Al Kharj Microtunneling project - Operation table Sunday 19/11/2023

Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Al Kharj Microtunneling project - Operation table Monday 20/11/2023

Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe Ahmed 49 153.7 9:24:00 11:30:00 376.4 -11.07 3.53
Fix Pipe, Change water Fittings & Installation team. 11:30:00 17:48:00
Push Pipe Moath 50 156.3 17:48:00 20:12:00 465.2 -45.22 -8.95
Fix Pipe Fittings & Installation team. 20:12:00 0:16:00
Push Pipe Moath 51 159.7 20:04:00 23:05:00 394.3 -28.6 -8.47
Fix Pipe, Change Water Fittings & Installation team. 23:05:00 10:32:00
Total pushing meter in day 9.00
Moath 6 meter
Azim 3 meter
Al Kharj Microtunneling project - Operation table Tuesday 21/11/2023

Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe Ahmed 52 162.7 finish time 11:37:00 484.3 -15.76 0.76
Fix Pipe Fittings & Installation team. 11:37:00 12:37:00
Push Pipe Ahmed 53 165.7 12:37:00 13:32:00 485.2 -26.35 2.52
Fix Pipe, change water Fittings & Installation team. 13:32:00 18:03:00
Push Pipe Moath 54 168.7 18:03:00 18:50:00 376.7 -33.03 52.59
Fix Pipe Fittings & Installation team. 18:50:00 19:38:00
Push Pipe Moath 55 171.7 19:38:00 20:49:00 444.2 -17.73 51.1
Fix Pipe, change water Fittings & Installation team. 20:49:00 0:58:00
Total pushing meter in day 12.00
Moath 6 meter
Ahmed 6 meter
Al Kharj Microtunneling project - Operation table Wednesday 22/11/2023

Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe Moath 56 174.7 finish time 1:39:00 402.9 12.15 41.44
Fix Pipe Fittings & Installation team. 1:39:00 2:32:00
Push Pipe Moath 57 177.7 2:32:00 3:18:00 378.4 15.38 13.34
Fix Pipe, change water Fittings & Installation team. 3:18:00 11:31:00
Push Pipe Ahmed 58 180.7 11:31:00 12:10:00 512.7 42.65 -9.36
Fix Pipe Fittings & Installation team. 12:10:00 13:28:00
Push Pipe Ahmed 59 183.7 13:28:00 14:18:00 456.6 -62.5 -54.63
Fix Pipe, change water Fittings & Installation team. 14:18:00 18:48:00
Push Pipe Moath 60 186.7 18:48:00 19:38:00 466.4 -63.64 -41.28
Fix Pipe Fittings & Installation team. 19:38:00 23:54:00
Total pushing meter in day 15.00
Moath 9 meter
Ahmed 6 meter
Al Kharj Microtunneling project - Operation table Thursday 23/11/2023

Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe Moath 61 189.7 23:54:00 0:43:00 534.4 -64.45 -34.44
Fix Pipe Fittings & Installation team. 0:43:00 2:02:00
Push Pipe Moath 62 192.7 2:02:00 2:53:00 532.9 -51.19 12.38
Fix Pipe Fittings & Installation team. 2:53:00 3:43:00
Push Pipe Moath 63 195.7 3:43:00 MACHINE BREAKTHROUGH
Fix Pipe Fittings & Installation team.
Total pushing meter in day 12.00
Moath 9 meter
Total in week in meter: 51
Al Kharj Microtunneling project - Operation table Friday 24/11/2023

Drive : 29 -- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe
Fix Pipe Fittings & Installation team.
Push Pipe
Fix Pipe, change Water Fittings & Installation team.
Total pushing meter in day
Moath meter
Al Kharj Microtunneling project - Operation table Saturday 25/11/2023

Drive : 29-- 30
No. Of Pushing
Description Operator Drive length start time finish time V- DEV. H- DEV. Ground Condition
pipe Force
Push Pipe
Fix Pipe Fittings & Installation team.
Push Pipe
Fix Pipe Fittings & Installation team.
Push Pipe
Fix Pipe, Change water Fittings & Installation team.
Push Pipe
Fix Pipe Fittings & Installation team.
total pushing meter in day
Moath meter
Total in week in meter:
Al Kharj Microtunneling project

Notes and recommendations

operational pushing pressure is too high

recommendations: 1- change all cutting roller for cutting desk after t


to have a good clerance between machine and ground (over cut roll
2- change water in clay ground every 3 meter push
recommendations: 1- change all cutting roller for cutting desk after t
to have a good clerance between machine and ground (over cut roll
2- change water in clay ground every 3 meter push

Operator : Eng. Ahmed Mass


endations

cutting desk after this drive to make sure


round (over cut roller)
sh
cutting desk after this drive to make sure
round (over cut roller)
sh

Eng. Ahmed Massadeh: