Professional Documents
Culture Documents
AF - Group 9 - Cash Flow Estimation and Risk Analysis
AF - Group 9 - Cash Flow Estimation and Risk Analysis
Taxes paid on salvaged assets = Tax Rate X (Salvaged value - Book Value
TIMING OF CASH FLOWS
In theory, capital budgeting analyses should deal with cash
flows exactly when they occure: therefore daily cash flows
theoritically would be better than annual flows. However, it
would be costly to estimate and analyze daily cash flows, and
they would probably be no more accurate than annual estimate
because simply cannot accurately forcast at daily level out 10
year or so into the future. Therefore, assume that all cash flows
occure at the end of the year.
SUNK COST
A sunk cost is an outlay that was incurred in
the past and cannot be recovered in the future
regradless of whether the project under
consideration is accepted.
OPPORTUNITY COST
ASSOCIATED WITH ASSETS THE FIRM
OWNS
Oppoertunity Cost is the best return
that could be earned on assets the firm
already owns if those assets are not
used for the new project.
Example:
Home Depot owns land with MV of $2
milion and that land will be used for the
new store and only $15 million will be
required if HD decides to build it.
EXTERNALITIES
Negative Within-Firm Externalities
Enviromental Externalities
ANALYSIS
OF AN EXPANSION
PROJECT
DEPRECIATION
BASICS
1. Straight Line
2. MACRS (Accelerated Rate Depreciations)
EFFECT OF DIFFERENT DEPRECIATION RATES
If we replaced the accelerated depreciation numbers in Table 13.1
with the constant values that would exist under the straight-line
method, the result would be a free cash flow time line on row 28.
CANNIBALIZATION
Project S does not involve any cannibalization effects. Suppose,
that Project S would reduce the after-tax cash flows of another
division by $50 per year. No other firm would take on this project
if our firm turns it down.
OPPORTUNITY COST
Suppose that the project would save money by using some
equipment the company owns and that equipment would be sold for
$100 after-tax, if the project is rejected. The $100 is an opportunity
cost, and should add $100 to the project’s cost. The result would be
an NPV of $78.82 - $100 = -$21.18, so the project would now be
rejected.
SUNK COST
Suppose the firm had spent $150 on a marketing study to
estimate potential sales. This $150 could not be recovered
regardless of whether the project is accepted or rejected.
OTHER CHANGE
TO THE INPUTS
Variables other than depreciation also could
be varied, and these changes would alter the
calculated cash flows and thus NPV and IRR.
REPLACEMENT
ANALYSIS
To find incremental cash flow by find cash flow differentials
between the new and old projects. (Excel formula needed)
1. Sensitivity analysis
2. Scenario analysis
3. Monte Carlo simulation
SENSITIVITY
ANALYSIS
Percentage change in NPV resulting from
a given percentage change in an input
variable, other things held constant.
SENSITIVITY
List of key inputs for Project S:
Equipment cost
Change in NOWC
Unit sales
Sales price
The NPVs over this life are then compared, and the project
with the higher common-life NPV is chosen.
EQUIVALENT
ANNUAL ANNUITIES (EAA)