This document provides a detailed cost estimate for the construction of a 34.81 km multi-lane road from Bangala to Onomamentu over a 15 year period. The total estimated cost is 5.842 billion pesos. Major costs include site assessment, design, project management, construction activities like earthworks and paving, utility relocation, and contingencies. Materials procurement such as asphalt, sand, gravel and cement account for over 4 billion pesos, while labor costs are estimated at over 2.8 billion pesos over the construction period.
This document provides a detailed cost estimate for the construction of a 34.81 km multi-lane road from Bangala to Onomamentu over a 15 year period. The total estimated cost is 5.842 billion pesos. Major costs include site assessment, design, project management, construction activities like earthworks and paving, utility relocation, and contingencies. Materials procurement such as asphalt, sand, gravel and cement account for over 4 billion pesos, while labor costs are estimated at over 2.8 billion pesos over the construction period.
This document provides a detailed cost estimate for the construction of a 34.81 km multi-lane road from Bangala to Onomamentu over a 15 year period. The total estimated cost is 5.842 billion pesos. Major costs include site assessment, design, project management, construction activities like earthworks and paving, utility relocation, and contingencies. Materials procurement such as asphalt, sand, gravel and cement account for over 4 billion pesos, while labor costs are estimated at over 2.8 billion pesos over the construction period.
Name of the Road: BANGALA TO ONOMAMENTO (34.81 Km multi-lane)
Duration: 15 years (4438 Working Days)
Description of Works Unit Quantity Amount Total
A. Preliminary Site Assessment Site Survey and Assessment per km ₱ 20,000 ₱ 696,200 Geotechnical Investigation per km ₱ 75,000 ₱ 2,610,750 Environmental Impact Assessment per km ₱ 100,000 ₱ 3,481,000 Subtotal ₱ 6,787,950 B. Design and Planning Conceptual Design per km ₱ 150,000 ₱ 5,221,500 Detailed Engineering Design per km ₱ 110,000 ₱ 3,829,100 Subtotal ₱ 9,050,600 C. Project Management Materials Procurement Asphalt per metric ton 100,000 tons ₱ 3,000 ₱ 300,000,000 Sand per cubic meter 106,500 cu. m ₱ 1,200 ₱ 127,800,000 Gravel per cubic meter 125, 350 cu. m ₱ 1,500 ₱ 188,025,000 Cement per bag(40 kg) 626,500 bags ₱ 300 ₱ 187,950,000 Steel per piece 300,000 pcs ₱ 100 ₱ 30,000,000 Geotextiles per square meter 500000 sq. m ₱ 150 ₱ 75,000,000 Pavement Markings and Signage Materials 4 Liters 25 cans ₱ 1,300 ₱ 32,500 Equipment and Machinery Excavators 10 ₱ 11000 ₱ 48,818,000 Bulldozers 6 ₱ 8250 ₱ 36,613,500 Motor Graders 4 ₱ 6000 ₱ 26,628,000 Road Rollers 10 ₱ 13000 ₱ 57,694,000 Asphalt Pavers per day 3 ₱ 4800 ₱ 21,302,400 Dump Trucks 15 ₱ 16000 ₱ 71,008,000 Concrete Mixer 3 ₱ 4800 ₱ 21,302,400 Cranes 2 ₱ 5000 ₱ 22,190,000 Compactors 4 ₱ 5200 ₱ 23,077,600 Labor per day 800 ₱ 800 ₱ 2,840,320,000 Subtotal ₱ 4,077,761,400 D. Construction Phase Earthworks and Grading ₱ 600,000,000 Road Pavement Construction ₱ 760,124,190 Utility Relocation Drainage sytem per km ₱ 500,000 ₱ 69,620,000 Water Lines per km ₱ 300,000 ₱ 41,772,000 Power Lines per line ₱ 450,000 ₱ 62,658,000 Telecommunications per line ₱ 280,000 ₱ 38,987,200 Material Quality Control and Testing 3% of total estimate ₱ 175,260,660 Subtotal 1,748,422,050 E. Contingency in the project Contingency Subtotal ₱584,202,200 TOTAL ₱ 5,842,022,000