54 FGD-JSA - Pickling & Passivation Work
54 FGD-JSA - Pickling & Passivation Work
19
Equipment: Hydro jet machine. Supervisor: H.Giri Prepared by: Mr.Ramesh Palnati
Eye Clothing Foot Face Hand Respiratory Head Hearing Other ____________________
Inside Outside Cold Heat Wet Dust Vapours / Mist Noise Vibration Other____________________
Lifting Grasping Pushing Sitting Reaching Bending Kneeling Standing Pulling Squatting Other__________________________
Others Site Work: - Site Conditions___Fuel / Lubricants___ Hazardous Chemicals___Mobile Plant / Vehicles___ Deep Excavation_____Vibration___ Explosion__ Work Near Water___ Falls
From Height__ Trips / Falls___ Fall of Material__ Fumes / Gas__ Lifting Operations___ Flying Particles__ Collapse of Structure___ Contaminated Ground___ Soft Ground___ Poor Light /
Visibility_____ Buried Services___ Manual Handling___Vehicle Overturning___ Adverse Weather Dust___ Heat__ Eye Hazard__ Ear Hazard__ Respiratory Hazard__
1
Head Hazard__ Hand Hazard__ Foot Hazard__ Radiation Hazard__ Electrical Hazard__ Fire Hazard__ Other Hazards
Sl.
Sequence of Operation – Activity Steps Hazard Recommended safe job procedures Action by
No.
Fall of men & material 1.Full body harness must be worn & anchored to rigid
Insufficient illumination & support during inspection
ventilation 2.Sufficient illumination & ventilation shall be ensured Site Engineer /
5 Visual inspection
Hit by structure while carryout the inspection Supervisor
Trips 3.Access & working platforms shall be free from loose
materials & obstacles
8 If any
Signature: Signature:
Name of site Safety In-charge : Mr. Arun Name of Site In-charge : Mr.Kumar Babu