DATE :- 12-12-2023

C1- AFCONS- Labour Report - Station Work(Structure)


Minimum Available As
SR. No Contractor Name Balance Short fall (%)
Required on 12.12.23
1 Tapovan Circle 125 73 52 42
2 GNLU 60 36 24 40
AFCONS
3 PDPU 40 5 35 88
4 Gift City 100 34 66 66
Total 325 148 177

C1- AFCONS-Labour Report - Entry & Exit Work


Minimum Available As
SR. No Contractor Name EE Balance Short fall (%)
Required on 12.12.23
1 Tapovan Circle-A 14
50 28 56
2 Tapovan Circle-B 8
3 GNLU-A 20
50 10 20
4 GNLU-B 20
AFCONS
5 PDPU-A 17
50 15 30
6 PDPU-B 18
7 Gift City-A 16
50 16 32
8 Gift City-B 18
Total 200 131 69

C1- AFCONS-Labour Report - Viaduct Work


Minimum Available As
SR. No Contractor Name Balance Short fall (%)
Required on 12.12.23
1 P0 80 63 17 21
2 P1 0 0 0
3 P2 0 0 0
4 P3 0 0 0
5 P4 (Extradose) 80 80 0 0
6 P5 50 4 46 92
7 P6 30 12 18 60
AFCONS
8 P7 0 5 -5
9 P8 0 4 -4
10 GP1 0 0 0
11 GP2 150 41 109 73
12 GP3 40 12 28 70
13 Casting yard 200 115 85 43
14 Erection 100 50 50 50
Total 730 386 344

Grand Total 1255 665 590