FEMA Public Assistance, State
Emergency Management, Red
Cross)
Project Standard go-by template with Expanded to include forms, Prepositioned contracts allow for
Management client-specific forms, procedures, procedures, and approvals linked to pre-disaster alignment around basic
Manual and approvals funding source work processes and reports
Procedures may vary by project Critical logistical hubs and choke
delivery approach (direct execution points can be pre-identified
or grant funded); contracting
strategy (design-bid build, design
build); and phase of project
Added approvals and complexity
may impact logistics chain
Workshare Global Engineering Centers (GECs) Funding agencies may drive work to Local engineering and construction
workshare limits need to move many be performed locally resource surveys may be periodically
resources to project location conducted as part of prepositioned
contract
2-2 GV20110547005.DOCX
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Design basis Optimized against well-defined Nature of funding sources may Existing planning documents should
owner criteria through a formal constrain solutions to replace in be inventoried and collected to
tollgate process kind, reducing opportunities to accelerate reconstruction planning
modify supply chain Efforts focused on achieving plans
versus creating entirely new ones
where possible
Planning collection in advance of
disaster also facilitates resiliency
reviews by local disaster planning
agencies
Degree of Maximized to reduce supply chain Required volumes limit Incorporate resiliency features as
design standardization opportunities part of new design basis
standardization
Labor Globally and locally sourced – OCONUS mobilization through Client organization must ensure
standard HR systems and Mobilization and Deployment Center response and reconstruction
processes (MDC) contractors have well developed
MDC in a Box for other-country mobilization plans and capabilities
national (OCN) mobilization
– From first speaking to a recruiter
to a putting boots on the ground,
the recruitment, training, and
on-boarding process can be
completed in 7 to 8 days
Prefabrication Maximized to address labor Initially focused on response-phase Identify staging and prefabrication
availability and cost needs sites in proximity to critical
Eliminates shipments of temporary infrastructure and population centers
equipment, materials, and Identify similar regional areas outside
construction consumables the evaluated zone
Reduces construction waste
streams
2-3 GV20110547005.DOCX
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Pre-assembly Maximized to address labor Typically limited by funding linkages Identify staging and prefabrication
availability and cost to job creation in affected area sites in proximity to critical
Eliminates shipments of temporary May be constrained by access route infrastructure and population centers
equipment, materials, and constraints Identify similar regional areas outside
construction consumables the evaluated zone
Reduces construction waste Identify major access routes and
streams weight and size constraints as part of
disaster planning efforts
Modularization Maximizes benefits associated with Uses constrained by client Identify staging and prefabrication
manufacturing efforts, such as those awareness and constraining sites in proximity to critical
realized on a smaller scale with procurement practices infrastructure and population centers
prefabrication and pre-assembly Site access may be constrained to Identify similar regional areas outside
Allows parallel construction to port areas and, at later stages, the evaluated zone
shorten schedules major overland logistical routes Identify major access routes and
Facilitates precommissioning weight and size constraints as part of
disaster planning efforts.
