Professional Documents
Culture Documents
Annexure 8 Buycon9.nlci - KNPRNGR
Annexure 8 Buycon9.nlci - KNPRNGR
Note: Any specifications /Datas as furnished in this Annexure are prepared based on the available information.
If any discrepancy is observed in later stage, it will be corrected by NUPPL and the same will be binding on
the contractor.
All the three units of the power plant are identical. The plant & equipment comprise of the following:
1. Plant water systems including raw water intake system.
2. Boilers and auxiliaries including SCR and ammonia storage and handling system.
3. Turbine Generators and auxiliaries system.
4. Plant Air compressor system.
5. Ash handling (Both bottom and fly ash) system.
6. Coal Handling System.
7. 765KV,400KV,132KV GIS and associated AIS portion of switchyard.
8. Electrical System.
9. Control and instrumentation system.
10. DG, DC & UPS system.
11. Waste Water Treatment System (Effluent Treatment system).
12. Fire-fighting system.
13. Air Condition and Ventilation System.
14. Hydrogen Generation Plant.
15. Sewage Treatment system.
Page 1 of 159
PLANT WATER SYSTEM
RAW WATER SYSTEM:
Raw water for the plant will be taken from West Allahabad branch canal near Bidhnu, Kasba village adjacent
to NH-86. Raw water from the Allahabad branch canal (ie., from Intake well) is delivered to raw water
Reservoir through Water conveyance system. Raw water from the reservoir is taken to inclined plate filter for
the pretreatment through the raw water pump house. Specific water consumption (SWC) shall be maintained
as < 3.0 m3/hr per MWHR in the plant as per the guidelines specified in Central Pollution Control Board
(CPCB) & Minister of Environment MOEF norms.
Six numbers of raw water Vertical turbine type intake pumps, (4W+2S) each with capacity of 2250 m3/hr and
2 x 1100 NB (Twin line Ductile iron pipe) with the total length of the pipe is 44.6 km (approximately). The
reservoir is designed for effective capacity of 4600000 m3 with minimum 30 days approximately for 3 x 660
MW.
Power supply for this system is taken from UP Discom at 11KV level. Power supply availability subject to UP
Discom schedule. O&M Service Provider shall take care of the operation of Raw water pump house
accordingly including scheduling assistance.
PRE TREATMENT:
The raw water (river water) will be treated in the pre-treatment plant mainly to remove physical
impurities like colour, turbidity & organic matter to meet the quality requirement of feed water to DM
plant, cooling water make up, plant service and potable water.
Three numbers of raw water pumps (2W+1S) each with capacity 2900 m3/hr and Three numbers of
AHP make up pumps (2W+1S) each with capacity 1500 Cum/hr. The raw water from the raw water
reservoir will be pumped to twelve (12) nos. (9W+3S) of Rapid Gravity Filters (RGF) each of net
capacity 630 cmh/hr and also provided with four numbers of Service water pumps (3W+1S) each with
capacity 290 Cum/hr.
The filtered water from the rapid gravity filter shall be collected in filter water reservoir and fire water
reservoir. Total Filter water reservoir storage capacity of 12000 cmh/hr (Each compartment 6000
cmh/hr) which will satisfy the 2 hrs of requirement. From the filtered water reservoir, water will be
pumped to other services such as cooling tower makeup, service water, plant potable water, colony
potable water, UF-RO-MB Plant, APH/ESP wash pumps,Filter back wash pumps, FGD make up
pumps etc.
To prevent bio-fouling in raw water, potable water and cooling water, chlorine dioxide is envisaged at
two locations. One at raw water reservoir area and other at CW pump house area.
Cooling tower make ups of capacity 3000 m3/hr (2W+1S) and CT Blow down is fed to Ash water tank
and CMB.
The portable water is pumped to all users after dosing of chlorine for disinfecting purposes. The
capacity of each potable water pump is 10 m3/hr (1W+1S), Colony Potable water pump capacity 50
m3/hr (1W+1S). APH/ESP Wash pumps capacity 300 m3/hr (2W),Filter Back wash pumps capacity
565 m3/hr (2W+1S),FGD make up pumps capacity 150 m3/hr (3W+1S) and UF RO MB Feed pumps
capacity 110 m3/hr (2W+1S),
Page 2 of 159
D.M.PLANT:
Water treatment (UF-RO) Scheme:
The Filtered water from Rapid Gravity Filter will be passed through basket strainer by UF feed pump to
remove the turbidity and suspended solids particle size <150 micron in the filter water so that the same
can be feed into Ultra filtration unit for further treatment. Ultra-Filtration mainly removes physical
impurities like colour, turbidity, and organic matter (COD) to meet the required feed water quality for
Reverse Osmosis (RO) unit. UF permeate will be stored in UF permeate water storage tank for further
treatment. UF backwash will be collected in the trench and will be routed N-Pit where the same will be
routed to Ash Water tank for further use. The UF permeate water will be pump to Cartridge Filter
through RO feed pump to remove particle size lesser than 5 microns. Before cartridge filter, Sodium
bisulphate will be dosed to remove residual chlorine. Antiscalant will be dosed to avoid fouling of RO
membranes. Acid dosing provision also provided to have LSI correction. If the quality of cartridge
outlet is acceptable to RO units, the same will be passed to the RO high pressure pump inlet wherein
the Filtered pressure will be increased more than the osmotic pressure required by the RO membrane to
get the required permeate recovery (80%). The reject water will be collected in N-pit and disposed off
to ash water tank for final disposal. Permeate will be routed to Degasser Tower to remove the dissolved
gases present in the permeate and collected in Degassed water storage tank. The Desagged water will
used for DM plant feed for further treatment.
The DM Plant will be having three streams of Mixed Bed (MB) with 55 m3/ hr net capacity of MB
Unit 3 x 50% (2W+1S).
200 m3/hr
Basket Strainer
200 m3/hr
Ultra-Filtration waste
180 m3/hr
UF Permeate Tank (200 m3)
180 m3/hr
Cartridge Filter
180 m3/hr
Page 3 of 159
RO High Pressure Pump
180 m3/hr
Reverse Osmosis Neutralization pit
180 m3/hr
Degassed Water Tank (140 m3)
DM Transfer Pumps
CW SYSTEM:
Technical process of circulating water system is as follows:
Circulating water pump with butterfly valve (MOV)
CW supply line
Condenser coolers
CW return line
Coarse screen
Page 4 of 159
ACW SYSTEM:
Technical process of Auxiliary cooling water system is as follows:
Coarse screen
NRV &
BFV(MOV)
CW return line
Page 5 of 159
Auxiliary cooling water pumps
1x100% TMCR vertical mixed flow pumps will be installed for each unit & 1 no of same capacity for
common stand by for all units (Totally 3W+1S); The type and performance of Auxiliary cooling water
pump is as follows:
NRV & Motor operated butterfly valve will be provided for outlet pipes of each Auxiliaries cooling
water pumps.
TECHNICAL DETAILS:
Manufacturer OEM : M/s L&T MHI Boiler Private Limited ,India
Rated Steaming capacity : 2100 t/h (BMCR)
Quantity : 3 Nos. (For 3x 660 MW units)
SH outlet steam pressure/ Temperature : 256 kg/cm2(a) / 568 °C
Rated RH steam flow : 1639.9 t/h (BMCR)
Rated steam pressure/Temp at RH inlet :57.32 kg/cm2 (a)/338 °C (BMCR)
Rated steam pressure/Temp at RH outlet : 55.35 kg/cm2 (a)/ 596 °C ( BMCR)
Feed water temperature at Eco inlet : 299.18 °C (BMCR)
Page 6 of 159
Exit gas temperature corrected : 126 °C (at the outlet of APH)
Hot primary air temp at RAPH outlet : 301 °C
Cold air temperature at RAPH inlet : 35 °C
Boiler Efficiency (HHV) : 88.8 % (BMCR Design coal)
Boiler coal consumption calculated : 419.3 TPH (design coal) (BMCR)
Coal pulverizing system is a direct fired pulverized fuel type with raw coal stored in coal bunkers,
transferred to mill by coal feeders. Primary air fan supplies hot air as medium for drying and
transporting to pulverizer. The Primary air Fan will blow the cold air into air preheater. The hot
Primary air from air preheater will mix with cold primary air to maintain the mill outlet temperature 65
~ 85 °C. The mill outlet pulverized coal will be transferred into burners through pulverized coal pipes.
Two sets of seal air fan per boiler will be used to seal mill, coal feeder and pneumatic shutoff gate on
pulverized coal pipes.
Page 7 of 159
Motor Rating : 37 KW
Coal feeder:
Type : Gravimetric belt type
Number of furnished : Eight (8)
Model : 36-RR-VB-SP
Make :Stock Redler India Pvt Ltd
Rated Capacity : 10.7 ~107 t/h
Motor Speed :1440 RPM
Motor : 5.5 KW & (0.37 KW for clean out conveyor)
Number of Coal feeder / Unit :8
Four coal pipes from each pulveriser split into eight pipes and are used to transport the coal to the eight
burners Pulverized coal pipes and bends are designed to prevent abrasion. The bends will be lined with
ceramic liners for wear protection. Pneumatically operated gates will be provided in coal pipes.
Pulveriser Orifices are installed on each coal pipe local to the pulveriser to achieve coal flow balancing.
Victaulic couplings is provided to take care of the thermal expansion movement.
Electrostatic Precipitator :
Dust emission concentration of the gas in the chimney will be less than 30mg/Nm3. The capacity of the
precipitator is based on 25% excess air, 15% AH leakage and 2% duct leakage.
Model : FPA-9X48M-128-147-A2.
Make : GE Power India Ltd.
Number of Pass :6
Number of field/Pass :9
Number of Ash Hoppers : 108 Numbers (with each 4 Tubular type heaters)
Inlet flue gas temperature : 140 & 123 °C (Design & guarantee condition)
Dust concentration at outlet : ≤ 30 & 18 mg/Nm3 (Design & guarantee)
De-dusting Efficiency : ≥ 99.96 & 99.97% (Design & guarantee condition)
Page 8 of 159
Volume flow : 266.67 m3/s
Static Pressure : 429 mmWC
Speed :990 RPM
Motor Rating :1602 KW
Fan Bearing : NDE Radial, Thrust bearing and DE Radial Bearing.
Control Oil Pumps : 2 X 100%
Lubricating Oil Pumps : 2 X 100%
RAPH High pressure water Washing Pump (2 X 100% common for All Units)
Type : Reciprocating pump 3 cylinders
Model : TG 8045
Make : Flow More Ltd
Capacity : 9 m3/Hr
Page 9 of 159
Pressure : 210 Kg/Cm2(g)
Pump Speed : 365 RPM
Motor Capacity : 120 HP
Water Separator :
Type : Vertical Cylindrical type
Number of furnished Water Separator : Two (2) sets
Water Separator drain tank : One (1) set
Page 10 of 159
Type : Single stage vertical Non Clog Sump pump
Model : 5414 A AWS 150 X 150
Make : Flow More Ltd
Capacity : 500 m3T/Hr
Head : 30 m
Motor Speed : 1480 RPM
Motor Rating : 75 KW
Bidder shall comply with all operation and maintenance requirements of OEM as per their O&M
manual requirements.
Ignitor
Page 11 of 159
Type :High Energy electric Arc (HEA) Spark
Number of furnished :Thirty two (32) sets besides oil burners (8 corners x 4 elevations)
Bidder shall comply with all operation and maintenance requirements of OEM as per their O&M
manual requirements.
SAFETY VALVES:
Water separator out let:
Numbers :4
Make : FUKUI SEISAKUSHO Co Ltd
Type : SL 1053-C3-H1(T)
Set Pressure :313.3 /311.8/310.3/308.8 bar A
Reliving capacity :412.7 /410.7 /408.8/406.8 T/Hr
RE Heater In let:
Numbers :4
Make : FUKUI SEISAKUSHO Co Ltd
Type : SL 633-M2(T)
Set Pressure :70.1/ 72.2 Ksc(g)
Reliving capacity :404.1/ 469.4T/Hr
Page 12 of 159
Type : PCV673-CA-(AR)
Set Pressure :65.6 Ksc(g)
Reliving capacity :232.9 T/Hr
DeNox system:
• Selective catalytic reduction (SCR) system (MHPS make) is envisaged in this project to
control NOx emission within MOEF norms of 100 mg/Nm3.
• 2x 60% SCR reactor housing with each 3 initial + 1 Future layer of plate type catalyst
• Rake type soot blower,
• 2 streams of AIG (Ammonia injection grid) and AFCU (Ammonia flow control unit),
• 2 x100% dilution air fan,
• Reagent for SCR system is Anhydrous ammonia.
Ammonia storage and handling unit (CECO Environmental India) common for 3 boilers
comprises of
• Unloading arm,
• 2 x 100% Unloading compressor (1W+1S), Blakmer (USA) make(HD 362), 11
KW/1440 flame proof motor,34.5 am3/Hr liquid transfer vapour recovery option
• 2 x 100% NH3 storage tank, 220 m3 each/Design pressure 22.86 Ksc(g)
• 2 x 100% Vapourizer (1W+1S),
• 3 Nos Accumulator,
• Waste Ammonia dilution tank,
• Retaining basin with 2 x 100% sump pump which pump drain to ETP,
• NH3 leakage detectors with sprinkling systems,
• Fire fighting system, Eye wash shower.
Design criteria: (At 100% BMCR Design coal)
• Inlet gas temperature – 328.5 Deg C
• Flue gas flow – 2642 TPH
• SCR Inlet Nox - 492mg/Nm3 @ 6% O2 dry basis
• SCR outlet NOx – 100mg/Nm3 @ 6% O2 dry basis
• NH3 slip – Not more than 2 ppm @ 6% O2 dry basis
• Catalyst life – 16000 hours
Unloading of Anhydrous ammonia from truck based on requirement, catalyst sampling and sending it
to lab to know about its remaining life, catalyst addition/ replacement based on catalyst management
plan and sample test results, Catalyst waste management, Maintaining NOx limit within MOEF norms,
NH3 slip within prescribed level are minimum part of O&M activity. Bidder shall comply with all
operation and maintenance requirements of OEM as per their O&M manual requirements.
MRHS Compressors:
Installed Quantity : 3 Numbers
Make : H.V Equipments Pvt.Ltd
Model : T-BTD-RM (Skid mounted)
Type : Reciprocating ,Balanced Opposed piston, Two Stage, Double acting
Page 13 of 159
Delivery pressure : 7.0 Ksc (g)
FAD Capacity : 23.44 M3/Min
Motor rating : 165 KW (3.3 KV)
CCCW system uses demineralized water as working medium. Because of this corrosion of the cooling
equipments decreases & heat exchange efficiency increases. It avoids the jamming of flow path thereby
increasing reliability & reducing the maintenance time. Two (2x100%) CCCW pumps & two (2x100%)
water-water plate heat exchangers are installed in CCCW system for SG & Auxiliaries, Plant air
compressors, MRHS and for AHP compressors.
OCCW system takes water from CW system, which is filtered by electrical strainer followed by an
increase in pressure by pressure pumps. After cooling the equipments the return line is connected to the
CW return pipe system.
SG CCCW System:
Equipment cooling water system comprising of overhead tank, NaOH dosing system, 2 X 100%
DMCW pumps (1 W + 1S) , 2 X 100% PHEs ( 1 W + 1 S) for cooling of auxiliaries in SG area viz.
lube & Hydraulic oil coolers of FD,PA, ID fans , RAPH lube oil coolers, BCP motor & Purge cooler,
Pulverisers lube oil & Journal oil coolers, Plant Air compressors system, MRHS compressors system
and AHS compressors system ,sample coolers and water cooled Access doors etc.
The DMCW in PHE is cooled by the Auxiliary Cooling water circulated by means of ACW pumps
located in CW pump house.
PHE Details:
Make / Model : Tranter India Pvt Ltd / GTP-310-L-6PR-313
Qty per unit : 2 nos. ( 1 W + 1 S)
Heat Load : 7622100 K cal/Hr
Flow Rate : ACW – 1760 m3/hr ; DMCW 941 m3/hr
No. of plates per PHE : 313
Total Heat transfer area :339 m2
SG package Elevators:
Following elevators are envisaged in Stem Generator Area:
Page 14 of 159
Motor Power : 22 KW
Battery Back up : 17 AH (12 V)
Make :Techno Industries Limited
Total Travel : 79.3 m
The unit AST PRDS comprises of One High Capacity pressure reducing control valve with separate
desuperheater (HCPRDS), One Low Capacity pressure reducing valve (LCPRV) and one motor
operated pressure reducing valve with full capacity on the bypass line of LCPRV.
Page 15 of 159
When boiler start up and Main steam line parameters meet the requirement of auxiliary steam, then the
main steam will supply the auxiliary steam (maximum of 130T/Hr). During normal service of the unit,
the CRH steam will supply the auxiliary steam (maximum of 43 T/Hr) with separate pressure and
temperature control valves.
Page 16 of 159
SG & Auxiliaries LIST OF Cranes available for 3 Units
Sl. No LOCATION Capacity Lift SPAN Quantity Type
MILLS -Single
1 30 T 12.09 2.9 12 Electric
Girder U/S Crane
Plant Compressor
2 House- single 5T 7.23 M 16.5 M 1 Electric
girder EOT crane
Fuel Oil Pump
3 House Single 5T 4.9 M 10 M 1 Manual
Girder U/S Crane
Page 17 of 159
Guaranteed Condenser pressure at VWO, 33 °C CW temperature : 62.378 mm Hg (a)
Guaranteed heat rate at 100% TMCR : 1781.2 kcal/kwh
Feed water extraction system : 3 HP heaters + 5 LP heaters + 1 Deaerator
STEAM TURBINE
The 3000-rpm steam turbine is composed of one HP, one double flow IP cylinder and two double-flow
LP cylinder. The HP cylinder is equipped with 2 admission chests; each comprises a main stop valve
and a control valve. IP cylinder has 2 main stop valves and 2 control valves located also in two
symmetrical chests. Overload valves are provided as an integral part of HP stop/control valves.
