Title : Manufacturing Plan

Doc. No. : AQ-PEM-F004


Project Title : SPAM JATILUHUR WATER TREATMENT PROJECT
Project No. : AQ190024
Client : WIKA
Date : 230608
Rev. No: A PROJECT PHASE: OFFSHORE

ACTUAL
SHIPMENT SHIPMENT SHIPMENT WEIGHTED PROGRESS BY VENDOR WEIGHTED PER PROGRESS BY Estimated Time Actual Time Estimated Time Actual Time
DESCRIPTION VENDOR QTY UOM Description WEIGHTED Progress Photo NOTES Position of Installation
NO. GROUP FROM VALUE % DATA VALUE % SITE SITE Delivery Delivery Arrival Arrival
VALUE %

CIBEET
3 pallet drive unit
3 open shaft
O1 1 Scrapers (Cibeet) JAG Metalbau 18 packages 3 bundle flat steel Germany 2.94% 100.00% 2.94% 7.97% 7.97% 11-May-23 12-May-23 22-Jun-23 27-Jun-23 Photos 27 Jun at Tj. Priuk Port. 13 July on warehouse hydro-PAQ = 3 units
3 bundle angle-profil
3 crate accessories
7 shaft Coagulation Basin = 3 pcs
O1 2 Mixers (Cibeet) E+B Umwelttechnik 7 packages 7 impeller France 3.10% 100.00% 3.10% 8.41% 8.41% 12-May-23 18-May-23 30-Jun-23 23-Jun-23 Photos 23 Jun at Tj. Priuk Port. 14 July on warehouse Flocculation = 3 pcs
7 head Post Coagulation = 1 pc
O2 3 Screens (Cibeet) Top Industry China 0.63% 100.00% 0.63% 1.70% 1.70% 25-Sep-23 25-Sep-23 12-Oct-23 11-Oct-23 Photos 11 Oct at Jakarta Port, 4 Nov at Warehouse Tambun
1 belt conveyor
1 set 1 mechanical coarse screen intake system = 1 set
Conveyors (Cibeet) Top Industry 2 mechanical fine screen China 0.76% 100.00% 0.76% 2.07% 2.07% 25-Sep-23 25-Sep-23 12-Oct-23 11-Oct-23 Photos 11 Oct at Jakarta Port, 4 Nov at Warehouse Tambun

2 pcs decanter centrifuges China


O2 4 Decanter LW 300 X 1290 (Cibeet) Gate Valve LWPZ 300 Jiangsu Huada 2 sets 2.87% 100.00% 2.87% 7.79% 7.79% 6-Oct-23 6-Oct-23 16-Oct-23 17-Oct-23 17 Oct at Jakarta Port, 4 Nov at Warehouse Tambun Dewatering = 2 sets
2 pcs water sludge separation gate valve
3 wooden pallets:
2 pallets of 33 pcs China
O2 5 Lamella (Cibeet) E+B Umwelttechnik 3 sets 1.37% 100.00% 1.37% 3.72% 3.72% 26-Sep-23 26-Sep-23 15-Oct-23 16-Oct-23 Photos at Jakarta Port hydro-PAQ = 3 sets
1 pallets of 34 pcs
total 100 pcs
O2 6 Gensets 1650 KVA/1350 KW (Cibeet) Asianet Ventures 1 pc China 6.15% 100.00% 6.15% 16.66% 16.66% 25-Oct-23 TBC 25-Nov-23 TBC Generator Room = 1 pc
Hydro-PAQ = 12 pcs
P1 20 pcs pump Penang, MY Photos
7 Sludge Pumps (Cibeet) Netzsch 20 units 1.03% 100.00% 1.03% 2.79% 2.79% 29-Oct-23 8-Oct-23 16-Oct-23 17-Oct-23 at Jakarta Port Chemical Dosing = 6 pcs
20 pcs temperature controller
Dewatering = 2 pcs
P1 Penang, MY Photos PPU for Flocculation = 2 pcs
8 Polymer Preparation Unit (PPU) - (Cibeet) Prominent 4 pcs 0.63% 100.00% 0.63% 1.71% 1.71% 29-Oct-23 8-Oct-23 16-Oct-23 17-Oct-23 at Jakarta Port
PPU for Dewatering = 2 pcs
4 pcs penstock
P1 9 Penstocks (Cibeet) 1 Lecotech 4 units 4 pcs handwheel Penang, MY 0.39% 100.00% 0.39% 1.05% 1.05% 29-Oct-23 8-Oct-23 16-Oct-23 17-Oct-23 Photos at Jakarta Port Reservoir = 4 pcs
4 pcs stem cover
5 pcs penstock
P2 10 Penstocks (Cibeet) 2 Lecotech 5 units 5 pcs handwheel Penang, MY 25-Oct-23 TBC 3-Nov-23 TBC hydrofil and intake channel
5 pcs stem cover
P1 11 Air Blowers TH-250 (Cibeet) Trundean 2 pcs Penang, MY 0.48% 100.00% 0.48% 1.29% 1.29% 29-Oct-23 8-Oct-23 16-Oct-23 17-Oct-23 Photos at Jakarta Port Hydro-FIL = 2 pcs
P1 6 pcs control unit Penang, MY Photos
12 Delta Mobrey Instruments (Cibeet) Delta Mobrey 6 sets 0.21% 100.00% 0.21% 0.57% 0.57% 29-Oct-23 8-Oct-23 16-Oct-23 17-Oct-23 at Jakarta Port Hydro-PAQ Sedimentation Basin = 6 sets
6 pcs ultrasonic gap sensor
Raw Water Intake Sump = 5 pcs
Intake Feed Pump Common Discharge Line = 1 pc
Hydro-PAQ Effluent Channel = 2 pcs
Hydro-PAQ Inlet Line A,B,C = 3pcs
Hydro-PAQ Sludge Recirculation Pumps Common Discharge A,B,C = 3 pcs
Hydro-PAQ Sludge Excess Pumps Common Discharge A,B,C = 3 pcs
P1 13 Instruments (Cibeet) E+H (Endress Houser) 1 lot 38 pcs instruments Penang, MY 1.54% 100.00% 1.54% 4.16% 4.16% 29-Oct-23 8-Oct-23 16-Oct-23 17-Oct-23 at Jakarta Port Post Coagulation Basin = 1 pc
Hydro-FIL = 12 pcs
Dirty Wash Water Pump Common Discharge Line = 1 pc
Back Wash Water Pumps Common Discharge Line = 1 pc
Clear Water Basin = 2 pcs
Reservoir = 3 pcs
Sludge Holding Tank = 1 pc
P1 14 Instruments - SM9000 & SM0510 (Cibeet) 31 pcs carton of instrument: 29-Oct-23 8-Oct-23 16-Oct-23 at Jakarta Port Polymer Dilution Panel = 4 pcs
Instruments - EVC004 & EVC002; KQ6005; E12163, EVE004 IFM 1 lot 3 pcs Carton Model SM0510 Penang, MY 0.13% 100.00% 0.13% 0.35% 0.35% 17-Oct-23 Coagulation Tank A = 2 pcs
P1 15 29-Oct-23 8-Oct-23 16-Oct-23 at Jakarta Port
(Cibeet) 4 pcs Carton Model EVC004 NaOCl A Tank = 2 pcs

