l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.

597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Proposed Baseline Program (G+M+R) At DIP-2nd, Dubai 244 20-Jan-24 19-Sep-24 0 19-Sep-24,...

Key Milestones 244 20-Jan-24 19-Sep-24 0 19-Sep-24,...


Contractual Milestones 244 20-Jan-24 19-Sep-24 0 19-Sep-24,...
G-KM-00010 Project Commencement Date to start mobilization 0 20-Jan-24 2 Project Co...
G-KM-00160 Issue of all Design NOC's Building Permit & IFC Drawing 0 20-Jan-24 20-Jan-24 0 Issue of a...
G-MP-00060 temporary Site Office/Labour Room/Store/HSE Room( Mobilization) 30 20-Jan-24 18-Feb-24 0 temporary ...
G-KM-00020 Project Completion Date 0 19-Sep-24 0 Project Co...
Control Milestones 0 0
Mobilization/ P&E Setup 30 20-Jan-24 18-Feb-24 0 18-Feb-24,...
G-KM-00090 Building Permit & Construction Commencement Date 0 18-Feb-24 0 Building P...
Access for Mobilization 0 20-Jan-24 20-Jan-24 0 20-Jan-24,...
G-MP-00010 Taking Over of Site to Start Mobilization 0 20-Jan-24 0 Taking Ove...
Intial Project Setup 30 20-Jan-24 18-Feb-24 0 18-Feb-24,...
G-MP-00020 Inspect Existing Site 7 20-Jan-24 26-Jan-24 0 Inspect Ex...
G-MP-00040 Procurement & Installation of Site Fencing 7 20-Jan-24 26-Jan-24 7 Procuremen...
G-MP-00090 Procurement & Installation of Site Porta Cabins 7 27-Jan-24 02-Feb-24 16 Procuremen...
G-MP-00030 Plot Cleaning & Grubbing 7 27-Jan-24 02-Feb-24 0 Plot Clean...
G-MP-00050 Procurement & Installation of Project Sign Board 16 03-Feb-24 18-Feb-24 0 Procuremen...
Engineering & Procurement 220 20-Jan-24 26-Aug-24 24 26-Aug-24,...
Shop Drawings - Civil, ID, External Works 174 04-Feb-24 26-Jul-24 55 26-Jul-24,...
Shop Drawings - MEP 169 04-Feb-24 21-Jul-24 60 21-Jul-24,...
Materials - Civil - Supplier/Subcontractor - PQ/Submittals & Approvals/Procurement 220 20-Jan-24 26-Aug-24 24 26-Aug-24,...
Antitermite 7 06-Feb-24 12-Feb-24 26 12-Feb-24,...
G-EP-CIV-11460
Antitermite - PQ/ Material Submittal 3 06-Feb-24 08-Feb-24 20 Antitermit...
G-EP-CIV-11470
Antitermite - Incorporate Comments & Final Approval 3 09-Feb-24 11-Feb-24 26 Antitermit...
G-EP-CIV-11480
Lead Time including delivery at site 1 12-Feb-24 12-Feb-24 26 Lead Time ...
Polythene sheet 5 07-Feb-24 11-Feb-24 28 11-Feb-24,...
G-EP-CIV-10400
Polythene sheet - Material Submittal 2 07-Feb-24 08-Feb-24 20 Polythene ...
G-EP-CIV-10410
Polythene sheet - Incorporate Comments & Final Approval 2 09-Feb-24 10-Feb-24 28 Polythene ...
G-EP-CIV-10420
Lead Time including delivery at site 1 11-Feb-24 11-Feb-24 28 Lead Time ...
Water proofing below Raft 9 20-Jan-24 28-Jan-24 42 28-Jan-24,...
G-EP-CIV-10370
Water proofing - Material Submittal Incl. Supplier PQ Submittal 3 20-Jan-24 22-Jan-24 42 Water proo...
G-EP-CIV-10380
Water proofing - Incorporate Comments & Final Approval 3 23-Jan-24 25-Jan-24 42 Water proo...
G-EP-CIV-10390
Lead Time including delivery at site 3 26-Jan-24 28-Jan-24 42 Lead Time ...
Protection screed below Raft 6 07-Feb-24 12-Feb-24 35 12-Feb-24,...
G-EP-CIV-11540
Protection screed - Material Submittal 2 07-Feb-24 08-Feb-24 35 Protection...
G-EP-CIV-11560
Protection screed - Incorporate Comments & Final Approval 2 09-Feb-24 10-Feb-24 35 Protection...
G-EP-CIV-11550
Lead Time including delivery at site 2 11-Feb-24 12-Feb-24 35 Lead Time ...
Dewatering 0 0
Steel 21 08-Feb-24 28-Feb-24 20 28-Feb-24,...
G-EP-CIV-11510
Steel - Material Submittal 7 08-Feb-24 14-Feb-24 20 Steel - Ma...
G-EP-CIV-11520
Steel - Incorporate Comments & Final Approval 7 15-Feb-24 21-Feb-24 20 Steel - In...
G-EP-CIV-11530
Lead Time including delivery at site 7 22-Feb-24 28-Feb-24 20 Lead Time ...
Formwork 30 12-Feb-24 12-Mar-24 33 12-Mar-24,...
G-EP-CIV-11220
Formwork - PQ/ Material Submittal 10 12-Feb-24 21-Feb-24 33 Formwork -...
G-EP-CIV-11230
Formwork - Incorporate Comments & Final Approval 10 22-Feb-24 02-Mar-24 33 Formwork -...
G-EP-CIV-11240
Lead Time including delivery at site 10 03-Mar-24 12-Mar-24 33 Lead Time ...
Concrete 27 08-Feb-24 05-Mar-24 26 05-Mar-24,...
G-EP-CIV-10250
Concrete - PQ/ Material Submittal 10 08-Feb-24 17-Feb-24 26 Concrete -...
G-EP-CIV-10260
Concrete - Incorporate Comments & Final Approval 10 18-Feb-24 27-Feb-24 26 Concrete -...
G-EP-CIV-10270
Lead Time including delivery at site 7 28-Feb-24 05-Mar-24 26 Lead Time ...
Blocks 50 25-Jan-24 14-Mar-24 12 14-Mar-24,...

Page 1 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
G-EP-CIV-10310
Blocks Supplier - PQ Submittal 10 25-Jan-24 03-Feb-24 12 Blocks Sup...
G-EP-CIV-10320
Blocks Supplier - PQ - Incorporate Comments & Final Approval 10 04-Feb-24 13-Feb-24 12 Blocks Sup...
G-EP-CIV-10330
Blocks Supplier - Appoint 0 13-Feb-24 12 Blocks Sup...
G-EP-CIV-10280
Blocks - Material Submittal 10 14-Feb-24 23-Feb-24 12 Blocks - M...
G-EP-CIV-10290
Blocks - Material Incorporate Comments & Final Approval 10 24-Feb-24 04-Mar-24 12 Blocks - M...
G-EP-CIV-10300
Lead Time including delivery at site 10 05-Mar-24 14-Mar-24 12 Lead Time ...
Wet area Waterproofing 90 20-Mar-24 17-Jun-24 25 17-Jun-24,...
G-EP-CIV-10430
Wet area Waterproofing - PQ Submittal 14 20-Mar-24 02-Apr-24 25 Wet area W...
G-EP-CIV-10440
Wet area Waterproofing - PQ - Incorporate Comments & Final Approval 14 03-Apr-24 16-Apr-24 25 Wet area W...
G-EP-CIV-10450
Wet area Waterproofing - Appoint 14 17-Apr-24 30-Apr-24 25 Wet area W...
G-EP-CIV-10470
Wet area Waterproofing - Material Submittal 14 01-May-24 14-May-24 25 Wet area W...
G-EP-CIV-10480
Wet area Waterproofing - Material - Incorporate Comments & Final Approval 14 15-May-24 28-May-24 25 Wet area W...
G-EP-CIV-10460
Lead Time including delivery at site 20 29-May-24 17-Jun-24 25 Lead Time ...
Floor screed 60 17-Apr-24 15-Jun-24 37 15-Jun-24,...
G-EP-CIV-11250
Floor screed - PQ/Material Submittal 12 17-Apr-24 28-Apr-24 37 Floor scre...
G-EP-CIV-11260
Protection screed - Incorporate Comments & Final Approval 18 29-Apr-24 16-May-24 37 Protection...
G-EP-CIV-11270
Lead Time including delivery at site 30 17-May-24 15-Jun-24 37 Lead Time ...
Anti carbonation coating - Ceiling / Decorative paint / acrylic emulsion 120 29-Apr-24 26-Aug-24 24 26-Aug-24,...
G-EP-CIV-10800
Anti carbonation coating painting S/c - PQ Submittal 14 29-Apr-24 12-May-24 24 Anti carbo...
G-EP-CIV-10810
Anti carbonation coating S/c -PQ Approval 14 13-May-24 26-May-24 24 Anti carbo...
G-EP-CIV-10820
Anti carbonation coating S/c -Appoint 14 27-May-24 09-Jun-24 24 Anti carbo...
G-EP-CIV-10830
Anti carbonation coating - Material Submittal 14 10-Jun-24 23-Jun-24 24 Anti carbo...
G-EP-CIV-10840
Anti carbonation coating - Incorporate Comments & Final Approval 14 24-Jun-24 07-Jul-24 24 Anti carbo...
G-EP-CIV-10850
Lead Time including delivery at site 50 08-Jul-24 26-Aug-24 24 Lead Time ...
Internal Painting 114 14-Feb-24 06-Jun-24 54 06-Jun-24,...
G-EP-CIV-11090
Internal Painting S/c - PQ Submittal 12 14-Feb-24 25-Feb-24 26 Internal P...
G-EP-CIV-11040
Internal Painting S/c - PQ Approval 12 26-Feb-24 08-Mar-24 26 Internal P...
G-EP-CIV-11050
Internal Painting S/c - Appoint 12 09-Mar-24 20-Mar-24 26 Internal P...
G-EP-CIV-11060
Internal Painting - Material Submittal 14 21-Mar-24 03-Apr-24 54 Internal P...
G-EP-CIV-11070
Internal Painting - Incorporate Comments & Final Approval 14 04-Apr-24 17-Apr-24 54 Internal P...
G-EP-CIV-11080
Lead Time including delivery at site 50 18-Apr-24 06-Jun-24 54 Lead Time ...
Mineral fibre ceilings for Security Control Room in Podiums 120 20-Mar-24 17-Jul-24 17 17-Jul-24,...
G-EP-CIV-10740
Mineral fibre ceiling S/c - PQ Submittal 14 20-Mar-24 02-Apr-24 17 Mineral fi...
G-EP-CIV-10750
Mineral fibre ceiling S/c -PQ Approval 14 03-Apr-24 16-Apr-24 17 Mineral fi...
G-EP-CIV-10760
Mineral fibre ceiling S/c -Appoint 14 17-Apr-24 30-Apr-24 17 Mineral fi...
G-EP-CIV-10770
Mineral fibre ceiling -Material Submittal 14 01-May-24 14-May-24 17 Mineral fi...
G-EP-CIV-10780
Mineral fibre ceiling - Incorporate Comments & Final Approval 14 15-May-24 28-May-24 17 Mineral fi...
G-EP-CIV-10790
Lead Time including delivery at site 50 29-May-24 17-Jul-24 17 Lead Time ...
Aluminium Works - Curtain Wall, Glazing Works, Canopy, Windows & Louvers 122 24-Feb-24 24-Jun-24 11 24-Jun-24,...
G-EP-CIV-10550
Aluminium Works S/c - PQ Submittal 12 24-Feb-24 06-Mar-24 11 Aluminium ...
G-EP-CIV-10560
Aluminium Works S/c -PQ Approval 12 07-Mar-24 18-Mar-24 11 Aluminium ...
G-EP-CIV-10570
Aluminium Works S/c -Appoint 12 19-Mar-24 30-Mar-24 11 Aluminium ...
G-EP-CIV-10580
Aluminium Works -Material Submittal 12 31-Mar-24 11-Apr-24 11 Aluminium ...
G-EP-CIV-10610
Mockup for Curtain Wall/ Glass/ Glazing Works 12 12-Apr-24 23-Apr-24 11 Mockup for...
G-EP-CIV-10590
Aluminium Works - Incorporate Comments & Final Approval including mockup 12 24-Apr-24 05-May-24 11 Aluminium ...
G-EP-CIV-10600
Lead Time including delivery at site (Aluminium Works Material) 50 06-May-24 24-Jun-24 11 Lead Time ...
G-EP-CIV-14620
Lead Time including delivery at site (Curtain Walling System Material) 40 06-May-24 14-Jun-24 21 Lead Time ...
Aluminium Works -WPC Strip Design 110 29-Feb-24 17-Jun-24 18 17-Jun-24,...
G-EP-CIV-14750
Aluminium Works S/c - PQ Submittal 12 29-Feb-24 11-Mar-24 18 Aluminium ...
G-EP-CIV-14760
Aluminium Works S/c -PQ Approval 12 12-Mar-24 23-Mar-24 18 Aluminium ...
G-EP-CIV-14770
Aluminium Works S/c -Appoint 0 23-Mar-24 18 Aluminium ...
G-EP-CIV-14780
Aluminium Works -Material Submittal 12 24-Mar-24 04-Apr-24 18 Aluminium ...
G-EP-CIV-14790
Mockup for Curtain Wall/ Glass/ Glazing Works 12 05-Apr-24 16-Apr-24 18 Mockup for...

Page 2 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
G-EP-CIV-14800
Aluminium Works - Incorporate Comments & Final Approval including mockup 12 17-Apr-24 28-Apr-24 18 Aluminium ...
G-EP-CIV-14810
Lead Time including delivery at site (Aluminium Works Material) 50 29-Apr-24 17-Jun-24 18 Lead Time ...
Wardrobes 0 0
Steel Doors 115 25-Mar-24 17-Jul-24 13 17-Jul-24,...
G-EP-CIV-10680
Steel doors S/c - PQ Submittal 14 25-Mar-24 07-Apr-24 13 Steel door...
G-EP-CIV-10690
Steel doors S/c -PQ Approval 14 08-Apr-24 21-Apr-24 13 Steel door...
G-EP-CIV-10700
Steel doors S/c -Appoint 14 22-Apr-24 05-May-24 13 Steel door...
G-EP-CIV-10710
Steel doors -Material/ Shop Drawing Submittal 14 06-May-24 19-May-24 13 Steel door...
G-EP-CIV-10720
Steel doors - Incorporate Comments & Final Approval for Material/ Shop Drawing 14 20-May-24 02-Jun-24 13 Steel door...
G-EP-CIV-10730
Lead Time including delivery at site 45 03-Jun-24 17-Jul-24 13 Lead Time ...
Handrails 118 20-Mar-24 15-Jul-24 16 15-Jul-24,...
G-EP-CIV-10490
handrail S/c - PQ Submittal 14 20-Mar-24 02-Apr-24 24 handrail S...
G-EP-CIV-10500
handrail S/c - PQ Approval 14 03-Apr-24 16-Apr-24 24 handrail S...
G-EP-CIV-10510
handrail S/c - Appoint 14 17-Apr-24 30-Apr-24 24 handrail S...
G-EP-CIV-10520
handrail - Material Submittal 14 01-May-24 14-May-24 24 handrail -...
G-EP-CIV-10530
handrail - Incorporate Comments & Final Approval 14 15-May-24 28-May-24 24 handrail ...
G-EP-CIV-10540
Lead Time including delivery at site 40 06-Jun-24 15-Jul-24 16 Lead Time ...
External Painting 96 21-Mar-24 24-Jun-24 26 24-Jun-24,...
G-EP-CIV-11400
External Painting Materials S/c - PQ Submittal 12 21-Mar-24 01-Apr-24 26 External P...
G-EP-CIV-11410
External Painting Materials S/c - PQ Approval 12 02-Apr-24 13-Apr-24 26 External P...
G-EP-CIV-11420
External Painting Materials S/c - Appoint 14 14-Apr-24 27-Apr-24 26 External P...
G-EP-CIV-11430
External Painting Materials -Material Submittal 14 28-Apr-24 11-May-24 26 External P...
G-EP-CIV-11440
External Painting Materials- Incorporate Comments & Final Approval 14 12-May-24 25-May-24 26 External P...
G-EP-CIV-11450
Lead Time including delivery at site 30 26-May-24 24-Jun-24 26 Lead Time ...
Precast wheel stoppers 140 09-Apr-24 26-Aug-24 24 26-Aug-24,...
G-EP-CIV-11340
Precast wheel stoppers Supplier - PQ Submittal 14 09-Apr-24 22-Apr-24 24 Precast wh...
G-EP-CIV-11350
Precast wheel stoppers Supplier -PQ Approval 14 23-Apr-24 06-May-24 24 Precast wh...
G-EP-CIV-11360
Precast wheel stoppers Supplier -Appoint 14 07-May-24 20-May-24 24 Precast wh...
G-EP-CIV-11370
Precast wheel stoppers -Material Submittal 14 21-May-24 03-Jun-24 24 Precast wh...
G-EP-CIV-11380
Precast wheel stoppers - Incorporate Comments & Final Approval 14 04-Jun-24 17-Jun-24 24 Precast wh...
G-EP-CIV-11390
Lead Time including delivery at site 70 18-Jun-24 26-Aug-24 24 Lead Time ...
Road markings 159 05-Mar-24 10-Aug-24 40 10-Aug-24,...
G-EP-CIV-10920
Road marking S/c - PQ Submittal 14 05-Mar-24 18-Mar-24 40 Road marki...
G-EP-CIV-10930
Road marking S/c -PQ Approval 18 19-Mar-24 05-Apr-24 40 Road marki...
G-EP-CIV-10940
Road marking S/c -Appoint 21 06-Apr-24 26-Apr-24 40 Road marki...
G-EP-CIV-10950
Road marking -Material Submittal 18 27-Apr-24 14-May-24 40 Road marki...
G-EP-CIV-10960
Road marking - Incorporate Comments & Final Approval 18 15-May-24 01-Jun-24 40 Road marki...
G-EP-CIV-10970
Lead Time including delivery at site 70 02-Jun-24 10-Aug-24 40 Lead Time ...
bicycle Stand 90 19-Apr-24 17-Jul-24 20 17-Jul-24,...
G-EP-CIV-11010
Bicycle Stand -Material Submittal 12 19-Apr-24 30-Apr-24 20 Bicycle St...
G-EP-CIV-11020
Bicycle Stand -Incorporate Comments & Final Approval 18 01-May-24 18-May-24 20 Bicycle St...
G-EP-CIV-11030
Lead Time including delivery at site 60 19-May-24 17-Jul-24 20 Lead Time ...
Garbage Trolley 114 19-Feb-24 11-Jun-24 56 11-Jun-24,...
G-EP-CIV-14820
Garbage trolley S/c - PQ Submittal 18 19-Feb-24 07-Mar-24 56 Garbage tr...
G-EP-CIV-14830
Garbage trolley S/c - PQ Approval 18 08-Mar-24 25-Mar-24 56 Garbage tr...
G-EP-CIV-14840
Garbage trolley S/c - Appoint 0 25-Mar-24 56 Garbage tr...
G-EP-CIV-14850
Garbage trolley - Material Submittal 24 26-Mar-24 18-Apr-24 56 Garbage tr...
G-EP-CIV-14860
Garbage trolley - Material Approval 24 09-Apr-24 02-May-24 56 Garbage tr...
G-EP-CIV-14870
Lead Time including delivery at site 40 03-May-24 11-Jun-24 56 Lead Time ...
Wooden Doors 114 25-Mar-24 16-Jul-24 53 16-Jul-24,...
G-EP-CIV-11100
Wooden Doors S/c - PQ Submittal 18 25-Mar-24 11-Apr-24 53 Wooden Doo...
G-EP-CIV-11110
Wooden Doors S/c - PQ Approval 18 12-Apr-24 29-Apr-24 53 Wooden Doo...
G-EP-CIV-11120
Wooden Doors S/c - Appoint 0 29-Apr-24 53 Wooden Doo...

Page 3 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
G-EP-CIV-11130
Wooden Doors - Material Submittal 24 30-Apr-24 23-May-24 53 Wooden Doo...
G-EP-CIV-11140
Wooden Doors - Material Approval 24 14-May-24 06-Jun-24 53 Wooden Doo...
G-EP-CIV-11150
Lead Time including delivery at site 40 07-Jun-24 16-Jul-24 53 Lead Time ...
Internal Signages 102 18-Apr-24 29-Jul-24 16 29-Jul-24,...
G-EP-CIV-14390
Nomination of Internal Signages Sub-Contractor 0 18-Apr-24 16 Nomination...
G-EP-CIV-14340
Internal Signages -Material Submittal 18 19-Apr-24 06-May-24 16 Internal S...
G-EP-CIV-14350
Internal Signages -Material Approval 18 03-May-24 20-May-24 16 Internal S...
G-EP-CIV-14360
Lead Time including delivery at site 70 21-May-24 29-Jul-24 16 Lead Time ...
Vanity marble top Counters 112 20-Mar-24 09-Jul-24 16 09-Jul-24,...
G-EP-CIV-14080
Vanity Counters - PQ Submittal 14 20-Mar-24 02-Apr-24 16 Vanity Cou...
G-EP-CIV-14090
Vanity Counters - PQ Approval 18 03-Apr-24 20-Apr-24 16 Vanity Cou...
G-EP-CIV-14100
Vanity Counters - Appoint 0 20-Apr-24 16 Vanity Cou...
G-EP-CIV-14110
Vanity Counters - Material Submittal 21 21-Apr-24 11-May-24 16 Vanity Cou...
G-EP-CIV-14120
Vanity Counters - Material Approval 21 05-May-24 25-May-24 16 Vanity Cou...
G-EP-CIV-14130
Lead Time including delivery at site 45 26-May-24 09-Jul-24 16 Lead Time ...
False ceiling work 104 20-Mar-24 01-Jul-24 14 01-Jul-24,...
G-EP-CIV-10860
False ceiling all types S/c - PQ Submittal 14 20-Mar-24 02-Apr-24 14 False ceil...
G-EP-CIV-10870
False ceiling all types S/c -PQ Approval 14 03-Apr-24 16-Apr-24 14 False ceil...
G-EP-CIV-10880
False ceiling all types S/c -Appoint 0 16-Apr-24 14 False ceil...
G-EP-CIV-10890
False ceiling all types -Material Submittal 12 17-Apr-24 28-Apr-24 14 False ceil...
G-EP-CIV-10900
False ceiling all types- Incorporate Comments & Final Approval 14 29-Apr-24 12-May-24 14 False ceil...
G-EP-CIV-10910
Lead Time including delivery at site 50 13-May-24 01-Jul-24 14 Lead Time ...
Materials - MEP - Supplier/Subcontractor - PQ/Submittals & Approvals/Procurement 177 19-Feb-24 13-Aug-24 37 13-Aug-24,...
MEP - Electrical 177 19-Feb-24 13-Aug-24 37 13-Aug-24,...
PVC Conduit & Accessories 89 10-Mar-24 06-Jun-24 39 06-Jun-24,...
G-EP-MEP-11950
Material Submittal 14 10-Mar-24 23-Mar-24 39 Material S...
G-EP-MEP-11960
Material - Incorporate Comments & Final Approval 15 24-Mar-24 07-Apr-24 39 Material -...
G-EP-MEP-11970
Lead Time including delivery at site 60 08-Apr-24 06-Jun-24 39 Lead Time ...
GI Cable Tray, Trunk &Accessories 87 20-Mar-24 14-Jun-24 31 14-Jun-24,...
G-EP-MEP-11980
Material Submittal 14 20-Mar-24 02-Apr-24 31 Material S...
G-EP-MEP-11990
Material - Incorporate Comments & Final Approval 18 03-Apr-24 20-Apr-24 31 Material -...
G-EP-MEP-12000
Lead Time including delivery at site 55 20-Apr-24 14-Jun-24 31 Lead Time ...
LV Cables 112 20-Mar-24 09-Jul-24 19 09-Jul-24,...
G-EP-MEP-12010
Material Submittal 14 20-Mar-24 02-Apr-24 19 Material S...
G-EP-MEP-12020
Material - Incorporate Comments & Final Approval 18 03-Apr-24 20-Apr-24 19 Material -...
G-EP-MEP-12030
Lead Time including delivery at site 80 20-Apr-24 09-Jul-24 19 Lead Time ...
Emergency & Exit Lighting System 121 20-Mar-24 18-Jul-24 26 18-Jul-24,...
G-EP-MEP-12070
Material Submittal 18 20-Mar-24 06-Apr-24 26 Material S...
G-EP-MEP-12080
Material - Incorporate Comments & Final Approval 15 07-Apr-24 21-Apr-24 26 Material -...
G-EP-MEP-12100
Submission of Shop Drawings 15 21-Apr-24 05-May-24 26 Submission...
G-EP-MEP-12110
Approval of Shop Drawings 15 05-May-24 19-May-24 26 Approval o...
G-EP-MEP-12090
Lead Time including delivery at site 60 20-May-24 18-Jul-24 26 Lead Time ...
Isolators 94 30-Mar-24 01-Jul-24 22 01-Jul-24,...
G-EP-MEP-12120
Material Submittal 14 30-Mar-24 12-Apr-24 22 Material S...
G-EP-MEP-12130
Material - Incorporate Comments & Final Approval 20 13-Apr-24 02-May-24 22 Material -...
G-EP-MEP-12140
Lead Time including delivery at site 60 03-May-24 01-Jul-24 22 Lead Time ...
UPS 86 30-Mar-24 23-Jun-24 26 23-Jun-24,...
G-EP-MEP-12150
Material Submittal 18 30-Mar-24 16-Apr-24 26 Material S...
G-EP-MEP-12160
Material - Incorporate Comments & Final Approval 18 17-Apr-24 04-May-24 26 Material -...
G-EP-MEP-12170
Lead Time including delivery at site 50 05-May-24 23-Jun-24 26 Lead Time ...
SMDB, DB's & MCC 88 09-Apr-24 05-Jul-24 20 05-Jul-24,...
G-EP-MEP-12180
Material Submittal 14 09-Apr-24 22-Apr-24 20 Material S...
G-EP-MEP-12190
Material - Incorporate Comments & Final Approval 14 23-Apr-24 06-May-24 20 Material -...

Page 4 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
G-EP-MEP-12200
Lead Time including delivery at site 60 07-May-24 05-Jul-24 20 Lead Time ...
LV Panels 127 29-Feb-24 04-Jul-24 28 04-Jul-24,...
G-EP-MEP-12210
Material Submittal 21 29-Feb-24 20-Mar-24 28 Material S...
G-EP-MEP-12220
Material - Incorporate Comments & Final Approval 21 18-Mar-24 07-Apr-24 28 Material -...
G-EP-MEP-12240
Submission of Shop Drawings 20 08-Apr-24 27-Apr-24 28 Submission...
G-EP-MEP-12250
Approval of Shop Drawings 20 26-Apr-24 15-May-24 28 Approval o...
G-EP-MEP-12230
Lead Time including delivery at site 50 16-May-24 04-Jul-24 28 Lead Time ...
Diesel Generators 117 20-Mar-24 14-Jul-24 67 14-Jul-24,...
G-EP-MEP-12260
Material Submittal 30 20-Mar-24 18-Apr-24 67 Material S...
G-EP-MEP-12270
Material - Incorporate Comments & Final Approval 36 10-Apr-24 15-May-24 67 Material -...
G-EP-MEP-12280
Lead Time including delivery at site 60 16-May-24 14-Jul-24 67 Lead Time ...
Access Control System 127 19-Feb-24 24-Jun-24 25 24-Jun-24,...
G-EP-MEP-12450
Access Control System S/c - PQ Submittal 14 19-Feb-24 03-Mar-24 25 Access Con...
G-EP-MEP-12460
Access Control System S/c - PQ Approval 14 04-Mar-24 17-Mar-24 25 Access Con...
G-EP-MEP-12410
Appointment of Contractor by SECL 15 18-Mar-24 01-Apr-24 25 Appointmen...
G-EP-MEP-12420
Material Submittal 15 02-Apr-24 16-Apr-24 25 Material S...
G-EP-MEP-12430
Material Approval 15 16-Apr-24 30-Apr-24 25 Material A...
G-EP-MEP-12440
Lead Time including delivery at site 55 01-May-24 24-Jun-24 25 Lead Time ...
Lighting Control System 152 15-Mar-24 13-Aug-24 37 13-Aug-24,...
G-EP-MEP-12690
Lighting Control System S/c - PQ Submittal 14 15-Mar-24 28-Mar-24 37 Lighting C...
G-EP-MEP-12700
Lighting Control System S/c - PQ Approval 14 29-Mar-24 11-Apr-24 37 Lighting C...
G-EP-MEP-12650
Appointment of Contractor 18 12-Apr-24 29-Apr-24 37 Appointmen...
G-EP-MEP-12660
Material Submittal 18 30-Apr-24 17-May-24 37 Material S...
G-EP-MEP-12670
Material Approval 18 18-May-24 04-Jun-24 37 Material A...
G-EP-MEP-12680
Lead Time including delivery at site 70 05-Jun-24 13-Aug-24 37 Lead Time ...
Telephone & Data System(intercom) 120 15-Mar-24 12-Jul-24 32 12-Jul-24,...
G-EP-MEP-12390
Telephone & Data System S/c - PQ Submittal 14 15-Mar-24 28-Mar-24 32 Telephone ...
G-EP-MEP-12400
Telephone & Data S/c - PQ Approval 14 29-Mar-24 11-Apr-24 32 Telephone ...
G-EP-MEP-12350
Appointment of Contractor 0 11-Apr-24 32 Appointmen...
G-EP-MEP-12360
Material Submittal 18 12-Apr-24 29-Apr-24 32 Material S...
G-EP-MEP-12370
Material Approval 18 26-Apr-24 13-May-24 32 Material A...
G-EP-MEP-12380
Lead Time including delivery at site 60 14-May-24 12-Jul-24 32 Lead Time ...
MEP - Plumbing 144 20-Mar-24 10-Aug-24 40 10-Aug-24,...
Drainage Pipes, Fittings & Sleeves 88 19-Apr-24 15-Jul-24 17 15-Jul-24,...
G-EP-MEP-12710
Material Submittal 14 19-Apr-24 02-May-24 17 Material S...
G-EP-MEP-12720
Material - Incorporate Comments & Final Approval 14 03-May-24 16-May-24 17 Material -...
G-EP-MEP-12730
Lead Time including delivery at site 60 17-May-24 15-Jul-24 17 Lead Time ...
Water Supply Valves & Strainers 92 29-Apr-24 29-Jul-24 52 29-Jul-24,...
G-EP-MEP-12860
Material Submittal 14 29-Apr-24 12-May-24 52 Material S...
G-EP-MEP-12870
Material - Incorporate Comments & Final Approval 18 13-May-24 30-May-24 52 Material -...
G-EP-MEP-12880
Lead Time including delivery at site 60 31-May-24 29-Jul-24 52 Lead Time ...
Pressure PVC Pipes & Fittings 92 14-Apr-24 14-Jul-24 67 14-Jul-24,...
G-EP-MEP-12800
Material Submittal 18 14-Apr-24 01-May-24 40 Material S...
G-EP-MEP-12810
Material - Incorporate Comments & Final Approval 24 02-May-24 25-May-24 67 Material -...
G-EP-MEP-12820
Lead Time including delivery at site 50 26-May-24 14-Jul-24 67 Lead Time ...
Sound Proof Pipes & Fittings 101 02-May-24 10-Aug-24 40 10-Aug-24,...
G-EP-MEP-12770
Material Submittal 18 02-May-24 19-May-24 40 Material S...
G-EP-MEP-12780
Material - Incorporate Comments & Final Approval 18 20-May-24 06-Jun-24 40 Material -...
G-EP-MEP-12790
Lead Time including delivery at site 65 07-Jun-24 10-Aug-24 40 Lead Time ...
PP-R Pipes & Fittings 106 25-Mar-24 08-Jul-24 73 08-Jul-24,...
G-EP-MEP-12890
Material Submittal 18 25-Mar-24 11-Apr-24 73 Material S...
G-EP-MEP-12900
Material - Incorporate Comments & Final Approval 18 12-Apr-24 29-Apr-24 73 Material -...
G-EP-MEP-12910
Lead Time including delivery at site 70 30-Apr-24 08-Jul-24 73 Lead Time ...

Page 5 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
HDPE Pipes & Fittings 112 30-Mar-24 19-Jul-24 62 19-Jul-24,...
G-EP-MEP-12920
Material Submittal 18 30-Mar-24 16-Apr-24 62 Material S...
G-EP-MEP-12930
Material - Incorporate Comments & Final Approval 24 17-Apr-24 10-May-24 62 Material -...
G-EP-MEP-12940
Lead Time including delivery at site 70 11-May-24 19-Jul-24 62 Lead Time ...
H/L Drainage Pipes & Fittings 97 29-Apr-24 03-Aug-24 47 03-Aug-24,...
G-EP-MEP-12740
Material Submittal 18 29-Apr-24 16-May-24 47 Material S...
G-EP-MEP-12750
Material - Incorporate Comments & Final Approval 24 17-May-24 09-Jun-24 47 Material -...
G-EP-MEP-12760
Lead Time including delivery at site 55 10-Jun-24 03-Aug-24 47 Lead Time ...
Catch Basins 120 20-Mar-24 17-Jul-24 24 17-Jul-24,...
G-EP-MEP-12830
Material Submittal 14 20-Mar-24 02-Apr-24 24 Material S...
G-EP-MEP-12840
Material - Incorporate Comments & Final Approval 36 03-Apr-24 08-May-24 24 Material -...
G-EP-MEP-12850
Lead Time including delivery at site 70 09-May-24 17-Jul-24 24 Lead Time ...
Sand Traps 0 0
Hair Traps 0 0
Circulation Pump 0 0
Booster Pumps 104 09-Apr-24 21-Jul-24 20 21-Jul-24,...
G-EP-MEP-12950
Material Submittal 14 09-Apr-24 22-Apr-24 20 Material S...
G-EP-MEP-12960
Material - Incorporate Comments & Final Approval 20 23-Apr-24 12-May-24 20 Material -...
G-EP-MEP-12970
Lead Time including delivery at site 70 13-May-24 21-Jul-24 20 Lead Time ...
Transfer Pumps 88 09-Apr-24 05-Jul-24 36 05-Jul-24,...
G-EP-MEP-12980
Material Submittal 12 09-Apr-24 20-Apr-24 36 Material S...
G-EP-MEP-12990
Material - Incorporate Comments & Final Approval 12 30-Apr-24 11-May-24 36 Material -...
G-EP-MEP-13000
Lead Time including delivery at site 55 12-May-24 05-Jul-24 36 Lead Time ...
Sump & Sewerage Pumps 0 0
Circulation Pumps 0 0
MEP - Miscellaneous 0 0
PC Rate Items - PQ/Submittals & Approvals/Procurement 103 20-Mar-24 30-Jun-24 15 30-Jun-24,...
Porcelain/ Ceramic tiles 103 20-Mar-24 30-Jun-24 15 30-Jun-24,...
G-EP-CIV-14020
Granite/Terrazo/Mosic/Marble/ Ceramic tiles Supplier - PQ Submittal 14 20-Mar-24 02-Apr-24 15 Granite/Te...
G-EP-CIV-14030
Granite/Terrazo/Mosic/Marble/ Ceramic tiles Supplier -PQ Approval 14 03-Apr-24 16-Apr-24 15 Granite/Te...
G-EP-CIV-14040
Granite/Terrazo/Mosic/Marble/ Ceramic tiles Supplier -Appoint 0 16-Apr-24 15 Granite/Te...
G-EP-CIV-14050
Granite/Terrazo/Mosic/Marble/ Ceramic tiles - Material Submittal 21 17-Apr-24 07-May-24 15 Granite/Te...
G-EP-CIV-14060
Granite/Terrazo/Mosic/Marble/ Ceramic tiles- Material Approval 21 01-May-24 21-May-24 15 Granite/Te...
G-EP-CIV-14070
Lead Time including delivery at site 40 22-May-24 30-Jun-24 15 Lead Time ...
Stone tiles 0 0
Provisional Sum Items - PQ/Submittals & Approvals/Procurement 185 19-Feb-24 21-Aug-24 29 21-Aug-24,...
Elevators 134 19-Feb-24 01-Jul-24 2 01-Jul-24,...
G-EP-CIV-14630
Elevator S/c - PQ Submittal 14 19-Feb-24 03-Mar-24 2 Elevator S...
G-EP-CIV-14640
Elevator S/c -PQ Approval 14 04-Mar-24 17-Mar-24 2 Elevator S...
G-EP-CIV-14650
Elevator S/c -Appoint 0 17-Mar-24 2 Elevator S...
G-EP-CIV-14660
Elevator -Material Submittal 12 18-Mar-24 29-Mar-24 2 Elevator -...
G-EP-CIV-14670
Elevator - Incorporate Comments & Final Approval 14 30-Mar-24 12-Apr-24 2 Elevator -...
G-EP-CIV-14680
Lead Time including delivery at site 80 13-Apr-24 01-Jul-24 2 Lead Time ...
Escalator 134 19-Feb-24 01-Jul-24 2 01-Jul-24,...
G-EP-CIV-14690
Escalator S/c - PQ Submittal 14 19-Feb-24 03-Mar-24 2 Escalator ...
G-EP-CIV-14700
Escalator S/c -PQ Approval 14 04-Mar-24 17-Mar-24 2 Escalator ...
G-EP-CIV-14710
Escalator all types S/c -Appoint 0 17-Mar-24 2 Escalator ...
G-EP-CIV-14720
Escalator -Material Submittal 12 18-Mar-24 29-Mar-24 2 Escalator ...
G-EP-CIV-14730
Escalators- Incorporate Comments & Final Approval 14 30-Mar-24 12-Apr-24 2 Escalators...
G-EP-CIV-14740
Lead Time including delivery at site 80 13-Apr-24 01-Jul-24 2 Lead Time ...
Sanitaryware & Accessories fitting 120 15-Mar-24 12-Jul-24 16 12-Jul-24,...
G-EP-MEP-14140
Sanitaryware & Accessories including glass partitions Supplier - PQ Submittal 14 15-Mar-24 28-Mar-24 16 Sanitarywa...
G-EP-MEP-14150
Sanitaryware & Accessories including glass partitions Supplier -PQ Approval 18 29-Mar-24 15-Apr-24 16 Sanitarywa...
G-EP-MEP-14160
Sanitaryware & Accessories including glass partitions Supplier -Appoint 0 15-Apr-24 16 Sanitarywa...

Page 6 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
G-EP-MEP-14170
Sanitaryware & Accessories including glass partitions Supplier - Material Submittal 18 16-Apr-24 03-May-24 16 Sanitarywa...
G-EP-MEP-14180
Sanitaryware & Accessories including glass partitions Supplier - Incorporate Comments & Final Approval 20 04-May-24 23-May-24 16 Sanitarywa...
G-EP-MEP-14190
Lead Time including delivery at site 50 24-May-24 12-Jul-24 16 Lead Time ...
Light Fixtures 114 20-Mar-24 11-Jul-24 22 11-Jul-24,...
G-EP-CIV-14250
Light Fittings Supplier - PQ Submittal 14 20-Mar-24 02-Apr-24 22 Light Fitt...
G-EP-CIV-14210
Light Fittings Supplier - PQ Approval 18 03-Apr-24 20-Apr-24 22 Light Fitt...
G-EP-CIV-14200
Light Fittings Supplier - Appoint 0 20-Apr-24 22 Light Fitt...
G-EP-CIV-14220
Material Submittal 18 21-Apr-24 08-May-24 22 Material S...
G-EP-CIV-14230
Light Fittings Material - Incorporate Comments & Final Approval 18 05-May-24 22-May-24 22 Light Fitt...
G-EP-CIV-14240
Lead Time including delivery at site 50 23-May-24 11-Jul-24 22 Lead Time ...
Gate Barriers 125 19-Apr-24 21-Aug-24 29 21-Aug-24,...
G-EP-MEP-12510
Gate Barriers & Parking System S/c - PQ Submittal 14 19-Apr-24 02-May-24 29 Gate Barri...
G-EP-MEP-12520
Gate Barriers & Parking System S/c - PQ Approval 14 03-May-24 16-May-24 29 Gate Barri...
G-EP-MEP-12470
Appointment of Contractor 0 16-May-24 29 Appointmen...
G-EP-MEP-12480
Material Submittal 18 17-May-24 03-Jun-24 29 Material S...
G-EP-MEP-12490
Material Approval 18 31-May-24 17-Jun-24 29 Material A...
G-EP-MEP-12500
Lead Time including delivery at site 65 18-Jun-24 21-Aug-24 29 Lead Time ...
Boundry wall Gate 125 29-Feb-24 02-Jul-24 16 02-Jul-24,...
G-EP-MEP-14240
Boundry wall Gate S/c - PQ Submittal 14 29-Feb-24 13-Mar-24 16 Boundry wa...
G-EP-MEP-14250
Boundry wall Gate S/c - PQ Approval 14 14-Mar-24 27-Mar-24 16 Boundry wa...
G-EP-MEP-14200
Appointment of Contractor 0 27-Mar-24 16 Appointmen...
G-EP-MEP-14210
Material Submittal 18 28-Mar-24 14-Apr-24 16 Material S...
G-EP-MEP-14220
Material Approval 18 11-Apr-24 28-Apr-24 16 Material A...
G-EP-MEP-14230
Lead Time including delivery at site 65 29-Apr-24 02-Jul-24 16 Lead Time ...
Construction 211 19-Feb-24 16-Sep-24 3 16-Sep-24,...
Preliminary Works 0 0
Substructure Works (Concrete) 75 19-Feb-24 03-May-24 0 03-May-24,...
Excavation & Site Work 30 19-Feb-24 19-Mar-24 0 19-Mar-24,...
G-CN-SUB-00790
Excavation 15 19-Feb-24 04-Mar-24 0 Excavation
G-CN-SUB-00800
Levelling, Compaction & Surface Preparation (including Compaction Testing) 5 05-Mar-24 09-Mar-24 0 Levelling,...
G-CN-SUB-00810
Anti Termite Application 1 10-Mar-24 10-Mar-24 0 Anti Termi...
G-CN-SUB-00820
Laying Polythene Sheet & PCC 1 11-Mar-24 11-Mar-24 0 Laying Pol...
G-CN-SUB-3250
Solid Block Work for raft(lift Area) 3 12-Mar-24 14-Mar-24 0 Solid Bloc...
G-CN-SUB-3210
Anti Termite Application 1 15-Mar-24 15-Mar-24 0 Anti Termi...
G-CN-SUB-3230
Horziontal & vertical Waterproofing Underneath Raft 3 16-Mar-24 18-Mar-24 0 Horziontal...
G-CN-SUB-3240
Protection Screed & Curing Underneath Raft 1 19-Mar-24 19-Mar-24 0 Protection...
Foundation Work 45 20-Mar-24 03-May-24 0 03-May-24,...
Water Tank & Pump room 37 20-Mar-24 25-Apr-24 1 25-Apr-24,...
Water tank and pump Room,lift(Raft work) 12 20-Mar-24 31-Mar-24 1 31-Mar-24,...
G-CN-SUP-6920
Reinforcement for Raft 7 20-Mar-24 26-Mar-24 0 Reinforcem...
G-CN-SUP-6930
Formwork for Raft 5 25-Mar-24 29-Mar-24 1 Formwork f...
G-CN-SUP-6940
Embedded MEP fixes in Core Walls 3 25-Mar-24 27-Mar-24 3 Embedded M...
G-CN-SUP-6960
Inspection, Approvals (By Consultant) 1 30-Mar-24 30-Mar-24 1 Inspection...
G-CN-SUP-6950
Concrete for Raft 1 31-Mar-24 31-Mar-24 1 Concrete f...
Water tank and pump Room,lift(Wall work) 13 01-Apr-24 13-Apr-24 1 13-Apr-24,...
G-CN-SUP-6820
Reinforcement for Core Walls,water tank wall 6 01-Apr-24 06-Apr-24 1 Reinforcem...
G-CN-SUP-6840
Embedded MEP fixes in Core Walls,water tank wall 4 05-Apr-24 08-Apr-24 4 Embedded M...
G-CN-SUP-6830
Formwork for Core Walls,water tank wall 6 06-Apr-24 11-Apr-24 1 Formwork f...
G-CN-SUP-6860
Inspection, Approvals (By Consultant)water tank wall 1 12-Apr-24 12-Apr-24 1 Inspection...
G-CN-SUP-6850
Concrete for Core Walls & water tank wall 1 13-Apr-24 13-Apr-24 1 Concrete f...
Slab of watertank & pump Room 12 14-Apr-24 25-Apr-24 1 25-Apr-24,...
G-CN-SUP-6870
FarmWork for Slab 5 14-Apr-24 18-Apr-24 1 FarmWork f...
G-CN-SUP-6880
Reinforcement for Slab 5 19-Apr-24 23-Apr-24 1 Reinforcem...
G-CN-SUP-6890
Embedded MEP fixes in Slab 2 22-Apr-24 23-Apr-24 1 Embedded M...

Page 7 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
G-CN-SUP-6910
Inspection, Approvals (By Consultant and Authority) 1 24-Apr-24 24-Apr-24 1 Inspection...
G-CN-SUP-6900
Concrete for Slab 1 25-Apr-24 25-Apr-24 1 Concrete f...
Neck Column And Tie Beam 25 27-Mar-24 20-Apr-24 0 20-Apr-24,...
A1060 Solid block work 6 27-Mar-24 01-Apr-24 0 Solid bloc...
A1070 Shuttering for Neck Column 5 31-Mar-24 04-Apr-24 0 Shuttering...
A1080 Consultant/Client approval -Neck Column 1 05-Apr-24 05-Apr-24 0 Consultant...
A1090 Concrete casting For Neck Column 1 06-Apr-24 06-Apr-24 0 Concrete c...
A1100 Backfilling and Compaction 5 07-Apr-24 11-Apr-24 0 Backfillin...
A1110 Reinforcement For tie beam 6 10-Apr-24 15-Apr-24 0 Reinforcem...
A1120 Shuttering For tie beam 5 13-Apr-24 17-Apr-24 0 Shuttering...
A1130 Consultant/Client Approval 1 18-Apr-24 18-Apr-24 0 Consultant...
A1140 Casting of tie Beam 1 18-Apr-24 18-Apr-24 0 Casting of...
A1150 De-shuttering Of tie Beam 2 19-Apr-24 20-Apr-24 0 De-shutter...
Slab on Grade 13 21-Apr-24 03-May-24 0 03-May-24,...
A1160 Back Filling And Compaction 4 21-Apr-24 24-Apr-24 0 Back Filli...
A1170 Anti termite & polithene Sheet 2 25-Apr-24 26-Apr-24 0 Anti termi...
A1180 Mesh A142 single layer 4 27-Apr-24 30-Apr-24 0 Mesh A142 ...
A1190 MEP sleves/Conduits 4 28-Apr-24 01-May-24 0 MEP sleves...
A1200 Consultant/Client approval 1 02-May-24 02-May-24 0 Consultant...
A1210 Concrete Casting 1 03-May-24 03-May-24 0 Concrete C...
Super Structure Works (Concrete) 30 04-May-24 02-Jun-24 15 02-Jun-24,...
Ground Floor To Mezzanine Floor 12 04-May-24 15-May-24 0 15-May-24,...
Verticals-Ground Floor to Mezzanine Floor 5 04-May-24 08-May-24 0 08-May-24,...
Columns 4 04-May-24 07-May-24 1 07-May-24,...
G-CN-SUP-03140
Reinforcement for Columns 2 04-May-24 05-May-24 0 Reinforcem...
G-CN-SUP-03150
Formwork for Columns 2 05-May-24 06-May-24 1 Formwork f...
G-CN-SUP-03160
Embedded MEP fixes in Columns 1 05-May-24 05-May-24 2 Embedded M...
G-CN-SUP-03170
Concrete for Columns 1 07-May-24 07-May-24 1 Concrete f...
G-CN-SUP-03180
Inspection, Approvals (By Consultant) 1 07-May-24 07-May-24 1 Inspection...
Core Walls & Stair Case Walls 5 04-May-24 08-May-24 0 08-May-24,...
G-CN-SUP-03190
Reinforcement for Core Walls & Stair Case Walls 2 04-May-24 05-May-24 0 Reinforcem...
G-CN-SUP-03210
Embedded MEP fixes in Core Walls & Stair Case Walls 1 05-May-24 05-May-24 2 Embedded M...
G-CN-SUP-03200
Formwork for Core Walls & Stair Case Walls 2 06-May-24 07-May-24 0 Formwork f...
G-CN-SUP-03220
Concrete for Core Walls & Stair Case Walls 1 08-May-24 08-May-24 0 Concrete f...
G-CN-SUP-03230
Inspection, Approvals (By Consultant) 1 08-May-24 08-May-24 0 Inspection...
Mezzanine Floor Slab 7 09-May-24 15-May-24 0 15-May-24,...
G-CN-SUP-03250
Formwork for Copping Beam,Fixing of Decking Slab Panel 4 09-May-24 12-May-24 0 Formwork f...
G-CN-SUP-03240
Reinforcementfor Copping Beam,Decking Slab Panel 4 10-May-24 13-May-24 0 Reinforcem...
G-CN-SUP-03260
Embedded MEP fixes in Slab 1 13-May-24 13-May-24 0 Embedded M...
G-CN-SUP-03270
Mezzanine Slab Inspection, Approval (By Consultant) 1 14-May-24 14-May-24 0 Mezzanine ...
G-CN-SUP-03280
Mezzanine Slab Inspection, Approval (By DM) 1 14-May-24 14-May-24 0 Mezzanine ...
G-CN-SUP-03290
Mezzanine Slab Concrete 1 15-May-24 15-May-24 0 Mezzanine ...
Mezzanine To Roof Floor 12 16-May-24 27-May-24 0 27-May-24,...
Verticals-Mezzanine To Roof 4 16-May-24 19-May-24 0 19-May-24,...
Columns 4 16-May-24 19-May-24 0 19-May-24,...
G-CN-SUP-6710
Reinforcement for Columns 2 16-May-24 17-May-24 0 Reinforcem...
G-CN-SUP-6720
Formwork for Columns 2 17-May-24 18-May-24 0 Formwork f...
G-CN-SUP-6730
Embedded MEP fixes in Columns 1 17-May-24 17-May-24 1 Embedded M...
G-CN-SUP-6740
Concrete for Columns 1 19-May-24 19-May-24 0 Concrete f...
G-CN-SUP-6750
Inspection, Approvals (By Consultant) 1 19-May-24 19-May-24 0 Inspection...
Core Walls & Stair Case Walls 4 16-May-24 19-May-24 0 19-May-24,...
G-CN-SUP-6660
Reinforcement for Core Walls & Stair Case Walls 2 16-May-24 17-May-24 0 Reinforcem...
G-CN-SUP-6670
Formwork for Core Walls & Stair Case Walls 2 17-May-24 18-May-24 0 Formwork f...

Page 8 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
G-CN-SUP-6680
Embedded MEP fixes in Core Walls & Stair Case Walls 1 17-May-24 17-May-24 1 Embedded M...
G-CN-SUP-6690
Concrete for Core Walls & Stair Case Walls 1 19-May-24 19-May-24 0 Concrete f...
G-CN-SUP-6700
Inspection, Approvals (By Consultant) 1 19-May-24 19-May-24 0 Inspection...
Roof Slab 8 20-May-24 27-May-24 0 27-May-24,...
G-CN-SUP-6770
Formwork for Copping Beam,Fixing of Decking Slab Panel 4 20-May-24 23-May-24 0 Formwork f...
G-CN-SUP-6760
Reinforcementfor Copping Beam,Decking Slab Panel 4 22-May-24 25-May-24 0 Reinforcem...
G-CN-SUP-6780
Embedded MEP fixes in Slab 3 23-May-24 25-May-24 0 Embedded M...
G-CN-SUP-6790
Roof Slab Inspection, Approval (By Consultant) 1 26-May-24 26-May-24 0 Roof Slab ...
G-CN-SUP-6800
Roof Slab Inspection, Approval (By DM) 1 26-May-24 26-May-24 0 Roof Slab ...
G-CN-SUP-6810
Roof Slab Concrete 1 27-May-24 27-May-24 0 Roof Slab ...
Roof To top Roof Floor 6 28-May-24 02-Jun-24 15 02-Jun-24,...
Verticals-Roof to Top Roof 3 28-May-24 30-May-24 15 30-May-24,...
Columns 3 28-May-24 30-May-24 15 30-May-24,...
G-CN-SUP-7020
Reinforcement for Columns 2 28-May-24 29-May-24 15 Reinforcem...
G-CN-SUP-7030
Formwork for Columns 2 28-May-24 29-May-24 15 Formwork f...
G-CN-SUP-7040
Embedded MEP fixes in Columns 1 29-May-24 29-May-24 15 Embedded M...
G-CN-SUP-7060
Inspection, Approvals (By Consultant) 1 29-May-24 29-May-24 15 Inspection...
G-CN-SUP-7050
Concrete for Columns 1 30-May-24 30-May-24 15 Concrete f...
Core Walls & Stair Case Walls 3 28-May-24 30-May-24 15 30-May-24,...
G-CN-SUP-6970
Reinforcement for Core Walls & Stair Case Walls 2 28-May-24 29-May-24 15 Reinforcem...
G-CN-SUP-6980
Formwork for Core Walls & Stair Case Walls 2 28-May-24 29-May-24 15 Formwork f...
G-CN-SUP-6990
Embedded MEP fixes in Core Walls & Stair Case Walls 1 29-May-24 29-May-24 15 Embedded M...
G-CN-SUP-7010
Inspection, Approvals (By Consultant) 1 29-May-24 29-May-24 15 Inspection...
G-CN-SUP-7000
Concrete for Core Walls & Stair Case Walls 1 30-May-24 30-May-24 15 Concrete f...
Top Roof 3 31-May-24 02-Jun-24 15 02-Jun-24,...
G-CN-SUP-7080
Formwork for Top Roof 1 31-May-24 31-May-24 15 Formwork f...
G-CN-SUP-7070
Reinforcement for Top Roof Slab 1 01-Jun-24 01-Jun-24 15 Reinforcem...
G-CN-SUP-7090
Embedded MEP fixes in Slab 1 01-Jun-24 01-Jun-24 15 Embedded M...
G-CN-SUP-7100
Top Roof Slab Inspection, Approval (By Consultant) 1 02-Jun-24 02-Jun-24 15 Top Roof S...
G-CN-SUP-7110
Top Roof Slab Inspection, Approval (By DM) 1 02-Jun-24 02-Jun-24 15 Top Roof S...
G-CN-SUP-7120
Top Roof Slab Concrete 1 02-Jun-24 02-Jun-24 15 Top Roof S...
Finishes(Civil & MEP) 112 28-May-24 16-Sep-24 3 16-Sep-24,...
U/G Work 60 14-Jun-24 12-Aug-24 38 12-Aug-24,...
Common Works 0 0
Miscellaneous Areas 52 22-Jun-24 12-Aug-24 7 12-Aug-24,...
Water Tank 36 22-Jun-24 27-Jul-24 23 27-Jul-24,...
G-CN-CID-P1-13280
Water Tank Finishes Works (GRP Lining etc.) 20 22-Jun-24 11-Jul-24 7 Water Tank...
G-CN-MEP-P1-13290
Water Tank MEP Works 20 08-Jul-24 27-Jul-24 23 Water Tank...
Sump Pits 40 04-Jul-24 12-Aug-24 7 12-Aug-24,...
G-CN-CID-P1-13300
Civil Finishes 20 04-Jul-24 23-Jul-24 7 Civil Fini...
G-CN-MEP-P1-13310
MEP Works 20 24-Jul-24 12-Aug-24 7 MEP Works
Storm Water Pits, Utility Chambers etc. 30 14-Jul-24 12-Aug-24 7 12-Aug-24,...
G-CN-CID-P1-13320
Civil Finishes 30 14-Jul-24 12-Aug-24 7 Civil Fini...
G-CN-MEP-P1-13330
MEP Works 30 14-Jul-24 12-Aug-24 7 MEP Works
Pump Rooms 47 14-Jun-24 30-Jul-24 51 30-Jul-24,...
Civil Works 47 14-Jun-24 30-Jul-24 51 30-Jul-24,...
G-CN-CID-P1-10260
preparation & rush coat 7 14-Jun-24 20-Jun-24 23 preparatio...
G-CN-CID-P1-10270
Plastering Works (including preparation & rush coat) 7 16-Jun-24 22-Jun-24 23 Plastering...
G-CN-CID-P1-10330
Waterproofing works 4 23-Jun-24 26-Jun-24 25 Waterproof...
G-CN-CID-P1-10280
Floor screed works 4 27-Jun-24 30-Jun-24 25 Floor scre...
G-CN-CID-P1-10290
First Coat Paint on Ceilings (including preparatory works) 4 01-Jul-24 04-Jul-24 25 First Coat...
G-CN-CID-P1-10340
First Coat Paint on Walls (including preparatory works) 5 05-Jul-24 09-Jul-24 25 First Coat...
G-CN-CID-P1-10300
Final Coat Paint on Ceiling 6 10-Jul-24 15-Jul-24 25 Final Coat...
G-CN-CID-P1-10350
Final Coat Paint on Walls (including preparatory works) 4 16-Jul-24 19-Jul-24 25 Final Coat...

Page 9 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
G-CN-CID-P1-10310
Fixing of Steel Doors & catladder 5 18-Jul-24 22-Jul-24 59 Fixing of ...
G-CN-CID-P1-10320
Epoxy painting works on Floor (including preparatory works & skirting) 4 27-Jul-24 30-Jul-24 20 Epoxy pain...
MEP Works 34 23-Jun-24 26-Jul-24 55 26-Jul-24,...
Electrical, LC,Telephone Data Works 34 23-Jun-24 26-Jul-24 20 26-Jul-24,...
1st Fix 7 23-Jun-24 29-Jun-24 23 29-Jun-24,...
G-CN-MEP-P1-10390
Installation of Cable Tray Trunking @ H/L, Wall 7 23-Jun-24 29-Jun-24 23 Installati...
2nd Fix 27 30-Jun-24 26-Jul-24 20 26-Jul-24,...
G-CN-MEP-P1-10430
Wiring for Lighting, Emergency Lighting, Small Power @ H/L, Wall 7 30-Jun-24 06-Jul-24 23 Wiring for...
G-CN-MEP-P1-10360
Cable Laying & Termination for Isolators @ Wall 9 02-Jul-24 10-Jul-24 22 Cable Layi...
G-CN-MEP-P1-10420
Installation & Termination of Isolators @ Wall 6 02-Jul-24 07-Jul-24 22 Installati...
G-CN-MEP-P1-10400
Installation & Termination of Control Panels @ Wall 9 11-Jul-24 19-Jul-24 22 Installati...
G-CN-MEP-P1-10410
Termination of Fire Pump & Domestic Water Pump @ Floor 5 22-Jul-24 26-Jul-24 20 Terminatio...
Plumbing 5 16-Jul-24 20-Jul-24 61 20-Jul-24,...
1st Fix 5 16-Jul-24 20-Jul-24 61 20-Jul-24,...
G-CN-MEP-P1-10470
Installation of Drainage Pipes, Water Supply Pipes @ H/L 5 16-Jul-24 20-Jul-24 61 Installati...
Ground Floor 86 28-May-24 21-Aug-24 29 21-Aug-24,...
Masonry / Common Works 62 28-May-24 28-Jul-24 53 28-Jul-24,...
B-CN-CID-GF-17660
Removal of backprops & clearance to proceed with blockworks 5 28-May-24 01-Jun-24 1 Removal of...
B-CN-CID-GF-17680
Block Works Incl. Layout 18 02-Jun-24 19-Jun-24 1 Block Work...
B-CN-CID-GF-17690
Block Cutting & Chasing Works for Services 18 05-Jun-24 22-Jun-24 1 Block Cutt...
B-CN-CID-GF-17700
Plastering Works (including preparation & rush coat) 18 09-Jun-24 26-Jun-24 1 Plastering...
B-CN-CID-GF-17670
Fix Subframes for Doors & Window Openings Finishing 12 17-Jul-24 28-Jul-24 53 Fix Subfra...
Pocket Sub Station Foundation 48 07-Jun-24 24-Jul-24 57 24-Jul-24,...
Civil Works 46 07-Jun-24 22-Jul-24 8 22-Jul-24,...
G-CN-CID-P1-11210
Excavation/Block Works/Shuttering for Foundation 7 07-Jun-24 13-Jun-24 30 Excavation...
G-CN-CID-P1-11130
Reinforcement Work 4 19-Jun-24 22-Jun-24 30 Reinforcem...
G-CN-CID-P1-11140
Inspection of Foundation 3 23-Jun-24 25-Jun-24 30 Inspection...
G-CN-CID-P1-11150
Casting of Foundation 3 18-Jul-24 20-Jul-24 8 Casting of...
G-CN-CID-P1-11180
Epoxy Coating on Floor 2 21-Jul-24 22-Jul-24 8 Epoxy Coat...
MEP Works 40 15-Jun-24 24-Jul-24 57 24-Jul-24,...
Electrical, LC,Telephone Data Works 40 15-Jun-24 24-Jul-24 57 24-Jul-24,...
1st Fix 4 15-Jun-24 18-Jun-24 30 18-Jun-24,...
G-CN-MEP-P1-11250
Installation of Cable Tray Trunking @ H/L, Wall 4 15-Jun-24 18-Jun-24 30 Installati...
2nd Fix 25 19-Jun-24 13-Jul-24 64 13-Jul-24,...
G-CN-MEP-P1-11220
Wiring for Lighting,, Emergency Lighting, Small Power @ H/L, Wall 4 19-Jun-24 22-Jun-24 81 Wiring for...
G-CN-MEP-P1-11230
Installation & Termination of DB 4 06-Jul-24 09-Jul-24 64 Installati...
G-CN-MEP-P1-11240
Cable Laying & Termination for DB 4 10-Jul-24 13-Jul-24 64 Cable Layi...
3rd Fix 4 21-Jul-24 24-Jul-24 57 24-Jul-24,...
G-CN-MEP-P1-11260
Fixing of Final Fixtures (Lighting, Wire Accessoris,Emergency Lighting) 4 21-Jul-24 24-Jul-24 57 Fixing of ...
Commerical Area(shops) 84 30-May-24 21-Aug-24 29 21-Aug-24,...
Civil Work 53 27-Jun-24 18-Aug-24 1 18-Aug-24,...
A1000 Obtain MEP Clearance above Ceiling 10 27-Jun-24 06-Jul-24 1 Obtain MEP...
A1230 Wall & Ceiling Paint Work-1st Coat 15 07-Jul-24 21-Jul-24 1 Wall & Cei...
A1050 Floor tiles 15 15-Jul-24 29-Jul-24 1 Floor tile...
A1220 Skirting & threshold 15 30-Jul-24 13-Aug-24 1 Skirting &...
A1240 Walll And Ceiling Paint work-Final Coat 5 14-Aug-24 18-Aug-24 1 Walll And ...
MEP Work 84 30-May-24 21-Aug-24 29 21-Aug-24,...
MEP Works 84 30-May-24 21-Aug-24 29 21-Aug-24,...
Electrical, LC,Telephone Data Works 44 09-Jul-24 21-Aug-24 29 21-Aug-24,...
1st Fix 7 09-Jul-24 15-Jul-24 50 15-Jul-24,...
PVC Conduiting through Block Wall 7 09-Jul-24 15-Jul-24 50 PVC Condui...
Installation of Cable Tray Trunking @ H/L 6 09-Jul-24 14-Jul-24 51 Installati...
2nd Fix 33 15-Jul-24 16-Aug-24 34 16-Aug-24,...

Page 10 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Installation of Isolator @ Wall, Ceiling 6 15-Jul-24 20-Jul-24 52 Installati...
Installation of Control Panel @ Wall, Ceiling 6 17-Jul-24 22-Jul-24 52 Installati...
Wiring for Lighting,Emergency Lighting, Small Power 12 30-Jul-24 10-Aug-24 29 Wiring for...
Cable Laying for Lighting Control @ Ceiling 8 30-Jul-24 06-Aug-24 39 Cable Layi...
LV Cable Laying 9 30-Jul-24 07-Aug-24 36 LV Cable L...
Installation of DB's & SMDB's @ Wall 8 04-Aug-24 11-Aug-24 36 Installati...
Termination of DB's & SMDB's 8 07-Aug-24 14-Aug-24 36 Terminatio...
Final Connection to Mechanical & Electrical Equipments 6 11-Aug-24 16-Aug-24 29 Final Conn...
3rd Fix 11 11-Aug-24 21-Aug-24 29 21-Aug-24,...
Installation of Wiring Accessories for Switches & Sockets 6 11-Aug-24 16-Aug-24 33 Installati...
Installation of Smoke/Heat/Sound/Voice Evacuation Speakers Detector's 5 13-Aug-24 17-Aug-24 33 Installati...
Installation of Emergency & Exit Lights 5 13-Aug-24 17-Aug-24 33 Installati...
Installation of 5 13-Aug-24 17-Aug-24 33 Installati...
Installation of CO Monitoring Devices @ Wall, Ceiling 5 13-Aug-24 17-Aug-24 33 Installati...
Fixing of Final Fixtures for Lighting 5 17-Aug-24 21-Aug-24 29 Fixing of ...
Installation of Lighting Control Sensor's 5 17-Aug-24 21-Aug-24 29 Installati...
Plumbing & Fire Fighting 26 30-May-24 24-Jun-24 40 24-Jun-24,...
1st Fix 11 30-May-24 09-Jun-24 55 09-Jun-24,...
Installation of Condensate Drain Pipes 11 30-May-24 09-Jun-24 40 Installati...
Installation of Water Supply, UPVC, 11 30-May-24 09-Jun-24 55 Installati...
2nd Fix 15 10-Jun-24 24-Jun-24 40 24-Jun-24,...
Installation of Catch Basins, Sanitary Ware installation, Floor Drains 15 10-Jun-24 24-Jun-24 40 Installati...
3rd Fix 0 0
Corridors & Lift Lobby 73 04-Jun-24 15-Aug-24 6 15-Aug-24,...
Civil Works 38 09-Jul-24 15-Aug-24 4 15-Aug-24,...
B-CN-CID-GF-18100
Obtain MEP Clearance above Ceiling 3 09-Jul-24 11-Jul-24 4 Obtain MEP...
B-CN-CID-GF-18110
Fix Ceiling Framing & Gypsum Board 7 12-Jul-24 18-Jul-24 4 Fix Ceilin...
B-CN-CID-GF-18120
First Coat Paint on Gypsum board ceiling 10 19-Jul-24 28-Jul-24 4 First Coat...
B-CN-CID-GF-18130
First Coat Paint on Walls & wall tiles 10 23-Jul-24 01-Aug-24 5 First Coat...
B-CN-CID-GF-18150
Fix Floor Tiles @ Corridor (Porcelain tiles) 8 26-Jul-24 02-Aug-24 4 Fix Floor ...
B-CN-CID-GF-18190
Fix Floor Tiles @ Lift Lobby Area 8 26-Jul-24 02-Aug-24 4 Fix Floor ...
B-CN-CID-GF-18090
Fixing of Doors (Incl. Frames) 8 03-Aug-24 10-Aug-24 4 Fixing of ...
B-CN-CID-GF-18160
Obtain Final MEP Clearance & Closing of Access Panels/ Openings 6 03-Aug-24 08-Aug-24 6 Obtain Fin...
B-CN-CID-GF-18200
Fix Wallpaper @ Lift Lobby Area 6 10-Aug-24 15-Aug-24 4 Fix Wallpa...
B-CN-CID-GF-18140
Final Coat Paint on Walls 5 11-Aug-24 15-Aug-24 4 Final Coat...
B-CN-CID-GF-18170
Final Coat Paint on Gypsum board ceiling 5 11-Aug-24 15-Aug-24 4 Final Coat...
B-CN-CID-GF-18180
Fixing of Signages 5 11-Aug-24 15-Aug-24 4 Fixing of ...
MEP Works 71 04-Jun-24 13-Aug-24 8 13-Aug-24,...
Electrical Works 71 04-Jun-24 13-Aug-24 8 13-Aug-24,...
1st Fix 8 04-Jun-24 11-Jun-24 21 11-Jun-24,...
B-CN-MEP-GF-18240
Installation of Cable Tray Trunking @ H/L, Walls for Corridor,Elec. Room 8 04-Jun-24 11-Jun-24 21 Installati...
2nd Fix 46 12-Jun-24 27-Jul-24 23 27-Jul-24,...
B-CN-MEP-GF-18230
LV Cable Laying for Corridor, Elec. Room 5 12-Jun-24 16-Jun-24 21 LV Cable L...
B-CN-MEP-GF-18280
GSM Cabling & Termination for Corridor 7 14-Jun-24 20-Jun-24 21 GSM Cablin...
B-CN-MEP-GF-18260
Cable Laying for Lighting Control for Corridor 6 16-Jun-24 21-Jun-24 59 Cable Layi...
B-CN-MEP-GF-18290
Structured Cabling for Data Telephone 6 03-Jul-24 08-Jul-24 4 Structured...
B-CN-MEP-GF-18220
Wiring for Lighting,Emergency Lighting, Small Power 6 22-Jul-24 27-Jul-24 12 Wiring for...
3rd Fix 54 21-Jun-24 13-Aug-24 8 13-Aug-24,...
B-CN-MEP-GF-18350
Installation of GSM Antenna's for Corridor 6 21-Jun-24 26-Jun-24 54 Installati...
B-CN-MEP-GF-18370
Installation of Wiring Accessories 6 28-Jul-24 02-Aug-24 12 Installati...
B-CN-MEP-GF-18300
Fixing of Final Fixtures (Lighting, Emergency Lighting) 6 06-Aug-24 11-Aug-24 8 Fixing of ...
B-CN-MEP-GF-18320
Installation of Lighting Control Sensor's for Corridor 6 06-Aug-24 11-Aug-24 8 Installati...
B-CN-MEP-GF-18330
Installation of Smoke/Heat/Sound/Voice Evacuation Speakers Detector's for Corridor 6 06-Aug-24 11-Aug-24 8 Installati...

Page 11 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B-CN-MEP-GF-18340
Installation of Emergency Exit Lights for Corridor 8 06-Aug-24 13-Aug-24 8 Installati...
B-CN-MEP-GF-18360
Installation of Telephone Outlet System 6 06-Aug-24 11-Aug-24 8 Installati...
Plumbing & Fire Fighting 0 0
1st Fix 0 0
2nd Fix 0 0
3rd Fix 0 0
Generator Room/MDB/LV Rooms 52 20-Jun-24 10-Aug-24 9 10-Aug-24,...
Civil Works 52 20-Jun-24 10-Aug-24 9 10-Aug-24,...
G-CN-CID-P1-11850
Block Works including layout 4 20-Jun-24 23-Jun-24 9 Block Work...
G-CN-CID-P1-11860
Plastering Works (including preparation & rush coat) 4 30-Jun-24 03-Jul-24 9 Plastering...
G-CN-CID-P1-11920
Waterproofing works 8 04-Jul-24 11-Jul-24 9 Waterproof...
G-CN-CID-P1-11870
Floor screed works 8 08-Jul-24 15-Jul-24 9 Floor scre...
G-CN-CID-P1-11880
First Coat Paint on Ceilings (including preparatory works) 5 16-Jul-24 20-Jul-24 9 First Coat...
G-CN-CID-P1-11890
Final Coat Paint on Ceiling 3 21-Jul-24 23-Jul-24 14 Final Coat...
G-CN-CID-P1-11900
Fixing of Aluminium Louvered Doors & Misc Metal Works (Trench Covers...) 5 21-Jul-24 25-Jul-24 20 Fixing of ...
G-CN-CID-P1-11930
First Coat Paint on Walls (including preparatory works) 8 21-Jul-24 28-Jul-24 9 First Coat...
G-CN-CID-P1-11940
Final Coat Paint on Walls (including preparatory works) 3 06-Aug-24 08-Aug-24 9 Final Coat...
G-CN-CID-P1-11910
Epoxy painting works on Floor (including preparatory works & skirting) 4 07-Aug-24 10-Aug-24 9 Epoxy pain...
MEP Works 43 24-Jun-24 05-Aug-24 9 05-Aug-24,...
Electrical, LC,Telephone Data Works 43 24-Jun-24 05-Aug-24 9 05-Aug-24,...
1st Fix 12 24-Jun-24 05-Jul-24 20 05-Jul-24,...
G-CN-MEP-P1-11950
Back Box Fixing @ Block Walls 4 24-Jun-24 27-Jun-24 9 Back Box F...
G-CN-MEP-P1-11960
PVC Conduiting through Block Walls 4 26-Jun-24 29-Jun-24 9 PVC Condui...
G-CN-MEP-P1-12020
Installation of Cable Tray Trunking @ H/L, Wall 4 02-Jul-24 05-Jul-24 20 Installati...
2nd Fix 14 06-Jul-24 19-Jul-24 19 19-Jul-24,...
G-CN-MEP-P1-11970
Wiring for Lighting, , Emergency Lighting, Small Power @ H/L, Wall 8 06-Jul-24 13-Jul-24 20 Wiring for...
G-CN-MEP-P1-11980
Installation of DB, SMDB 8 06-Jul-24 13-Jul-24 20 Installati...
G-CN-MEP-P1-12040
Cabling for LV 5 09-Jul-24 14-Jul-24 19 Cabling fo...
G-CN-MEP-P1-11990
Cable Laying & Termination of DB, SMDB 8 10-Jul-24 17-Jul-24 20 Cable Layi...
G-CN-MEP-P1-12030
Installation of LV Panels 5 14-Jul-24 19-Jul-24 19 Installati...
3rd Fix 8 29-Jul-24 05-Aug-24 9 05-Aug-24,...
G-CN-MEP-P1-12050
Installation of Wiring Accessories for Switches & Sockets 5 29-Jul-24 02-Aug-24 12 Installati...
G-CN-MEP-P1-12060
Installation of Smoke/Heat/Sound/Voice Evacuation Speakers Detector's 5 29-Jul-24 02-Aug-24 12 Installati...
G-CN-MEP-P1-12070
Installation of Emergency & Exit Lights 5 29-Jul-24 02-Aug-24 12 Installati...
G-CN-MEP-P1-12080
Fixing of Final Fixtures (Lighting, Wire Accessoris, Emergency Lighting) 8 29-Jul-24 05-Aug-24 9 Fixing of ...
Plumbing & Fire Fighting 0 0
1st Fix 0 0
2nd Fix 0 0
3rd Fix 0 0
Electrical, ELV & Service/ Store Rooms 42 28-Jun-24 08-Aug-24 11 08-Aug-24,...
Civil Works 42 28-Jun-24 08-Aug-24 11 08-Aug-24,...
G-CN-CID-P1-11390
Block Works Incl. Cutting & Chasing Works 4 28-Jun-24 01-Jul-24 11 Block Work...
G-CN-CID-P1-11300
Plastering Works (including preparation & rush coat) 4 09-Jul-24 12-Jul-24 11 Plastering...
G-CN-CID-P1-11360
Waterproofing works 4 13-Jul-24 16-Jul-24 12 Waterproof...
G-CN-CID-P1-11310
Floor screed works 4 17-Jul-24 20-Jul-24 27 Floor scre...
G-CN-CID-P1-11320
First Coat Paint on Ceilings (including preparatory works) 3 17-Jul-24 19-Jul-24 12 First Coat...
G-CN-CID-P1-11370
First Coat Paint on Walls (including preparatory works) 3 20-Jul-24 22-Jul-24 12 First Coat...
G-CN-CID-P1-11340
Fixing of Doors 2 23-Jul-24 24-Jul-24 12 Fixing of ...
G-CN-CID-P1-11330
Final Coat Paint on Ceilings 2 02-Aug-24 03-Aug-24 11 Final Coat...
G-CN-CID-P1-11380
Final Coat Paint on Walls 3 04-Aug-24 06-Aug-24 11 Final Coat...
G-CN-CID-P1-11350
Epoxy painting works on Floor (including preparatory works & skirting) 3 06-Aug-24 08-Aug-24 11 Epoxy pain...
MEP Works 31 02-Jul-24 01-Aug-24 13 01-Aug-24,...
Electrical, LC,Telephone Data Works 31 02-Jul-24 01-Aug-24 13 01-Aug-24,...
1st Fix 16 02-Jul-24 17-Jul-24 11 17-Jul-24,...

Page 12 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
G-CN-MEP-P1-11400
Back Box Fixing @ Block Walls 5 02-Jul-24 06-Jul-24 11 Back Box F...
G-CN-MEP-P1-11410
PVC Conduiting through Block Walls 5 04-Jul-24 08-Jul-24 11 PVC Condui...
G-CN-MEP-P1-11450
Installation of Cable Tray Trunking @ H/L, Wall 5 13-Jul-24 17-Jul-24 11 Installati...
2nd Fix 9 18-Jul-24 26-Jul-24 11 26-Jul-24,...
G-CN-MEP-P1-11430
Wiring for Lighting Control 8 18-Jul-24 25-Jul-24 11 Wiring for...
G-CN-MEP-P1-11440
Structured Cabling for Data Telephone @ Wall,H/L 6 18-Jul-24 23-Jul-24 13 Structured...
G-CN-MEP-P1-11420
Wiring for Lighting,Emergency Lighting, Small Power @ H/L, Wall 6 21-Jul-24 26-Jul-24 11 Wiring for...
3rd Fix 7 26-Jul-24 01-Aug-24 13 01-Aug-24,...
G-CN-MEP-P1-11490
Fixing of Final Fixtures (Lighting, Wire Accessoris,Emergency Lighting) 7 26-Jul-24 01-Aug-24 11 Fixing of ...
G-CN-MEP-P1-11460
Installation of Wiring Accessories for Switches & Sockets 6 27-Jul-24 01-Aug-24 13 Installati...
G-CN-MEP-P1-11470
Installation of Smoke/Heat/Sound/Voice Evacuation Speakers Detector's 6 27-Jul-24 01-Aug-24 11 Installati...
G-CN-MEP-P1-11480
Installation of Emergency & Exit Lights 6 27-Jul-24 01-Aug-24 11 Installati...
Fire Fighting 0 0
2nd Fix 0 0
Drive way & Parking Area 20 07-Jul-24 26-Jul-24 25 26-Jul-24,...
Civil Works 20 07-Jul-24 26-Jul-24 25 26-Jul-24,...
G-CN-CID-P2-17420
Coat Paint 7 07-Jul-24 13-Jul-24 25 Coat Paint
G-CN-CID-P2-17450
fixing of interlock work 20 07-Jul-24 26-Jul-24 25 fixing of ...
G-CN-CID-P2-17370
Apply Driveway & Parking Area epoxy Coating/ Road Markings (including preparatory works) 7 10-Jul-24 16-Jul-24 25 Apply Driv...
G-CN-CID-P2-17360
Install Wheel Stoppers 5 17-Jul-24 21-Jul-24 25 Install Wh...
G-CN-CID-P2-17390
Install Signages & Traffic Signages 3 17-Jul-24 19-Jul-24 31 Install Si...
G-CN-CID-P2-17400
Install Gate Barriers (including all associated works) 4 22-Jul-24 25-Jul-24 25 Install G...
Mezzanine Floor 99 10-Jun-24 16-Sep-24 3 16-Sep-24,...
Roof Floor 82 15-Jun-24 04-Sep-24 15 04-Sep-24,...
Common Works 21 15-Jun-24 05-Jul-24 25 05-Jul-24,...
G-CN-CID-P2-17680
Removal of backprops & clearance to proceed with blockworks 5 15-Jun-24 19-Jun-24 15 Removal of...
G-CN-CID-P2-17690
Block Works Incl. Layout 10 20-Jun-24 29-Jun-24 15 Block Work...
G-CN-CID-P2-17700
Block Cutting & Chasing Works for Services 10 24-Jun-24 03-Jul-24 15 Block Cutt...
G-CN-CID-P2-17710
Plastering Works (including preparation & rush coat) 10 26-Jun-24 05-Jul-24 25 Plastering...
Commerical Area(shops) 63 04-Jul-24 04-Sep-24 15 04-Sep-24,...
Civil Work 63 04-Jul-24 04-Sep-24 15 04-Sep-24,...
A1300 Obtain MEP Clearance above Ceiling 10 04-Jul-24 13-Jul-24 15 Obtain MEP...
A1330 Wall & Ceiling Paint Work-1st Coat 15 14-Jul-24 28-Jul-24 15 Wall & Cei...
A1310 Floor tiles 20 22-Jul-24 10-Aug-24 15 Floor tile...
A1320 Skirting & threshold 20 11-Aug-24 30-Aug-24 15 Skirting &...
A1340 Walll And Ceiling Paint work-Final Coat 5 31-Aug-24 04-Sep-24 15 Walll And ...
MEP Work 61 04-Jul-24 02-Sep-24 17 02-Sep-24,...
MEP Works 61 04-Jul-24 02-Sep-24 17 02-Sep-24,...
Electrical, LC,Telephone Data Works 61 04-Jul-24 02-Sep-24 17 02-Sep-24,...
1st Fix 20 04-Jul-24 23-Jul-24 42 23-Jul-24,...
PVC Conduiting through Block Wall 15 04-Jul-24 18-Jul-24 42 PVC Condui...
Installation of Cable Tray Trunking @ H/L 15 09-Jul-24 23-Jul-24 42 Installati...
2nd Fix 36 24-Jul-24 28-Aug-24 22 28-Aug-24,...
Installation of Isolator @ Wall, Ceiling 6 24-Jul-24 29-Jul-24 43 Installati...
Installation of Control Panel @ Wall, Ceiling 6 26-Jul-24 31-Jul-24 43 Installati...
Wiring for Lighting, Emergency Lighting, Small Power 12 11-Aug-24 22-Aug-24 17 Wiring for...
Cable Laying for Lighting Control @ Ceiling 8 11-Aug-24 18-Aug-24 27 Cable Layi...
LV Cable Laying 9 11-Aug-24 19-Aug-24 24 LV Cable L...
Installation of DB's & SMDB's @ Wall 8 16-Aug-24 23-Aug-24 24 Installati...
Termination of DB's & SMDB's 8 19-Aug-24 26-Aug-24 24 Terminatio...
Final Connection to Mechanical & Electrical Equipments 6 23-Aug-24 28-Aug-24 17 Final Conn...
3rd Fix 11 23-Aug-24 02-Sep-24 17 02-Sep-24,...
Installation of Wiring Accessories for Switches & Sockets 6 23-Aug-24 28-Aug-24 21 Installati...
Installation of Smoke/Heat/Sound/Voice Evacuation Speakers Detector's 5 25-Aug-24 29-Aug-24 21 Installati...