The superheated steam conditions (during 100% TMCR guarantee condition ) at the turbine inlet are:
HPT Inlet: P = 247 kgf/cm2 (a), T = 565 °C, m = 1878.22 T/h,
IPT Inlet: P = 50.512 (a), T = 593 °C, m = 1545.75 T/h
Turbine VWO capacity : 2023.27 t/h (TMCR)
Condenser
Main Condenser
➢ Single pass, dual pressure, water cooled condenser accepting steam from two LP Turbine
modules.
➢ The plant is designed to operate continuously at 105% TMCR load (VWO condition) and 1%
makeup with a design cooling water temperature of 33°C
➢ Design CW flow : 74,550 TPH
➢ CW temperature rise : 8.47 °C
➢ Total No. of Tubes : 22260 each in HP & LP Condensers.
Page 18 of 159
➢ Total Heat Transfer area : 25169.73 m2 per HP & LP Condenser.
➢ Tube material : A 249 TP 304
Page 19 of 159
Condensate Extraction Pump
➢ Three (3x50%) vertically installed, motor driven condensate pumps ( 2 W + 1 S)
➢ Each pump discharge has a recirculation line to the condenser. A common recirculation line is
also provided downstream of the gland steam condenser.
❖ Make / Model : KSB Pumps Ltd . / WKTB 8/1+4
❖ Type : Vertical , Centrifugal, Double suction, Canister type
❖ Rated Flow / TDH : 771 m3 / hr , 308 mwc
❖ Motor rating : 1230 kW
Page 20 of 159
o One (1) Acid Measuring tank
o Two (2 x 100%) Acid (HCL) Dosing pump
o One (1) Alkali Preparation cum Measuring tank
o Two (2 x 100%) Alkali Dosing Pump
o One (1) Alkali diluent water heating tank (Hot water tank) with (2x50% heaters)
➢ Resin
❖ Anion : 900S04 , 3065 litres per vessel
❖ Cation : 1500H, 4600 litres per vessel
❖ Inert : 600i litres per vessel
➢ Supplier : BGRE
Deaerator
➢ Manufacturer : Sterling Deaerator Company , USA And Altech Infrastructure Pvt Ltd, India
➢ Type : Spray scrubber
➢ Model : 14 HS-143ø950
➢ Shell Diameter & Thickness : 4400 mm OD x 28 mm nom thickness
➢ Straight length and overall length : 28964 mm (Overall length 32090 mm) of shell
➢ The feedwater storage tank is sized to provide at least 6 (six) minutes of BMCR flow
Page 21 of 159
the HP steam turbine extraction line.
➢ All the heaters are isolated individually and bypassed on the feedwater side by means of three-
way valves
Page 22 of 159
Hydrazine Ammonia Oxygen
Total skids / 2 nos. 2 nos. 2 nos
unit
Dosing pumps 2 nos pump 2 nos pump 4 Cylinders
/ Cylinders per per skid ( ie . 8
skid per unit)
30 per unit in
common rack
Pump Make V.K.Pumps V.K.Pumps V.K.Pumps
Pump / cylinder 100 lph 100 lph 10 m3 gas /
Capacity cylinder
Head 35 bar (g) 35 bar (g) -
Cranes:
Sl. Location Handling Capacity Qty Span Max lift O&M manual
No. equipment (nos) (M) (MH/AH)
Main Aux
hook hook
1 Double girder TG 195T 25T 2 27.5 29M/34M Available
EOT Crane building
AB bay
2 Double girder TG 60T 3 9.05 11.3 Available
EOT Crane building
BC bay for
BFP
3 Electrically Turbine 7.5T 1 13.2 7.6 Available
operated maintenan
under slung ce building
crane
4 Double CWPH/ 50T 10T 1 17.8 12/12 Not available
Girder EOT INDOO
R
5 Single CWPH/ 5T 1 8.8 12.7 Not available
Girder Semi OUTD
Gantry OOR
Crane
Hoist:
Sl. Equipment to be handled Hoist type Total qty (nos) Selected hoist Range of lift
No. (operation) capacity (T) (M)
SWL
1 CW inlet & outlet of BFV Electric hoist 3 15 11
@ condenser
2 Vacuum pump-HP LP Electric hoist 3 4 5
condenser
3 Vacuum pump-HP LP Electric hoist 3 4 5
Page 23 of 159
condenser
4 DMCW PUMP (TG) Electric hoist 3 5 5
5 Equipment in machine Electric hoist 2 3 10
room of TG building
elevators
6 Equipment in machine Electric hoist 1 2 10
room of service building
elevators
7 CEP strainer Manual hoist 3 0.5 8
8 CEP strainer Manual hoist 3 0.5 9
9 Drip pump Electric hoist 6 4 6
10 CRH NRVs actuator insert Manual hoist 3 1 6
11 LP1 LP2 duplex heater Electric winch 2 15 NA
tube bundle withdrawal
12 Unit electric HT switch Electric hoist 3 2 7
gear
13 MDBFP booster pump Electric hoist 3 3 5
14 TDBFP lube oil skid Manual hoist 6 0.5 4
15 AC plant room Centrifugal Electric hoist 1 4 5
chiller
16 AC plant room – CWP & Electric hoist 1 3 6.3
CHWP)
17 AHU fan motor handling Chain pulley 2 0.5 NA
block with
trolley and
trolley
18 Air washer unit fan motor Chain pulley 3 0.5 NA
handling block with
trolley and
trolley
19 Plant drain sump (BC row) Chain pulley 3 1 NA
block with
trolley
20 Plant drain sump (A row) Chain pulley 3 1 NA
block with
trolley
21 Transformer yard Vertical Chain pulley 1 1 NA
screw sump pump block with
trolley
22 AWU- fan motor handling Manual hoist 1 0.5 9.5
unit#2
23 AWU- fan motor handling Manual hoist 1 0.5 9.5
unit#3
Page 24 of 159
HVAC:
Ventilation system:
Page 25 of 159
Exhaust-Bifurcated 7500 CMH 1W+1S
Exhaust 12600 CMH 13W
Exhaust 13900 CMH 2W
Exhaust 16000 CMH 6W
Exhaust 16500 CMH 1W
Exhaust-Bifurcated 27600 CMH 2W+1S
Exhaust-Bifurcated 28000 CMH 2W+1S
Exhaust-Bifurcated 28200 CMH 2W+1S
Exhaust-Bifurcated 28700 CMH 4W+2S
Exhaust 37950 CMH 2W
4 Propeller fan 400-1150 CMH TG Building, 56
Turbine
1150-2000 CMH 19
maintenance
building &
Service building
5 Roof extractor fan 50230 CMH CWPH 21 Not available
6 Propeller fan 300 CMH CWPH 2 Not available
Elevator:
Sl. No. Description Location Capacity Qty (Nos)
1 Passenger cum goods TG building 1500 kg 2
2 Passenger Service building 1088 kg 1
SUMP PUMP:
Sl. No. Description Capacity (lpm) Head (m) QTY (Nos)
1 CEP portable sump 167 20 1
pump
2 Portable sump pump for 167 20 2
chemical application
3 Portable oily waste sump 167 20 2
pumps
4 CW pit submersible 583 25 6
pumps
5 Plant drain sump pit 1250 35 6
pumps(BC rows)
6 Plant drain sump pit 167 10 6
pumps(A rows)
Page 26 of 159
PLANT AIR COMPRESSOR SYSTEM:
Separate air compressor house was provided for Plant air compressors for meeting the plant
instruments & service air requirement except AHS.
Bottom Ash handling system (BA & eco ash): (1 set for each boiler)
Bottom Ash System of each unit will consist of triple ‘V’ water impounded, storage type, water-cooled
refractory lined bottom ash hopper located directly below the bottom water wall header of boiler.
Bottom ash will be collected continuously from the boiler furnace. Each ‘V’ section of the hopper will
have two outlets provided with two clinker grinders & electric drives installed directly below the feed
gate assembly to limit the size of clinkers. One jet pump will be provided below each clinker grinder
for conveying ash slurry to the ash slurry pump house for further transportation to ash dyke. Out of two
clinker grinders and two jet pumps provided for each “V” section, one grinder and jet pump will
operate while other will be standby. The deashing of water impounded hopper will be operated once in
a shift of 8 hours. Ash collected in the economizer hopper will also be collected in the BAH by means
of flushing apparatus provided below the economizer hoppers.
1 No. water impounded Bottom ash hopper (capacity:8 hours storage capacity-540 m3)
1 No. clinker grinder (granularity: ≤ 25 mm) of capacity 85 tph
2 Nos. (1W+1S) high pressure jet pumps (2x100%) of capacity 85 tph)
One no. overflow water tank and two nos. overflow water pumps are provided per unit to
recirculate the overflow water from the BAH
Page 27 of 159
Ash water recovery system: (1 set for three Units)
Overflow water from the ash pond will be decanted and reused for ash handling system. The overflow
water in the ash pond will be routed to a overflow sump (3000 M3) adjacent to the ash disposal area.
Three (3) ash water recovery pumps (2W+1SB) each having a capacity of 850 M3/hr will be installed
to pump the overflow water to the AHP clarifier for reuse in ash disposal system. 3 tonnes capacity
SGEOT crane is provided in the Ash water recovery pump house for equipment handling. Necessary
HVAC system also provided for proper ventilation in the building.
One (1) clarifier of 2500 M3/hr capacity will be provided for treating overflow water from ash pond,
bottom ash overflow water from all the three units and drains of ash handling system. Necessary
chemical dosing system shall be provided. Clarifier outlet water quality shall be 20 ppm (maximum).
The clarified water shall be pumped to ash water sump for reuse in ash handling system.
Page 28 of 159
• Each air compressor house is provided with 7.5 tonnes capacity Single Girder EOT
crane for handing of equipments in the respective compressor house. Necessary
HVAC system also provided for proper ventilation in the buildings.
• Silo utility building also provided for locating the silo fluidizing blowers with
heaters, instrument sir compressors silo area instrument air requirement, etc, 3 tonnes
SGEOT also provided for equipment handling. Necessary HVAC system also
provided for proper ventilation in the building.
• Each fly ash silos provided with two electrically operated hoists for equipments
handling having 2tonnes capacity..
• Two nos. 2T electric hoist provided for each unit AHS vacuum pump area for
equipment handling.
• Each buffer hoppers provided with two electrically operated hoists for equipments
handling having 2tonnes capacity..
Coarse ash from SCR hoppers will be disposed-off to ash slurry sump through feeder ejector.
One conveying stream per unit will be provided. Capacity-85 tph
Page 29 of 159
COAL HANDLING SYSTEM:
Coal source and Characteristics
The coal for the power station will be made available from NLC Talabira (Odisha) Mines or/and NLC
South Pachwara (Jharkhand) south coal block Mines. Coal transportation is envisaged through Railway
Wagons which will be received via dedicated Railway Siding of NUPPL project.
System Description
Unloading system
Coal handling yard will have six lines of Railway Tracks, one for track hopper, four for wagon tipplers
and one for manual unloading. The details are as under;
• One Track Hopper arrangement is envisaged to have the facility of bottom
discharge system in place with bottom discharge wagons (BOB RN type). Coal
from track hopper will be reclaimed by four (4) nos of Rotary Discharge Machines
(i.e paddle feeder) and will be fed further to conveying system.
• Four wagon tipplers will be used for unloading coal from BOX-N type wagons.
The coal thus received will be transported through Apron feeders provided with
dribble feeders to feed to further Conveyors.
Coal conveying details
• Coal Conveying System will consist of 31 nos of Belt Conveyors including reversible
yard conveyors, Tripper Conveyors, reclaim conveyor from Emergency Reclaim
Hopper. The details of the conveyors are furnished below.
Sl. No. Conveyor No Width Speed Capacity
1 BC-1A
2 BC-1B
3 BC-1C
4 BC-1D
5 BC-2A
6 BC-2B
7 BC-2C
8 BC-2D
9 BC-2E
10 BC-2F
11 BC-3A
2900 TPH
12 BC-3B 2000 mm 2.7 m/sec
(Rated)
13 BC-4A
14 BC-4B
15 BC-5A
16 BC-5B
17 BC-6A
18 BC-6B
19 BC-7A
20 BC-7B
21 BC-8A
22 BC-8B
23 TBC-1A
Page 30 of 159
24 TBC-1B
25 TBC-2A
26 TBC-2B
27 TBC-3A
28 TBC-3B
29 RYBC-1A
30 RYBC-1B
31 RC-1
• Apart from the above, two shuttle conveyors in JT-3 & JT-4 & two belt feeders in
crusher house are also envisaged.
• The Coal Conveying system also includes 12 nos. of Junction Towers, One Crusher
House and one sampling tower.
• Specification of Conveyor Belts – 2000 mm width, Belt Speed – 2.7 m/s for
conveyors and feeders; 1m/s for shuttle conveyor, rated capacity – 2900 TPH.
• With the help of 6 nos (2 Nos per Unit) of travelling tripper coal will be fed to
bunkers.
Coal Stockpile
There are four nos of coal stockpile of length of minimum 865 mtrs each. Width of each stockpile is 50
mtrs and height is 10 mtrs. The storage capacity of coal stockpile is 1016548 Tonnes( 30 days coal
requirement). There are two nos of reversible bucket wheel type stacker cum reclaimer of stacking
capacity 2900 TPH(rated) and reclaiming capacity of 2400 TPH(Avg). Boom length of each stacker
cum reclaimer is 45 mtrs.
System Control
Program Control, Protection and monitoring system are furnished in CHP. Local Control Furnished for
Coal Handling Plant.
Page 31 of 159
• The rated capacity of Vibrating Grizzly Feeder is 1500 t/h. The input coal size will be (-) 300 mm.
The separation size is (-) 50 mm.
• The rated capacity of Ring Granulator is 1500 TPH. The input size is (-)300 mm and output
size is (-)50 mm.
Belt Scales
• Belt Weighers are installed in the system as follows
• BC-2A/2B – BW-1A/1B
• BC-1C/1D – BW-1C/1D
• BC- 3A/3B – BW-2A/2B
• RC-1 – BW-3
• BC-5A/5B – BW-4A/4B
• SR 1A (Stacker cum Reclaimer) – BW-5
• SR 1B – BW-6
Following types of Dust Suppression/Dust Extraction System are provided for Coal handling
plant:
• Belt Conveyor transfer points: Dry Fog Dust Suppression System
• Wagon Tippler: Plain Water Dust Suppression System
• Pre-spray system of wagons: Plain Water Dust Suppression System
• Track Hopper: Plain Water Dust Suppression System
• Emergency Reclaim Hopper: Plain Water Dust Suppression System
• Coal Stockpile: Plain Water Dust Suppression System
• Stacker cum Reclaimer: Dry fog Dust Suppression System
• Crusher House – Dust Extraction System
• Bunker Building – Dust Extraction System.
Cranes & Hoists
• Five Nos of EOT Cranes (Four at Wagon Tippler Complex (20/6.3 MT) &
one at CHP Maintenance building (15/5 MT) are provided.
• Total 129 Nos of Electric Hoists of various capacity are provided in Coal
Handling Plant Buildings.
• Total 138 Nos of Manual Hoists of various capacity are provided in Coal
Handling Plant Buildings.
Page 32 of 159
ELECTRICAL SYSTEMS:
Generator Details:
Make : GE power /Alstom Bharat Forge Power
Model : 50WT23E-138
Quantity: 3 Nos
Rated Output (MW) : 660MW, 3 Ф Stator winding Water cooled Stator core and rotor
winding-Hydrogen
i) Excitation type : static
ii) Rated Frequency (Hz) : 50 Hz
iii) Rated Power Factor : 0.85
iv) Rated terminal voltage : 22kV
v) Rated Speed : 3000 rpm
vi) Rated Phase Current : 20377 A
vii) Excitation Current at rated output : 5496 A
viii) Short Circuit ratio (without negative tolerance) : 0.48
ix) Direct axis synchronous reactance (unsaturated) X d : 201%
x) Direct axis transient reactance (saturated) X d ’ : 28%
xi) Direct axis sub-transient reactance (unsaturated) X d ” : 19%
xii) Capacity of Excitation Transformer : 6810KVA, dry type
xiii) Excitation current : 5756 A
xiv) Excitation voltage : 565 V
Page 33 of 159
iii. Line – Ghatampur TPS to Kanpur (PG) D/C - approx-60KM (without switchable line
reactors or PIR): 2 Bays
iv. Bus Reactor 125MVAR: 1 Bay
v. Bus PT: 2 Nos.
vi. Spare Line: 2 Nos.
Spare line bay provided with indoor equipment along with GIB extended just outside GIS building.
Spare line bay provided with indoor equipment along with GIB extended just outside GIS building.
Page 34 of 159
vii. Temp. Rise
Top oil by thermometer -- 50 °C
Winding by resistance -- 55 °C
All other associated equipments viz., Generator stator water coolers / air coolers, Seal oil system,
Exciter, HT < Bust ducts, NGR, UAT’s, protection Panels, Relays, MCC’s, PCC’S, Control Panels.
HT, LT, Control & Communication cable and cable carrier systems, Oil filled Transformers
(11KV/3.3KV) Dry Type Transformers (11KV/0.4Kv), associated 11KV, 3.3KV, 0.4KV Switchgears,
HT & LT Motors, DC Motors, Actuators, ACDBs, PDBs, DC systems, illumination systems, UPS,
VFDs, Earthing & lightning systems, Electrics of DG sets, Elevators, hoists & Cranes, ILMS & Metal
detector, local control panels and push buttons, etc., available in Main Plant and all BOP systems.
Plant Communication system: 5 Digit & 3 Digit EPABX, Exchange Battery & Chargers, various types
of telephone Instruments and associated JBs, Cabling systems and other accessories.