trending of SCU
Compact unit with sensor and LCD Screen
P1 16 Instruments (Cibeet) Chem Kimia 1 unit Output Penang, MY 0.16% 100.00% 0.16% 0.44% 0.44% 29-Oct-23 8-Oct-23 16-Oct-23 17-Oct-23 Photos at Jakarta Port hydro-PAQ Coagulation-Flocculation Transfer Pipe = 1 unit
Sensor Calibration
Accessories: rotameter, flow control, valve and piping
P2 17 Valves (steel) - (Cibeet) Chuah Valve Manufacture 1 lot Penang, MY 5.10% 100.00% 5.10% 13.82% 13.82% 25-Oct-23 TBC 3-Nov-23 TBC on progress fabrication hydropaq, hydrofil, blower discharge, decanter
P2 18 PLC Panel (Cibeet) Bakat 1 set Penang, MY 4.79% 100.00% 4.79% 12.98% 12.98% 25-Oct-23 TBC 3-Nov-23 TBC MCC Room
P2 19 Chemical Dosing Boxes (Cibeet) BW Water 1 lot Penang, MY 0.83% 75.00% 0.62% 2.24% 1.68% 20-Nov-23 TBC 28-Nov-23 TBC chemical room
Raw Water Intake Sump = 2 pcs
Dirty Wash Water Basin = 2 pcs
Clear Wash Water Basin = 1 pc
Service Water Pump = 2 pcs
Clear Water Basin = 1 pc
Reservoir = 2 pcs
Decanter Feed Pump Common Discharge Line = 2 pcs
Polymer Dosing Discharge Line = 4 pcs
Coagulation Tank = 1 pc
Coagulation Tank Common Outlet Pipe = 1 pc
P2 20 Instruments (Cibeet) Sanpo 1 lot Penang, MY 0.78% 100.00% 0.78% 2.11% 2.11% 20-Nov-23 TBC 28-Nov-23 TBC Photos delivered in BW Penang Warehouse NaOCl A Tank = 1 pc
Pre-NaOCl Dosing Pump Suction Common Line = 1 pc
NaOH Tank = 1 pc
NaOH Dosing Pump Discharge = 1 pc
H2SO4 Tank = 1 pc
H2SO4 Dosing Pump Discharge = 1 pc
Service Water Tank = 1 pc
Service Water to PPU Common Line = 1 pc
Intake Sump Pump = 1 pc
Back Wash Sump Pump = 1 pc
Distribution Sump Pump = 1 pc

Intake Feed Pump = 2 pcs


Hydro-PAQ Sludge Recirculation Pump Discharge Line A,B,C = 6 pcs
Hydro-PAQ Sludge Excess Pump Discharge A,B,C = 6 pcs
Dirty Wash Water Pump Discharge Line = 2 pcs
Back Wash Water Pump Discharge Line = 2 pcs
Service Water Pump Discharge Line = 2 pcs
Decanter Feed Pump = 2 pcs
Penang, MY Polymer Dosing Discharge Line = 4 pcs
P2 21 Instrument - PI - Pressure Gauge Wika 45 Pcs 0.00% 100.00% 0.00% 0.00% 0.00% 20-Nov-23 TBC 28-Nov-23 TBC Photos delivered in BW Penang Warehouse
Decanter Polymer Dosing Pump = 2 pcs
Coagulant Dosing Pump Discharge = 4 pcs
Post Coagulant Dosing Pump Discharge = 2 pcs
Pre-NaOCl Dosing Pump Discharge = 2 pcs
Post-NaOCl Dosing Pump Discharge = 2 pcs
NaOH Dosing Pump Discharge = 2 pcs
H2SO4 Dosing Pump Discharge = 2 pcs
Service Water Line = 3 pcs
P2 22 Valves (pressure relief) - (Cibeet) Bermad 1 lot Penang, MY 0.33% 100.00% 0.33% 0.91% 0.91% 25-Oct-23 TBC 3-Nov-23 TBC production completed intake channel
P4 23 Valves (plastic) (Cibeet) Hershey 1 lot Penang, MY 0.31% 100.00% 0.31% 0.84% 0.84% TBC TBC TBC TBC delivered in BW Penang Warehouse in chemical system and service water
P3 24 CPVC Pipe & Fittings (Cibeet) Hershey 1 lot Penang, MY 0.34% 100.00% 0.34% 0.92% 0.92% TBC TBC TBC TBC in chemical system and service water
P3 25 Bellows expansion joints (Cibeet) Flytech 1 lot Penang, MY 0.24% 100.00% 0.24% 0.65% 0.65% TBC TBC TBC TBC almost in centrifugal pump
P3 26 Local Control Panels (Cibeet) BW Water 1 lot Penang, MY 0.29% 0.00% 0.79% 0.00% TBC TBC TBC TBC MCC Room
P3 27 Valve Control Panels (Cibeet) BW Water 1 lot Penang, MY 0.27% 0.00% 0.73% 0.00% TBC TBC TBC TBC MCC Room
P3 28 Gaskets (Cibeet) SJP 1 lot Penang, MY 0.08% 100.00% 0.08% 0.23% 0.23% TBC TBC TBC TBC in all valves
P3 Penang, MY from backwash to hydrofil, from dirty wash to intake and from hydropaq to sludge
29 Nuts/Bolts (Carbon Steel (black)) - Cibeet Advanced Bolt 1 lot 0.24% 100.00% 0.24% 0.64% 0.64% TBC TBC TBC TBC
decanter
TBC from backwash to hydrofil, from dirty wash to intake and from hydropaq to sludge
30 Carbon Steel Pipe & Fittings Hunan 1 lot 0.90% 52.00% 0.47% 2.45% 1.27% TBC TBC TBC TBC
decanter
36.91% 35.70% 100.00% 95.47%

