MINUTES OF MEETING

Date/Time:

PT. TRITON GLOBAL MARITIM


Venue: Commercial Office

Subject: Kick Off Meeting

Attendances: Please see attached

Disclaimer: The minutes of meeting and discussions is without prejudice to CRC rights including to any
termination, etc which are fully reserved under the Contract.

Ite
Discussion Summary Action by Target Date
m#

1.0 GENERAL

Kick off meeting held on CRC office meeting


1.1 CRC
room

1.2 Introduction from CRC andBATAMEC CRC/BATAMEC

Presentation from BATAMEC regarding


1.3 BATAMEC
Execution Plan

Scope of Work and Cost for CONTRACT that


1.4 BATAMEC/CRC
will be signed by BATAMEC & CRC

Repair Wellhead and Platform CPP: CRC need


to confirm total of BATAMEC Project Team that
1.5 BATAMEC
can be accommodated in CPP during the
execution of work.

2.0 HSE

CRC highlighted Contractor has to comply with


2.1 BATAMEC
CRC’s HSE Regulation

BATAMEC should provide Job Safety Analysis


2.2 BATAMEC
and Risk Assessment for the project.

BATAMEC should provide Permit to Work every


2.3 BATAMEC/CRC
day to be signed by CRC Rep’s at field.

BATAMEC noted and agreed on that


2.2 BATAMEC
requirements

3.0 PROJECT CONTROL & SCHEDULE

3.1 Project office will be at Jakarta &Batam BATAMEC

CRC request to BATAMEC to submit the schedule to be


3.2 BATAMEC
reviewed and to be updated every day.

Page 1 of 2
4.0 ENGINEERING

CRC highlighted the engineering scope of work to be


4.1 BATAMEC
finalized and submit to CRC by asap.

4.2 BATAMEC to add re-drawing and datasheet into SOW BATAMEC

4.3 BATAMEC noted on that request. BATAMEC

5.0 PROCUREMENT
CRC highlighted that the procurement process shall not
5.1 make impact on the schedule in order to reach project CRC/BATAMEC
completion as per schedule.
5.2 BATAMEC noted on that concern BATAMEC

6.0 SCOPE OF WORK & COST

Pursuant to the Project Cost and Scope that


has been presented by BATAMEC previously,
the latest revision is prepared to cover to the
6.1 BATAMEC
following CRC requirements.

CRC Request BATAMEC to revise the detail


Breakdown, change into the RFQ standard form
6.2 BATAMEC
and description that meet CRC Procurement
Standard.
7.0 OTHERS
CPP LIVING QUARTER / PORTACAMP existing
capacity for 12 Pax only, could not
accommodate additional persons from
7.1 BATAMEC
CONSTRUCTION CONTRACTOR. Therefore
CONTRACTOR must bring in WORK BARGE with
sufficient capacity.

The contents of these Notes have been reviewed and agreed by:

CRC

Name: Date:
Designation:
BATAMEC

Name: Date:
Designation:

Page 2 of 2