DATE: December 14, 2023

PROJECT: ASCOM
LOCATION: Tarlac City
TTENTION:
SUBJECT: COST PROPOSAL FOR FIRE PROTECTION SYSTEM TESTING & COMMISSIONING

Description Unit Cost Total Cost


Item No. Qty Unit
Material Labor Material Labor Total
I.0 General Requirements
1.0 Mobilization/Demobilization (Manpower and Testing Equipment) 1.00 lot 30,000.00 30,000.00 0.00 30,000.00
2.0 Temporary Facilities 1.00 lot 30,000.00 30,000.00 0.00 30,000.00
3.0 Documentation 1.00 lot 20,000.00 30,000.00 20,000.00 30,000.00 50,000.00
Sub-total I.0 110,000.00

II.0 Water Base Automatic Fire Suppression System


Implementation of Testing and Commissioning base on approved methodolody submitted

1.0 Fire Water Line Assemby 300,000.00


2.0 Fire Hose House 300,000.00
Repair of deffects/punchlist arise during testing & commissioning by others
Sub-total II.0 600,000.00

Value Added Tax (Excluded) 0.00

GRAND TOTAL 710,000.00

Prepared By :
Engr. Jaypee M. Pastor