BEKASI
5 pallet drive unit
5 open shaft
O1 1 Scrapers (Bekasi) JAG Metalbau 33 package 5 bundle flat steel Germany 6.08% 100.00% 6.08% 9.63% 9.63% 25-Sep-23 25-Sep-23 7-Nov-23 TBC Photos on delivery process hydro-PAQ = 5 units
5 bundle angle-profil
5 crate accessories
21 shaft Coagulation Basin = 10 pcs
2 Mixers (Bekasi) E+B Umwelttechnik 21 package 21 impeller France 5.17% 100.00% 5.17% 8.20% 8.20% 9-Sep-23 9-Sep-23 10-Oct-23 20-Oct-23 Photos 20 Oct at Jakarta Port. 25 Oct on warehouse Flocculation = 10 pcs
21 head Post Coagulation = 1 pc
3 Screens (Bekasi) Top Industry 2 belt conveyor type D China 1.31% 100.00% 1.31% 2.08% 2.08% 25-Sep-23 25-Sep-23 12-Oct-23 11-Oct-23 Photos 11 Oct at Jakarta Port, 4 Nov at Warehouse Tambun
1 belt conveyor type H
2 set intake system = 2 sets
1 mechanical coarse screen
Conveyors (Bekasi) Top Industry China 1.01% 100.00% 1.01% 1.60% 1.60% 25-Sep-23 25-Sep-23 12-Oct-23 11-Oct-23 Photos 11 Oct at Jakarta Port, 4 Nov at Warehouse Tambun
2 mechanical fine screen
2 pcs decanter centrifuges China
4 Decanter LW 450 X 1800 (Bekasi)Gate Valve LWPZ 450 Jiangsu Huada 2 set 4.79% 100.00% 4.79% 7.59% 7.59% 6-Oct-23 6-Oct-23 16-Oct-23 17-Oct-23 17 Oct at Jakarta Port, 4 Nov at Warehouse Tambun Dewatering = 2 sets
2 pcs water sludge separation gate valve

5 Lamella (Bekasi) E+B Umwelttechnik 35 set 35 wooden pallets (1150 pcs) China 2.29% 100.00% 2.29% 3.63% 3.63% 26-Sep-23 26-Sep-23 15-Oct-23 16-Oct-23 Photos at Jakarta Port hydro-PAQ = 35 sets

