PP Integration
PP Integration
1) When you create and release the production order, the planned costs will
be calculated from BOM and Routing/Master Recipe master data.-Co document
will be generated for Planned postings
3) When operations in routings are confirmed, the cost centers in the work
centers will be charged with the activity costs
here secondary cost postings will be triggered in the production cost
centers.
4) After final confirmation of the operations, the GRN will takes place against
the production order, here also CO and FI documents will be generated -CO11
FI-Entry-
Finished Goods A/C Dr
To cost of goods produced A/C
5) If the production order is not confirmed fully, we have to run WIP at the
month end-KKAO
FI entry- WIP A/C Dr
To Change in WIP A/ c Cr
The above entry will be reversed at the time of settlement of production order.