Degree of Best practice moving beyond major Use adequate owner-provided Prepositioned response and
client-furnished equipment to include select advance financing limits reconstruction contracts should
materials and construction bulks, piping, cabling, Contracting practices by provide for use of commercial
equipment pumps, motors, and MCC government limit PMC+ contracting practices to the maximum extent
Targeted levels nominally approaches possible
30 percent Multiplicity of buyers (lack of Contractors with well-developed
Necessitates strong materials sourcing hub) reduces supply chain supply chains are essential in
management organization as part of efficiency post-disaster settings
expanded program management
contractor (PMC) role (PMC+)
Supplier Maximize use of PMC's SRAs to Effective use limited to private Prepositioned response and
relationship simplify supply chain, gain greater sector facilities and clients due to reconstruction contracts should
agreements assurance on delivery timeframes, traditional limitations on competitive provide for use of commercial
(SRAs) and consolidate shipments procurement and form of contract for practices to the maximum extent
High level of pre-transaction non-private buyers possible
information transferred between High demand drives use of Contractors with well-developed
buyer and supplier non-traditional sourcing for which supply chains are essential in
reduced supplier-buyer information post-disaster settings
exchange has previously occurred
2-4 GV20110547005.DOCX
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Global sourcing Leverage of ongoing supplier Expanded sourcing effort to meet Periodic assessments should be
analysis and assessment activities required timeframes and budgets made of basic construction material
consistent with anticipated business requires augmented vendor availability for a range of disasters
volumes by supply category and inspection, QA/QC, and expediting (local, regional, multi-regional)
regions efforts
Appropriate supply sources Identification of supplies of materials
pre-identified prior to major program for construction and required
activities non-process infrastructure (NPI)
undertaken for limited number of
disaster types and locations in
advance of disaster-limiting logistics
system planning activities
Sourcing Pre-acquisition surveys confirm Supply origins for certain bulk Best-value procurement, with strong
integrity environmental, labor, and legal materials (timber) and their quality and inspection efforts,
compliance by supply base preparation or treatment for use may produces more consistent and timely
Local supply capabilities well be difficult to ascertain outcomes and, at the end of the day,
defined and capacity building Compliance with global procurement the most cost-effective outcome, all
undertaken off a known base norms harder to police at the costs considered
subcontractor level
Mission-critical, Traditional long-lead items procured Supply chain compression activities Prepositioned response and
unique through early funding commitments may include: reconstruction contracts should
equipment – New sources of supply provide for use of commercial
sourcing – Multi-vendor awards practices to the maximum extent
– Use of CFM as feedstock to possible
selected vendors Contractors with well-developed
– Phased procurement and pricing supply chains are essential in
– Expedited transport (Aeroflot) post-disaster settings
Quality of Standard vendor qualification and May take physical possession, but Strained logistical chains require the
locally inspection programs not title, at end of inspection line to right shipments, at the right time, to
procured Material (batch) inspections prevent material substitution the right place
material further straining overall logistical Poor quality and associated
chain back-shipment and rework or
workarounds strain an already
over-taxed supply chain
2-5 GV20110547005.DOCX
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Expediting Focused on baseline schedule Reflect evolving needs and Trafficking into the disaster area
execution on-the-ground conditions should not be left to inexperienced
suppliers buying shipment services
on a low-cost and uncoordinated
basis
Traffic routing Focused on baseline schedule Reflect evolving needs and Trafficking into the disaster area
and logistics execution on-the-ground conditions should not be left to inexperienced
plan Consider evolving condition of suppliers buying shipment services
transport routes and other logistics on a low-cost and uncoordinated
facilities basis
Increased number of logistics choke
points and greater competition for
logistics capabilities
Building Routine activity Government capacity may be Identify and put in place an
permits and inadequate given widespread expedited process for temporary or
consents for damage and competing demands transitional facilities after a declared
temporary for permits disaster
construction Delay of logistical and temporary
and logistical construction facilities may result
facilities Mechanisms for waivers may not
exist
Warehousing Consistent with higher CFM More limited CFM and shortages of Mechanisms to identify vacant,
labor and materials may make large-scale commercial facilities
warehousing a lower priority facility equipped to receive and warehouse
Inability to reliably implement a equipment and materials should be
just-in-time supply chain can make pre-established (Examples: vacant
warehousing an even more "big box" stores, warehouses, and
significant activity supermarkets)
Warehousing may need to be
located closer to site of
reconstruction activities because of
weakened local logistics networks
Material Warehouse and lay-down areas Augmented security Pre-establish badging requirements