6 Gensets 2250 KVA / 1800 KW (Bekasi) Asianet Ventures 5 pcs China 10.25% 100.00% 10.25% 16.24% 16.24% 25-Oct-23 TBC 25-Nov-23 TBC Generator Room = 5 pcs
hydro-PAQ = 25 pcs
P1 40 pcs pump Penang, MY Photos
7 Sludge Pumps (Bekasi) Netzsch 40 unit 1.72% 100.00% 1.72% 2.72% 2.72% 29-Oct-23 8-Oct-23 16-Oct-23 at Jakarta Port Chemical Dosing = 13 pcs
40 pcs temperature controller 17-Oct-23 Dewatering = 2 pcs
P1 Penang, MY Photos PPU for Flocculation = 2 pcs
8 Polymer Preparation Unit (PPU) - (Bekasi) Prominent 4 pcs 1.05% 100.00% 1.05% 1.67% 1.67% 29-Oct-23 8-Oct-23 16-Oct-23 at Jakarta Port
PPU for Dewatering = 2 pcs
P1 9 Air Blowers units TH-300A (Bekasi) Trundean 3 pcs Penang, MY 0.80% 100.00% 0.80% 1.26% 1.26% 29-Oct-23 8-Oct-23 16-Oct-23 Photos at Jakarta Port hydro-FIL = 3 pcs
10 pcs control unit 17-Oct-23
P1 10 Delta Mobrey Instruments (Bekasi) Delta Mobrey 10 set Penang, MY 0.35% 100.00% 0.35% 0.55% 0.55% 29-Oct-23 8-Oct-23 16-Oct-23 Photos at Jakarta Port hydro-PAQ Sedimentation Basin = 10 pcs
10 pcs ultrasonic gap sensor
P1 11 Instruments - SM9000 & SM0510 (Bekasi) 7 pcs carton of instrument: 29-Oct-23 8-Oct-23 16-Oct-23 at Jakarta Port Polymer Dilution Panel = 11 pcs
Instruments - EVC004 & EVC002; KQ6005; E12163; EVE004 IFM 1 lot 1 pcs Carton Model SM9000 Penang, MY 0.31% 100.00% 0.31% 0.48% 0.48% 17-Oct-23 Coagulation Tank A = 4 pcs
P1 12 29-Oct-23 8-Oct-23 16-Oct-23 at Jakarta Port
(Bekasi) 2 pcs Carton Model KQ6005 NaOCl Tank A, B, C = 6 pcs
trending of SCU
Compact unit with sensor and LCD Screen
P1 13 Instruments (Bekasi) Chem Kimia 2 unit Output Penang, MY 0.27% 100.00% 0.27% 0.43% 0.43% 29-Oct-23 8-Oct-23 16-Oct-23 17-Oct-23 Photos at Jakarta Port hydro-PAQ Coagulation-Flocculation Transfer Pipe = 2 unit
Sensor Calibration
Accessories: rotameter, flow control, valve and piping
16 pcs penstock
P3 14 Penstocks (Bekasi) Lecotech 16 unit 16 pcs handwheel Penang, MY 0.96% 85.00% 0.82% 1.53% 1.30% 20-Nov-23 TBC 28-Nov-23 TBC intake channel, hydrofil and reservoir
16 pcs stem cover
P5 15 Chemical Dosing Boxes (Bekasi) 2 BW Water 1 lot Penang, MY 1.38% 70.00% 0.97% 2.19% 1.53% TBC TBC TBC TBC chemical room
Raw Water Intake Sump = 2 pcs
Dirty Wash Water Basin = 2 pcs
Clear Wash Water Basin = 1 pc
Service Water Pump Discharge Line = 2 pcs
Clear Water Basin = 1 pc
Reservoir = 2 pcs
Decanter Feed Pump Common Discharge Line = 2 pcs
Polymer Dosing Discharge Line = 11 pcs
Coagulation Tank = 1 pc
Coagulant Tank Common Outlet Pipe = 1 pc
P2 Penang, MY Photos NaOCl Tank = 1 pc
16 Instruments (Bekasi) Sanpo 1 lot 37 pcs instrument 1.30% 100.00% 1.30% 2.05% 2.05% 20-Nov-23 TBC 28-Nov-23 TBC delivered in BW Penang Warehouse
Pre-NaOCl Dosing Pump Discharge = 1 pc
Post-NaOCl Dosing Pump Discharge = 1 pc
NaOH Tank = 1 pc
NaOH Dosing Pump Discharge = 1 pc
H2SO4 Tank = 1 pc
H2SO4 Dosing Pump Discharge = 1 pc
Service Water Tank = 1
Service Water to PPU Common Line = 1 pc
Intake Sump Pump = 1 pc
Back Wash Sump Pump = 1 pc
Distribution Sump Pump = 1 pc
Raw Water Intake Sump = 5 pcs
Intake Feed Pump Common Discharge Line = 1 pc
Hydro-PAQ Effluent Channel = 2 pcs
Hydro-PAQ Inlet Line = 10 pcs
Hydro-PAQ Sludge Recirculation Pump = 10 pcs
Hydro-PAQ Sludge Excess Pump Common Line = 5 pcs
P3 17 Instruments (Bekasi) E+H (Endress Houser) 1 lot 75 pcs instrument Penang, MY 2.56% 100.00% 2.56% 4.06% 4.06% 20-Nov-23 TBC 28-Nov-23 TBC delivered in BW Penang Warehouse Post Coagulation Basin = 1 pc
Hydro-FIL = 33 pcs
Dirty Wash Water Pump Common Discharge Line = 1 pc
Back Wash Water Pump Discharge Line = 1 pc
Clear Water Basin = 2 pcs
Reservoir = 3 pcs
Sludge Holding Tank = 1 pc
Intake Feed Pump Discharge Line = 5 pcs
Hydro-PAQ Sludge Recirculation Pump = 15 pcs
Hydro-PAQ Sludge Excess Pump Discharge = 10 pcs
Dirty Wash Water Pump Discharge Line = 2 pcs
Back Wash Water Pump Discharge Line = 3 pcs
Service Water Pump Discharge Line = 2 pcs
Decanter Feed Pump Discharge Line = 3 pcs
Polymer Dosing Discharge Line = 11 pcs
P2 18 Instrument - PI - Pressure Gauge Wika 77 pcs 0.00% 100.00% 0.00% 0.00% 0.00% TBC TBC TBC TBC Photos delivered in BW Penang Warehouse
Decanter Polymer Dosing Pump Discharge = 2 pcs
Coagulant Dosing Pump Discharge = 11 pcs
Post Coagulant Dosing Pump Discharge = 2 pcs
Pre-NaOCl Dosing Pump Discharge = 2 pcs
Post-NaOCl Dosing Pump Discharge = 2 pcs
NaOH Dosing Pump Discharge = 2 pcs
H2SO4 Dosing Pump Discharge = 2 pcs
Service Water Line = 3 pcs
P5 19 Valves (steel) - (Bekasi) Chuah Valve Manufacture 1 lot Penang, MY 8.50% 80.00% 6.80% 13.47% 10.78% TBC TBC TBC TBC hydropaq, hydrofil, blower discharge, decanter
P5 20 Valves (plastic) - (Bekasi) Hershey 1 lot Penang, MY 0.52% 100.00% 0.52% 0.82% 0.82% TBC TBC TBC TBC in chemical system and service water
P5 21 CPVC Pipe & Fittings (Bekasi) Hershey 1 lot Penang, MY 0.57% 100.00% 0.57% 0.90% 0.90% TBC TBC TBC TBC in chemical system and service water
P5 22 Bellows expansion joints (Bekasi) Flytech 1 lot Penang, MY 0.40% 100.00% 0.40% 0.64% 0.64% TBC TBC TBC TBC almost in centrifugal pump
P4 23 PLC Panel 2 (Bekasi) Bakat 1 lot Penang, MY 7.99% 50.00% 3.99% 12.66% 6.33% TBC TBC TBC TBC MCC Room
24 Local Control Panels (Bekasi) BW Water lot Penang, MY 0.49% 0.00% 0.77% 0.00% TBC TBC TBC TBC MCC Room
25 Valve Control Panels (Bekasi) BW Water 1 lot Penang, MY 0.45% 0.00% 0.71% 0.00% TBC TBC TBC TBC MCC Room
P2 26 Valves (pressure relief) - (Bekasi) Bermad 1 lot Penang, MY 0.56% 100.00% 0.56% 0.88% 0.88% TBC TBC TBC TBC production completed intake channel
27 Gaskets (Bekasi) SJP 1 lot Penang, MY 0.14% 100.00% 0.14% 0.22% 0.22% TBC TBC TBC TBC in all valves
P5 Penang, MY from backwash to hydrofil, from dirty wash to intake and from hydropaq to sludge
28 Nuts/Bolts (Carbon Steel (black)) - Bekasi Advanced Bolt 1 lot 0.39% 100.00% 0.39% 0.62% 0.62% TBC TBC TBC TBC
decanter
TBC from backwash to hydrofil, from dirty wash to intake and from hydropaq to sludge
29 Carbon Steel Pipe & Fittings Hunan 1 lot 1.51% 0.00% 0.00% 2.39% 0.00%
decanter

