Professional Documents
Culture Documents
Methodology
Methodology
ISLAMABAD OFFICE: Plot No. 39, Street No. 1, I-10/3, Islamabad-44000, Pakistan
Phone No.(51) 410 2001 (4 Lines) Fax : (51) 444 3749
Email : islamabad@nuricon.com, khalid.khan@nuricon.com
INTRODUCTION
Nuricon Petroservices (Pte.) Ltd. (Nuricon), the most experienced Corrosion
Engineering and Pipeline Integrity Services Company in Pakistan is pleased to
provide Pakistan State Oil Company Ltd (PSO) with our proposal to provide Pipeline
Integrity Direct Assessment and CP System Audit. By virtue of our experience and
resources, Nuricon is confident that they can provide a competitive and quality
solution to PSO
In terms of scope of work, all the assessments including pre, indirect, direct and post,
surveys and reporting shall be done by the Nuricon.
In order to provide a high standard and quality of works , Nuricon shall ensure that
the personnel involved for the execution of the project are ably qualified which shall
include Maqsood Temuri as the Project Manager ably supported by Javed Waheed
and Asif Siddiqui all of whom have I-Corr certification as per tender requirement . The
Nuricon team under the supervision of Maqsood Temuri shall utilize a delegated
approach to ensure that Nuricon accomplish and complete the project to the
complete satisfaction of PSO.
We will also like to highlight several similar projects for ECDA have been executed
and successfully completed by the Nuricon for PSO in 2010 under contract No
411009707 and in 2021 under contract No 4110029368 . Hence, Nuricon is ideally
suited to carry out this project for PSO. Besides this Nuricon has conducted ECDA
for Sui Northern Gas Company Ltd, Oil & Gas Development Company Ltd, United
Energy Pakistan, OMV Pakistan, Central Power Generation Company Ltd ( WAPDA)
etc.
1. Methodology:
The basic methodology for carrying out Pipeline External Corrosion Direct
Assessment (ECDA) is described in the ANSI/NACE Standard SP 0502/2002.
However, there are some details which are more fully described in this
document.
The ECDA process typically follows four separate activities, namely pre-
assessment, indirect inspection, direct examination and post assessment.
Nuricon will add a final step which is the selection of appropriate rehabilitation
and refurbishment methodologies, which is typically the information a pipeline
owner would require to bring the pipeline in question up to an acceptable
integrity level in order to reduce and manage the risk of operation of that
particular pipeline.
2. Pre-assessment:
The Pre-Assessment process shall collect and integrate all relevant available
history of the pipelines in question. This process is necessary to firstly
determine whether ECDA is feasible, secondly to define ECDA regions and
thirdly to select the appropriate tools and techniques that will be used for direct
assessment.
The information required for this process will be obtained from the following
sources:
Construction information.
Material supply data sheets.
As-built drawings, maps and hand over documentation.
Cathodic protection design, as-built and hand over documentation.
Cathodic protection operational information, including monthly and
yearly monitoring results and any modifications and upgrades made to
the CP system.
Overline survey information, including DCVG, CIPS, PCM, GPS and
soil resistivity surveys conducted previously.
Leak history information.
Repair history information (coating and metallurgical defects/corrosion).
Operational history, including temperature, pressure etc.
Records of any modifications made to the pipeline.
Standard operating procedures.
Records of information gathered during digs and excavations to
undertake inspection or repairs.
Hydrotest or tightness-test data.
Records relating to any cleaning pigging undertaken previously.
Different combinations of tools may be required for different portions of the same
pipeline, or for different pipelines, depending on the site and ROW conditions. It is
important to realize that it is therefore possible to use different combinations of
techniques along the same pipeline.
a. On and instant off potentials at the test points and any critical locations
such as cased crossings etc., wherever possible.
b. Identifications of shorted casings or pipelines.
c. Identifying shorted isolation joints.
d. Inspection of test posts, current measuring posts, etc and identifying
the abnormalities and recommend the corrective measures.
e. Note any useful features along the pipeline ROW.
f. Check Transformer Rectifier (TR) or any other Power Source outputs
and their conditions.
g. Take circuit resistances by gradually increasing TR outputs from zero
up to a maximum and determining average circuit resistance by
graphical method.
h. Check for Sacrificial CP System if any.
i. Note resistance/output of individual anode, if such provision is available
in the system (i.e., if leads from individual anodes are above ground in
the junction box). Clamp on meter or shunts would be used for the
measurements.
j. Pipeline (cathode) resistance would be estimated from the groundbed
resistance measurements.
k. Subsequent to the Indirect Inspections the locations that are identified
as Priority-1 and are near to the source of stray current would be
assessed for the possible stray current interference.
NACE ECDA standard stipulates only 2 overline surveys but in some cases,
more than two overline techniques may need to be used.
3. Direct assessment:
Bell hole excavations shall be carried out to allow physical examination of the
pipeline by Nuricon personnel.
The results from the overline surveys will be analysed by Nuricon personnel
and the defects shall be ranked. Nuricon typically would require that a number
of defects are exposed, across the range i.e. minor, moderate and severe.
Once all the data has been analysed, an action plan will be developed with
interventions split into three categories as follows:
4. Post assessment:
This step shall evaluate the effectiveness of the ECDA process and determine
inspection intervals. Nuricon shall study all the data including coordinating the
finding with the field reports followed by a report.
Nuricon shall provide information on what options are available to the operator
in order to upgrade the pipeline. However our proposal does not include any
rehabilitation work but does include the restoration of coating inspected by
Nuricon during direct inspection.
Nuricon shall arrange to provide all accommodation and food for our
personnel during their visit to the various sites. However PSO shall be
responsible to provide security for our personnel in security sensitive areas.
7. Technical Clarification:
In the tender documents following discrepancies or comments are noted
8. Project Team:
The team being offered by Nuricon is as following. However not all of the
personnel shall be utilized for the project but will comprise of the below team:
All the above personnel are full time employees of Nuricon Petroservices as
per tender requirement.
It may be noted that Mr. Maqsood Temuri and Mr. Asif Siddiqui are AMP
(NACE) Corrosion Specialist) alongwith FICorr. However, Mr. Javed Waheed
is M-Icorr and AMP (NACE) Senior Corrosion Technologiest.