Public address system, Talk back systems, Audio Conferencing system, Wireless communication
systems and associated JBs, cabling systems and other accessories.
CCTV system for entire plant and associated various types of Cameras and accessories.
Page 35 of 159
BOP – M/s BGR Energy Systems Pvt. Ltd.
Their scope involves supply of respective are Field instruments, Special instruments, Analysers,
SWAS, JB, LIE/LIR, Cables, Trays, conduits, impulse pipes, Power cylinders, control valves, Solenoid
valves, fittings, glands, lugs, ferrules, name plate, lab equipments, AAQMS (inside & outside plant
premises), CEMS, PADO, Simulator, HMS, VMS, VMAS, Master clock, LVS, UPS, Battery, Control
system peripherals like WS, printers, racks, tables, chairs, Network components, OPC, Soft
communication, UCP, Control systems, Control Panel, RIO, PLC, DDCMIS.
Control of the plant is envisaged from the Work stations installed in the Main plant Control room and
the respective are BOP control room. There are hard and soft signal exchanges between the various
DDCMIS to ensure complete control of the plant. Other standalone systems viz, compressor, Dryer
etc., control is envisaged from the field with minimum monitoring from the control room. In case of
emergency, unit critical loads can be operated through the hard push buttons form the Unit control
panel
Some of the major component supplied by the package contractors are listed below.
TG C&I System:
1. TG DDCMIS- ALSPA(M/s GE POWER)
2. TG VMS- M/s Bently Nevada
Page 36 of 159
3. Control valve- M/s Masoneilan valves
4. COLTC PLC- M/s GE
5. Generator Remote IO Panel- M/s Pepperl+Fuchs
6. Control valve- M/s Masoneilan valves
7. COLTC PLC- make GE
8. HVAC C&I system
9. Generator Remote IO Panel- M/s Pepperl+Fuchs
10. CPU service area & CPU Regeneration instruments and analyzers
Page 37 of 159
g. Auxiliary cooling water C&I system
i. ACW VMS system- Ge-Oil and Gas-Bently Nevada
ii. ACW RIO- ABB
The minimum quantity of system is mentioned in the below table for the reference. Actual quantity
may increase/decrease according to the plant requirement:
Tentative
Sr. no. Description
Population
Page 38 of 159
Emergency Power supply management and UPS
DG set
The plant is provided with an emergency AC supply facility comprising DG Power for complete
station. The Capacity of DG set is considered loss of normal supply due to any contingency. The DG
sets have AMF (Auto Mains Failure) feature capable of starting picking up load Within 30 seconds. The
minimum load is considered will be safe shut down, essential lighting lift and charging of storage
batteries. DG switchgear is have inter-connection among themselves for reliability purpose. There are
Four DG sets for complete station and each DG set will be sized on the basis of emergency loads of one
unit. In the case of failure of the normal power supply, this emergency supply will be guaranteed by the
automatic start-up of the diesel generator set. Emergency loads will start-up in batches.
DC System
Main power plant building unit DC system, coal handling plant building DC system water treatment
plant DC system and other BOP DC system are provided for the DC loads.
The various wastes generated from different sources of a thermal power plant are collected and treated
to meet the quality requirement for various purposes within the plant. Waste water from each units shall
undergo required treatment and then they shall be equalized in a central monitoring basin. Acid and
alkali dosing shall be done at gravity to achieve neutralized combined effluent which will be further
treated to achieve ZLD (zero liquid discharge).
Any effluent discharged outside the plant boundary will meet all the standards stipulated by the local
pollution control board. Based on the philosophy, the effluent treatment system consist of Central
Monitor Basin (CMB), Acid dosing tank, Alkali dosing tank, CMB Effluent transfer pump, ETP
distribution chamber, High Rate Solid Contact Clarifier (HRSCC), clarifier water sump, clarified water
transfer pumps, sludge pumps, sludge disposal pump, sludge pit air blower, lime dosing tank, lime
recirculation feed pumps, ferric dosing tanks, ferric dosing pump, poly electrolyte dosing tank, poly
electrolyte pump, Ferric chloride bulk storage tanks, ferric chloride unloading pumps, Dual media
filters, Basket filters, Ultra filteration skids, UF back wash pumps, UF permeate water storage tank, RO
feed pumps, RO feed cartridge filters, RO high pressure pumps, RO skids, Degasser tower, top
distributor, tower packing, Degasser water storage tank, Degasser air blower and RO permeate transfer
pump.
Firefighting system
• The fire-fighting system is responsible for protecting the whole power plant. The fire- fighting system
will consist of water fire-fighting system (Hydrant and Spray), inert gas firefighting system (automatic
& local flooding), foam protection system, portable fire extinguishers and the fire alarm and detection
system. The hydrant fire-fighting system and spray fire-fighting system will be provided separately,
and the ring pipe net of them will be provided in all the required area in the power plant.
• The water fire- fighting system will consist of hydrant fire Firefighting pumps and spray firefighting
pumps. Five (5) nos. of vertical turbine fire water pumps (3 nos. for Hydrant + 2 nos. for Spray) with
drive electrical motors (Each capacity 410 m3/hr). Three (3) nos. of vertical turbine fire water pumps
(2 Nos for Hydrant + 1 No for Spray) driven with compression ignition diesel engines (Each capacity
410 m3/hr) and Two (2) (1W +1S) vertical turbine jockey (Each capacity 75 m3/hr). Four (4) nos. of
horizontal centrifugal type booster pumps (Two motor driven and the other diesel engine driven) for
hydrant pump (Each capacity 171 m3/hr) and Spray booster pump (Each capacity 410 m3/hr) service
for maintaining required pressure on higher elevations of power house and boiler building. Spray
system is consist of High Velocity Water Spray System (HVWS) and Medium Velocity Water Spray
System (MVWS)
• The fixed foam fire-fighting system will consist of foam proportional mixer & storage tanks (each
capacity 2500 liters), Foam main pump (Electric and Diesel pump capacity 2.5 m3/hr), foam
generators, foam hydrant, pipe and other accessories etc.,
• One centralized total flooding type inert gas (clean agent) extinguishing system shall be provided for
Main Control rooms, above false ceiling, and inside the rooms voids, electronic equipment rooms,
Computer rooms, UPS rooms battery and battery charger room.
• Clean agent automatic direct/ indirect low pressure Fire detection & suppression system with linear
pneumatic heat detection tube shall be provided for Stacker Reclaimer PMCC, Wagon Tippler PMCC
and Track Hopper MCC.
• Fire Detection Alarm & Control system, Portable, Mobile Fire Extinguishers and Mobile Tenders with
accessories is provided in the power plant.
• The design and construction of the fire detection and protection equipment will be to internationally
accepted standards and in compliance with the regulations of the Tariff Advisory Committee and other
relevant statutory requirements for the licensing and fire insurance (with minimum premium) of the
complete power stations.
HVAC
Ventilation system
In Steam Generator areas like ESP ,Unitary Air Filtration (UAF) system is provided and other areas
like Boiler maintenance room, Bunker bay and FOPH etc are provided with dry type ventilation system
i.e, Supply by either Centrifugal fans (with ducting) / wall mounted tube axial fan, air intake lover.
Exhaust by wall mounted tube axial exhaust fans, bifurcated fans, Gravity dampers and propeller fans
based on the system requirement.
Page 40 of 159
Air supply (from both the sides of the TG bay) through evaporative cooling units & exhaust through
power roof ventilators in turbine hall. Four evaporative cooling units & eighteen power roof ventilators
are provided for each unit, and fourteen power roof ventilators are operating,four is standby.
In BOP areas, Unitary Air Filtration (UAF) system is provided for 400kV and 765 kV GIS hall and
other areas are provided with dry type ventilation system i.e, Supply by either Centrifugal fans (with
ducting) / wall mounted tube axial fan, air intake lover. Exhaust by wall mounted tube axial exhaust
fans, bifurcated fans, Gravity dampers and propeller fans based on the system requirement.
Separate central all-air conditioning system shall be furnished for CCR & EER.
Two AHU are provided for each AC system. One is operating, the other is standby, Each AHU have
primary and middle efficiency filters, cooling coil section, humidifier section, muffler section. The
ventilation rate of CCR AC system is 80000m3/h,50000m3/h for 2# and 3# EER,25000m3/h for 1#
EER The fresh air quantity shall be exceeded 10% of total. Smoke extractor shall be provided and air
conditioning system shall be interlocked with smoke/fire detectors. The 40mm think centrifugal glass
wool heat insulation board is furnished for air duct. The 0.5mm thick aluminium alloy sheet is furnished
for the air conditions duct.
The chilled water for AHU comes from refrigerating plant room of CCB. The temperature of supply
and return chilled water is 7/12 deg C.
22 TR (1W+1S) – Water cooled Precision Air Conditioners (PAC) for 132kV GIS relay panel room,
19.1 TR (1W+1S) – Water cooled Precision Air Conditioners (PAC) for 400kV GIS relay panel room,
22 TR (1W+1S),– Water cooled Precision Air Conditioners (PAC) for 765kV GIS relay panel room,
15.5 TR (2W+ 2S)- 765Kv/400kV/132kV – Common Control room and 29.9 1 TR (2W+ 2S) – Water
Cooled Precision Air Conditioners (PAC) for Chemical Laboratory. Condensing units, cooling towers,
condenser water pumps and fresh air fans are the associated equipments included in the water cooled
precision AC units.
Hi- Wall mounted Split type Air conditioning system for are provided for all BOP Control room and
other AC rooms in the capacity range of 1 TR, 1.5 TR, 2.0 TR , 2.5 TR and 3.0 TR.
ANNEXURE - AA
Nature and Scope of Work
COMPRESSOR
Overhauling: Cleaning, replacement of lubricating oil/repair & replacement of lubricating oil
pump, replacement of drive/belts/couplings ,oil and air filters cleaning/replacement, inspection
of compressor internals /Impeller / screw inspection/ replacement /repair of internals/heat
exchanger/air receiver pressure and temperature indicators etc., and boxing up, alignment to the
drive equipment etc. and taking trial run of the compressor to the satisfaction will be under the
scope of O&M Service Provider.
AIR DRYER
Page 42 of 159
Overhauling and Cleaning and repair/replacement of valves, desiccant/refrigerant/ expansion
valves/ compressors/ fasteners/ pressure and temperature gauges/moisture trap/heat
exchangers/piping etc. and taking trial of the dryer to the satisfaction will be under the scope of
O&M Service Provider.
Boiler area all the floor accumulation clearing, periodical water washing and maintaining
cleanliness of area and equipment.
Unless otherwise excluded, the scope of the Contractor shall include all the operation and
maintenance work required to ensure the healthiness of the system/equipment and enable
sustained operation of the plant with availability above the guaranteed value, without
compromising the operability / overall life of the equipment / system.
Valves:
Repair, Replacement and preventive maintenance of all types of valves including safety valves.
Floating and adjustment of the Blow down, Popping and relieving pressure setting of safety
valves as per recommendations including online trevi test floating. Periodical Bush house
cleaning, greasing, Bearing & Bush replacement, actuator removal & replacement. Overhauling
and re-conditioning of all valves for improving the performance (Easy operation, rectification
of passing and gland leakage, and improving the reliability) includes cleaning, lapping, blue
matching, Machining of valve components like seat and disc, replacement of Internals etc and
hydraulic test of seat and bonnet of gate, globe, bonnet less and pressure seal bonnet type and
on-line leak arresting., etc.
Page 43 of 159
Care shall be taken to contain service air usage to other area in order to conserve service air,
during simultaneous light up of units with LDO/Air atomizing and during simultaneous fuel oil
support firing condition. Also 100% availability of service air and instrument air compressors
shall be ensured.
Pressure parts:
Thorough inspection (physical and NDT i.e. preventive Thickness survey), cleaning (internal
and external) and replacement, repair of Boiler pressure parts which includes super heater
tubes, reheater tubes, water wall tubes, Economizer, LTSH, Steam cooled walls, screen tubes,
all the interconnecting pipes and headers and the valves connected to the various parts of the
boiler. Repair, replacement of gauge glasses, servicing of steam and sample collection and
cooling system.
• Upkeep of Insulation and refractory works, repair & replacement of refractory.
• Sky climber Erection, operation and maintenance (safety net to be provided by
O&M Service Provider)
• Quick erect scaffolding drawl, erection, dismantling, servicing and hand over.
(Safety net to be provided by O&M Service Provider).
• Water washing / Jet cleaning of first and 2nd pass for inspection and preventive
maintenance. All the tools, equipments, materials required will be in the scope of
the O&M Service Provider. (Hoses, lighting, pressurizing pumps etc).
• Tube thickness survey including wall blower area, hopper panels, leading tubes
in banks and all wall & coil bends.
• Inspection and cleaning of all headers through inspection hole cutting &
welding, nozzle weld joints checking.
• Sample pieces cutting, inspection and finding inference as per the OEM manual.
• Water separator inside inspection, cleaning & weld joints healthiness check.
• Tube support lugs, rod spacers, support plates, spacer tubes and hanger tubes are
to be periodically inspected and repaired/replaced.
• Pendent superheaters & Reheaters all bends RT during overhaul for finding the
status of inside scales and rectification/replacement of tube bends if required.
• Protective sleeves, baffles and support saddles inspection, repair / replacement.
• Performing water side, SH Hydro test, inspection and repair.
• Penthouse inspection and cleaning.
• Periodic Safety valve, ERV servicing & floating (including performing online
safety valve floating as per the necessity).
• Online leak arresting of pressure parts lines and valves.
• Reheater hydrotest with PTD erection and dismantling.
• BCP servicing, strainer cleaning, Oil system, hydraulic actuator maintenance for
hydraulic valves & servicing of valves in the circulation system.
• Erection and dismantling of all necessary temporary scaffolding including pipe
& clamps for carrying out O&M activities.
• Hard facing of coal burner tips.
• Servicing of power cylinder, Burner tilt mechanism.
• Wind box inspection, cleaning, dampers servicing, repair/replacement.
• Manhole doors servicing, replacement of ropes.
• Pipe Hangers preventive maintenance, cold and hot values checking and
adjustment.
• Wall blower area tube erosion checking, sleeve replacement and preventive tube
replacement.
• SH, RH side gas dampers inspection, repair and rectification.
Page 44 of 159
• Buck stays periodical cleaning, inspection and repair.
• Inspection, repair /replacement of Insulation and refractory.
• In continuation with above mentioned activities, minimum indicative work
schedule for each unit overhauling of Boiler & Auxiliaries are detailed as below:
SL Remark
Description UOM Qty
No
Erection and Dismantling of cuplok
1 scaffolding in the 1st pass of the LPS 1
boiler
Water washing of the boiler: 1st
2 LPS 1
Pass, horizontal pass, 2nd Pass
Cleaning of Boiler by Manual
3 LPS 1
Scrapping / Wire brush
Cleaning of ash from top of
4 LPS 1
penthouse, cat house and dog house
5 Servicing of peep holes Nos 50
Rectification/Replacement of
6 protection plates in various areas of Nos 1000
Pressure Parts
Replacement of tubes and welding
7 Nos 550
of HP joints
Area and boiler tubes will be
identified by the
NUPPL representative. Approx.
Preparation of boiler pressure parts 40,000 locations may be
8 components for NDT (It includes LPS 1 required to be readied for
Tube Thickness Survey) tube thickness survey. Any
tubes where thickness reduction
is more than 20%, the same
shall also be replaced.
Fabrication of tube bends upto
9 Nos 10
70NB (Cold/Hot Bending)
Alignment of tubes of SH Div.
10 Panels, Platen SH panels & Nos 170
Reheater etc.
Scaffolding erection in Boiler
11 LPS 1
Horizontal pass & 2nd pass
Repair of seal plate of water wall
12 LPS 1
S-panel at seal trough
Removal and installation of orifices
13 LPS 1
in Ring Header
Runni
14 Fin welding ng 500
Meter
15 Stress Relieving of Joints Nos 75
Areas will be identified by
16 Carrying out RT (Elliptical shot) Nos 2000
NUPPL representatives
Carrying out PAUT (Phased Array Areas will be identified by
17 Nos 4000
Ultrasonic Testing) NUPPL representatives
Page 45 of 159
Actual
Repairing/Rewelding of erection
18 Nos Identifie
weld joints based on RT/PAUT
d Qty
Application of plastic refractory
19 above and below burner blocks MT 15
inside furnace
Overhauling Of Coal and Oil
20 Set 1
Burners
21 Replacement of Coal Burners No 32
22 Cleaning Of Wind Box and Repairs LPS 1
Repair, Cleaning and Replacement
23 LPS 1
of Baskets (if any) in RAPH, SCR
23 LPS 1
Note: Carrying out complete overhauling of Boiler & Auxiliaries is in the scope of O&M Service
provider. Arranging all requisite resources including skilled manpower, Crew for SR/
Radiography/PAUT etc. with all necessary licence, T&T, all statutory requirements & any other legal
formalities (including precautions, documentations) etc. shall be in the scope of O&M service provider.
Page 46 of 159
ID/FD/PA FANS
• Condition monitoring and predictive maintenance.
• Preventive, break down, Overhaul maintenance of ID/PA/FD fan.
• Silencer cleaning and repair/replacement.
• PCD, servomotor preventive maintenance, bearings, Blade inspection, repair and
replacement.
• Attending oil leakages, oil seals checking, replacement, alignment works,
balancing. Expansion joint inspection, patch work and replacement.
• Lub oil, control oil, hydraulic oil system servicing, servicing of cooling and
sealing air fans.
• Cleaning, replacement of lube oil, control oil, cooling water gaskets. Cleaning,
inspection of rotor, runner, shaft, bearing, coupling, housing ,casing ,ducting
,fasteners, dampers, servomotor, operating mechanisms and rpair/replacement of
the above as and when required , alignment and leveling of machines with its
drive equipment etc., to the satisfaction. Hard facing, HVOF coating and repair /
replacement of Impeller, blades. Static and Dynamic balancing of the impeller as
and when required.
• Filter cleaning, lub oil tank cleaning, lub oil & control oil change etc.
• Stall probe tuning and rectification.
AIR PREHEATER:
• Cleaning, Repair, Replacement, Preventive Maintenance, Overhauling,
Inspection of Guide & Support Bearings.
• Inspection, adjustment and repair/replacement all type of seals like radial, axial,
bypass, rotor post etc.
• Inspection, repair, replacement of soot blowers & its piping, water washing
piping, nozzles.
• Inspection, repair, replacement of Gearbox & its internals, clutch, fluid coupling
and Air motor servicing.
• Inspection, cleaning, Basket removal & insertion, repair / replacement of
baskets, reversal of baskets and Rotor leveling.
• Servicing of lube oil system, Ash cleaning in guide bearing area, Manhole rope
replacement, servicing.
• All types of scaffolding required for inspection and maintenance of RAPH, duct
and expansion joints for inspection, repair and replacement.
• Water washing, high pressure water wash cleaning to clean ash deposition, ABS
formation in RAPH elements as and when required.
Hard facing of any part of ducts gates and damper as and when required.
Cleaning and repair of all the ducts, erosion checking in ducts & internal stiffeners, expansion
joints & its protection plates, supports and dampers inspection, repair & replacement of eroded
parts including plate bending from coal mill up to chimney. Ducts external support, slide
bearing checking, cleaning and rectification.
Page 47 of 159
Diversion plates, vanes checking, repair & replacement including plate bending.
Inspection, repair /replacement of Insulation.
COAL MILL
Cleaning, inspection, replacement, overhauling of lubricating & Hydraulic oil station, heat
exchangers and gearboxes. Inspection, repair, hard facing, replacement/adjustment of mill
internals like grinding rings, grinding table liners, rollers, springs, Hydraulic power pack,
vanes, bolts & nuts, fasteners, coupling, journal, bearing, Bush, spindle. Repair & replacement
of Scrapper assembly ,classifier & vanes ,actuator mechanism, leveling and alignment with
drive equipment etc., and trial run to the satisfaction. Gap setting of rollers, Alignment, over
load inspection foreign material/accumulation removal, greasing and lubrication, hydraulic
system servicing, Rotation of components according to wear, Mill choke cleaning checking,
servicing /replacement of air rings, plate valves, orifice, HAD & CAD servicing, Coal pipe
bend replacement and coal pipe thickness checking & patch work, replacement. Ceramic liners
inspection, wear check and replacement.
1. Total predictive, preventive & break down maintenance of mechanical equipment of Mill
and its auxiliaries
a. Cleaning, inspection, replacement of lubricating & hydraulic oil, Bladder pressure
checking & mtce.
b. Hydraulic loading system preventive and break down maintenance.
c. Overhaul of lube oil station, heat exchangers and gearboxes.
d. Inspection, replacement, adjustment of mill internal like rollers, liner plates, vanes,
bolts & nuts, coupling, grouting if required, leveling and alignment with drive
equipment etc., and trial run to the satisfaction.
e. Regular purification/centrifuging of GB and hydraulic oil maintenance.
f. Modification of line, Equipment, Painting if required.
g. Regular PM, Overhauling of equipment.
h. The contractor will guarantee for the performance of the mill for the parameters like,
oil/gas leakages, mill fineness and thru-put after major overhaul. Fixed orifice &
variable orifice cleaning, inspection and repair.
i. Total Maintenance of all valves in mill area, Valve machining and Total Maintenance
of Hydraulic and lube oil station.
j. Mill discharge valve, burner inlet valve & victaulic coupling/other couplings, coal pipe
sleeve joints, inspection, preventive maintenance, repair & replacement.
2. Housekeeping, equipment cleaning and area cleaning of the whole mill bay after
maintenance and during operation shall be in scope of contractor.
3. Existing equipment storage sheds shall be handed over to contractor and any further
maintenance shall be in contractor’s scope.
4. Central Material Management shall be part of NUPPL scope. Contractor will draw
Material, spare parts from here, handling & transportation to work place for temporary
storage, usage shall be in Contractor's scope. Segregation and Disposal of scrap to the
scrap yard shown by the NUPPL engineer in charge is in the scope of the contractor.
5. All other T&P irrespective of its nature being either special or general are in the scope of
Contractor like hydraulic jack, puller etc.
6. Operation and Maintenance of the entire crane in the mill bay shall be in contractor’s
scope.
7. Equipment transport, handling system and maintenance shall be in contractor scope.
8. Special equipment, vehicle required for mill maintenance, mill gearbox and any other
mill parts or auxiliaries shifting within the plant for maintenance is in contractor’s scope.
9. All consumables like all type of Rope, all types of Gaskets, nut and bolts etc as applicable
are in contractor scope.
Page 48 of 159
10. Maintenance and preparation of Mill overhauling is in contractor’s scope.
11. Timely PM of mill as per the Schedule is in contractor’s scope.
12. Maintenance report, spare reconciliation report has to be provided on daily basis by the
contractor.
13. Tracking of wear rate of crushing elements and thereby planning mill overhauling is in
contractor’s scope.
14. All coal discharge piping up to burner inspection & maintenance like, ultrasonic thickness
survey, patch welding, replacement and online leakage arresting is in contractor’s scope.
15. Oil handling and oil purification to meet the required purity level suggested as per
engineer in charge shall be in contractor scope.
16. Any metal built up or hard facing of any part of mill and its auxiliaries are in contractor’s
scope.
17. Repair, replacement of coal pipe and bends. Online leakage arresting, patch welding to be
done as and when required.
18. Any kind of welding and cutting required is in contractor’s scope. Availability of the
welding machines and cutting sets and its maintenance shall be in contractor’s scope.
19. Execution of any kind of modification required for improving the performance of mill
and auxiliaries.
20. CAVT (cold air velocity test) of boiler to be done during O/H.
COAL FEEDER:
Overhaul, Cleaning, inspection, repair/replacement, overhauling and PM of bunker shut off
gate, feeder inlet valve, feeder discharge valve, coal feeder, clean out conveyor chain, scrapper
servicing, replacement, motor etc of coal feeding system. Belt replacement, Belt tension
adjustment, coal accumulation choke cleaning, weigh rollers and load cell preventive
maintenance and calibration, bearing lubrication, scrapper belt, pulley replacement, gear box
servicing, replacement, arresting leakages, plate valves servicing. Head pulley, sprockets and
take up pulley servicing inspection and replacement, removal of foreign material. etc.
Expansion joints, chute liners inspection, repair and replacement.
COAL BUNKER:
Bunker emptying with temporary emptying chute assembling and dismantling, transportation of
coal-to-coal yard. etc. Washing / cleaning of bunker inside for preventive maintenance.
Erosion, thickness survey, metal build up / plate replacement including plate bending, SS liner
inspection, repair and replacement, Bunker top grills checking repair & replacement.
SEAL AIR, DILUTION AIR, SCANNER AIR FAN & PENT HOUSE COOLING FAN:
Cleaning, replacement of lubrication oil/system, gaskets replacement, inspection of rotor,
runner, shaft, bearing, coupling, housing, casing, ducting, fasteners, dampers, operating
mechanisms and repair, replacement of the above as and when required. Alignment and
levelling of machines with its drive equipment etc., to the satisfaction. Hard facing,
replacement of Impeller. Static and Dynamic balancing of the impeller as and when required,
filter cleaning/replacement., etc.
Page 49 of 159
SCR and Ammonia storage & Handling system:
1. Safe Unloading and handling of Anhydrous Ammonia based on plant requirement, Leak
checking and emergency handling.
2. Catalyst modules management (Addition and replacement) and catalyst installation for
addition and replacement by O&M Service Provider based on catalyst handling and
installation plan of OEM/requirement based on effectiveness.
3. Catalyst waste management/ safe storage /disposal as per the directives of NUPPL. Waste
disposal shall be as per environmental / hazardous waste disposal norms. Used catalyst
storage at scrap yard and disposal by O&M Service Provider.
4. Catalyst health monitoring. Sampling (two samples from each layer), number marking,
packing, sending the sample to catalyst OEM lab or third-party lab (Lab for testing shall
be based on NUPPL approval) twice a year and follow up shall be made to obtain the lab
test reports. Based on catalyst lab test report, O&M Service Provider shall predict the
remaining catalyst life and provide their recommendation for subsequent order of catalyst
for addition/ replacement requirements. Catalyst ordering plan instruction to NUPPL shall
be provided by O&M Service Provider minimum one year prior to requirement of catalyst
at site. Charges for sample courier and testing will be reimbursed by NUPPL.
5. NUPPL will order the catalyst and deliver at site based on O&M Service Provider
requirement. From plant entry, it is O&M Service Provider’s responsibility to receive,
Unload & store properly at site as per OEM recommendations.
6. Overhaul, Cleaning, inspection, repair/replacement, overhauling, PM of Ammonia
unloading compressor, unloading arm, dilution air fan, Vaporizer, Accumulator, Sump
pump, AFCU, Ammonia injection grid, dampers, storage tank, dilution tank, sprinkler
system, eye shower, Ammonia leak detectors, catalyst, rake type soot blower,
Instruments, analyzers etc.,
7. Inspection of SCR reactor Support Bearings.
8. Conducting periodic mock safety drills.
9. Nitrogen purging before any maintenance/ overhaul.
10. Operating the sump pump and sending the collected ammonia drain in retention basin to
ETP at required time interval.
11. Catalyst cleaning at regular interval by operating the rake type soot blower in auto
sequence or by manual selection, regular inspection of catalyst layers and manual
cleaning.
12. Monitor/control the SCR outlet NOx level, NH3 slip and SCR inlet minimum operating
temperature within prescribed limit.
13. All required PPE for ammonia handling will be in the scope of O&M Service Provider.
14. Hazob study and statutory certificate renewal liaisoning is in the scope of contractor.
15. Inspection, repair /replacement of Insulation.
ESP:
Periodical inspection of ESP internals, accumulation clearing, water washing whenever
required and necessary repairs, replacement of collecting electrodes, discharge electrodes,
screens, its rapping mechanism, insulators, gearboxes, hoppers eroded portion, chutes,
distribution plates /divertors, valves and bottom hopper fluidizing system and blowers etc., and
taking trial of the above machinery and plant to the satisfaction. Hopper plate healthiness
checking leak identification and arresting, choke removal and heater repair/replacement.
Preventive and break down maintenance of solenoid valve, Control system, PLC logic setting
and maintenance, Electrical system and mechanical system maintenance.
Page 50 of 159
ESP floor accumulation clearing, periodical water washing and maintaining cleanliness of area
and equipment.
Fuel oil storage Tanks, Drain oil tanks inspection, cleaning and preventive maintenance
including spray and foam system. Oil spillage cleaning, in FOPH area. Foam and hydrant
system checking and preventive maintenance.
Hazob study and statutory certificate renewal liaisoning is in the scope of contractor.
Scope of work includes removal of damaged sheet & insulation / for maintenance requirement,
covering the pipe/duct /surface with preformed pipe section or light resin bonded mattress with
one side wire netting. The insulation will be covered by aluminum sheet/GI sheet.
The repairing and replacement application of entire refractory in boiler and other areas, curing
and dry out will be in the scope of contractor.
Page 51 of 159
Maintaining the local store, with the history of spare issued and used; proper tagging and health
card, testing date to be fixed. Testing of spare parts before use. Maintaining the defective parts,
damaged batteries, used grease. Monthly reconciliation status of spares, lubricants, motors,
bearings, consumables and to be provided to owner. Defective parts only be declared as scrap,
if it is found to be unfit for repair /reconditioning with written approval of owner. If the owner
repairs any defective component/part/equipment declared as scrap by the contractor will be
debited from Contractor’s bill.
SG MISCELANIOUS WORKS:
Walk down inspection, line flushing, preservation requirement of boiler, tanks etc, acid
cleaning as required, corrosion mapping, all NDT services required, welding Pre and post heat
requirements. Over hauling of all SG area lifts / elevator, cranes and hoists, load testing,
statutory inspection assistance. Over hauling, inspection, cleaning, repair of HVAC equipment
in SG package. Boiler periodic housekeeping, floors & structure periodic cleaning, coal dust
cleaning. Ash dust cleaning, Buck stay cleaning, buck stay pin checking, replacement, freeness
checking, furnace guides and restrainers healthiness checking/repair /replacement, boiler
hopper inspection, cleaning and sealing system maintenance, Routine inspection of Burners,
wind box area periodic cleaning. Inspection, replacement and rectification of all Metallic /
Nonmetallic expansion joints.
Periodic checking of Protection and interlock of all SG and auxiliaries and specifically after
shut down/ over haul shall be conducted and results to be furnished to the owner.
Chimney
Periodic chimney inside inspection and ash accumulation cleaning in ring collectors and
transition ducts. Repair and replacement of damaged liner, collector portion. Checking of
healthiness of expansion joints, repair & replacement of expansion joints. Boro silicate liner
inspection / rectification and maintenance of rack and pinion elevator. Maintenance of Chimney
Aviation lighting.
DM PLANT
Overhauling of pumps, valves/ lubrication/ replacement of leader/ nozzles/valves /gaskets/
pipes/ arresting leakage of water, providing assistance to transfer the resins/sand/activated
carbon for replacement or for internal inspection, repairs of acid/alkali storage tanks/pipe
lines/valves/pumps/supports and chemical dosing system to main plant Turbine system
Page 52 of 159
,auxiliary boiler dozing system ,CCW water dosing system of Boiler & Turbine and providing
assistance for acid / alkali unloading etc., and circulating water treatment.
CIRCULATING WATER & CW and ACW PUMP HOUSE AND COOLING TOWERS
Overhauling of CW and ACW pumps/repair and overhauling of BFVs/ARVs/replacement of
fills/repairing of PVC fittings/ repairing of precast concrete supports/ fasteners/drift
eliminator/doors/ valves/ headers/ nozzles/flanges repair , Coarse screen, stop log gates and
overhauling of chemical dosing system & chlorination system to C.W. system.
Unless otherwise excluded, the scope of the Contractor shall include all the operation and
maintenance work required to ensure the healthiness of the system/equipment and enable
sustained operation of the plant with availability above the guaranteed value, without
compromising the operability / overall life of the equipment / system.
ELEVATOR
Preventive, predictive, routine maintenance and overhauling elevator and its sub- assemblies
(gearboxes, transmission shaft, couplings, rollers, hoist drum, ropes etc.)
HVAC
Preventive, predictive, routine and Breakdown maintenance of HVAC System including
package type, window type, split type and Centralized air conditioners, water coolers and
purifiers, Cleaning, checking, repair and replacement of air filters/fans/gas
charging/replacement of compressor/power and control Circuits/humidity/temperature
DIESEL GENERATORS
Preventive, predictive, routine and Breakdown maintenance of DG, Excitation, battery, battery
charger, synchronizer, control circuit, power circuit & panels including troubleshooting,
cleaning, checking, repair and replacement of faulty parts. Cleaning and changing of filters /
lubrication of bearings / winding and bearing temperatures /testing/ meggering /exciter
connections/earthing.
Page 53 of 159
HYDROGEN GENERATION STATION
The hydrogen generating system and its auxiliary equipment maintenance, repair, inspection,
overhauling, replacement will be in the scope of contractor
The job covers transportation of fabricated structure to site & erection / assembly act.
Assembly, bolting, welding, alignment etc. come in the scope. The contractor will do grouting.
The contractor has to arrange the consumables like gas, electrodes, clamps tools & tackles etc.
MOTORS
Removing/Replacement/Rewinding/Transportation/Shifting/Alignment/Earth connections etc.
ON LINE SEALING
On-line leak sealing Steam and water etc., (Identification of exact leakage by removing
insulation, scaffolding & preparatory jobs to carry out the work.)
REVERSE ENGINEERING
Drawing development of any equipment/system to be identified & completed within 01 year of
effective start of the contract.
TECHNICAL CONDITION
The contractor shall arrange himself the tools and tackles including welding machines, gas-
cutting sets. TIG welding sets, flexible grinding machine, hand drilling machines, pneumatic
grinding machine, screw and hydraulic jacks, lifting tools and tackles (chain blocks, hook
chuck, slings etc), hand lamps with transformer (24 V only) etc. for the routine maintenance
and Owner shall provide only some special tools supplied by the EPC contractor. All contractor
tools should have valid certification and proper history and records should be maintained for
above lifting, hand and power operated tools in line with ISO systems.
2. ELECTRICAL SYSTEM:
SCOPE OF WORK
The Scope of work shall cover complete electrical system available inside the power plant
campus. The Construction Power supply and electrical power supply maintenance shall be in
the scope of O&M Service Provider. Major electrical systems only are detailed as follows, the
electrical equipment /system not mentioned here but available inside the power plant campus
shall also be included in the O&M Scope.
Page 54 of 159
765 KV,400 KV & 132 KV GIS SWITCH YARD:
Preventive, Predictive, Breakdown and Shutdown maintenance of GIS, Line, SCADA system,
PLCC/FOTE system, CMS, EMS, ABT, SF6 system, Insulators, Gas Insulated Ducts, Circuit
Breaker, Isolator, CT, CVT, LA, Wavetrap,. Repair, Replacement of
equipments/parts/defectives along with shifting-lifting-Loading-Unloading of material. CBM,
Thermography, Testing of equipments.
Preventive, scheduled predictive, Breakdown & Shutdown maintenance of switch gears and
replacement of insulators/SF6 pressure/megger values of the equipment/oil level in CT &
/CVT/ICT/LA/Insulators /circuit breaker operation timings / interlocks /control and power
circuits tightness of all connections/removal of grass in switchyard/Closing and opening
operation of isolators/earth pits & connections, meggering of earth pits, safety requirements. IR
value testing, of all above items, change fasteners, oil testing, replacement of CT, PTS,
Replace/Repair of any part of the above yard. CBM of all equipment, Thermography of OH
line. Checking and maintenance of Fire-fighting system. Prepare and maintenance of check list
daily and maintenance done during the shutdowns. Arrangement of OEM as per requirement.
