PROJECT- ELECTRICAL

PAHINGA, CANDELARIA, QUEZON

FIRST FLOOR

CIRCUIT NO. 1- LIGHTINGS


L-O 9 holes
WALL LAMP 7 holes
SWITCH 11 holes
PENLIGHT 8 holes
ADDITIONAL
CANOPY 6 holes
PENLIGHT 6 holes
CUBLIGHT 2 holes

TOTAL OF 49 HOLES

49 HOLES X 300 (per Hole) =

TOTAL = Php 14, 700

FIRST FLOOR

CIRCUIT NO. 2- CONVENIENCE OUTLET


ROOM 2 holes
DINING 9 holes
LIVING 6 holes
GARAGE 1 hole
CR 1 hole
CABLE 1 hole
A-C-U 1 hole

TOTAL OF 21 HOLES

21 HOLES X 300 (per Hole) =

TOTAL = Php 6,300

SECOND FLOOR
CIRCUIT NO. 3- LIGHTINGS
L-O 14 holes
WALL LAMP 6 holes
SWITCH 11 holes
PENLIGHT 8 holes
ADDITIONAL
CANOPY 3 holes
PENLIGHT 4 holes
CUBLIGHT 2 holes
WALL LAMP 5 holes

TOTAL OF 53 HOLES

53 HOLES X 300 (per Hole) =

TOTAL = Php 15,900

SECOND FLOOR

CIRCUIT NO. 4 - CONVENIENCE OUTLET


ROOM 1 AND 2 8 holes
LIVING ROOM 6 holes
TERRACE 2 holes
HEATER 2 holes
AIRCON 2 holes
ADDITIONAL
A-C-U 2 holes
OUTLET 1 hole
CABLE 1 hole

TOTAL OF 24 HOLES

24 HOLES X 300 (per Hole) =

TOTAL = Php 7, 200

BREAKER 12 X 300 = Php 3,600

INSTALL- PANELBOARD
WIRING- ENTRADA TO METER BASE- Php 1, 000
TOTAL COST OF LABOR
ELECTRICAL- 300 PER HOLE

FIRST FLOOR L-O Php 14, 700


FIRST FLOOR C-O Php 6, 300
SECOND FLOOR L-O Php 15, 900
SECOND FLOOR C-O Php 7, 200
BREAKER Php 3,600
INSTALL- PANELBOARD WIRING Php 1,000

TOTAL Php 48,700

MON REYES
Electrician
Contact No.: 09560271512