63.09% 54.40% 100.00% 86.22%


100.00% 90.11%
Title : Manufacturing Progress

Doc. No. : AQ-PEM-F004

Project Title : SPAM JATILUHUR WATER TREATMENT PROJECT


Project No. : AQ190024
Client : WIKA
Date : 221013
Rev. No: A PROJECT PHASE: ONSHORE: FROM INDONESIA

SHIPMENT
PROGRESS BY
SHIPMENT SHIPMENT WEIGHTED ACTUAL WEIGHTED PROGRESS BY Estimated Time Actual Time Estimated Time Actual Time
DESCRIPTION VENDOR QTY UOM Description VENDOR Progress Photo NOTES Position of Installation
NO. GROUP VALUE % PROGRESS % PER SITE SITE Delivery Delivery Arrival Arrival
FROM TO DATA%

CIBEET
1 unit overhead crane 2 ton
1 1.1 Overhead Crane C PT Maeda Wijaya Prakarsa (MAEWISA) 2 sets Jakarta Tambun 0.80% 90.00% 0.72% 2.13% 1.92% pump room and intake channal
1 unit overhead crane 1 ton
1 1.2 Filter Nozzles PT Tridita Yasa Mandiri 11,340 pcs Bekasi Tambun 2.40% 100.00% 2.40% 6.39% 6.39% 11-Jun-23 19-Jun-23 19-Jun-23 19-Jun-23 Photos DO signed; storage on Warehouse Tambun hydro-FIL
Collection Trough, Flocculation Basin and Lamella
1 1.3 Turbine and other Fabricated Items - C PT Medina Engineering 1 lot Bekasi Tambun 5.11% 87.14% 5.11% 13.62% 13.62%
Support
- Collection Through Cibeet PT Medina Engineering 30 pcs Cikarang Tambun 1.63% 100.00% 1.63% 4.33% 4.33% 1-Jun-23 26-May-23 26-May-23 26-May-23 Photos DO signed; storage on Warehouse Tambun
3 pcs top shell
3 pcs baffle
- Turbine (Draft Through)/(Flocculation Basin) PT Medina Engineering 3 sets Cikarang Tambun 2.32% 100.00% 2.32% 6.19% 6.19% 15-Jun-23 16-Jun-23 16-Jun-23 16-Jun-23 Photos DO signed; storage on Warehouse Tambun
3 pcs inlet pipe hydro-PAQ
3 pcs bottom shell

18 pcs frame UNP


- Lamella Support Cibeet PT Medina Engineering 6 sets 36 pcs Flat Steel 2675 Cikarang Tambun 1.16% 100.00% 1.16% 3.10% 3.10% 15-Jun-23 16-Jun-23 16-Jun-23 16-Jun-23 Photos DO signed; storage on Warehouse Tambun
36 pcs Flat Steel 3095

