ID Task Task Name Duration Start Finish 26 Nov '23 10 Dec '23 24 Dec '23 07 Jan '24

Mode F T S W S T M F T S W S T M
1 JT INTERNATIONAL ASIA 41 days Wed Fri 12/01/24 29/11 12/01
MANUFACTURING INC 29/11/23
2 JTI MAIN PLANT RECLAIMER AREA 41 days Wed Fri 12/01/24 29/11 12/01
WALL PARTITION AND SPEED 29/11/23
SHUTTER DOOR'S RELOCATION
3 I. PRELIMINARIES 4 days Wed 29/11/23
Sat 02/12/23 29/11 02/12

4 1. Mobilization 1 day Wed 29/11/23Wed 29/11/23 29/11 29/11

5 2. Material Procurement 2 days Thu 30/11/23Fri 01/12/23 30/11 01/12

6 3. Board ups / Signages 1 day Sat 02/12/23 Sat 02/12/23 02/12 02/12

7 II. SITE WORKS 37 days Mon 04/12/23


Fri 12/01/24 04/12 12/01

8 A. PROTECTION WORKS 4 days Mon 04/12/23


Thu 07/12/23 04/12 07/12

9 1. Temporary Wall / Wall Isolation


1 day Mon 04/12/23Mon 04/12/23 04/12 04/12

10 2. Floor Protection 1 day Mon 04/12/23Mon 04/12/23 04/12 04/12

11 3. Temporary Ventilation 1 day Mon 04/12/23Mon 04/12/23 04/12 04/12

12 4. Scaffold Erection 3 days Tue 05/12/23Thu 07/12/23 05/12 07/12

13 B. Relocation of Roll Up 9 days Fri 08/12/23 Sat 16/12/23 08/12 16/12

14 1. Demolition of Existing Wall 5 days Fri 08/12/23 Tue 12/12/23 08/12 12/12

15 2. LOTO Works + Power Supply 1 day Wed Wed 13/12 13/12


Disconnection 13/12/23 13/12/23
16 3. Dismantle of Ifarflex roll up 1 day Thu Thu 14/12/23 14/12 14/12
and horman door 14/12/23
17 4. Installation and relocation of 1 day Fri 15/12/23 Fri 15/12/23 15/12 15/12
ifarflex roll up and horman
18 5. Testing / restoration of wall 1 day Sat 16/12/23 Sat 16/12/23 16/12 16/12

19 III. PARTITION OF RECLAIMER AREA


19 days Sun 17/12/23Sun 07/01/24 17/12 07/01

20 1. CHB Laying 5" 7 days Sun 17/12/23Sat 23/12/23 17/12 23/12

Task Inactive Task Manual Summary Rollup External Milestone

Project: Main Plant Wall Partition and Speed Shutter Doors Relocation Split Inactive Milestone Manual Summary Deadline

Milestone Inactive Summary Start-only Progress


Date: 30/11/2023
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks


ID Task Task Name Duration Start Finish 26 Nov '23 10 Dec '23 24 Dec '23 07 Jan '24
Mode F T S W S T M F T S W S T M
21 2. Installation of Square Tube 7 days Mon 25/12/23Tue 02/01/24 25/12 02/01

22 3. Installation of Metal Track 7 days Mon 25/12/23Tue 02/01/24 25/12 02/01

23 4. Installation of Metal Stud 2x47 days Mon 25/12/23Tue 02/01/24 25/12 02/01

24 5. Installation of Gypsum Board 3/8


7 days Mon 25/12/23Tue 02/01/24 25/12 02/01

25 6. Painting Works / Finishing 5 days Wed 03/01/24Sun 07/01/24 03/01 07/01

26 IV. PROJECT TURN OVER / 5 days Mon Fri 12/01/24 08/01 12/01
ACCEPTANCE 08/01/24
27 1. Punchlisting 1 day Mon 08/01/24Mon 08/01/24 08/01 08/01

28 2. Rectification / Punchlisting 3 days Tue Thu 11/01/24 09/01 11/01


rectification 09/01/24
29 3. Buy off/ Turn over 1 day Fri 12/01/24 Fri 12/01/24 12/01 12/01

Task Inactive Task Manual Summary Rollup External Milestone

Project: Main Plant Wall Partition and Speed Shutter Doors Relocation Split Inactive Milestone Manual Summary Deadline

Milestone Inactive Summary Start-only Progress


Date: 30/11/2023
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks