BEAM DETAIL

COL. HOOPS & COL. TIES


REFER TO TYPICAL COLUMN
DETAIL & COLUMN SCHEDULE

0.30 L 0.40 L 0.30 L


SPLICE ONLY WITHIN THIS ZONE TIE BEAM
SECTION SECTION SECTION
AT SUPPORT AT MIDSPAN AT SUPPORT
STIRRUPS
50
75

STRAIGHT BARS LS
TOP & BOTTOM
CUT/EXTRA BARS
TOP & BOTTOM REFER TO TYP
SPLICING DETAIL
FOR BEAMS

NGL
FOOTING DEPTH

SUBGRADE COMPACTED
COLUMN TO 90% OF MAXIMUM
L , CLEAR SPAN OF TIE BEAM
DRY DENSITY @ OPTIMUM
MOISTURE CONTENT
THK

FOOTING
100

JOINT HOOPS COMPACTED GRAVEL


REFER TO TYPICAL COLUMN BEDDING (TYP.)
DETAIL & COLUMN SCHEDULE

W W

# TOP BARS # TOP BARS


H H
# BOTTOM BARS # BOTTOM BARS

SECTION AT SUPPORT SECTION AT MIDSPAN


VERTICAL BARS AS PER COLUMN SCHEDULE
COLUMN TIES
SEE SLAB ON
AT SUPPORTS AT MIDSPAN STIRRUP STIRRUP WEB BARS REMARKS GRADE DETAILS 40
BEAM BEAM
TYPE SPACING ON BEAM SIDES
DESIGNATION W H TOP BOTTOM TOP BOTTOM NGL

FTB1 200 350 2-Ø16 2-Ø16 2-Ø16 2-Ø16 - - BEAM


FOOTING DEPTH

50
700

STIRRUP SPACING:
A - 10mm∅ STIRRUPS: 1 @ 50, 4 @ 100, 4 @ 150, REST @ 200 TO MID SPAN
75

SCHEDULE OF TIE BEAM REINFORCEMENT


100

75 COMPACTED GRAVEL
BEDDING (TYP.)
JOINT HOOPS
AS PER COLUMN SCHEDULE