2 2.1 Cables (partial 1) PT Prysmian 1 lot 8300 m Cikarang Tambun 6.51% 100.00% 6.51% 17.35% 17.35% 28-Sep-23 29-Sep-23 28-Sep-23 29-Sep-23 DO signed; storage on Warehouse Tambun electrical accessories
2 2.2 FRP Chemical Tanks PT Graha Adhi Jaya 5 pcs N. JKTA Tambun 0.40% 100.00% 0.40% 1.07% 1.07% 20-Jul-23 20-Jul-23 20-Jul-23 20-Jul-23 Photos DO signed; storage on Warehouse Tambun chemical room = 5 pcs
2 2.3 Transformer PT Asata Utama 2 pcs JKTA Tambun 2.60% 100.00% 2.60% 6.93% 6.93% 22-Jun-23 22-Jun-23 22-Jun-23 22-Jun-23 Photos DO signed; storage on Warehouse Tambun transformer room = 2 pcs
2 2.4 FRP Pipe & Fittings - Partial 1 PT Graha Adhi Jaya 35 sets (pipe, flange, elbow, shop joint) 2.00% 100.00% 2.00% 5.33% 5.33% 15-Jun-23 19-Jun-23 15-Jun-23 19-Jun-23 Photos DO signed; storage on Site intake to hydropaq
1 lot N. JKTA Site
FRP Pipe & Fittings - Partial 2 PT Graha Adhi Jaya 30 sets (pipe, flange, elbow, shop joint) 28-Aug-23 28-Aug-23 28-Aug-23 28-Aug-23 DO signed; storage on Site intake to hydropaq
2 2.5 Low Voltage MCC Panels PT Industri Elektrik Metal 2 pcs JKTA Tambun 6.91% 100.00% 6.91% 18.42% 18.42% 16-Oct-23 14-Oct-23 16-Oct-23 14-Oct-23 Photos DO Signed; Storage on Site MCC Room = 2 pcs
2 2.6 Sand & Gravel PT. Heksagon Karyatama Indonesia 1 lot Bandung Tambun 2.45% 0.00% 0.00% 6.54% 0.00% TBC TBC TBC TBC hydrofil
already on warehouse as below: (25 oct) intake system = 2 pcs
12 pumpset Cibeet Hydro-FIL = 6 pcs
3 3.2 Centrifugal Pumps 1 (Partial) Wilo 16 unit Tangerang Tambun 6.31% 100.00% 6.31% 16.82% 16.82% 11-Oct-23 11-Oct-23 11-Oct-23 11-Oct-23
12 pumpset Bekasi Water Distribution = 4 pcs
3 sump pump Pump Sump Area = 4 pcs
4 4.4 CCTV TBC TBC JKTA Tambun 0.34% 0.00% 0.00% 0.91% 0.00% TBC
6 6.1 Medium Voltage Switchgear PT Uni Makmur Elektrika 1 pcs JKTA Tambun 1.68% 100.00% 1.68% 4.49% 4.49% TBC TBC TBC TBC Photos FAT 14 Sep MCC Room
Street Lighting TBC street
Electrical Accessories (Cables for LV, MV) PT. Prima Indah Lestari TBC MCC Room
37.50% 34.62% 100.00% 92.33%
BEKASI
1 1.1 Overhead Crane B PT Maeda Wijaya Prakarsa (MAEWISA) 2 sets 2 crane 10 ton JKTA Tambun 1.33% 50.00% 0.67% 2.13% 1.07% pump room and intake channal
1 1.2 Filter Nozzles PT Tridita Yasa Mandiri 116,270 pcs Bekasi Tambun 4.00% 100.00% 4.00% 6.39% 6.39% 11-Jun-23 20-Jun-23 20-Jun-23 20-Jun-23 Photos DO signed; storage on Warehouse Tambun hydro-FIL
Collection Trough, Flocculation Basin and Lamella
1 1.3 Turbine and other Fabricated Items - B PT Medina Engineering 1 lot Bekasi Tambun 8.51% 100.00% 8.51% 13.62% 13.62%
Support
- Collection Through Bekasi PT Medina Engineering 100 pcs Bekasi Tambun 2.71% 100.00% 2.71% 4.33% 4.33% 22-Jun-23 22-Jun-23 22-Jun-23 27-Jun-23 Photos DO signed; storage on Warehouse Tambun

10 pcs top shell


10 pcs baffle (10 short & 10 long)
10 pcs inlet pipe/tube shell
- Turbine (Draft Through)/(Flocculation Basin) PT Medina Engineering 10 sets Bekasi Tambun 3.87% 100.00% 3.87% 6.19% 6.19% 21-Jun-23 21-Jun-23 21-Jun-23 27-Jun-23 Photos DO signed; storage on Warehouse Tambun hydro-PAQ
10 pcs bottom shell
80 pcs L-Connector for Baffle Flocculation Basin
Rubber for Collection Trough

10 pcs Frame WF
10 pcs Frame UNP
- Lamella Support Bekasi PT Medina Engineering 10 sets Bekasi Tambun 2.13% 100.00% 2.13% 3.41% 3.41% 23-Jun-23 23-Jun-23 23-Jun-23 23-Jun-23 Photos DO signed; storage on Warehouse Tambun
10 pcs Flat Steel 3637
10 pcs Flat Steel 3652
2 2.1 Cables (partial 2) PT Prysmian 1 lot Cikarang Tambun 10.84% 100.00% 10.84% 17.35% 17.35% 15-Dec-23 29-Sep-23 15-Dec-23 29-Sep-23 FAT 8 Dec electrical accessories
2 2.2 FRP Chemical Tanks PT Graha Adhi Jaya 8 pcs N. JKTA Tambun 0.67% 60.00% 0.40% 1.07% 0.64% TBC TBC TBC TBC Photos Chemical Room = 8 pcs
2 2.3 Transformer PT Asata Utama 5 pcs JKTA Tambun 4.33% 100.00% 4.33% 6.93% 6.93% 22-Jun-23 22-Jun-23 22-Jun-23 22-Jun-23 Photos DO signed; storage on Warehouse Tambun Transformer Room = 5 pcs
2 2.4 FRP Pipe & Fittings - Partial 1 PT Graha Adhi Jaya N. JKTA Tambun 3.33% 40.00% 1.33% 5.33% 2.13% TBC TBC TBC TBC Embedded Pipe Delivered to Bekasi Site (10 Oct) intake to hydropaq
1 lot
FRP Pipe & Fittings - Partial 2 PT Graha Adhi Jaya TBC TBC TBC TBC FAT 4-Jan 2024, to bekasi site if Ready intake to hydropaq
2 2.5 Low Voltage MCC Panels PT Industri Elektrik Metal 5 pcs JKTA Tambun 11.51% 60.00% 6.91% 18.42% 11.05% 1-Nov-23 TBC 1-Nov-23 TBC Photos On progress fabrication MCC Room = 5 pcs
2 2.6 Sand & Gravel PT. Heksagon Karyatama Indonesia 1 lot Bandung Tambun 4.09% 0.00% 0.00% 6.54% 0.00% TBC TBC TBC TBC hydrofil

already on warehouse as below: (25 oct) Intake System = 5 pcs


12 pumpset Cibeet Hydro-FIL = 7 pcs
3 3.2 Centrifugal Pumps 2 (Partial) Wilo 28 unit Tangerang Tambun 10.51% 50.00% 5.26% 16.82% 8.41% 11-Oct-23 11-Oct-23 11-Oct-23 11-Oct-23
12 pumpset Bekasi Water Distribution = 11 pcs
3 sump pump Sump Area = 5 pcs

