Professional Documents
Culture Documents
Operation Table Week 19-11-22 (2023)
Operation Table Week 19-11-22 (2023)
Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Al Kharj Microtunneling project - Operation table Monday 20/11/2023
Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe Ahmed 49 153.7 9:24:00 11:30:00 376.4 -11.07 3.53
Fix Pipe, Change water Fittings & Installation team. 11:30:00 17:48:00
Push Pipe Moath 50 156.3 17:48:00 20:12:00 465.2 -45.22 -8.95
Fix Pipe Fittings & Installation team. 20:12:00 0:16:00
Push Pipe Moath 51 159.7 20:04:00 23:05:00 394.3 -28.6 -8.47
Fix Pipe, Change Water Fittings & Installation team. 23:05:00 10:32:00
Total pushing meter in day 9.00
Moath 6 meter
Azim 3 meter
Al Kharj Microtunneling project - Operation table Tuesday 21/11/2023
Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe Ahmed 52 162.7 finish time 11:37:00 484.3 -15.76 0.76
Fix Pipe Fittings & Installation team. 11:37:00 12:37:00
Push Pipe Ahmed 53 165.7 12:37:00 13:32:00 485.2 -26.35 2.52
Fix Pipe, change water Fittings & Installation team. 13:32:00 18:03:00
Push Pipe Moath 54 168.7 18:03:00 18:50:00 376.7 -33.03 52.59
Fix Pipe Fittings & Installation team. 18:50:00 19:38:00
Push Pipe Moath 55 171.7 19:38:00 20:49:00 444.2 -17.73 51.1
Fix Pipe, change water Fittings & Installation team. 20:49:00 0:58:00
Total pushing meter in day 12.00
Moath 6 meter
Ahmed 6 meter
Al Kharj Microtunneling project - Operation table Wednesday 22/11/2023
Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe Moath 56 174.7 finish time 1:39:00 402.9 12.15 41.44
Fix Pipe Fittings & Installation team. 1:39:00 2:32:00
Push Pipe Moath 57 177.7 2:32:00 3:18:00 378.4 15.38 13.34
Fix Pipe, change water Fittings & Installation team. 3:18:00 11:31:00
Push Pipe Ahmed 58 180.7 11:31:00 12:10:00 512.7 42.65 -9.36
Fix Pipe Fittings & Installation team. 12:10:00 13:28:00
Push Pipe Ahmed 59 183.7 13:28:00 14:18:00 456.6 -62.5 -54.63
Fix Pipe, change water Fittings & Installation team. 14:18:00 18:48:00
Push Pipe Moath 60 186.7 18:48:00 19:38:00 466.4 -63.64 -41.28
Fix Pipe Fittings & Installation team. 19:38:00 23:54:00
Total pushing meter in day 15.00
Moath 9 meter
Ahmed 6 meter
Al Kharj Microtunneling project - Operation table Thursday 23/11/2023
Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe Moath 61 189.7 23:54:00 0:43:00 534.4 -64.45 -34.44
Fix Pipe Fittings & Installation team. 0:43:00 2:02:00
Push Pipe Moath 62 192.7 2:02:00 2:53:00 532.9 -51.19 12.38
Fix Pipe Fittings & Installation team. 2:53:00 3:43:00
Push Pipe Moath 63 195.7 3:43:00 MACHINE BREAKTHROUGH
Fix Pipe Fittings & Installation team.
Total pushing meter in day 12.00
Moath 9 meter
Total in week in meter: 51
Al Kharj Microtunneling project - Operation table Friday 24/11/2023
Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe
Fix Pipe Fittings & Installation team.
Push Pipe
Fix Pipe, change Water Fittings & Installation team.
Total pushing meter in day
Moath meter
Al Kharj Microtunneling project - Operation table Saturday 25/11/2023
Drive : 29-- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe
Fix Pipe Fittings & Installation team.
Push Pipe
Fix Pipe Fittings & Installation team.
Push Pipe
Fix Pipe, Change water Fittings & Installation team.
Push Pipe
Fix Pipe Fittings & Installation team.
total pushing meter in day
Moath meter
Total in week in meter:
Al Kharj Microtunneling project