security typically have controlled access and Perimeter patrols and requirements for security or
routine security Larger guard force auxiliary police
2-6 GV20110547005.DOCX
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Trafficking Most contractors rely on supplier to Key link in supply chain Trafficking into the disaster area
ship goods management as logistical system should not be left to inexperienced
Supplier not expert responds to stress and reconfigures suppliers buying shipment services
– Materials arrive late, or worse, post-disaster on a low-cost and uncoordinated
damaged because the supplier basis
went with the low-cost shipper,
without checking quality and
safety records
Fluor controls delivery
– Use companies that have good
tracking (GPS) and dispatching
capabilities
– Can change routes or even
delivery locations as the situation
dictates
Logistical Generally industry standard Special requirements to address Strategies for changed logistical risk
contract forms changed shipper risks: management should be
– Demurrage pre-assessed and decisions made
– Labor strife on types of risk best retained
– Excess wear and tear
– Lost productivity
– Availability of fuel
– Security
Construction Seek to minimize volumes Expanded volumes associated with Pre-identification of temporary and
waste generated (25 percent of site debris permanent debris storage locations
construction materials are waste) High mixed waste and preferred logistical movements
Minimize mixed waste Potential need to classify portions as associated with debris handling for a
Recycle hazardous waste range of total impacts
Less-than-full Limited attention beyond CFM Logistically expensive, especially Trafficking into the disaster area
truckload volumes where possession times or number should not be left to inexperienced
shipments of shipments are effectively rationed suppliers buying shipment services
on a low-cost and uncoordinated
basis
2-7 GV20110547005.DOCX
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Staging areas Staging area at port or key local hub Inefficient supply chains may Identify staging and prefabrication
Staging and warehouse area at or exacerbate staging area needs sites in proximity to critical
near site Out-of-zone staging process utilized infrastructure and population centers
to control flow into valuable shipping Identify similar regional areas outside
space and routes the evaluated zone
Identify major access routes and
weight and size constraints as part of
disaster planning efforts
Road and Conditions and capacities generally Conditions and capacities unknown Preposition a structural assessment
bridge well understood Significant degradation may not be contract for critical logistical
transport evident infrastructure to provide early
information of logistical degradation
of any form
Oversized Limited to high-value equipment and Logistics constraints may cause Client organizations must recognize
shipments modules shipment sizes to be constrained, that the linkage between end use
Platooned where possible increasing volumes shipped and and shipping and other logistical
associated labor requirements activities grows in importance in a
post-disaster situation
Prepositioned contracts, with
experienced post-disaster
construction contractors who have
strong logistics capabilities, provide
owner organizations with the
capability to efficiently respond and
recover
2-8 GV20110547005.DOCX
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Ocean freight Heavy lift needs identified in Competition for vessels or harbor Client organizations must recognize
conjunction with long-lead and constraints may drive undesirable that the linkage between end use
modularization planning load sizes and combinations and shipping and other logistical
activities grows in importance in a
post-disaster situation
Prepositioned contracts, with
experienced post-disaster
construction contractors who have
strong logistics capabilities, provide
owner organizations with the
capability to efficiently respond and
recover
Transportation Generally industry standard Unavailability and cost or coverage Strategies for changed logistical risk
insurance limitations may affect logistics management should be
choices pre-assessed and decisions made
on types of risk best retained
Port capacity Often saturated by global-scale Traditional challenges scaled up and Preposition a structural assessment
and operations programs potentially impacted by damage at contract for critical logistical
May necessitate separate material the port infrastructure to provide early
handling wharfs Cargo handling operations may be information of logistical degradation
overwhelmed by lack of coordinated of any form
prioritization of needs Trafficking into the disaster area
should not be left to inexperienced
suppliers operating on an
uncoordinated basis
Construction Lease-versus-buy decisions Competition for equipment may Local construction equipment
equipment intermittently constrained by drive less than desirable ownership resource surveys may be periodically
availability decisions conducted as part of prepositioned
Specialized equipment identified at Most efficient equipment may not be contract
early stage available
Shortages of major equipment
operators
2-9 GV20110547005.DOCX
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Construction May be delivered as part of PMC+ Increased maintenance Local construction equipment
fleet services requirements associated with resource surveys may be periodically
maintenance Fueling operations may best be difficult site conditions may conducted as part of prepositioned
done as a client-furnished service necessitate larger fleet sizes contract
Fuel logistics may be critical Fuel supply is critical resource
challenge during early phases