Energy meter readings on daily basis.
HT MOTORS
Preventive, routine, predictive, Breakdown maintenance & overhauling of HT motors:
Cleaning, Checking, repair and replacement of lubricating oil/bearings/vibration/signature
analysis/terminal connection/control and power circuits/tightness of power cable
terminations/insulation/fasteners/winding resistance and inductance/interlock and trip
contacts/cooling system/abnormal sound/rewinding/machining work for rotor shaft-housing-
end covers and bearing temperature/Circuit Breaker operations/earth connections/control and
power cable laying and jointing/safety requirements/Shock pulse monitor/Temperature
Page 55 of 159
measurements / Vibration measurement/Testing of Motors(IR & PI Test, Tan Delta Test,
Winding Resistance Test) . Replacement of damaged parts, bearings PB, TB loops etc.
LT MOTORS
Preventive, routine, predictive, Breakdown maintenance & overhauling of LT motors :
Cleaning, Checking, repair and replacement of lubricating oil or grease/bearings/
fasteners/vibration/terminal connection/control and power circuits/tightness of power cable
terminations/insulation/winding resistance and inductance/interlock and trip contacts/cooling
system and ribs/abnormal sound/ machining work for rotor shaft- housing-end covers/ winding
and bearing temperature/Circuit Breaker or starter operations/earth connections/control and
power cable laying & jointing /safety requirements/Shock pulse monitor/Temperature
measurements/Vibration measurement/Rewinding etc. Routine test as per requirement.
DC MOTORS
Preventive, Scheduled, predictive, Breakdown & Shutdown maintenance of DC motors.
Cleaning, Checking, repair and replacement of carbon brushes holders’ air filter commutator
drop test. IR value load and no load trials, repair/replacements of motors. DC panel power &
control checking, clamping, repair and replacement of components. Routine test as per
requirement.
CRANES
Preventive, routine, predictive and breakdown maintenance of EOT, Monorail, Hoists &
Elevators : Cleaning, checking, repair and replacement of control and power fuses/fixing and
moving contacts/arching chutes/control and power circuits/insulation values of switch gear and
bus/Operation of contactors and MCCB/ interlocks/tightness of power and control circuits/load
Page 56 of 159
currents/ammeters/voltmeters/relays/control transformer/, timers/manipulator /limit
switches/down shop leads / pantographs/cables/control and power cable laying & jointing
indications/earthing/danger boards/safety Requirement.
PROTECTION SYSTEM
Cleaning, checking of all the relay and protective panels of 765 KV, 400 KV, 132 KV,11KV,
3.3 KV, 0.415 KV and all other voltage level system protection relays/instrument transformers
and generator protection system. Check the tightness of control circuits/auxiliary supply / signal
and protective relays/testing and calibration of protective relays/trip circuits/ earthings/primary
injection test/secondary injection test, once in a year or as per requirement. Calibration of
Energy meters installed as per UPPCL / UPERC guidelines.
CONTROL ROOMS
Periodical cleaning, checking, repair and replacement of GCP and ECP control panel
elements/tightness of control circuits/AC and DC supply/indication bulbs/rotary switches/signal
lamps/annunciators.
ESP
Periodical cleaning, Testing and checking of all the HV and LV panels, Thyristor panels
rectifier transformers, rapper motors, hopper heaters Support insulator Heaters, Micro
controller panel, other electrical equipment available in ESP. Tightness of control and power
circuits’ terminals have to be performed periodically.
Page 57 of 159
HVAC EQUIPMENT, WATER COOLERS AND PURIFIERS
Preventive, predictive, routine and Breakdown maintenance of HVAC System including
package type, window type, split type and Centralized air conditioners, water coolers and
purifiers, Cleaning, checking, repair and replacement of air filters/fans/gas
charging/replacement of compressor/power and control Circuits/humidity/temperature
/Earthing for plant and offices.
VFDS
Checking, Cleaning, tightening of control & Power connections, replacement of components,
control circuits checking, trouble shooting and condition monitoring.
DIESEL GENERATORS
Preventive, predictive, routine and Breakdown maintenance of DG, Excitation, battery, battery
charger, synchronizer, control circuit, power circuit & panels including troubleshooting,
cleaning, checking, repair and replacement of faulty parts. Cleaning and changing of filters /
lubrication of bearings / winding and bearing temperatures /testing / meggering / exciter
connections/earthing. DG set Auto start testing on weekly basis is also included in the scope.
Data backup of SCADA, RMS & EMS system has been made by O&M Service Provider as
and when required by Owner /Server capacity reaches its upper limit.
EARTHING&LIGTNING:
Ensuring Earthing & lightning protection system availability as per system requirement.
Periodic watering for the earth pit and Earth Resistance Measurement has to be carried out by
the O&M Service Provider. Repairing work of earth pit chamber to be carried out by O&M
Service Provider.
Page 58 of 159
PLANT SECURITY SURVEILANCE&COMMUNICATION SYSTEM:
Following systems have to be Operated & maintained by the O&M Service Provider
• Plant Security and Surveillance CCTV System
• Public Announcement & Talk Back System
• EPABX-Telephone System
• UHF Wireless system
O&M Service Provider has to ensure the 24X7 operation of all the CCTV cameras and
continuous recording for the backup.
SHIFTING/LOADING/UNLOADING
Shifting, Loading, unloading of materials, spare parts from store to workplace, work place to
store, central store to local store, local store to central store, inside the plant movement and to
outside agency for repairing with arrangement of hydra and suitable vehicle.
LOCAL STORE
Maintaining the local store with the history of spare issued and used; proper tagging and health
card/testing date to be fixed. Testing of spare parts before use. Maintaining the defective parts,
damaged batteries, used grease. Monthly reconciliation status of spares, lubricants, motors,
bearings, consumables to be provided to owner. Defective parts only be declared as scrap with
written approval of owner. If the owner repairs any defective component/part/equipment
declared as scrap by the contractor will be debited from Contractor’s bill.
SAFETY/5S
Safety at workplace, Work permit system, proper check sheets, placing of danger board, men
on work board, hazard identification & elimination, cleaning of workplace, proper tagging,
LOTO, cleaning of panel rubber mats. 24V lamp with transformer while working in confined
area.
Page 59 of 159
TECHNICAL CONDITIONS
Providing necessary manpower, extension board with cable & top, LED, halogen, hand lamp,
tools and tackles for overhauling of transformers and generators and auxiliaries as and when
required and when experts come from outside.
All the supervisors should have ‘C’ license and skilled electricians should have either ‘B’ or
‘C’ license to carry out the maintenance work in the entire electrical system. Contractor should
have either EA or ESA license to carry out any addition/modification/defect rectification works
in the electrical system.
The contractor shall arrange necessary tools and tackles like measuring instruments like
Megger (HT & LT), Multimeter, Tong tester (AC and DC), Earth megger, timing testing kit,
Contact resistance meter, timing testing kit, micro-ohmmeter, secondary injection kit, variac,
phase sequence meter, hydrometer, Motor checker etc. for routing, preventive and breakdown
maintenance.
For regular maintenance work, emery roll, sand paper, commutator cleaner, electronic
component cleaner, necessary Insulation tape (PVC/Para/Empire/Fibre-glass/Glass
mica/Cotton), cotton waste, cotton cloth, Petrol, Kerosene, Diesel, CRC-226, Rustolene, CTC,
lugs, soldering iron, de-soldering pump, test board, 24 V hand lamps with transformer and all
cleaning elements etc., shall be in the contractor scope.
The contractor should take care of the safety for employees and Machinery. For that the
contractor should arrange the required earth rods, hand gloves (15 KV), fuse Pullers, Torch
light and insulated tools etc.,
Standard bearing heater (coil type and oil immersed), Standard bearing inserting pipes (Not
handmade), and all types of standard pullers for removal of bearings, couplings and pulleys are
in contractor scope.
O&M Service Provider has to coordinate and do Liasioning work for any external technical
audit.
Immediate attention is to be paid for the breakdown defects, problems for all control & Power
circuits and to be rectified in a reasonable time.
All power and control wiring modifications, replacement of any part for indigenization of
spare, any type of temporary arrangements for any requirement is there in maintenance agency
scope.
Daily checks for all equipment should be done daily in a particular time and the same should be
submitted to NUPPL engineers daily.
Filled logbook duly signed by the supervisor should be submitted to NUPPL engineers daily.
However, the completed log book should be handed over to NUPPL for future reference.
Page 60 of 159
All spares handling with tagging, maintaining the lab equipment and related areas, store rooms
and overhauling areas neatly.
Any requirement of the system to work in online has to be taken up online and the safety of
men and material has to be taken care by the contractor.
Maintaining of all records should be as per ISO standards. Tr. Oil BDV, Tr. Oil Acidity, Earth
Resistance, Equipment List, HT motors IR, PI & Dielectric absorption factor, History of
equipment, List of authorized persons, Check list for all equipment, PM Schedules month wise,
yearly, CAPA, Overhauling report, Daily & Month-wise Spare Consumption report, Analysis
of Break down (MTBF), Failure Analysis Report etc. All above are to be maintained in
chronological order as a part of ISO. Filing of history cards in regular basis.
Page 61 of 159
limit switches, solenoid valves, on-line analyzers, analytical instruments etc.
• Routine checking of control power supply, main power supply, connection
tightness etc. for all the C&I systems, impulse line tightness checking/leakage
detection and arresting for all the pneumatic actuators and tightness associated
with hydraulic lines.
• Contractor has to arrange for temporary power supply from the point provided in
plant by Owner for site calibration, maintenance, and repair works execution.
Contractor shall provide all the hardware required for making these
arrangements.
• Contractor has to arrange for temporary instrument air supply line, from the
point provided at site for calibration, maintenance, and repair works execution.
Contractor shall provide all the hardware required for making these
arrangements.
• All maintenance/repair jobs in standalone control system, DDCMIS and PLCs’
will be in Contractor scope.
• Contractor using the laboratory/laboratory equipment provided by Owner will
carry out all calibration works in the laboratory or if possible in the field itself
whichever is applicable. The routine/preventive maintenance in the laboratory
such as charging/replacing batteries for electronic equipment, minor
rectification/repair jobs, cleaning of laboratory will be in Contractor scope.
• Contractor has to daily/periodically check/inspect the field instruments, panels,
actuators, transmitters, impulse lines etc. In case of any
damage/misalignment/mal- operation/abnormal conditions/ leakage, will have to
immediately rectify and inform the same to Owner Engineers.
• All maintenance/repair/overhauling etc. for the pneumatic/hydraulic actuators.
• Interlock; loop (starting from field end till the field end to panel end).
Continuity-checking, cable, impulse line-tracing, sequence of operation
checking, trip setting are to be carried out by Contractor at the
discretion/guidance/assistance of Owner Engineers.
• Routine/daily cleaning/removal of oil stains, dust, rust from panels, air filters of
panels, actuators, junction boxes, field transmission assemblies, flame scanners,
ignitors, field instruments/mounting/supports, other equipment etc. will be in
Contractor scope. Whenever possible mechanical means will be used.
• Maintenance, minor repair works, cleaning of computers, printers, mouse etc.
involved in plant automation.
• Painting of damaged, dismantled, and rusted portions etc. in field
instrumentation and panels.
• Applying lubricant, cleaning filters, removing chokes in the impulse line, filters,
plugging leaks etc.
• Attending Trouble shooting and other emergency time/jobs.
• Removing the indicators, recorders, transmitters, valves and other instruments,
equipment, monitors of the entire power plant and transporting them to stores,
laboratory and vice versa or outside the plant for servicing, repair and re-fixing
them in their appropriate places.
• Checking of cables and terminations, Laying and connecting of cables as and
when required
• Fabrication of items like canopies, junction boxes, Panel cutouts for installing
any instruments, mounting brackets for any field mounted instruments, siphons
for instruments, thermowell for temperature gauges and impulse lines
fabrications.
• The checking instruments like multimeters, meggers, clamp meter, loop
Page 62 of 159
calibrator, HART calibrator, pneumatic receiver gauges, soldering station,
pneumatic/instrument line tools like cutter bender etc. shall be contractor’s
scope.
• All consumables including brass fittings, non-metallic & metallic tubes shall be
under contractor’s scope.
• The removing, replacement, shifting of field and panel instruments and control
valves as per advice of Owner engineers shall be in contractor’s scope.
• Maintenance of lab instruments, provided by Owner & of its own.
• Calibration of Master calibrating instrument by recognized and authorized
external agency.
• Passivation and preservation of removed instrument.
• OEM support for specialized activities on owner’s instruction.
• Tools as per owner’s instruction.
• Tagging of instruments and cables.
• Instrument network maintenance
• Communication tools such as laptop, cables will be contractors’ scope however
relevant software will be owner’s scope
• Requirements related to boiler inspector and environmental auditors to be
fulfilled by contractors
• Material movement from store to site and site to store.
• Managing of local store for critical spares.
• Site cleaning after maintenance activity.
• Calibration of pneumatic/hydraulic actuators, positioners etc. whenever required
for smooth operation of the plant. Maintenance of pneumatic actuators and C&I
components of hydraulic actuators.
• Maintenance of Turbovisory instruments: Vibration sensors like Acceleration /
seismic / piezoelectric/proximity/LVDT, Etc.
• Preventive maintenance of O&M Service Provider stations / Servers / Network
components including switches, media converters and its cables.
• Preventive maintenance of Backup drives, Data archiving of Historian PC.
Backup of all controllers including logics, graphics etc are to be taken
periodical basis (For eg. In each month or 15 days).
• Cleaning & Re-arranging the Spares in the C&I stores and Lab.
• Cleaning of instrument cable trays.
• Regular Maintenance of furnace camera.
• Maintenance of oil burner ignitors & assemblies.
• Flushing of transmitters (non-critical in regular maintenance, critical one in shut
down).
• Soot blower maintenance during three shift operation for RAPH & Boiler.
• Preventive maintenance of mill instruments during mill maintenance period.
• Maintaining the daily log for the preventive maintenance activities.
• OFC cable splicing work.
• Uploading of air quality and pollution data to pollution control boards.
• All maintenance and calibration SOPs to be prepared and maintained.
• All equipment and instruments specification, history register to be maintained.
• All DCS /PLCS SYSTEMS all types of lists of spares to be maintained by
maintaining history register separately.
• All consumables including printers, scanners, printer cartridge & papers etc to be
maintained.
• Supporting manpower required for any modifications recommended by OEM.
Page 63 of 159
• All panels(C&), monitors, keyboards, control desks, CER rooms, CCR room and
engineering rooms are neatly cleaned and maintained.
• Electronic and other C&I scrap materials including cable scrap to be shifted to
the designated location.
• All local JBs and local panels to be covered with water/dust proof material and
to be maintained regularly.
• Contractor shall depute experts in various areas such as PLC, DCS,
ANALYZERS, CEMS, Hydraulics, Pneumatics, Laboratory (chemical and
instrument) etc.
• Contractor has to inform owner about their spare requirements well in advance.
Contractor has to develop SMPs and has to take approval of owner.
• Contractor has to keep minimum manpower (for normal maintenance or for
overhauling/shutdown) as decided by owner. Contractor manpower must be
available in plant in all the running units for 24 hours in shift basis.
• Laying / Removal of instrumentation and control cables as and when any
modification, safety, maintenance requirement jobs are being done.
• The supporting services required for maintenance of GA1, GA2, GA3 DCS
system, separate AMC/BMC contract shall be under the scope of O&M Service
Provider.
• The supporting services required for maintenance of Aux Boiler PLC system,
HVAC PLC, Bidhanu Pump house PLC shall be under O&M Service Provider
scope.
• All standard chemicals / buffer solutions required for calibration of analyzers
shall be under the scope of O&M Service Provider.
All the parameters related to the health and safety shall be closely monitored and controlled by
the dedicated supervisory manpower and the reports shall be submitted to NUPPL periodically
as per the below format/any other format sought by NUPPL from time to time:
Page 64 of 159
Restricted Work Injury
Lost Time Injury (Not
Including Fatalities)
Fatal Injury
Man Hours Worked
Man-days Lost Due To
Restricted Work Injury
Man-days Lost Due To
Lost Time Injury
Total Man-days Lost
Near Misses
The O&M Service provider shall strictly follow Standard Operating Procedures (SOP’s) for the
works which shall not be limited to the following as a part of O&M policy:
• Work Permit System
• Handling of Gas cylinders
• Vehicle Maintenance
• Material Handling
• Electrical Isolation
• Rigging Safety
• Work at Height
• Excavation Job
• Work in confined space
• Hydra Crane operation
EXCLUSIONS
• CISF offices housekeeping (inside and outside plant boundary)
• Township
• Coal Railway siding (limited to track area only)
BUILDINGS
1. Walls clean.
2. Windows clean.
3. Walls free of unnecessary hangings.
4. Proper light provided.
5. Platforms in good condition.
6. Stairs clean and well lit. Handrails and steps of sound construction and well
maintained.
Page 68 of 159
FLOORS
1. Good floor surface.
2. Kept clean and free of loose material. Clean in corners, behind radiators, along
walls, and around pillars or columns.
3. Free of oil, grease, etc.
4. Operating floors, or work positions free of loose scrap, metal or other materials.
5. Free of unnecessary articles.
6. Bins provided for refuse.
AISLES
1. Free of obstructions.
2. Safe and free passage to fire-fighting equipment and fire exits.
3. Safe and free access to work positions.
4. Clearly defined.
TOOLS
1. Properly arranged in place.
2. Free of oil and grease.
3. Inspected and maintained in good order.
4. Tool rooms and racks in clean and orderly condition.
FIRE PREVENTION
1. Store flammable and combustible liquids in proper containers
2. Keep reactive chemicals separated
3. Prevent the accumulation of combustibles
4. Keep combustibles away from electrical equipment and hot machinery
Page 69 of 159
4. Ensure that electrical panels can be opened
CHEMICAL SAFETY
1. Make sure containers are properly labeled
2. Inspect containers for signs of damage
3. Wear required PPE
4. Follow safe storage and handling procedures
5. Clean up spills
MACHINE SAFETY
1. Keep the area around machines clear
2. Inspect machines before use
3. Make sure all guards are operating
4. Follow lockout/tagout procedures
5. Clean machines and put away tools
ELECTRICAL SAFETY
1. Keep heaters and furnaces clear
2. Inspect electrical cords before use
3. Don’t overload outlets or circuits
4. Keep combustibles away from electrical equipment
5. Keep electrical equipment clean
PPE HOUSEKEEPING
1. Inspect PPE before each use
2. Clean PPE regularly
3. Store PPE properly
4. Replace PPE when necessary
Page 70 of 159
recyclable materials in the designated bins with lids.
• To keep the floors free from excessive material.
• To ensure that aisles and walkways are clear, unobstructed and in good order.
• To ensure that materials are stacked correctly and safely in the correct places.
• To do an informal housekeeping inspection of the area on a daily basis and to
rectify housekeeping hazards.
• To monitor that no items are stacked in no stacking areas such as under fire
equipment and electrical switchgear.
• Report faded housekeeping notices and signs.
• Always return tools to their correct place after use.
• Ensure that spill and other tripping \ slipping hazards are cleaned up or fixed.
Page 71 of 159
appropriate conditions and affixed with GHS labels.
Physical barriers and warnings signs are installed around -Yes -No
workplace hazards (e.g., sharp objects, protruding objects, a
hot surface, a floor opening).
Proper waste bins for general waste, recyclable waste, -Yes -No
hazardous waste, and so on are provided at work areas to
facilitate responsible disposal.
Combustible waste is properly disposed of. For example, -Yes -No
oily rags are disposed in closed metal waste bins.
Waste (including hazardous waste) is collected regularly so -Yes -No
that there is no unnecessary accumulation of waste.
A predetermined disposal area has been designated for -Yes -No
situations where waste materials (e.g., bulky waste, toxic
waste) need to be accumulated till the next waste collection
date.
Page 72 of 159
8. The received material shall be properly stored and the unwanted package
materials or spoiled/ damaged materials shall be disposed at the disposal yard or
any other designated location as per the instruction of NUPPL EIC.
9. Assisting in dispatches of materials returned to suppliers & sending materials for
repair or transfer.
10. Packing materials as required for Delicate/Electronic items as per site requirement
shall be arranged by the O&M Service Provider.
11. The O&M Service Provider shall be responsible for the safe handling of materials.
In the case of the loss of materials due to theft/ or otherwise / any shortage of
material due to any abnormal reasons / improper material handling leading (during
unloading, loading, shifting) any material damage, the value of such loss of
material (attributable to O&M Service Provider) shall be to the account of the
O&M Service Provider.
12. Assistance in Stock verification and identification: Posting of day-to-day receipts
and issues in stock ledgers/ computer master by O&M Service Provider, so that
the current balances of each item are known without physical counting or
checking.
13. The vehicle should be unloaded immediately after receiving within the
permissible time period. In case of any demurrage charges to be paid for
unloading of receipt materials due to the fault of the O&M Service Provider, as
defined in the scope of work, the actual demurrage charges will be booked in the
account of O&M Service Provider.
14. Shifting, loading, unloading of materials, spare parts from NUPPL main store/
O&M local store to workplace, workplace to the NUPPL main store/ local store,
NUPPL main store to local store, local store to NUPPL main store, inside the
plant movement and to an outside agency for repairing with the arrangement of
hydra and suitable vehicle are in O&M Service Provider’s scope.
15. The O&M Service Provider shall deploy the following indicative minimum
manpower with a total of 24 Nos to NUPPL Main Store/Central Store on daily
basis:
a. Store Manager: 1 No.
b. Store Supervisors (including data entry operator): 6 Nos
c. Heavy Duty Vehicle Operator: 3 Nos
d. Skilled Workmen: 3 Nos
e. Semi-Skilled Workmen: 3 Nos
f. Un-Skilled Workmen: 8 Nos
Note:
a. The above said minimum manpower is only indicative. However, the O&M
Service Provider shall continuously engage sufficient number of personnel for
ensuring trouble free work execution.
b. On non-working days, minimum manpower shall be ensured at central store as
per the instruction of NUPPL EIC in order to provide trouble free spare issuing
as per site requirement.
16. Providing necessary assistance in Performing the necessary store’s operation
management from the steps mentioned below as notified by NUPPL EIC:
a. SAP codification of all items including spares and consumables.
b. Receipt of material and making Transport Memorandum “(TM)
c. Case opening (COP)
Page 73 of 159
d. Check Measurement Report. (CMR)
e. Goods Receipt Note (GRN).
f. Issue of accepted & accounted material to the Indenters based on stores
requisition (SRQ).
g. Issue of rejected material to the supplier based on their request letter
17. Transportation of materials/ rejected materials: The O&M Service Provider to Co-
ordinate of consignments received at Kanpur/ Ghatampur/ Hamirpur/ nearby
vicinity (within a range of 100 Km) and arrangement of transportation of the same
to the site. Transportation of material from Kanpur/Ghatampur/ Hamirpur /nearby
vicinity is applicable for small weight material only (i.e. up to 100 kg). The
transportation charges will be charged by the contractor/service provider to
NUPPL. If it is heavy equipment, NUPPL shall arrange a vehicle and the O&M
Service Provider shall provide necessary manpower assistance and coordination
with the transporter for the shifting of material.
18. Assisting in the periodical checking of the materials and reporting the defects to
the NUPPL stores authorities.
19. Rearranging the materials from one location to another location whenever
required as per the directions of NUPPL EIC in and around the store area.
Assisting in the normalization of the system.
20. Housekeeping & Cleaning: The entire store’s division area shall be always kept
clean to avoid any accidents. Periodically cleaning the stored materials and
materials storage racks with required industrial blower equipment (minimum 02
Nos), Up Keeping the store’s area to keep free from dust by using powered
Industrial vacuum cleaners (minimum 2 Nos), including cleaning accessories and
protective covers/materials for motors, circuit boards, bearings, materials which
require protection against dust/ coal/ ash inside/outside the stores shed and
housekeeping shall be in the scope of O&M Service Provider. Wherever packing
is required, the O&M Service Provider shall pack the materials in a visible way so
as to safeguard the materials from the dust environment/rain water.
21. Housekeeping and packing of materials - Store area, store office and materials
cleaning including sweeping, cleaning, disposal and complete removal of dust,
floor water washing, removal of bushes, wood, stones, etc, are in the scope of
O&M Service Provider at Main store/ Central Store/ Warehouse and O&M site
stores.
22. Routine inspection / checking of stores area oil/ gas/ chemical storage area to be
carried out by O&M Service Provider in each shift.
23. Cleaning the oil spillage due to oil leaks by providing sand/ cleaning the spillage
with cotton waste. Dumping the collected waste in the suitable bins provided.
Informing any oil leakage to NUPPL Stores EIC.
24. Scrap Disposal Co-ordination works: The O&M Service Provider to co-ordinate
for e-auction of scraps in the disposal yard and allied works as directed by
NUPPL Store EIC.
25. Miscellaneous store-related works comprise counting, weighing, and stacking of
materials in specified locations with identification labels, and painting/ writing/
marking on items for identification, Maintenance of weighing scales & weighing
machines.
26. The O&M Service Provider to consolidate the requirements of common items like
consumables, lubricants, cement, gas cylinders, welding rods, steel items and
Page 74 of 159
other items as notified by various divisions of NUPPL at the instruction of
NUPPL Stores EIC.
27. The departmental sub-stores where day to day maintenance spares need to be
maintained, shall be coordinated by the O&M Service Provider for smooth
operation. O&M Service Provider can be made responsible for the stock
maintenance of these spares which shall be reconciled along with the maintenance
activities.
28. The O&M Service Provider shall be conversant with SAP system for entering all
the inputs. Customized provision with necessary access for the O&M service
provider in NUPPL SAP system may be provided by NUPPL if required.
Page 75 of 159
5. Responsible for the overall operations of the Plant (Excluding CCR and
Switchyard Control Room Operation).
6. Responsible to the Plant Manager to develop operational objectives consistent
with achieving maximum plant efficiency to meet Owner requirements in the most
safe, reliable, economical and environmentally safe manner.
7. Establish operating budgets and maintain operation records.
8. Responsible for scheduling of all operations personnel and for the Operation of
the Plant in a manner consistent with the Plan of Daily Operation and the Owner's
Requirements.
9. Will be on call 24 hours per day with backup from the Plant Manager.
10. The Operation Manager will be skilled in the operation and maintenance of power
plant equipment so as to be able to direct emergency repairs of that equipment.
11. Reports to Plant Manager.
12. Duties:
- Maintenance of Plant files and records of plant operating data
- Monitor the functions of the DCS and control room computer, devices and switches that
will maintain the necessary process parameters.
- Monitor process parameter reading from controls for long term variances from normal
trends
- To respond to the variances and to issue instructions to adjust and maintain proper
process conditions.
- Maintain an operating log book.
- Direct the Operators to achieve the goals of operating the plant during the shift
- Assist the Plant Management in running an efficient and high availability plant.
- Maintain the Maintenance Requests Log and be aware of the maintenance work in Plant
so that it will not affect the plant operation
Control Room (Excluding CCR and Switchyard Control Room) Engineers (Shift In-
charge & Desk Operator)
1. O&M Service provider shall envision for 3×8 hour shifts to ensure 24X7
operation manpower availability. The Shift in-charge have primary responsibility
for the overall safe and efficient operation of the plant during their shift.
2. Desk Operator’s Reports to Shift In-charge and Responsible for Safe operation of
the Plant including monitoring, recording and charting plant performance via
computerized monitoring systems in the control room. Be able to direct the start-
up and shut-down of the entire Facility. Monitor the functions of the DCS and
control room computer, devices and switches that will maintain the necessary
process parameters. Maintaining the plant operating data records.
3. Each Shift engineer will lead a shift crew, who will have responsibility for
operator and equipment technicians who will have responsibility for local
equipment operation, and for performing routine maintenance tasks including
lubrication, greasing, filter changes, etc.
4. The Operators, under the direction of the SIC are responsible for the safe
operation of the Plant to include monitoring, recording and charting plant
performance via computerized monitoring systems in the control room.
5. The Operators will be able to direct the start-up and shut-down of the entire
Facility in a controlled fashion as well as react to emergencies without risking the
safety of personnel or equipment.
6. The Operators will direct the work of other plant Operators and report to the
Operation Manager.
7. The Relief Operators will be available to perform and/or assist in mechanical
maintenance activities as required, and will also be available to cover shifts
vacated by other Operators due to vacation, sick, and personal time.
8. Duties:
- Operate keyboard and console to access computers
- Monitor, record and chart readings from the computerized plant control and monitoring
systemfor variance from prescribed operating standards or procedures.
- Respond to variances by adjusting and maintaining process parameters according to
Operating Instructions Manual and current practices.
- Maintain close contact with other Field Operators to maintain process parameters per
system requirements.
- Monitor Plant-operating functions in accordance with Operating Manual for items
indicating maintenance.
- Operate the plant in a safe and efficient manner.
- Report items beyond scope and capabilities of shift personnel to Operation Manager.
- Assure that the control room is staffed on a constant basis.
- Maintain Plant files and record of plant operating data.
- Assure proper information is observed, maintained and recorded for water, temperature,
and pressure level throughout the Plant per prescribed settings.
- Monitor Plant equipment and facilities for safe performance and correct operations.
- Respond to variances as instructed by the Operators or Operation Manager to adjust and
maintain proper operation of equipment.
Page 77 of 159
- Monitor Plant facilities and equipment for safe performance of equipment and
operation.
- Perform adjustments and minor maintenance corrections on equipment found operating
beyond the prescribed setting or an unsafe condition (oil, air, heater, steam, and leaks,
piping).
Page 78 of 159
Technician, Electrical:
1. Responsible for performing routine and complex maintenance tasks on all Plant
electrical equipment.
2. Reports to the Maintenance Manager.
3. Duties:
- Diagnose systems and electrical circuit equipment problems
- Repair Plant electrical equipment
- Maintain electrical drawing files and maintenance records on all plant electrical
equipment
- Develop preventive maintenance programs on all electrical equipment
- Assist in training shift personnel in preventive maintenance and operating procedures
- Review engineering specifications and drawings
- Maintain Spare Parts inventories on all electrical equipment in the Plant
- Responsible for assisting the Maintenance Manager in scheduled and unscheduled plant
outages and shutdowns
- Be familiar with, and adhere to, all Site EHS regulations
- Evaluate electrical system data to determine maintenance schedules and ensure optimum
operation of the Plant
- Experience on low and high voltage circuits
Page 79 of 159
Plant Engineer (Efficiency)
The Plant Engineer is responsible for the technical performance of the plant. The Plant Engineer
is responsible for developing and conducting system and equipment component testing
programs to assess performance, reducing operational costs by improved plant efficiency, and
for interfacing with regulatory agencies on plant environmental compliance issues.
Sr Chemist/Chemist
The Plant Chemist is responsible for fuel testing and maintaining water chemistry of the plant
including the testing and maintenance of all the laboratories.
Safety Officer
The Safety Officer will conduct plant safety inspections, audit the effectiveness of safety
procedures and provide routine training for operation and maintenance personnel. The Officer
will utilize outside resources as required to maintain an effective workforce skill.
Page 80 of 159
ANNEXURE - B - FUEL SPECIFICATIONS
Tentative COAL ANALYSIS FOR O&M
1.2 Ash % 42 43 35 34
2.5 Moisture % 9 12 12 12
2.6 Ash % 42 43 35 34
2.5 to 15.7
(j) Kinematic viscosity (cst)
(at 40°C)
Page 81 of 159
ANNEXURE C -RAW WATER ANALYSIS
1 PH at 250C - 7.09
77 (Normal)
2 Turbidity NTU 200 (Maximum)
Page 82 of 159
ANNEXURE D - PLANT ENVIRONMENTAL DATA
Page 83 of 159
ANNEXURE - E
O&M SCORECARD
IF HSESC>60 , Score=
As per the HSE Score
10 HSE (HSESC) /100 7
Card (HSESC)
If HSESC < 60, Score=0
Total 100
Page 84 of 159
Contractor Performance Score Card - BMD
Month: - GTPP 3x660 MW
Sl. Weig Action Additio
Parameter Criteria Score Remarks nal
No. htage Plan Remark
Page 85 of 159
Contractor Performance Score Card - TMD
Month :- GTPP 3x660 MW
Addit
Sl. Weig Action ional
Parameter Criteria Score Remarks
No. htage Plan Rema
rk
• Full Marks if Availability is 100%.
1 TDBFP Availability • Prorata for availability >=90% & < 100% 15
• Else: Zero
EOT Crane • Full Marks if Availability is 100%.
2 Availability (TG and • Prorata for availability >=90% & < 100% 5
TDBFP Area) • Else: Zero
Ensuring availability of
• Full Marks if Availability is 100%.
Oil Purification unit for
3 • Prorata for availability >=90% & < 100% 10
various system in TG
• Else: Zero
Area
Maintaining Oil Full Marks: If Oil quality within OEM
4 Quality as per OEM standard Limit 10
standard Else: Zero
Condenser Vacuum Full Marks if above >0.91
5 (Attributable to O&M Prorata bet 0.89 to 0.91 10
Service Provider) Below 0.89: Zero Marks
Availability of
following critical
system in Turbine • Full Marks if Availability is 100%.
6 Area: • Prorata for availability >=90% & < 100% 10
a. CPU • Else: Zero
b. OLTCS
c. DFs
• Full Marks, if Compliance is 100%.
PM Schedule
• 90% of Marks if compliance ≥95% &
Completion
7 <100% 10
(PTW issued to O&M
• 70% of Marks if compliance ≥90% & <95%
Service provider)
• Else: Zero
• Full Marks if Defect Compliance ≥95%
• 90% of Marks if compliance ≥90% & <95%
8 Defect Compliance 10
• 70% of Marks if compliance ≥80% & <90%
• Else: Zero
Full marks if No of leakages is Zero
9 Oil Leakage 3 marks if No of leakages is > 0 & <=2 5
Else Zero
CBM Compliance
• 100% Compliance: Full Marks
(Vibration, Oil
10 • Prorata for Compliance from 90 to 100% 10
analysis, thermography
• Else: Zero
etc.)
Compliance to audit
observations points
• Full Marks if Compliance ≥90%.
such as Fire Fighting,
• 80% marks if compliance ≥80% & <90%.
Statutory, Safety
11 • 60% marks if Compliance ≥70% & <80% 5
Standards, IMS, EnMS,
for the month as per scheduled plan.
UA/ UC, VSAP, Safety
• Else zero
Alert, leadership
walkdown, etc.
Total 100
Page 86 of 159
Contractor Performance Score Card- Water & BOP
Month: - GTPP 3x660 MW Power Plant
Sl. Action Additional
Parameter Criteria Weightage Score Remarks
No. Plan Remark
• Full Marks if firefighting
Firefighting system
Equipment Availability 100%
availability (pumps,
1 • Prorata from 90% to 100% 10
hoses, Hydrant
availability
points, nozzles etc.)
• Else zero
Availability of Fire
Hydrant at Highest • Full Marks if Availability
2 Point & Farther Point 100% 5
in NUPPL Plant • Else zero
Premises
Full Marks: if availability is 100
Availability of Spray %
3 Deluge valves in Prorata for availability >=90 % 10
Auto & <100 %
Else: Zero
By running Jockey Pump: Full
Maintaining Fire Marks
4 Hydrant & Spray If any other pump running is 5
Header Pressure required at no fire condition:
Zero
• Full marks if there is no
Leakages from Acid leakage or one leakage which is
and alkali storage attended in stipulated time.
5 10
and conveying • 80% marks for 2 leakages
system • 60% marks for 3 leakages
• else zero
The COC criteria
COC (Monthly • Score 5: If COC> 5 value is subject
6 running average of • Score 3: If COC>=4 & <5 5 to revision after
all units) • Else zero commissioning
of FGD.
Vertical Pumps • Full Marks if Availability is
Availability >=95%
7 10
including standby • Prorata from 85% upto 95%.
system • Else: Zero
i. Pre-
Treatment
Plant:
Turbidity < 2
NTU
ii. UF-RO-MB
Deviation from DM Ful Mark if no deviation Plant:
8 10 UF-SDI < 3
Water Quality: Else: Zero
RO-RO Permeate
< 4 ppm
CO2 at the outlet
of DG tower
after RO < 5ppm
as CO2
Page 87 of 159
MB Unit
Conductivity at
the outlet < 0.1
microsiemens/cm
Ph: 7+/- 0.2
Total Silica <
0.01 ppm as Sio2
CW Chemical
Dosing:
Scale inhibition
efficiency <
15mg/dm2/day
Residual
Chlorine in CW
system in ppm:
0.1 to 0.2 ppm
Full marks: If availability
Ensuring availablity >=98%
9 of HVAC System in Prorata for availability from 10
all areas 85% upto 98%
Else: Zero
Full mark: If SWC < 3:
Sp Water
10 prorata upto 3.5 5
Consumption (SWC)
Else: Zero
• Full Marks, if Compliance is
PM Schedule 100%.
Completion • 90% of Marks if compliance
11 (PTW issued to ≥95% & <100% 10
O&M Service • 70% of Marks if compliance
provider) ≥90% & <95%
• Else: Zero
• Full Marks if Defect
Compliance ≥95%
• 90% of Marks if compliance
12 Defect Compliance ≥90% & <95% 5
• 70% of Marks if compliance
≥80% & <90%
• Else: Zero
CBM Compliance • 100% Compliance: Full Marks
(Vibration, Oil • Prorata for Compliance from
13 5
analysis, 90 to 100%
thermography etc.) • Else: Zero
Total 100
Page 88 of 159
Contractor Performance Score Card - EMD
Month: - GTPP 3x660 MW
Sl. Action Additional
Parameter Criteria Weightage Score Remarks
No. Plan Remark
Interlock/protection
checking as & when
required within
Full Marks: If compliance is
defined time line
1 100% 5
(Note: Nil spurios
Else: Zero
tripping of
equipment/unit shall
be ensured)
Testing of all
Monthly
electrical equipment
• Full Marks if schedule schedule
as per schedule.
2 adherence is 100%. 5 will be
(Ensure time
• Else zero provided by
synchronization for
EMD
all numerical relays)
Testing/ Calibration
of meters with
• Full Marks if schedule
certification as per
3 adherence is 100%. 5
requirement. Ensure
• Else zero
time synchronization
for all energy meters)
• Full Marks: If Compliance is
100%
Attending
4 • Prorata for compliance 90% 5
Illumination defects
to 100%.
• Else: Zero
Availability of HT, • Full Marks if availability is
LT Breakers and all 100% (Excluding Planned
5 10
Transformers / maintenance)
Reactors • Else zero
Full Marks: Nos of failure is
LT Motor Failure Nil
6 (Excluding MOV & 50% of mark: If nos of failure 5
MOD Actuators) is 1 (quarterly)
Else: Zero
Full Marks: If No of failure <=
MOV & MOD 2 per month
7 Actuators Motor 50% of mark if no of failures 5
Failure >2 & <=5
Else: Zero
Ensure 100% • Full Marks if availability is
8 Standby of HT/LT 100% 5
Drive Motor • Else zero
Battery banks & • Full Marks if availability is
9 Chargers, UPS 100% 5
System availability` • Else zero
Page 89 of 159
Sl. Action Additional
Parameter Criteria Weightage Score Remarks
No. Plan Remark
• Full Marks if availability is
10 DG Sets Availability 100% 5
• Else zero
Availability of • Full Marks if availability is
11 132kV, 400kV and 100% 5
765kV System • Else zero
Availability of • Full Marks if availability is
12 PLCC, FOTE and 100% 5
SCADA system • Else zero
Human Error
(Attributable to Full Marks: If no of errors is
13 O&M Service Zero 5
Provider) during Else: Zero
executing any job
Availability of • Full Marks, if Availability is
Elevators inside 100%.
14 5
NUPPL Plant • Prorata for >= 75% & <100%
Premises • Else: Zero
• Full Marks, if Compliance is
PM Schedule 100%.
Completion • 90% of Marks if compliance
15 (PTW issued to ≥95% & <100% 10
O&M Service • 70% of Marks if compliance
provider) ≥90% & <95%
• Else: Zero
Full Marks if Defect
Compliance >90%
80% marks if Defect
Defect/ Notification
16 compliance >80% & <90% 10
Compliance
50% marks if Defect
Compliance>75% & <80%
else zero
CBM Compliance • 100% Compliance: Full
(Vibration, Oil Marks
17 analysis, • Prorata for Compliance from 5
thermography, DGA 90 to 100%
analysis etc.) • Else: Zero
Total 100
Page 90 of 159
Contractor Performance Score Card - CHP
Page 91 of 159
Contractor Performance Score Card - AHP
Page 92 of 159
Contractor Performance Score Card - C&I
Page 93 of 159
To be filled for CHP, AHP, Boiler, Turbine, WTP&BOP, EMD, C&I, Civil, Admin
Page 94 of 159
Check for
Full Mark: If
a) Coal / Ash / Dust Sipplage control
compliance >90 &
and Accumulation cleanliness
<=100%
b) Structure, Equipment, Pipeline etc.
80% Mark: If
Cleanliness
AHP Area compliance >80 &
5 c) No unwanted material lying 10
Cleanliness <=90%
d) No Stagnant water/ Oil Spillage
50% Mark: If
e) Proper equipment /System tagging /
compliance >70 &
nomenclature is maintained
<=80%
f) Anyother in the opinion of NUPPL
Else zero
EIC
Check for
a) Cable Gallery/Engineering
Rooms/Switchgear cleanliness Full Mark: If
b) Dirt/coal dust on panels/feeders & compliance >90 &
cable galleries etc. <=100%
Elctrical c) Unwanted material, tools, tags lying 80% Mark: If
and C&I in rooms compliance >80 &
6 10
Area d) No Stagnant water/ Oil Spillage <=90%
Cleanliness e) Broken windows/glasses 50% Mark: If
f) All panels are sealed & locked compliance >70 &
g) Proper equipment /System tagging / <=80%
nomenclature is maintained Else zero
i) Anyother in the opinion of NUPPL
EIC
Check for:
Full Mark: If
a)Garbage, scrap,unwanted material
compliance >90 &
lying on road.
<=100%
b) Road Markings are proper or not
Road / 80% Mark: If
c) Lighting is proper or not
Trenches / compliance >80 &
7 d) Stagnant Water 15
Drains <=90%
e) Devegetation
Cleaning 50% Mark: If
f) Trench is covered
compliance >70 &
g) No Choking in Drains/ Trenches
<=80%
h) Anyother in the opinion of NUPPL
Else zero
EIC
Check for:
a) Floor cleaning
Full Mark: If
b) Check for unwanted papers/ files
compliance >90 &
lying at offices/worktables.
<=100%
in rooms
Work 80% Mark: If
c) Proper tagging / nomenclature is
Office & compliance >80 &
8 done for office assets. 10
Toilet <=90%
d) Lighting is proper or not
Cleaning 50% Mark: If
e) Toilet Cleaning: As per the
compliance >70 &
frequency mentioned in the SOW
<=80%
(Mopping, Wiping, Scrubbing etc.) and
Else zero
collection/disposal of waste/garbage
after segregation
Score 5: If
Check for:
Drinking identified drinking
a) water availability
water water points
10 b) water quality 5
availability compiled all 4
c) Water cooler availability
and quality criteris
d) schedule maintenance
else zero
Total 100
Page 95 of 159
Contractor Performance Score Card- Compliance
= (No.
*Reference to a certain Act is inclusive of
of provisions
Rules/Guidelines/Bye-laws/Notifications/Ordinances/any
complied)
other document having the force of law in India, made under
x100
the Act.
(Total provisions
**> will be construed as >=
tracked - No. of
***< will be construed as <
provisions Not
E.g. a score of 90% would be included in
Applicable)
Score <100% but >90%
as per TLCM
Portal.
Full Marks: If
Achievement of compliances under
A1 compliance is 100% 10
Boilers Act
Else: Zero
Full Marks: If
Achievement of compliances under
A2 compliance is 100% 8
Factories Act
Else: Zero
Full Marks: If
Adherence to legal requirements in
A3 compliance is 100% 3
relation to radioactive material
Else: Zero
Full Marks: If
Achievement of compliances under
A4 compliance is 100% 2
Electricity Act
Else: Zero
Full Marks: If
Industrial & Achievement of compliances under
A5 compliance is 100% 5
Safety Explosives Act
Else: Zero
Page 96 of 159
Compliance of Conditions under Full Marks: If
B2 NOC received from CGWA & compliance is 100% 5
Guidelines Else: Zero
Criteria:
Score = 100% - 5
marks
Score <100% but
Adherence to all compliances under >90% - 4 marks
C1 Contract Labour Act and Inter State Score <90% but 5
Migrant Workmen Act. >80% - 3 marks
Score <80% but
>75% - 2 marks
Score < 75% - 0
marks
Labour
Criteria:
Score = 100% - 5
marks
Score <100% but
>90% - 4 marks
Adherence to all compliances under
C2 Score <90% but 5
Factories Act.
>80% - 3 marks
Score <80% but
>75% - 2 marks
Score < 75% - 0
marks
Page 97 of 159
Criteria:
Adherence to all compliances under: Score = 100% - 5
Employees Provident Fund & marks
Miscellaneous Provisions Act, Score <100% but
Equal Remuneration Act, >90% - 4 marks
C3 Payment of Wages Act, Score <90% but 5
Payment of Bonus Act, >80% - 3 marks
Payment of Gratuity Act, Score <80% but
Minimum Wages Act, >75% - 2 marks
and Employees Compensation Act. Score < 75% - 0
marks
Criteria:
Score = 100% - 5
marks
Score <100% but
>90% - 4 marks
Adherence to all remaining
C4 Score <90% but 5
compliances under Labour laws.
>80% - 3 marks
Score <80% but
>75% - 2 marks
Score < 75% - 0
marks
Total 100
O&M Service Provider NUPPL
Page 98 of 159
CONTRACTOR MONTHLY SAFETY HEALTH
Document No:
AND ENVIRONMENT SCORECARD
Agency PO No Work
MAX ACTUAL
SN PARAMETERS SCORING CRITERIA EVIDENCE
SCORE SCORE
40 % Weightage for Safety
Availability of
head and 60% for Safety MIP Sheet
Competent Safety
Management Supervisors: approved by the
Officers with required
1 in Place Full Marks: if availability is 10 Safety
qualification as per the
(MIP) 100% Department and
statutory requirement,
Else: on Pro rata HOD
applicable time to time
availability for the month.
Compliance of Safety
Training Need
Training to the Full Marks: for 100%
Identification
Safety manpower engaged by compliance
2 15 and compliance
Training O&M service provider Else: Marks as per pro rata
sheet with Pre
as per NUPPL Basis
and Post
schedule
Housekeeping,
Removal of
debris/dried
Fire Full Marks: if no fire
vegetation,
3 Prevention incident occured 10
deployment of fire
Measures Else: Zero
watch person after
execution of any
hotwork,
License and
Certificates - TPI for
Certificates and
Lifting Tools Tackles,
Licenses as
Pressure Vessels,
applicable and
Statutory Vehicles, Skilled Each non-compliance will
4 10 Non-
Compliance Persons, etc. carry five marks deduction.
Compliances in
Compliances in Gas
statutory
Cylinder handing and
processes
Emergency
preparedness
Availability of First-
Availability Aid Boxes with Full Mark: If compliance is
5 of First-Aid required contents as 100% 5
Boxes per the location Else: Zero
decided by NUPPL
Periodic Medical
Compliance > 90% - 100%
6 PME Examination 5 PME Records
Marks else 0 marks.
compliance
Page 99 of 159
1. Protected Rest
Sheds
2. Well maintained Full Mark: Compliance >
Provision of Washrooms 90%
7 Ameniitties / 3. Availability of 75% of Mark: if 15
Facilities Potable Drinking safe compliancer >=80 & < 90%
water else 0 marks.
4. Well maintained
Bathroom / Toilets
Implemention of
Corrective Action, Full Mark: Within NUPPL
Corrective Store Audit
8 approved by NUPPL Specified time limit 10
Action Score Sheets
for any non- Else: Zero
compliance
Full Marks: Min. 2 nos of
Any new initiative to
initiative per month
Pro-Active prevent any loss /
9 50% Mark: if 1 no of 5
Action damage to man/
initiative per month
machine
Else: Zero
1.Timely submission
of MIS (Statutory
Reports, Data for MIS
in format) -100 %
before 4th of every
month for preceding
month.-3 marks
2.Compliance to Env
Acts ,Rules,
EC,CTE,CTO
,Authorisation and all
permission -100 %
compliance-3 marks
3.Waste management
including Hazardous
,Non-Hazardous ,High Full marks for 0 deviation
Environment Audit and
10 Volume low effect otherwise 0 for specific 15
Management Notice records
waste etc. -100 % points
compliance to Waste
management
requirement -2 marks
4.Upkeep (including
AMC & calibration as
applicable ) of all
monitoring equipment
-CEMs, CAAQMs,
EQMS, Stack
monitoring Ambient
Air Monitoring ,Water
Monitoring
equipment)-100
calibrated and
working-2 marks
TOTAL 100
Monetary
Penalties:
Injury:
Signature:
Name:
To inculcate safe practices, NUPPL follows NLCIL Sustainability frame work and ensure its 100%
compliance. To ensure Zero Harm Various Safety and Environment Performance standard are in place.
List embedded in the document.
The works should be undertaken in accordance with the applicable international guidelines, standards
and specifications on HSE (ICMM / IFC/ OCED etc.)
Responsibility Matrix
/ Scope
Sl.
PLANT O& M
No. Description of work / Activity REMARK
Owner Contractor
1 Start-up Services -
Preventive
3 Maintenance NA NA O&M O&M O&M O&M O O&M
Routine
4 Maintenance NA NA O&M O&M O&M O&M O O&M
Note: Any discrepancy w.r.t. any clause (if arises during execution of the contract) between Scope
Matrix (Annexure-K) and Technical Scope of work detailed in Section-C, the decision of NUPPL in
this regard shall be final and binding on the O&M Service Provider.
13 Heavy duty Vehicle Driver-HMV High > 3 Yrs experience is desirable. Service of
Operator School any Industry in Material handling machinery
Operator
(Hydra/Backhoe/Crane/Forklift/Trailer/Picku
p Van/Man lift)
13 Assistant Graduate (Engineering) With minimum desirable 03 years of
Purchase experience in purchase
Officer
14 Mill Wright ITI > 10 Yrs in respective field of deployment is
Fitter desirable
15 IBR Welders ITI > 06 Yrs in respective field of
deployment with relevant certificate
is desirable
16 Sr Fitter ITI > 06 Yrs in respective field of deployment is
desirable
Welder ITI > 03 Yrs in respective field of deployment
17 with min3G welding certificate
18 Grinders,
Electrician, ITI > 03 Yrs in respective field of deployment is
C&I, Cutter, desirable
Riggers
19 Fabricator ITI > 06 Yrs in respective field of deployment is
desirable
20 Insulation Fitter ITI > 05 Yrs in respective field of deployment is
desirable
21 Helper NIL Industrial Experience of at least 01 Yr is
desirable
22 Housekeeping NIL NIL
Safety Head Any full time engineering Industrial Experience of at least 05 Yr is
graduate with ME desirable
industrial safety / diploma
in industrial safety from
CLI/RLI
Safety Supervisor Any full time engineering Industrial Experience of at least 03 Yr is
graduate / diploma with desirable
ME industrial safety /
diploma in industrial safety
from CLI/RLI / State govt
affiliated
Note: NUPPL reserves the right for any relaxation in minimum qualification and experience criteria for
PAP, if they are engaged through this contract as per the NUPPL HR guidelines.
4.02 Dum Dum Putty, Ceramic Compound for coal pipe & it’sorifice repairing √
Atomic Absorption Spectro Photo Meter ACETALENE, ARGON, NITROUS OXIDE gas cylinder
1
Nichrome Wire
Oxygen Gas
2 Atomic Bomb Calorimeter
Thread
Nitrogen Cylinder
Caliberation Cylinder
10 Magnetic Stirrer Cum Hot Plate Magnet
11 Maximum & Minimum Thermo Meters Wick
Note: Above mentioned consumables are indicative only. Any other general-purpose consumables (in
the opinion of NUPPL) required during execution of the contract which is not mentioned in the above
list, shall also be in the scope of O&M Service Provider.
30 ESP TR SET Kraft Powercon ON call basis Kraft Powercon ON Call basis
02 No of visit /
Station and Common DDCMIS & BOP
1 M/s ABB Year and ON
DDCMIS (WTP, AHP, CHP, Chlorination)
call basis
2 SG DDCMIS M/s Emerson
3 TG DDCMIS ALSPA(M/s
24 DG sets Jackson
Boiler
Techno Industries 03 No of visit / Year
Page 127 of 159
6 Nos and ON Call
basis
Service Building
03 No of visit / Year
TG Building and ON Call
basis
Administration Building
03 No of visit / Year
30 Elevators (Chimney ) Alicraft – 01 No
and ON Call
basis
Note: Any discrepancy in the details provided above arises during execution of the contract, the
updated details as provided by NUPPL from time to time shall be taken into account by the O&M
Service Provider for fixing the AMC/RCs.
