Risk Assessment: Act/Hse/Ra 001: Use The Risk Score Calculator To Determine The Level of Risk of Each Hazard

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

HEALTH SAFETY AND ENVIRONMENT Author: Approved:

Issued: Rev. Date:


RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with mobile crane
Revision: 0

RISK SCORE CALCULATOR Project Name: xxx


Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls RA Ref No.: xxx
What w ould be the
CONSEQUENCE Frequent/Almost certain (5) Rarely (1) Can the hazard be Elim inated or removed
Continuous or will happen
Often (4) Likely (3) Possible (2) Less than once every 5 RA compilation
of an occurrence be? 6 to 12 times a year 1 to 5 times a year Once every 5 years from the w ork place? Review date:
frequently years Date:
Catastrophic (5) Can the product or process be substituted for Date:
High 25 High 20 High 15 Medium 10 Medium 5
Multiple Fatalities a less hazardous alternative?
Serious (4) Can the hazard be engineered aw ay w ith
High 20 High 16 High 12 Medium 8 Low 4 Compiled by:
Class 1 single fatality guards or barriers?
Moderate (3)
Can Adm inistration Controls be adopted
Class2 (AWI or LTI) or Class 1 High 15 High 12 Medium 9 Medium 6 Low 3 Reviewed by:
Permanently disabling effects
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work Medium 10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipm ent & Approved by:
restrictions. MTI Clothing be w orn to safe guard against
Insignificant (1) hazards?
FAI
Medium 10 Medium 4 Low 3 Low 2 Low 1
Overall Task Details Relevant Applicable MAS:
Additional Training required: NOC’s Required for task:
 01412 – Lifting Operations;
Lifting operations using mobile crane within site boundary
 00941 – Lifting equipment Riggers / Slingers

Specific Task Step Initial Risk


Additional Control
No (In sequence of Hazard Details Consequence/Risk Rating Control Measures Residual Risks RR
Measures
works) P S RR
i. All cranes to be Third Party Certificated by a DM approved inspector,
 Unauthorized operation of the mobile
documentation available on arrival to site;
crane resulting in incident;
Crane checks on Documentation
12 ii. Operators to have in-date Third Party certificate by approved body, Crane quarantined until
1 arrival to site  Use of mobile crane  Failure due to use of un-certificated 3 4 unavailable for Low
HIGH available for review on arrival to site; evidence provided
crane; review
PRIOR TO USE iii. Crane load indicator to be installed and functioning correctly;
iv. Visual inspection of crane undertaken by competent person;

i. Worker pedestrian routes to be designed and implemented with clear


 Collision with plant or vehicles and
signage to provide segregation;
live traffic;
Access of crane to ii. Instruction to workers at induction on use of access routes around the Workers not
 Plant and workers in  Workers struck by plant, very high
2 work areas project; complying with Regular topic in TBT’s Low
same working area; risk of fatality; flagmen
iii. Flagmen to be used to control crane movements;
 Uncontrolled crane reversing;
iv. The Logistics plan shall clearly illustrate crane access and egress points;

 Overturning due to incorrect siting or


incorrect outrigger extension; i. Ensure crane is set up/rigged out correctly, is on firm level ground as per
crane plan with outriggers fully extended; Unable to fully Lift revised, crane moved to
 Working in proximity  Collision with overhead services;
Siting and setting up of 12 ii. Solid barriers should be situated, where practicable, to protect crane from extend outriggers new area;
3 to existing structures 3 4 Low
High traffic routes around working radius of cab; due to restrictions
crane and services;  Blocking access routes; Crane never used without full
in area
 Load striking moving and/or iii. Consideration given to overhead services and existing structures when outrigger extension
stationary structures; siting crane;

i. ATC Minimum Acceptable Standard ATC/OHS/MAS/00941 to be adhered


to at all times;

Lifting of equipment  Incident due to use of defective ii. Lift Plan to be completed prior to any lift taking place by crane supervisor Machine
Machine isolated and
 Operator competency; lifting gear / equipment; and engineer; breakdown
and material quarantined until repaired.
20 iii. Ensure all lifting tackle and equipment have valid test certificate before
4  Lift planning;  Crane collapse due to lifting loads 4 5 Low
HIGH use (6 monthly 3 rd party inspections);
(Mobile crane beyond SWL; Spoil removed and treated as
Hydraulic fluid spill
Operator) iv. Method statements and risk assessments to be submitted and adhered to hazardous waste
 No crane documentation in place;
for technical and/or non-routine lifts;
v. Crane load indicator to be functioning correctly, and not to be overridden
under any circumstances;

Page 1 of 2 HSEQ -Rev-01(Aug-2018)


HEALTH SAFETY AND ENVIRONMENT Author: Approved:

Issued: Rev. Date:


RISK ASSESSMENT: ACT/HSE/RA 001 Lifting Operations with mobile crane
Revision: 0

Specific Task Step Initial Risk


Additional Control
No (In sequence of Hazard Details Consequence/Risk Rating Control Measures Residual Risks RR
Measures
works) P S RR
vi. Operator to adhere to crane safe working load limits , weight of load and
COG established before lifting;

i. Lift controlled by designated trained rigger/banks man using approved


 Persons underneath load struck by
hand signals only;
materials;
ii. No personnel situated or walking under elevated loads, avoid over-
 Load swinging / spinning
 Lifting operations sailing of personnel if practicable; Work stopped, area cleared
uncontrolled;
around workers; iii. No over-sailing of loads over live traffic routes without road closure; Incident – falling and full investigation
 Falling materials; 20 materials undertaken
5 Crane supervision  Workers in crane 4 5 iv. No lifts undertaken when wind speed exceeds 40kph; Low
operating radius;  Damage to lifting slings from sharp High
edges; v. No blind lifts without visual and communication aids, radios etc.;

 Over-sailing of material over live vi. Tag lines shall be used to guide materials while lifting, 2 lines minimum
10m in length;
traffic routes;
vii. Slings protected from sharp edges with rubber etc.;
 High winds – adverse weather;
viii. Riggers to undertake visual inspection of all lifting equipment daily;

i. Only trained and competent mechanics to attempt any repairs on mobile


cranes, including engine, hydraulics, lifting mechanism, rams etc.;

 Untrained staff attempting repairs; ii. If any breakdowns occur, regardless of management pressure, the crane
shall be isolated, locked and plant department informed of the breakdown;
 Inadequate and unsafe repairs,
resulting in failure of equipment; iii.Machine barriered off if in risk areas such as access routes, traffic routes
Crane Maintenance etc. If on live traffic routes advanced warning vehicle to be mobilized;
6  Injury to operatives; 3 4 12 Low
(revised 06-06-2018)  Injury to mechanics undertaking
repairs; iv. Mechanics shall be advised of time, activity and nature of breakdown;
v. Under no circumstances shall temporary repairs be undertaken on any
mobile crane;
vi. During repairs under no circumstances shall workers be placed at risk by
pinch points, crush area, high pressure release or moving parts;

Page 2 of 2 HSEQ -Rev-01(Aug-2018)