Non-process Growing challenge Meeting the NPI challenge may be Identify NPI requirements for a range
infrastructure Increased use of modular camp and constrained by site access of disasters (scale and type) as part
(NPI) ancillary facilities (transport or site-based debris) and of prepositioned contract activities
Requires early site access community perceptions Identify gaps in existing capacity
Site power and water may be met Competition for generators and
from nearby networks in many water treatment may limit rates of
instances or temporary generators certain construction activities
or treatment plants elsewhere
Craft training Skills, construction safety, and Training expanded to include Develop post-disaster craft training
process safety training focused on increased awareness of hazards program template for likely
labor force are intended to serve associated with prior destruction and post-disaster conditions to be
program's needs any ongoing risk conditions encountered
Consistent safety culture across Multiple client and contractor Emergency authorities to include a
program reinforces safety structures without strong program mandate for safety
control undermine efforts to build
safety culture
Local labor force may move
between contractors more
frequently, diminishing the training
investment made by any one
contractor (no overall program
focus)
Small tools Implement program-wide small tools Small tools program a requirement Prepositioned contractor should have
program to control cost, reduce to address shortages and expanded an in-place, small tools capability to
theft, and improve safety workforce foster response and reconstruction
activities
Vehicle safety Driver certification and safe driving Difficulties may be encountered in Strengthened driver inspection
program driver certification and training, program as part of materials receipt
Reduced accidents support given competition for limited supply process
increased logistics availability
2-10 GV20110547005.DOCX
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Human Not typically encountered Protocols put in place and may Defined program for human remain
remains cause partial site shutdown and recovery, with clearly assigned
reconfigured site or supply chain responsibilities and augmentation
logistics plan for large-scale events
Communication Utilize regional communication Regional communication networks Project Management Plan should
networks and supplement with may be unavailable or degraded, identify planned communication
site-based communications as impacting efficiency of supply chain strategy and contractor
needed operations provided-capabilities (Example:
Sat-Phone)
In-country Policies defined: Institutional frameworks may be Establish institutional frameworks for
logistical – Imports and duties inappropriate for post-disaster engineering, construction, and
institutional – Weight limits response and rebuilding logistical response activities and the
infrastructure – Packaging requirements Institutional frameworks for specialized issues associated with
– Rules of origin modification may be absent, reconstruction
– Required documentation contributing to logistical chain Clearly identify variance from normal
– Typical approval timeframes ineffectiveness or uncertainty processes and authorities
Agency roles understood (even if
inefficient)
Site transport Typically bus transport from site Local transport may be Logistical plan should identify
gate or construction camp dysfunctional extraordinary transportation
Local transport, if available Travel times for critical specialty capabilities:
labor may necessitate increased – Heavy lift
helicopter operations – River access
– Heliport or potential landing sites
in vicinity of staging areas
– Warehouse
– Command centers
Cash flow Positive cash flow or minimum The need to bridge cash Prepositioned contracts should have
working capital needs do not requirements of subcontractors necessary payment mechanisms,
influence logistical decision making makes payment terms an invoicing requirements, and approval
increasingly important selection mechanics thoroughly addressed
factor in sourcing decisions
2-11 GV20110547005.DOCX
Logistics- Global Scale CAPEX Program -
Affecting Leveraged Execution and Recommendations for Post-Disaster
Activities Procurement Post-Disaster Reconstruction Management
Anticorruption Required business process Risks greatly increase, and Strong transparency and
and monitoring and surveillance become anticorruption requirements in place
transparency larger activities and incorporated into all contracts
May impact sources of supply,
logistic routes, and ports of entry
May necessitate increased security
in logistics chain
Stakeholder Keep stakeholders informed in Changed stakeholder groups, Communication plans, focused on
engagement advance of logistics activities priorities, and communication both response and reconstruction
impacting local or regional difficulties impact the effective activities, developed in advance
transportation networks communication of planned logistic
activities that affect local and
regional networks
Stakeholder impacts may be
exacerbated by difficulties in
stakeholder engagement
Change Critical activity for efficient supply Impacts of change magnified in Responsibility and timely decision
management chain operations logistics chain post disaster processes incorporated into Project
Management Plan and institutional
frameworks for post-disaster
operations
2-12 GV20110547005.DOCX
Example of Fluor’s Response Capabilities
3-1 GV20110547004.DOCX
Contact Information
bob.prieto@fluor.com
1.609.919.6376 (New Jersey office)
1.609.919.6359 (office fax)
1.917.518.9430 (mobile)
1.803.370.4359 (BlackBerry)
4-1 GV20110547006.DOCX
View publication stats