The O&M Service Provider shall bring all the required Tools & Tackles and their consumables,
equipment/Machineries required for performing the service as per scope of work and site requirement.
The special tools of OEM/OES for various plant equipment as received from our EPC contractors will
be provided by NUPPL on returnable basis subject to availability.
The following is the minimum indicative list of T&P. However, the O&M Service Provider shall
submit the detailed list of T&P, required for execution of the contract as per scope during
commencement of mobilisation period after award of the contract. The minimum requirement of Heavy
Machineries/Material Handling Equipment are also detailed in this Annexure.
S No. DESCRIPTION
3 Thread Inserts
4 Tap sets
8 Slugging spanner
14 Surface Plate 2mt. ×2mt. & upto 06 micron flatness preferably Mitutoyo Make:
(C.I. or granite).
16 Dial Gauges
a) 0 to 10 mm (L.C.: 0.01mm)
b) 0 to 05 mm (L.C.: 0.01mm)
c) Lever type (Range: 2.4mm/ 1.6mm)
17 SS Shims
18 Bench Vice/ Grinder
19 Feeler Strips of 01 mtr. Length
20 Chain Pulley Block
21 Chain Pulley Block
22 Heating Blowpipe
23 Measuring Instruments:
23.1 Outside Micrometers
a) 0‐25mm
b) 25‐50mm
c) 50‐150mm
Complete set of screw drivers and nut drivers suitable for working in relay
18 Panels
7 Max Puller 2 MT
8 Personal Protective Equipment for every work‐man /staff as per NTPC safety rules
(Helmet, Safety Google, Mask, Welders Goggles, Hand gloves, Welders' hand
gloves, ear plugs, life vest, safety belt and rope, safety net, safety harness etc.)
9 Hand drilling machine upto 12mm
15 Ring, D Spanner, box spanner, Socket spanner set (complete range upto 32mm)
22 Fine cut Files (a) Flat, (b) Round, (c) Half Round
37 Grinding Machine
35 Hydraulic Jacks
36 Mechanical Jacks
PRECISION TOOLS
47 Winch – 5 ton
48 Winch – 10 ton
49 Laser alignment machine
50 Torque wrench ( various size)
57 Trolley mounted Welding machine with DG set & accessories for Ash pipeline
Maintenance
SL No Description Specification
Tyre Mounted Hydraulic Telescopic Crane (Hydra) Min. 16 T
JCB
Tractor
Heavy Duty Trailer
Tippers of 16 - 22 MT carrying capacity
Mobile water tankers (around 10KL)
Road sweeping machine
Floor Cleaning Machine
Tyre Mounted Telescopic Hydraulic Boom Lift with
Note: Above mentioned T&P and Machineries list are tentative. Specification of the items shall be adjusted
based on site conditions and as per requirement. Available Special T&P as received from OEM/ EPC
contractor will be provided by NUPPL to O&M Service Provider. Any additional tools required as per scope
of work shall be in the scope of contractor only. All T&P, Machieries and related consumables shall be
brought in sufficient quantity.
Tests & analysis which cannot be carried out at NUPPL laboratory and also for meeting some of the statutory
requirement shall be arranged by O&M Service Provider at their own cost at reputed NABL accredited
laboratories approved by NUPPL.
MOEF/ PCB guidelines and IS standards for Effluents as per the attached list as minimum and to meet the
requirement /revisions of MOEF /PCB time to time:
Sl. Number
No. ENVIRONMENTAL MONITORING SCHEDULE of Stations Frequency
THROUGH THIRD PARTY
1.00 AMBIENT AIR QUALITY
1.01 PM10, PM2.5, SO2, NOx, Pb, Ni, As, CO, Hg, Ozone, , 9 MONTHLY
Ammonia, Benzene and Benzo(a)pyrene - 13 Parameters
1.02 PM10,PM2.5,SO2,Nox & Hg 9 TWICE A WEEK
1.03 Heavy Metal in Particulate Matter 5 QUATERLY
2.00 STACK MONITORING
2.01 275 m RCC Tri-Flue Chimney Stack Monitoring (Off- 3 MONTHLY
Line), PM 10, PM 2.5, SO2, NOx, CO, CO2, Oxygen
3.00 WATER QUALITY MONITORING
3.01 Surface Water Quality 4 QUATERLY
3.02 Ground Water Quality 13 QUATERLY
3.03 Piezometric wells 7 QUATERLY
3.04 Effluent Water - pH, O&G, TSS, COD, BOD & TDS 5 MONTHLY
4.00 NOISE MONITORING
4.01 Ambient Noise Level Monitoring(Day &Night) 8 MONTHLY
5.00 COAL ANLAYSIS
5.01 Coal (Heavy Metals, Sulphur Content, Ash Content) 4 MONTHLY
3. Coal for Analysis (other than tests required for regular O&M)
Page 139 of 159
Coal Proximate Analysis Quaterly
Ultimate Analysis Quaterly
HGI Half yealy
Grindability Index Half yealy
4. Ash Analysis
Ash Oxide Analysis Quaterly
Ash Fusion Analysis Quaterly
Seive Analysis Quaterly
Blaines Analysis Quaterly
All glass wares and consumables for lab equipment’s shall be arranged by O&M Service Provider at their own
cost.
NOTE:
The tests mentioned above are indicative, any test required for day-to-day O&M requirement and any other
statutory tests required shall also be with the scope of O&M Service Provider.
Further need based tests if any which are required by owner shall be carried out by O&M Service Provider at
owners cost on reimbursement basis. Testing to be done at NABL accredited laboratories approved by NUPPL
and subject to the prior approval of Engineer in Charge of NUPPL. O&M Service Provider shall get the testing
done at their cost and owner shall reimburse the test fees.
A. The Contractor shall provide to the Owner in the morning every day, a copy of a daily report for the
previous day and schedule of works planned for the next day, including details of (Excluding BTG
Operation).
The following reports shall be prepared in co-ordination with BTG operation staff/Head.
1. Output (gross and net units exported) for that day and daily fuel consumption (coal,
LDO, HFO) of the plant (to the extent such information is available for such period)
and auxiliary energy consumed.
2. Consumption of raw water, de-mineralized water, chemicals and other items.
3. Available capacity & outages.
4. Generation of fly ash and disposal of dry ash for economic use;
5. Accident and failure reporting
6. Safety record
7. Stock details of Coal, LDO, major lubricants, raw water, distillate, chemicals, fly ash;
8. Actual PLF for the day, cumulative heat rate for the month and year as of date.
9. Deemed generation for the day for the month and year as of date
10. Manpower report category wise.
B. The contractor shall generate a weekly report also containing above information.
C. The contractor shall prepare one monthly reports exclusively for the purpose of raising
invoices and such report shall include the following details;
1. Scheduled generation ex bus
2. Actual generation ex bus
3. Deemed generation for the month
4. Gross Generation.
5. Station heat rate.
6. Auxiliary consumption
7. Monthly report on availability factor.
D. Within ten days of the end of the month to which it relates (the "Relevant month"), the
contractor shall provide to the NUPPL a monthly report (the" Monthly Report") which shall
include but not be limited to the following;
1. A review of operation for the Relevant Month (Including fuel consumption, load factor,
actual output, actual heat rate, efficiency and outages).
2. All the daily reports to be consolidated so that a comprehensive report can be prepared.
3. Information relating to safety and the incidence of accidents at the plant
4. Such information as the NUPPL may reasonably request to assess the level of operator
Liquidated damages and which relate to the performance of the operator's obligations
since the first day of the Contract Year in which the Relevant Month falls;
5. Such information as the NUPPL may reasonably request in connection with compliance
with all applicable Environmental Laws.
E. The contractor shall also modify the above reports (described in 1to3) as may be required by
the relevant Authority (ex. CEA/RLDC/CERC) and if required submit the report as per the
relevant format.
Page 142 of 159
F. CONTENT OF ANNUAL OPERATIONS REPORT
1. ANNUAL GENERATION
a. Declared Available Capacity (Summary)
b. GTPS Dispatch (Summary)
4. OUTAGE SUMMARY
a. Scheduled Outages
b. Forced Outages
c. Equipment Outages
6. ENVIRONMENTAL REPORT
a. Emissions Compliance
b. Environmental Events
c. Reports in compliance with MOEF /Pollution Control Board guidelines &
requirement
7. SAFETY/SECURITY
a. Injuries
b. Lost Time Accidents
c. Security Events
8. PERSONNEL ACTION
a. Additions
Page 143 of 159
b. Reductions
c. Union Activity (Contractor workforce).
J. Documenting Calorific value of fuels as fed basis to the boiler (Measuring at Coal Feeder) as
per the BEE procedures.
The following reports shall be prepared & maintained in co-ordination with NUPPL BTG operation
staff/Head.
Logs to be retained for three (3) years:
a) Daily Report
b) Weekly Report
c) Monthly report
d) Capacity Declaration
e) Amendment to Capacity Declaration
f) Availability Report
g) Performance test reports
h) Necessary Documents as required to be furnished to BEE (Bureau Of Energy Efficiency) to be
maintained
Logs to be retained for four (4) calendar years / seven (7) calendar years
j) Injury/Medical Records
k) Logs/Charts - Generation and Output
l) Logs/Charts - Emissions
m) Correspondence Files
n) Dispatch Orders
o) Welding Records
p) Fuel Analysis Reports
q) Accounting Records and Reports
r) Logs/Charts - Control Room
s) Contractor Logbook
CHP O&M:
1. FOR Operation log book:
a. Daily
b. Defects register
2. FOR Maintenance log book – Mechanical / Electrical / Instrumentation
a. Routine Maintenance – daily/weekly/monthly.
b. Breakdown Maintenance – Maintaining records for works carried out.
c. Details of spares consumed.
For every month, report shall be furnished for admit the bills, in respect of CHP O&M for certification
from respective divisions.
EMD/ Bid Guarantee BG and PBG shall be submitted on the format Generated through GeM
Portal.
1.0 The CONTRACT made this …… day of ….…………… in the year 2023 between M/s NEYVELI
UTTAR PRADESH POWER LIMITED having office at The Chief Executive Officer/NUPPL,
Neyveli Uttar Pradesh Power Limited, Ghatampur Thermal Power Project, Near Lahurimau – Kasimpur
Village, Ghatampur Tehsil, P.O. Samuhi – 209 206 Kanpur Nagar Dist., Uttar Pradesh, hereinafter
called the “PURCHASER” and M/s ......................................., Address:
............................................................................................., hereinafter called the “BIDDER” for the
work “NUPPL/GTPS: The work of Operation & Maintenance Contract for 3X660 MW Coal based
Ghatampur Thermal Power Station (GTPS) at Kanpur Nagar District, Uttar Pradesh” in accordance
with the Purchaser’s Tender No. ……………………………………….. and Letter of Award No. Lr.
No. …………………………………………. forming part of this agreement, is registered as Agreement
No. CEO/NUPPL/......../2022 Dt. ................
2.0 It is further to confirm the acceptance of the Bid proposal as notified by the Purchaser’s Letter of Award
No Lr. No. …………………………………………………………………………………. and the
Bidder’s acceptance Dt...................
3.0 The Purchaser has accepted the proposal of the Bidder with such changes/modifications mutually agreed
to, through the exchange of Correspondence and minutes of the meeting for the above work.
4.0 The Purchaser hereby agrees to pay to the Bidder on due performance of the ‘Contract’ a price of Rs.
......................./- (Rupees ................................................................ only) including GST in the manner
and in accordance with the terms specified in the LOA/Letter of Award and allied/related
correspondences.
5.0 In WITNESS whereof the parties hereto have hereunder affixed their signatures with official seals on
the day, month and year written as above.
Signature: Signature:
Designation: Designation:
Address: Address:
Witness Witness:
2........................................... 2...........................................
The requirement of the tender agreement as stated above will be fulfilled by me / us to the entire
satisfaction to the Neyveli Uttar Pradesh Power Limited.
Date:
Signature of Bidder
Seal of the firm
I/We hereby declare that Our Firm/Entity/Company is not banned/debarred/blacklisted by any other Central Public
Sector Enterprises (CPSES)/Government Entities as on the date of the original scheduled date of tender opening.
I/We, hereby agree that in case while processing the tender or during post award of the tender, any such
banned/debarred/blacklisted instances by other Central Public Sector Enterprises (CPSES) / Government Entities, is
known to NUPPL, the same will amount to the suppression of the material information, and our offer / bid will be
disqualified by NUPPL. If the tender is under process. If already awarded, then the Purchase Order/Contract will be
terminated by NUPPL.
In the above circumstances, I/We, will not have any claim on NUPPL towards such disqualification or termination
of Contract/Purchase Order.
Sub: O & M Contract for 3X660 MW Coal based GTPS for a period of Three Year (Extendable for further
Two years based on owner’s need).
a. EMD Details
b. Turnover during the last FIVE years
Signature of Tenderer
Date:
1. Bidders Details:
1.1 Constitution or Legal status of Bidder (attach copy)
Place of registration:
Principal place of business:
Power of Attorney of signatory Bid: (attach)
1.2 Details of the turnover: Annual Turnover Data for the last five years.
1.3 Joint Venture details:
Name of all partners of a joint venture
1. Lead partner
2. Partner
Signature of Tenderer
Date:
1 Details of EMD
2 Validity of offer (180 Days From date of Opening of Techno-
Commercial Bid)
3 Copy of PAN No. with details
4 Payment details (for EFT)
a Account Name
b Banker's Name
c Branch
d Address, City/Town, District, State
e Account type
f A/c No & EFT No
g IFSC Code
h MSME (Applicable/Not Applicable)
i If applicable, indicate Registration No. & Registering
Authority
6 NUPPL/NLCIL Vendor Code of the bidder.
7 Experience details of the bidder as per approved PQR (Will be
updated after approval of proposal).
Details of the bidder
8 (Name, Address, Phone No, with whom reference may be
made)
9 Annual Turnover of the bidder as per approved PQR (Will be
updated after approval of proposal).
10 Net worth of the bidder as per approved PQR (Will be updated after
approval of proposal).
11 GSTIN Registration details
a GSTIN No.
b Rate of GST
12 Copies of Income Tax details for the last 5 years
Signature of Tenderer
Date:
Seal of the firm
Page 155 of 159
ANNEXURE : Y-1
EXPERIENCE DETAILS
Ref: NUPPL Tender No.
Sub: O & M Contract for 3X660 MW Coal based GTPS for a period of Three Year (Extendable for further
Two years based on owner’s need).
2. The average PLF (as per actual generation), SHR, Auxiliary Energy Consumption, Secondary Fuel
Oil Consumption, Availability achieved by the power plant handled by the bidder during one
complete financial year of the contract period.
3. Infrastructure and Experienced and Trained Manpower:
a. Details of infrastructural facilities like maintenance tools and equipment, software for
performance monitoring, office infrastructure, Transportation facilities etc.
b. List of stream wise Engineers and technical personnel on payroll of company.
4. Unit wise Organization chart and detailing qualification, training and relevant experience who will
be deployed on the assignment in the event of selection.
5. List of spares required for O&M of GTPS
Signature of Tenderer
Date:
To
Chief Executive Officer
Neyveli Uttar Pradesh Power Limited
Ghatampur Thermal Power Project Site Office,
Near Lahurimau – Kasimpur Village,
Ghatampur Tehsil, P.O. Samuhi – 208 001,
Kanpur Nagar Dist., Uttar Pradesh.
Dear Sir,
Name of the work: “The work of Operation & Maintenance Contract for 3X660 MW Coal based Ghatampur
Thermal Power Station (GTPS) for a period of Three Years (Further extendable for two
more year based on owner’s need) at Ghatampur tehsil, Kanpur Nagar District, Uttar
Pradesh State”.
*****
With reference to the above tender, we hereby give the undertaking that:
Date: Signature:
DD MM YYYY
……………………………………
Name of the Authorized representative of bidder’s Establishment
Company Seal
Place: _____________
AND WHEREAS as per the terms of the said agreement the guarantor has agreed to stand guarantee for the
amount of advance payment in favour of the O&M Service Provider principals subject to the terms and
conditions stated below:
NOW THIS DEED WITNESSES that in pursuance of the above said agreement of the guarantor to stand
guarantee and in consideration of the Corporation making as advance payment of Rs…………… (in
words)…….. the guarantor hereby covenants with the Corporation as follows:
1. The guarantor shall be liable in respect of the amounts due and owing to the Corporation in respect
of the advance payment to the extent of Rs… (in words)……………………
against any loss or damage caused to or suffered or would be caused to or suffered by the Corporation
by reason of any breach of the terms of the said agreement by the Contractor.
2. The Guarantor hereby undertakes to pay the amounts due and payable under this guarantee without
any demur, merely on a demand from the said Corporation stating that the amount claimed is due by
way of loss or damage caused to or suffered or would be caused to or suffered by the Corporation by
reason of any breach by the said Contractor any terms contained in the said agreement in respect of the
O&M Service Provider. Any such demand made on the guarantor shall be conclusive as regard the
amount due and payable by the guarantor under this guarantee. However the liability of the guarantor
under this guarantee shall be restricted to an amount not exceeding Rs………………………
3. The guarantor further agrees that the agreement herein contained shall remain in force and effect till
all the works completed in all respects required under the above said order are completed to the
satisfaction of the Corporation or till the Corporation certifies that the terms and conditions of the said
agreement have been fully properly carried-out by the said contractor and accordingly discharges the
guarantee. Unless a demand or claim made under this guarantee is made on the guarantor in writing on
or before the ……………… ………………………………the guarantor shall be discharged from all
liability under this guarantee thereafter.
4. The guarantor further agrees with the Corporation that the Corporation shall have the fullest liberty
without the consent of the guarantor and without affecting in any manner the obligation of the
guarantor hereunder to vary any of the terms of the said agreement or to extend the time of
performance by the said contractor from time to time or to postpone for any time or from time to time
WITNESS
1.
2.