Professional Documents
Culture Documents
Gantt Chart Main Plant Reclaimer Area Wall Partition and Shutter Door's Relocation
Gantt Chart Main Plant Reclaimer Area Wall Partition and Shutter Door's Relocation
Mode F T S W S T M F T S W S T M
1 JT INTERNATIONAL ASIA 41 days Wed Fri 12/01/24 29/11 12/01
MANUFACTURING INC 29/11/23
2 JTI MAIN PLANT RECLAIMER AREA 41 days Wed Fri 12/01/24 29/11 12/01
WALL PARTITION AND SPEED 29/11/23
SHUTTER DOOR'S RELOCATION
3 I. PRELIMINARIES 4 days Wed 29/11/23
Sat 02/12/23 29/11 02/12
6 3. Board ups / Signages 1 day Sat 02/12/23 Sat 02/12/23 02/12 02/12
14 1. Demolition of Existing Wall 5 days Fri 08/12/23 Tue 12/12/23 08/12 12/12
Project: Main Plant Wall Partition and Speed Shutter Doors Relocation Split Inactive Milestone Manual Summary Deadline
23 4. Installation of Metal Stud 2x47 days Mon 25/12/23Tue 02/01/24 25/12 02/01
26 IV. PROJECT TURN OVER / 5 days Mon Fri 12/01/24 08/01 12/01
ACCEPTANCE 08/01/24
27 1. Punchlisting 1 day Mon 08/01/24Mon 08/01/24 08/01 08/01
Project: Main Plant Wall Partition and Speed Shutter Doors Relocation Split Inactive Milestone Manual Summary Deadline