4 4.4 CCTV TBC TBC JKTA Tambun 0.57% 0.00% 0.00% 0.91% 0.00% TBC
6 6.1 Medium Voltage Switchgear PT Uni Makmur Elektrika 1 pc JKTA Tambun 2.81% 100.00% 2.81% 4.49% 4.49% TBC TBC TBC TBC On progress fabrication MCC Room
Street Lighting TBC street
Electrical Accessories (Cables for LV, MV) PT. Prima Indah Lestari TBC MCC Room

62.50% 45.05% 100.00% 72.08%


100.00% 79.67%
6-Jun-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.94% 25.67% 68.87%
OFFSHORE BEKASI 63.06% 43.15% 68.42%
Total 100.00% 68.82%

ONSHORE CIBEET 37.50% 15.60% 41.59%


ONSHORE BEKASI 62.50% 22.64% 36.23%
Total 100.00% 38.24%

28-Jun-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.94% 25.67% 68.87%
OFFSHORE BEKASI 63.06% 43.15% 68.42%
Total 100.00% 68.82%

ONSHORE CIBEET 37.50% 17.75% 47.33%


ONSHORE BEKASI 62.50% 22.76% 36.42%
Total 100.00% 40.51%

8-Jul-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.94% 26.50% 71.72%
OFFSHORE BEKASI 63.06% 42.46% 67.33%
Total 100.00% 68.96%

ONSHORE CIBEET 37.50% 18.67% 49.80%


ONSHORE BEKASI 62.50% 23.86% 38.17%
Total 100.00% 42.53%

14-Jul-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.94% 26.81% 72.57%
OFFSHORE BEKASI 63.06% 42.62% 67.59%
Total 100.00% 69.43%

ONSHORE CIBEET 37.50% 19.31% 51.49%


ONSHORE BEKASI 62.50% 24.13% 38.61%
Total 100.00% 43.44%
28-Jul-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 27.15% 73.49%
OFFSHORE BEKASI 63.05% 43.02% 68.22%
Total 100.00% 70.17%

ONSHORE CIBEET 37.50% 24.27% 64.73%


ONSHORE BEKASI 62.50% 25.28% 40.45%
Total 100.00% 49.55%

5-Aug-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 27.15% 73.49%
OFFSHORE BEKASI 63.05% 43.02% 68.22%
Total 100.00% 70.17%

ONSHORE CIBEET 37.50% 26.43% 70.48%


ONSHORE BEKASI 62.50% 26.04% 41.66%
Total 100.00% 52.47%

10-Aug-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 27.73% 73.49%
OFFSHORE BEKASI 63.05% 43.77% 68.22%
Total 100.00% 71.50%

ONSHORE CIBEET 37.50% 26.43% 70.48%


ONSHORE BEKASI 62.50% 26.04% 41.66%
Total 100.00% 52.47%

26-Aug-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 28.36% 76.76%
OFFSHORE BEKASI 63.05% 44.61% 70.76%
Total 100.00% 72.97%

ONSHORE CIBEET 37.50% 26.43% 70.48%


ONSHORE BEKASI 62.50% 26.04% 41.66%
Total 100.00% 52.47%
1-Sep-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 28.62% 77.47%
OFFSHORE BEKASI 63.05% 46.92% 74.41%
Total 100.00% 75.54%

ONSHORE CIBEET 37.50% 33.38% 89.01%


ONSHORE BEKASI 62.50% 29.19% 46.71%
Total 100.00% 62.57%

8-Sep-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 29.38% 79.52%
OFFSHORE BEKASI 63.05% 47.38% 75.15%
Total 100.00% 76.76%

ONSHORE CIBEET 37.50% 34.62% 92.33%


ONSHORE BEKASI 62.50% 29.77% 47.64%
Total 100.00% 64.39%

16-Sep-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 32.91% 89.16%
OFFSHORE BEKASI 63.05% 51.01% 80.87%
Total 100.00% 83.92%

ONSHORE CIBEET 37.50% 34.62% 92.33%


ONSHORE BEKASI 62.50% 29.77% 47.64%
Total 100.00% 64.39%

23-Sep-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 34.11% 92.39%
OFFSHORE BEKASI 63.05% 51.01% 80.87%
Total 100.00% 85.12%

ONSHORE CIBEET 37.50% 34.62% 92.33%


ONSHORE BEKASI 62.50% 29.77% 47.64%
Total 100.00% 64.39%
2-Oct-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 34.11% 92.39%
OFFSHORE BEKASI 63.05% 51.01% 80.87%
Total 100.00% 85.12%

ONSHORE CIBEET 37.50% 34.62% 92.33%


ONSHORE BEKASI 62.50% 40.08% 64.12%
Total 100.00% 74.70%

7-Oct-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 34.15% 92.39%
OFFSHORE BEKASI 63.05% 51.03% 80.87%
Total 100.00% 85.18%

ONSHORE CIBEET 37.50% 34.62% 92.33%


ONSHORE BEKASI 62.50% 42.63% 64.12%
Total 100.00% 77.25%

13-Oct-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 34.61% 92.50%
OFFSHORE BEKASI 63.05% 51.03% 80.90%
Total 100.00% 85.64%

ONSHORE CIBEET 37.50% 34.62% 92.33%


ONSHORE BEKASI 62.50% 42.63% 64.12%
Total 100.00% 77.25%

20-Oct-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 34.61% 92.50%
OFFSHORE BEKASI 63.05% 51.03% 80.90%
Total 100.00% 85.64%

ONSHORE CIBEET 37.50% 34.62% 92.33%


ONSHORE BEKASI 62.50% 43.90% 64.12%
Total 100.00% 78.52%
27-Oct-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 35.11% 93.86%
OFFSHORE BEKASI 63.05% 51.03% 80.90%
Total 100.00% 86.14%

ONSHORE CIBEET 37.50% 34.62% 92.33%


ONSHORE BEKASI 62.50% 45.05% 72.08%
Total 100.00% 79.67%

4-Nov-23
Actual Weighted
Weighted Value % Progress by Site
Value %
OFFSHORE CIBEET 36.95% 35.11% 93.86%
OFFSHORE BEKASI 63.05% 54.40% 84.81%
Total 100.00% 89.51%

