REKOD PEMBAYARAN GAJI BASRI

BIL PROGRESS TARIKH (Minggu) Jumlah Baki Catatan


1 Minggu 1 (13-17 Nov) 2000.00 65500.00
2 Minggu 2 (19-24 Nov) 3000.00 62500.00
Ground Beam 20%
3 Minggu 3 (27 Nov - 1 Dis) 2500.00 60000.00
RM13 500
4 Minggu 4 (3-8 Dis) 3000.00 57000.00
5 Minggu 5 (10-15 Dis) 2500.00 54500.00 13000.00
6 Minggu 6 (17-22 Dis) 2500.00 52000.00
7 Minggu 7 (24-29 Dis) 2000.00 50000.00
8 Minggu 8 (31 Dis-5Jan) 2000.00 48000.00
9 Roof Beam 35% Minggu 9 (7-12 Jan) 1500.00 46500.00
10 RM23 625 Minggu 10 (14-19 Jan) 3000.00 43500.00
11 Minggu 11 (21-26 Jan) 3000.00 40500.00
12 Minggu 12 (28 Jan - 02 Feb) 2500.00 38000.00
13 Minggu 13 (4-9 Feb) 3500.00 34500.00 20000.00
14 Minggu 14 (11-16 Feb) 3000.00 31500.00
15 Minggu 15 (18-23 Feb) 2500.00 29000.00
16 Roof 15% Minggu 16 (25 Feb - 2 Mac) 2500.00 26500.00
17 RM10 125 Minggu 17 (4-9 Mac) 2000.00 24500.00
18 Minggu 18 (11-16 Mac) 3000.00 21500.00
19 Minggu 19 (18-23 Mac) 1500.00 20000.00 14500.00
20 Minggu 20 (25-30 Mac) 2000.00 18000.00
Kaki Lima 5%
21 Minggu 21 (1-6 Apr) 1500.00 16500.00
RM3 375
22 Minggu 22 (8-13 Apr) 3500.00
23
24 JUMLAH SEMASA 51000.00 51000.00
25
26
27
28
29
Wall Plaster 20%
30
RM13 500
31

32
Finishing 5%
33
RM3 375
34
Total 100%
JUMLAH SEMASA 102000.00 -34500.00
RM67 500