Page 13 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Installation of Emergency & Exit Lights 5 25-Aug-24 29-Aug-24 21 Installati...
Installation of 5 25-Aug-24 29-Aug-24 21 Installati...
Installation of CO Monitoring Devices @ Wall, Ceiling 5 25-Aug-24 29-Aug-24 21 Installati...
Fixing of Final Fixtures for Lighting 5 29-Aug-24 02-Sep-24 17 Fixing of ...
Installation of Lighting Control Sensor's 5 29-Aug-24 02-Sep-24 17 Installati...
Plumbing 26 04-Jul-24 29-Jul-24 52 29-Jul-24,...
1st Fix 11 04-Jul-24 14-Jul-24 52 14-Jul-24,...
Installation of Condensate Drain Pipes 11 04-Jul-24 14-Jul-24 52 Installati...
Installation of Water Supply, UPVC, 11 04-Jul-24 14-Jul-24 52 Installati...
2nd Fix 15 15-Jul-24 29-Jul-24 52 29-Jul-24,...
Installation of Catch Basins, Sanitary Ware installation, Floor Drains 15 15-Jul-24 29-Jul-24 52 Installati...
3rd Fix 0 0
Corridors & Lift Lobby 40 30-Jun-24 08-Aug-24 42 08-Aug-24,...
Civil Works 40 30-Jun-24 08-Aug-24 42 08-Aug-24,...
G-CN-CID-P2-17670
Block Works Incl. Cutting & Chasing Works 5 30-Jun-24 04-Jul-24 42 Block Work...
G-CN-CID-P2-17560
Plastering Works (including preparation & rush coat) 8 05-Jul-24 12-Jul-24 42 Plastering...
G-CN-CID-P2-17570
Floor screed works 8 13-Jul-24 20-Jul-24 42 Floor scre...
G-CN-CID-P2-17590
Obtain MEP Clearance for Grid Works 2 15-Jul-24 16-Jul-24 43 Obtain MEP...
G-CN-CID-P2-17620
First Coat Paint on Walls & wall tiles 7 15-Jul-24 21-Jul-24 42 First Coat...
G-CN-CID-P2-17580
Fix Ceiling frame for Gypsum Board 5 17-Jul-24 21-Jul-24 43 Fix Ceilin...
G-CN-CID-P2-17640
Obtain MEP Clearance for Ceiling Closure 4 22-Jul-24 25-Jul-24 42 Obtain MEP...
G-CN-CID-P2-17600
Gypsum board ceiling closing 7 23-Jul-24 29-Jul-24 42 Gypsum boa...
G-CN-CID-P2-17610
First Coat Paint on gypsum board ceiling 7 24-Jul-24 30-Jul-24 42 First Coat...
G-CN-CID-P2-17630
Fix Granite Tile Flooring 5 26-Jul-24 30-Jul-24 47 Fix Granit...
G-CN-CID-P2-17650
Obtain Final MEP Clearance & Closing of Access Panels/ Openings 5 02-Aug-24 06-Aug-24 42 Obtain Fin...
G-CN-CID-P2-17660
Final Coat Paint on gypsum board ceiling 4 05-Aug-24 08-Aug-24 42 Final Coat...
MEP Works 31 02-Jul-24 01-Aug-24 49 01-Aug-24,...
Electrical, LC,Telephone Data Works 31 02-Jul-24 01-Aug-24 44 01-Aug-24,...
1st Fix 8 02-Jul-24 09-Jul-24 45 09-Jul-24,...
G-CN-MEP-P2-18450
PVC Conduiting through Block Wall 6 02-Jul-24 07-Jul-24 43 PVC Condui...
G-CN-MEP-P2-18460
Installation of Cable Tray Trunking 6 04-Jul-24 09-Jul-24 45 Installati...
2nd Fix 15 06-Jul-24 20-Jul-24 43 20-Jul-24,...
G-CN-MEP-P2-18440
GSM Cabling 6 06-Jul-24 11-Jul-24 46 GSM Cablin...
G-CN-MEP-P2-18400
Wiring for Lighting,Emergency Lighting, Small Power 7 08-Jul-24 14-Jul-24 43 Wiring for...
G-CN-MEP-P2-18420
Cable Laying for Lighting Control 7 08-Jul-24 14-Jul-24 43 Cable Layi...
G-CN-MEP-P2-18430
Structured Cabling for Data Telephone 7 08-Jul-24 14-Jul-24 43 Structured...
G-CN-MEP-P2-18410
Final Connection to Mechanical & Electrical Equipments 6 15-Jul-24 20-Jul-24 43 Final Conn...
3rd Fix 11 22-Jul-24 01-Aug-24 44 01-Aug-24,...
G-CN-MEP-P2-18360
Installation of Wiring Accessories for Switches & Sockets 5 22-Jul-24 26-Jul-24 48 Installati...
G-CN-MEP-P2-18350
Installation of Lighting Control Sensor's 5 25-Jul-24 29-Jul-24 47 Installati...
G-CN-MEP-P2-18380
Installation of Emergency & Exit Lights 6 25-Jul-24 30-Jul-24 43 Installati...
G-CN-MEP-P2-18340
Fixing of Final Fixtures for Lighting 4 26-Jul-24 29-Jul-24 46 Fixing of ...
G-CN-MEP-P2-18390
Installation of GSM Antenna's 5 26-Jul-24 30-Jul-24 44 Installati...
G-CN-MEP-P2-18370
Installation of Smoke/Heat/Sound/Voice Evacuation Speakers Detector's 6 27-Jul-24 01-Aug-24 42 Installati...
Plumbing 7 05-Jul-24 11-Jul-24 70 11-Jul-24,...
1st Fix 6 05-Jul-24 10-Jul-24 70 10-Jul-24,...
G-CN-MEP-P2-18490
Installation of Condensate Drain Pipe 6 05-Jul-24 10-Jul-24 70 Installati...
2nd Fix 7 05-Jul-24 11-Jul-24 70 11-Jul-24,...
G-CN-MEP-P2-18470
Installation of Water Supply, UPVC, 5 05-Jul-24 09-Jul-24 70 Installati...
G-CN-MEP-P2-18480
Installation of Zone Control Valves @ H/L 5 07-Jul-24 11-Jul-24 70 Installati...
3rd Fix 0 0
Roof water proffing 20 06-Jul-24 25-Jul-24 25 25-Jul-24,...
A1430 Roof water proffing 20 06-Jul-24 25-Jul-24 25 Roof water...
Stair Case Finishes 51 17-Jun-24 06-Aug-24 13 06-Aug-24,...
ST01 45 17-Jun-24 31-Jul-24 19 31-Jul-24,...

Page 14 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Civil Works 45 17-Jun-24 31-Jul-24 19 31-Jul-24,...
B-CN-SCF-CO-20580
Plastering Works (including preparation & rush coat) 10 17-Jun-24 26-Jun-24 13 Plastering...
B-CN-SCF-CO-20550
Apply First Coat Paint Walls & Ceiling 8 22-Jun-24 29-Jun-24 23 Apply Firs...
B-CN-SCF-CO-20540
tiles work(landing,riser,steps) 8 28-Jun-24 05-Jul-24 23 tiles work...
B-CN-SCF-CO-20600
Fix door frame 8 06-Jul-24 13-Jul-24 23 Fix door f...
B-CN-SCF-CO-20590
Fix door shutter & iron mongery 7 14-Jul-24 20-Jul-24 23 Fix door s...
B-CN-SCF-CO-20530
Install Hand Rails 8 16-Jul-24 23-Jul-24 19 Install Ha...
B-CN-SCF-CO-20560
Epoxy Painting in Floors 7 22-Jul-24 28-Jul-24 19 Epoxy Pain...
B-CN-SCF-CO-20570
Apply Final Coat Paint to Walls & Ceiling 5 27-Jul-24 31-Jul-24 19 Apply Fina...
MEP Works 19 09-Jul-24 27-Jul-24 23 27-Jul-24,...
Electrical, Lighting Works 19 09-Jul-24 27-Jul-24 23 27-Jul-24,...
2nd Fix 8 09-Jul-24 16-Jul-24 27 16-Jul-24,...
B-CN-SCF-CO-20610
Wiring for Lighting, Fire Telephone, Emergency Lighting 8 09-Jul-24 16-Jul-24 27 Wiring for...
3rd Fix 7 21-Jul-24 27-Jul-24 23 27-Jul-24,...
B-CN-SCF-CO-20620
Fixing of Final Fixtures for Lighting 7 21-Jul-24 27-Jul-24 23 Fixing of ...
B-CN-SCF-CO-20630
Installation of Wiring Accessories 7 21-Jul-24 27-Jul-24 23 Installati...
B-CN-SCF-CO-20640
Installation of Emergency & Exit Lights 7 21-Jul-24 27-Jul-24 23 Installati...
B-CN-SCF-CO-20650
Installation of Fireman Telephone 7 21-Jul-24 27-Jul-24 23 Installati...
ST02 46 22-Jun-24 06-Aug-24 13 06-Aug-24,...
Civil Works 46 22-Jun-24 06-Aug-24 13 06-Aug-24,...
B-CN-SCF-CO-20720
Plastering Works (including preparation & rush coat) 8 22-Jun-24 29-Jun-24 13 Plastering...
B-CN-SCF-CO-20690
Apply First Coat Paint Walls & Ceiling 8 02-Jul-24 09-Jul-24 13 Apply Firs...
B-CN-SCF-CO-20680
tiles work(landing,riser,steps) 8 07-Jul-24 14-Jul-24 13 tiles work...
B-CN-SCF-CO-20740
Fix door frame 8 12-Jul-24 19-Jul-24 13 Fix door f...
B-CN-SCF-CO-20670
Install Hand Rails 10 19-Jul-24 28-Jul-24 13 Install Ha...
B-CN-SCF-CO-20730
Fix door shutter & iron mongery 8 20-Jul-24 27-Jul-24 13 Fix door s...
B-CN-SCF-CO-20700
Epoxy Painting in Floors 8 27-Jul-24 03-Aug-24 13 Epoxy Pain...
B-CN-SCF-CO-20710
Apply Final Coat Paint to Walls & Ceiling 8 30-Jul-24 06-Aug-24 13 Apply Fina...
MEP Works 30 05-Jul-24 03-Aug-24 16 03-Aug-24,...
Electrical, Lighting 30 05-Jul-24 03-Aug-24 16 03-Aug-24,...
3rd Fix 8 27-Jul-24 03-Aug-24 16 03-Aug-24,...
B-CN-SCF-CO-20760
Fixing of Final Fixtures for Lighting 8 27-Jul-24 03-Aug-24 16 Fixing of ...
B-CN-SCF-CO-20770
Installation of Wiring Accessories 8 27-Jul-24 03-Aug-24 16 Installati...
B-CN-SCF-CO-20780
Installation of Emergency & Exit Lights 8 27-Jul-24 03-Aug-24 16 Installati...
B-CN-SCF-CO-20790
Installation of Fireman Telephone 8 27-Jul-24 03-Aug-24 16 Installati...
2nd Fix 8 05-Jul-24 12-Jul-24 30 12-Jul-24,...
B-CN-SCF-CO-20750
Wiring for Lighting, Fire Telephone, Emergency Lighting 8 05-Jul-24 12-Jul-24 30 Wiring for...
Work Inside Shafts - Elec. Room, ELV Room, Tel. Room 33 27-Jun-24 29-Jul-24 21 29-Jul-24,...
MEP - Electrical/ELV 20 27-Jun-24 16-Jul-24 21 16-Jul-24,...
B-CN-WIS-CO-21110
Installation of Cable Tray & Trunking 10 27-Jun-24 06-Jul-24 21 Installati...
B-CN-WIS-CO-21090
Emergency Lighting System Riser 10 07-Jul-24 16-Jul-24 21 Emergency ...
B-CN-WIS-CO-21100
Structured Cable Riser 0 07-Jul-24 07-Jul-24 24 Structured...
Civil Works 23 07-Jul-24 29-Jul-24 21 29-Jul-24,...
B-CN-WIS-CO-21140
Installation of Access Ladders & Misc Metal Works 10 07-Jul-24 16-Jul-24 24 Installati...
B-CN-WIS-CO-21130
Block Works Closing Shaft Areas 10 17-Jul-24 26-Jul-24 21 Block Work...
B-CN-WIS-CO-21150
Plastering works for closed shaft areas 10 20-Jul-24 29-Jul-24 21 Plastering...
Work Inside Shafts in Corridors 54 15-Jun-24 07-Aug-24 43 07-Aug-24,...
MEP - Plumbing 45 15-Jun-24 29-Jul-24 52 29-Jul-24,...
B-CN-WIS-CO-21210
Water Supply Riser Works Up To Roof Floor incl. test 10 15-Jun-24 24-Jun-24 34 Water Supp...
B-CN-WIS-CO-21220
Fire Fighting Riser Works Up To Roof Floor incl. test 10 15-Jun-24 24-Jun-24 35 Fire Fight...
B-CN-WIS-CO-21230
Copper Pipe Works Up To Roof Floor incl. test 10 15-Jun-24 24-Jun-24 87 Copper Pip...
B-CN-WIS-CO-21200
Drainage Riser Works Up To Roof Floor incl. test 10 20-Jul-24 29-Jul-24 12 Drainage R...
Civil Works 44 25-Jun-24 07-Aug-24 12 07-Aug-24,...
B-CN-WIS-CO-21260
Installation of Access Ladders & Misc Metal Works 10 25-Jun-24 04-Jul-24 34 Installati...
B-CN-WIS-CO-21250
Block Works Closing Shaft Areas 10 23-Jul-24 01-Aug-24 12 Block Work...

Page 15 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
B-CN-WIS-CO-21270
Plastering works for closed shaft areas 10 29-Jul-24 07-Aug-24 12 Plastering...
Conveying System (Elevators) 47 02-Jul-24 17-Aug-24 2 17-Aug-24,...
Lift-1-2(passanger & Goods) 43 02-Jul-24 13-Aug-24 6 13-Aug-24,...
Installation 36 02-Jul-24 06-Aug-24 6 06-Aug-24,...
A1350 Handing over to Sub Contractor 0 02-Jul-24 2 Handing ov...
A1360 lift Installlation 36 02-Jul-24 06-Aug-24 6 lift Insta...
Testing & Commissioning 7 07-Aug-24 13-Aug-24 6 13-Aug-24,...
A1390 third Party Testing & Commissioning certificate 7 07-Aug-24 13-Aug-24 6 third Part...
Escalators 47 02-Jul-24 17-Aug-24 2 17-Aug-24,...
Installation 47 02-Jul-24 17-Aug-24 2 17-Aug-24,...
A1400 Handing over to Sub Contractor 0 02-Jul-24 2 Handing ov...
A1410 lift Installlation 40 02-Jul-24 10-Aug-24 2 lift Insta...
Testing & Commissioning 7 11-Aug-24 17-Aug-24 2 17-Aug-24,...
A1420third Party Testing & Commissioning certificate 7 11-Aug-24 17-Aug-24 2 third Part...
External Elevation - Aluminium & Glazing Works 55 15-Jun-24 08-Aug-24 11 08-Aug-24,...
Ground Floor 40 15-Jun-24 24-Jul-24 26 24-Jul-24,...
B-CN-AGW-CO-21930
Framing (Tube)for Door 14 15-Jun-24 28-Jun-24 21 Framing (T...
B-CN-AGW-CO-21910
Framing for Aluminium Windows 14 25-Jun-24 08-Jul-24 11 Framing fo...
B-CN-AGW-CO-21920
WPC Strip Design Clips for frame 14 25-Jun-24 08-Jul-24 11 WPC Strip ...
B-CN-AGW-CO-21960
Aluminium Windows Installation 16 29-Jun-24 14-Jul-24 36 Aluminium ...
B-CN-AGW-CO-21940
Aluminium Windows Installation 16 09-Jul-24 24-Jul-24 26 Aluminium ...
B-CN-AGW-CO-21950
WPC Strip Design frame 16 09-Jul-24 24-Jul-24 26 WPC Strip ...
Mezzanine Floor 29 09-Jul-24 06-Aug-24 13 06-Aug-24,...
B-CN-AGW-CO-22010
Framing for Aluminium Windows 14 09-Jul-24 22-Jul-24 11 Framing fo...
B-CN-AGW-CO-22020
Framing for Aluminium Doors 14 09-Jul-24 22-Jul-24 14 Framing fo...
B-CN-AGW-CO-22030
WPC Strip Design Clips for frame 14 09-Jul-24 22-Jul-24 13 WPC Strip ...
B-CN-AGW-CO-22040
Aluminium Windows Installation 14 23-Jul-24 05-Aug-24 14 Aluminium ...
B-CN-AGW-CO-22050
Aluminium Doors 14 23-Jul-24 05-Aug-24 14 Aluminium ...
B-CN-AGW-CO-22060
WPC Strip Design frame 14 24-Jul-24 06-Aug-24 13 WPC Strip ...
Roof 27 13-Jul-24 08-Aug-24 11 08-Aug-24,...
B-CN-AGW-CO-22070
Framing for Aluminium Windows 14 13-Jul-24 26-Jul-24 12 Framing fo...
B-CN-AGW-CO-22080
Framing for Aluminium Doors 14 13-Jul-24 26-Jul-24 12 Framing fo...
B-CN-AGW-CO-22090
WPC Strip Design Clips for frame 14 13-Jul-24 26-Jul-24 11 WPC Strip ...
B-CN-AGW-CO-22100
Aluminium Windows Installation 12 27-Jul-24 07-Aug-24 12 Aluminium ...
B-CN-AGW-CO-22110
Aluminium Doors 12 27-Jul-24 07-Aug-24 12 Aluminium ...
B-CN-AGW-CO-22120
WPC Strip Design frame 12 28-Jul-24 08-Aug-24 11 WPC Strip ...
Building External Finishes 50 07-Jun-24 26-Jul-24 24 26-Jul-24,...
Elevation-1 40 07-Jun-24 16-Jul-24 24 16-Jul-24,...
B-CN-BEF-CO-22420
External Plaster Works 20 07-Jun-24 26-Jun-24 22 External P...
B-CN-BEF-CO-22400
External Painting Works 20 27-Jun-24 16-Jul-24 24 External P...
Elevation-2 45 12-Jun-24 26-Jul-24 24 26-Jul-24,...
B-CN-BEF-CO-22460
External Plaster Works 20 12-Jun-24 01-Jul-24 24 External P...
B-CN-BEF-CO-22440
External Painting Works 20 07-Jul-24 26-Jul-24 24 External P...
Elevation-3 33 22-Jun-24 24-Jul-24 24 24-Jul-24,...
B-CN-BEF-CO-22500
External Plaster Works 20 22-Jun-24 11-Jul-24 24 External P...
B-CN-BEF-CO-22480
External Painting Works 20 05-Jul-24 24-Jul-24 24 External P...
Elevation-4 34 23-Jun-24 26-Jul-24 24 26-Jul-24,...
B-CN-BEF-CO-22540
External Plaster Works 20 23-Jun-24 12-Jul-24 26 External P...
B-CN-BEF-CO-22520
External Painting Works 20 07-Jul-24 26-Jul-24 24 External P...
Mock Up Works 0 0
Mockup 0 0
Garbage Chute Works 0 0
LPG Installations 0 0
Main Entrance 66 01-Jun-24 06-Aug-24 14 06-Aug-24,...
ME-00001 Civil Work(inclding tiling,Ceiling and paint) 45 01-Jun-24 15-Jul-24 14 Civil Work...

Page 16 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
ME-00002 MEP work 45 11-Jun-24 06-Aug-24 11 MEP work
Miscellaneous/ Other Works 71 28-May-24 06-Aug-24 20 06-Aug-24,...
External MEP works 71 28-May-24 06-Aug-24 20 06-Aug-24,...
G-CN-MSC-CO-57590
Excavation & compaction for buundry wall Foundation 10 28-May-24 06-Jun-24 30 Excavation...
G-CN-MSC-CO-57600
Reinforcement Work for B wall Foundation 12 07-Jun-24 18-Jun-24 30 Reinforcem...
G-CN-MSC-CO-57560
Earth Work 10 19-Jun-24 28-Jun-24 45 Earth Work
G-CN-MSC-CO-57570
Drainage piping 10 24-Jun-24 03-Jul-24 54 Drainage p...
G-CN-MSC-CO-57580
Installation of interlock 12 24-Jun-24 05-Jul-24 45 Installati...
G-CN-MSC-CO-57610
Block & Plaster Work For boundry wall 15 03-Jul-24 17-Jul-24 16 Block & Pl...
G-CN-MSC-CO-57630
Garbage trolley & cycle Stand installation 20 18-Jul-24 06-Aug-24 20 Garbage tr...
G-CN-MSC-CO-57640
Boundry wall Gate 5 18-Jul-24 22-Jul-24 16 Boundry wa...
G-CN-MSC-CO-57620
Paint Work 12 23-Jul-24 03-Aug-24 16 Paint Work
Authority Approvals 129 06-May-24 11-Sep-24 7 11-Sep-24,...
Civil Defense - FLS (Fire Life Services) & LPG 7 20-Aug-24 26-Aug-24 0 26-Aug-24,...
G-AA-00010 Application/ 1st Inspection of DCD 3 20-Aug-24 22-Aug-24 0 Applicatio...
G-AA-00020 Attending/Incorporation of Comments raised by DCD 2 23-Aug-24 24-Aug-24 0 Attending/...
G-AA-00030 Dubai Civil Defense Final Inspection & Approval 2 25-Aug-24 26-Aug-24 0 Dubai Civi...
DU/Etisalat 19 11-Aug-24 29-Aug-24 20 29-Aug-24,...
G-AA-00040 DU/Etisalat 1st Inspection 5 11-Aug-24 15-Aug-24 20 DU/Etisala...
G-AA-00050 Attending Comments & Apply for Re Inspection 9 16-Aug-24 24-Aug-24 20 Attending ...
G-AA-00060 DU/Etisalat Final Inspection & Approval 5 25-Aug-24 29-Aug-24 20 DU/Etisala...
Drainage - DM 129 06-May-24 11-Sep-24 7 11-Sep-24,...
G-AA-00070 Obtain Cost Estimate from Authority 40 06-May-24 14-Jun-24 12 Obtain Cos...
G-AA-00080 Payment of Estimate to Authority by Client 35 15-Jun-24 19-Jul-24 12 Payment of...
G-AA-00090 Dubai Muncipality Inspection (1st Inspection) 10 20-Aug-24 29-Aug-24 7 Dubai Munc...
G-AA-00100 Incorporate Dubai Muncipality Comments 10 30-Aug-24 08-Sep-24 7 Incorporat...
G-AA-00110 Approval of Final Inspection Chamber 3 09-Sep-24 11-Sep-24 7 Approval o...
Water Supply - DEWA 118 09-May-24 03-Sep-24 0 03-Sep-24,...
G-AA-00120 Submission of Design Drawings by Consultant to DEWA 4 09-May-24 12-May-24 14 Submission...
G-AA-00130 Approval of Design Drawing by DEWA 4 13-May-24 16-May-24 14 Approval o...
G-AA-00140 Preparation & Submisssion of Shop Drawings to DEWA 7 17-May-24 23-May-24 14 Preparatio...
G-AA-00150 Approval of Shop Drawings from DEWA 10 24-May-24 02-Jun-24 14 Approval o...
G-AA-00160 Obtain Cost Estimate from DEWA 10 03-Jun-24 12-Jun-24 14 Obtain Cos...
G-AA-00170 Payment of Estimate to DEWA by Client 5 08-Jun-24 12-Jun-24 14 Payment of...
G-AA-00180 Application for Issue of Water Meters to DEWA 7 13-Jun-24 19-Jun-24 14 Applicatio...
G-AA-00190 Delivery of Main/Sub Water Meters by DEWA 40 20-Jun-24 29-Jul-24 14 Delivery o...
G-AA-00200 Installation of Main/Sub Water Meters 7 30-Jul-24 05-Aug-24 14 Installati...
G-AA-00210 Application/ First Inspection by DEWA 4 06-Aug-24 09-Aug-24 14 Applicatio...
G-AA-00230 Incorporation of Comments raised by DEWA 7 10-Aug-24 16-Aug-24 14 Incorporat...
G-AA-00220 Submission of Temporary DM Approval to DEWA for approval of Water Supply 5 12-Aug-24 16-Aug-24 17 Submission...
G-AA-00240 2nd Inspection/Approval by DEWA 3 17-Aug-24 19-Aug-24 14 2nd Inspec...
G-AA-00250 Final Inspection & Operational Water Supply by DEWA after DM BCC 1 03-Sep-24 03-Sep-24 0 Final Insp...
LV - DEWA 43 23-Jul-24 03-Sep-24 0 03-Sep-24,...
Permanent Power 43 23-Jul-24 03-Sep-24 0 03-Sep-24,...
G-AA-00260 Application for Inspection of Substation & RMU Room by Consultant to DEWA 2 23-Jul-24 24-Jul-24 8 Applicatio...
G-AA-00270 1st Inspection of Substation & RMU Room 2 25-Jul-24 26-Jul-24 8 1st Inspec...
G-AA-00280 Incorporation of Comments raised by DEWA 2 27-Jul-24 28-Jul-24 8 Incorporat...
G-AA-00290 2nd Inspection/Approval of Substation & RMU Room 2 29-Jul-24 30-Jul-24 8 2nd Inspec...
G-AA-00300 Obtain Cost Estimate from DEWA to Consultant 1 31-Jul-24 31-Jul-24 8 Obtain Cos...
G-AA-00310 Payment of Estimate to DEWA by Client 1 01-Aug-24 01-Aug-24 8 Payment of...
G-AA-00320 Delivery & Installation of Transformers & HV Works by DEWA 18 02-Aug-24 19-Aug-24 8 Delivery &...
G-AA-00330 Application/ 1st Inspection of LV Installation - Electrical Installations by Consultant to DEWA 2 20-Aug-24 21-Aug-24 8 Applicatio...
G-AA-00340 Attending/Incorporation of Comments raised by DEWA 2 22-Aug-24 23-Aug-24 8 Attending/...

Page 17 of 18 TASK filter: All Activities


© Oracle Corporation
l PROJECT. Proposed G M Roof Commercial Building,Shopping Centre on Plot No.597-1186 at DIP Dubai

Activity ID Activity Name Original Start Finish Total Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024
Duration Float
Jan Feb Mar Apr May Jun Jul Aug Sep Oct
G-AA-00350 Application/ 2nd Inspection of LV Installation - Electrical Installations by Consultant to DEWA 2 24-Aug-24 25-Aug-24 8 Applicatio...
G-AA-00380 Receipt/ Release Of Permanent Power from DEWA 1 03-Sep-24 03-Sep-24 0 Receipt/ R...
DDA-Completion Certificate 7 27-Aug-24 02-Sep-24 0 02-Sep-24,...
G-AA-00420 DDA-Building Completion Certificate (1st Inspection) 2 27-Aug-24 28-Aug-24 0 DDA-Buildi...
G-AA-00430 Incorporate DDA Comments 2 29-Aug-24 30-Aug-24 0 Incorporat...
G-AA-00440 Final DDA Inspection 2 31-Aug-24 01-Sep-24 0 Final DDA ...
G-AA-00450 Issuance of Building Completion Certificate by DDA 1 02-Sep-24 02-Sep-24 0 Issuance o...
Testing & Comissioning 13 04-Sep-24 16-Sep-24 0 16-Sep-24,...
Electrical/LV/ELV Systems 13 04-Sep-24 16-Sep-24 0 16-Sep-24,...
G-TC-00010 Electrical/ LV Testing & Commissioning 13 04-Sep-24 16-Sep-24 0 Electrical...
G-TC-00020 ELV System Testing & Commissioning 13 04-Sep-24 16-Sep-24 0 ELV System...
Plumbing 13 04-Sep-24 16-Sep-24 0 16-Sep-24,...
G-TC-00040 Fire Fighting System Testing & Commissioning 13 04-Sep-24 16-Sep-24 0 Fire Fight...
G-TC-00050 Plumbing System Testing & Commissioning (including water tank & water system) 13 04-Sep-24 16-Sep-24 0 Plumbing S...
Other Systems 13 04-Sep-24 16-Sep-24 0 16-Sep-24,...
G-TC-00070 BMU Testing & Commissioning 13 04-Sep-24 16-Sep-24 0 BMU Testin...
G-TC-00080 Garbage Chute Testing & Commissioning 13 04-Sep-24 16-Sep-24 0 Garbage Ch...
G-TC-00090 Lift System Testing & Commissioning 13 04-Sep-24 16-Sep-24 0 Lift Syste...
Handover Procedure 38 13-Aug-24 19-Sep-24 0 19-Sep-24,...
G-HP-00050 Snagging & Desnagging Works-Ground Floor 25 13-Aug-24 06-Sep-24 9 Snagging &...
G-HP-00010 Snagging & Desnagging Works- Mazzanine & Roof 20 20-Aug-24 08-Sep-24 5 Snagging &...
G-HP-00020 As-Built Dossiers, O&M Manuals 5 09-Sep-24 13-Sep-24 5 As-Built D...
G-HP-00060 Final Demobilisation of staff & site setup (including laydown area) 2 09-Sep-24 10-Sep-24 6 Final Demo...
G-HP-00070 Final Site Cleaning 2 17-Sep-24 18-Sep-24 0 Final Site...
G-HP-00080 Project Handing Over 1 19-Sep-24 19-Sep-24 0 Project Ha...