ONSHORE CIBEET 37.50% 34.62% 92.33%


ONSHORE BEKASI 62.50% 45.05% 72.08%
Total 100.00% 79.67%
CVM Valves

Work In Progress - Delivery 1a & 1b Date:31 Oct 2023


Work Order No. 226 / 2023 Schedule - Year 2023
Month Jun Jul Aug Sep
Work week 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39

Production for Delivery 1a - Cibeet Manual Valves


1 Butterfly Valve / Lug Type /
Manual Valves DN50-DN500
2 Check Valve DN50-DN200
3 Knifegate Valve DN80-DN150
Casting Machining Assemble Testing

Work Progress %
100% Delivered

Production for Delivery 1b - Cibeet Manual Valves


1 Butterfly Valve DN600 Manual
2 Tilted Disc DN400, DN450

Casting Machining Assemble Testing

Work Progress %
100% Delivered

Work In Progress - Delivery 2a, 2b, 2c


Work Order No. 226 / 2023 Schedule - Year 2023
Month Jun Jul Aug Sep Oct
Work week 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47

Production for Delivery 2a - Cibeet Auto Valves


1 Butterfly Valve / Lug Type / Electric Delivery Completed.
DN80, DN150, DN200.
DN300, DN400, DN450.
2 Knifegate Valve / Electric
DN80, DN100.

3 Butterfly Valve / Lug Type / Electric


DN300 (7pcs)
4 Knifegate Valve / Electric
DN100 (2pcs)
5 Delivery of AUMA Electric
Actuators (Batch 2).
Casting Machining Assemble Testing

Work Progress % Valves ready, waiting for the delivery of elec. Actuators

Production for Delivery 2b - Bekasi Manual Valves


1 Butterfly Valve / Double Flange /
Manual Valve DN700, DN1000. Delivery Completed.

2 Knifegate Valves Manual. Delivery Completed.

Casting Machining Assemble Testing

Work Progress %
100% Delivered

D:\CS Chuah\Production Planning\Production Schedule BW / Delivery 1&210/31/2023


CVM Valves

Work In Progress - Delivery 3a, 3b, 4 Date: 31 Oct 2023


Work Order No. 226 / 2023 Schedule - Year 2023
Month Jun Jul Aug Sep Oct Nov Dec
Work week 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52

Production for Delivery 3a - Bekasi Auto Valves


1 Butterfly Valve / Lug Type / Delivered
Auto Valves DN100, DN250,
2 Knifegate Valve
DN80, 1pc.
DN150, 3pcs.
Casting Machining Assemble Testing

Work Progress % Valves ready, waiting for the delivery of elec. Actuators (Batch 2).

Production for Delivery 3a - Bekasi Auto Valves


1 Butterfly Valve / Lug Type /
Auto Valves DN450, DN500.
2 Butterfly Valve / Double Flange /
Auto Valves DN600
3 Tilted Disc Check Valves
DN400, DN450, DN700.
Casting Machining Assemble Testing

Work Progress %
90%

Production for Delivery 3b - Bekasi Electric Actuators


1 Delivery of AUMA Electric
Actuators (Batch 3), and
Assemble Bekasi Auto Valves.
Delivery Lead Time Assemble Testing

Work Progress % 75%

Production for Delivery 4- Bekasi Auto Valves


1 Butterfly Valve / Double Flange /
Auto Valves DN700, DN900
Casting Machining Assemble Testing

Work Progress % 75%

D:\CS Chuah\Production Planning\Production Schedule BW / Delivery 3&410/31/2023


Photo Report

Location: Warehouse Tambun


Date: 4/11/2023

No Description Photo

1 Decanter for Cibeet and Bekasi


Photo Report

Location: Warehouse Tambun


Date: 4/11/2023

No Description Photo

1 Screen Conveyor for Cibeet and Bekasi


PROGRESS REPORT
DATE : 27.10.2023
CLIENT : BW WATER SDN BHD
PRODUCT : 1. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 1 SET
2. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 4 SETS
3. WM RS PENSTOCK 800WX800H C/W ISO FL F10 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 11 SETS

1
PROGRESS REPORT
DATE : 27.10.2023
CLIENT : BW WATER SDN BHD
PRODUCT : 1. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 1 SET
2. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 4 SETS
3. WM RS PENSTOCK 800WX800H C/W ISO FL F10 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 11 SETS

2
PROGRESS REPORT
DATE : 27.10.2023
CLIENT : BW WATER SDN BHD
PRODUCT : 1. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 1 SET
2. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 4 SETS
3. WM RS PENSTOCK 800WX800H C/W ISO FL F10 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 11 SETS

3
PROGRESS REPORT
DATE : 27.10.2023
CLIENT : BW WATER SDN BHD
PRODUCT : 1. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 1 SET
2. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 4 SETS
3. WM RS PENSTOCK 800WX800H C/W ISO FL F10 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 11 SETS

1. PARTIALLY LASER CUT AND BENDING COMPLETED FOR 800MM PENSTOCK

4
PROGRESS REPORT
DATE : 27.10.2023
CLIENT : BW WATER SDN BHD
PRODUCT : 1. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 1 SET
2. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 4 SETS
3. WM RS PENSTOCK 800WX800H C/W ISO FL F10 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 11 SETS

5
PROGRESS REPORT
DATE : 27.10.2023
CLIENT : BW WATER SDN BHD
PRODUCT : 1. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 1 SET
2. WM RS PENSTOCK 1900WX2500H C/W ISO FL F16 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 4 SETS
3. WM RS PENSTOCK 800WX800H C/W ISO FL F10 SS304
(CLOSED FRAME & EXTENDED FRAME) – QTY 11 SETS

2. WELDING IN PROCESS FOR 800MM PENSTOCK