KCSS CTR 03 GEN PRG 02 (H) Program of Performance AK
KCSS CTR 03 GEN PRG 02 (H) Program of Performance AK
PROJECT NAME: DESIGN, CONSTRUCTION & COMMISSIONING OF THE KIGALI CENTRALIZED SEWERAGE SYSTEM
EMPLOYER: WASAC
ENGINEER: CES
SIGNATURE:
‘I certify that the Contract requirements with applicable changes made by Variations
are met and that nothing in this submittal shall be construed as establishing a basis for
an extra cost or extension of the Time for Completion unless accompanied by a claim
in accordance with the Conditions of Contract.’
16/11/23 Task Milestone External Tasks Deadline Critical Split Manual Progress
Page 1 of 3
KCSS-CTR-03-GEN-PRG-03(G) Program of Performance
ID Task Name Duration Start Finish 2024 2025 2026 2027
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
58 1.1.2.2.13.1 Building inspections for compliance 5 days 19/11/23 23/11/23
16/11/23 Task Milestone External Tasks Deadline Critical Split Manual Progress
Page 2 of 3
KCSS-CTR-03-GEN-PRG-03(G) Program of Performance
ID Task Name Duration Start Finish 2024 2025 2026 2027
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
116 1.2.6.4.1.2 Batch 2 1 day 19/12/23 19/12/23
117 1.2.6.4.1.3 Batch 3 1 day 19/12/23 19/12/23
118 1.2.6.4.1.4 Batch 4 1 day 19/12/23 19/12/23
119 1.2.6.4.1.5 Batch 5 1 day 19/12/23 19/12/23
120 1.2.6.4.1.6 Batch 6 1 day 19/12/23 19/12/23
121 1.2.6.4.1.7 Batch 7 1 day 19/12/23 19/12/23
122 1.2.6.4.1.8 Batch 8 1 day 19/12/23 19/12/23
123 1.2.6.4.1.9 Batch 9 1 day 19/12/23 19/12/23
124 1.2.6.4.1.10 Batch 10 1 day 19/12/23 19/12/23
125 1.2.6.4.1.11 Batch 11 1 day 19/12/23 19/12/23
126 1.2.6.4.2 Consultant Review 28 days 20/12/23 16/01/24
127 1.2.6.4.3 CRCEG Resubmission 14 days 17/01/24 30/01/24
128 1.2.6.4.4 Consultant's Approval 14 days 31/01/24 13/02/24
129 1.2.6.4.5 Milestone 4: Final Detailed Design 0 days 13/02/24 13/02/24 13/02
Approval
130 1.3 Construction Mobilization 195 days 26/12/23 08/07/24
131 1.3.1 Construction Permits 30 days 14/01/24 12/02/24
132 1.3.2 Procurement of General Materials 195 days 26/12/23 08/07/24
133 1.3.3 Arrangements for Labour 195 days 26/12/23 08/07/24
134 1.3.4 Procurement of Construction Equipment 195 days 26/12/23 08/07/24
135 1.4 Construction Phase 747 days 29/01/24 13/02/26
136 1.4.1 Consumables (B1.11) 30 days 22/07/24 20/08/24
137 1.4.2 Procurement of Specialized WWTP equipment 180 days 21/08/24 16/02/25
and shipping
138 1.4.3 Sewer Networks 715 days 29/01/24 12/01/26
139 1.4.3.1 Sewer network shop drawings 650 days 29/01/24 08/11/25
140 1.4.3.2 Sewerage construction (B1.4) 700 days 13/02/24 12/01/26
141 1.4.4 Pumping Station Works 430 days 13/04/24 16/06/25
142 1.4.4.1 Pumping station shop drawings 350 days 13/04/24 28/03/25
143 1.4.4.2 Pumping station construction works 400 days 13/05/24 16/06/25
144 1.4.5 Waste Water Works 720 days 13/02/24 01/02/26
145 1.4.5.1 Waste water works shop drawings 560 days 04/07/24 14/01/26
146 1.4.5.2 WWTP excavation works 160 days 13/02/24 21/07/24
147 1.4.5.3 WWTP works 560 days 22/07/24 01/02/26
148 1.4.5.4 Maturation ponds excavation works 180 days 13/02/24 10/08/24
149 1.4.5.5 Maturation ponds civil works 150 days 11/08/24 07/01/25
150 1.4.5.6 Milestone 5: Practical completion 0 days 01/02/26 01/02/26 01/02
151 1.4.6 Training (B1.6) 75 days 17/07/25 29/09/25
152 1.4.6.1 Study tour to WWTP in China 15 days 17/07/25 31/07/25
153 1.4.6.2 On site training 30 days 31/08/25 29/09/25
154 1.4.7 Commissioning 287 days 03/05/25 13/02/26
155 1.4.7.1 Operation Manuals 57 days 09/08/25 05/10/25
156 1.4.7.1.1 Contractors Submission A 1 day 09/08/25 10/08/25
157 1.4.7.1.2 Consultant Review 28 days 10/08/25 07/09/25
158 1.4.7.1.3 Contractor's Revisions&Resubmission 14 days 07/09/25 21/09/25
16/11/23 Task Milestone External Tasks Deadline Critical Split Manual Progress
Page 3 of 3