Groundwater Monitoring Network Data Sheet

Mutamba Mineral Sands Pz = Piezometer


Mz = Mozambqiue Site Supervisor
SITE DESCRIPTION S## = Station ID

Groundwater Station ID [Pz-Mz-S##] Drilling Contractor Thompson Drilling


Drill Operator Jerry
Station Location
Lithological Unit to Monitor Length of Cap CAP
X (Easting) (m) [ ] δ ab ove Grd Level Elevation Units (m
Y (Northing (m) [ ] [9- 6]= WGS84) from Lidar
[1] Elevation (m WGS84 Ellipsoid) [ ] Depth (m BGL)
Start Date of Drilling GrdLvl 0.00 [1]
End Date of Drilling
Drilling Method NOTE Case Concrete
Lengths are
Planned depth of Drill Hole (m BGL) 2.93m Piezometer
Expected depth 2 Water Table (WT) [1-2] ESTIMATED Case
Diameter of Drill Hole (mm) 152.4 Depth to
ESTIMATED
[6] Final Depth of Drill Hole [Σ] (m bgl) Water Level
Elevation of Water
PIEZOMETER DESCRIPTION to PLAN Level (m WGS84)
from Groundwater
Screen Type ID (0=Dual screen with gravel) 0 D RILL Depth model
[4] Depth2Top Screen below Grd [Ω] (m bgl) WT [3] [2]
Number of Case sections above screen [ ] Add
Water Table
[7] Length of case above Top Screen (m) Scr een Depth
[8] Length of Screened section [β] (m) =2.93
± 3m PIEZOMETER
Length case plus screen [7+8]
Depth to Length of casing
[5] Length of Sump [ Γ ] (m) [=6 minus-7+8] above screens
Top Screen
[9] Total Length Casing+screen+sump (m) [7]
Ω [4]
Length of slotted screen(s) [ ]
Add 2.93m for 1 Screen section length
Backfill screen section (Fine/Medium/Coarse) pack screen is 2.93m. Slotted
Bentonite seal (Yes or No) section length is 1m.

SCREEN DESCRIPTION for Dual Screen section Add Total length of


Depth to Base screen section
Screen Type Class in Database 0.00 screen [2.93]
Internal Diam of Inner Screen (mm) 102.00 β [5] [8]
Outer Diameter of Outer screen (mm) 114.00 Sump Add sump
Add sump
Slot width of Inner screen (mm) 0.30 [9]
[6]
Slot Width of Outer screen (mm) 0.30 ΣΓ
PROCEDURE to Determine Depth of Drill Hole GENERAL COMMENTS # Cases Length
[1] Measure X,Y,Z from GPS or LiDar 1 2.93
[2] Estimate Elevation (Z) of Water Table from Model 2 5.86
[3] Estimate Depth to Water Table from [1] minus [2] 3 8.79
[4] Depth to Top Screen WT=3m (Minimum) 4 11.72
[5] Calculate total length of screen section [β] 5 14.65
[6] Minimum length of sump is 0.5m 6 17.58
Add all sections to get the Drill DEPTH OF HOLE 7 20.51
Final Depth of Hole determined by Lithology (Geologist) 8 23.44
Cut Top Case to ±0.75m to fit Cap 9 26.37
m BGL = meters Below Ground Level 10 29.30
mBToC= meters Below Top of Cap
Rio Tinto PIEZOMETER GROUNDWATER MONITORING DATA CAPTURE
MOZAMBIQUE SHEET – MUTAMBA
Pz = Piezometer
Mz = Mozambqiue
M## = Station ID
PIEZOMETER
DATA Pz-Mz-M See list below
Groundwater
Logger_ID Station
(Serial ID
Number) See list below
Operator
Date (YYYY/MM/DD)
Time (HH:MM:SS)
Dipped Water Level Depth FROM mbToC
Top Of Steel Cap (ToCap)
IF there are any LOGGER_ID
Changes to the Altitude
Logger settings Depth2Logger
record these ones Offset
m BGL = meters Below Ground Level Remove Cap with PROCEDURE
key
m BtoC=meters Below Top of Cap Remove Levelogger & cap into bucket
Dip water level & record reading
Pz-Mz-M## LOGGER_ID Download levelogger to leveloader
Bp-Mz-M00 1053517 Replace levelogger and cap
Pz-Mz-M00 1054920 Replace and secure steel Cap
Pz-Mz-M01 1054911
Pz-Mz-M02 1054863
Pz-Mz-M03 1054898
Pz-Mz-M04 1054857
Pz-Mz-M05 1054900
Pz-Mz-M06 1054868
Pz-Mz-M07 1054870
Pz-Mz-M08 1054865
Pz-Mz-M09 1054907
Pz-Mz-M10 1054871
Pz-Mz-M11 1054923
Pz-Mz-M12 1054896
Pz-Mz-M13 1054913
Pz-Mz-M14 1054904
Pz-Mz-M15 1054873
testing 1054914
COMMENTS

SITE EQUIPMENT
Dipper
Cap Key
Bucket
Leveloader + cable
Rio Tinto FORM SHEET FOR SLUG TESTS
MOZAMBIQUE Pz = Piezometer See List Below
Mz = Mozambqiue
S## = Station ID
PIEZOMETER USE in Slug Test Logger
Groundwater Station ID Pz-Mz- Project_ID Groundwater Stn ID
Logger_ID (Serial Number) Location “Slug Test:Stn_ID”
DATE (YYYY/MM/DD) of Slug Test
LOGGER_ID for Slug Test 1054920
Logger Program # (USE 10s ec scan rate)
LOGGER_ID for water supply 1054914
Logger Program # (Use 10 sec scan rate)
DATE (YYYY/MM/DD)
TIME (HH:MM:SS)
Dipper Water Level BEFORE TEST
ADD water at maximum rate for 1 minute
Check when WL reaches Pre-Test level ± 1cm
ADD water at maximum rate for 2 minute ▼
Check when WL reaches Pre-Test level ± 1cm
ADD water at maximum rate for 3 minute Water
STOP TEST WHEN WL REACHES Pre-Test Level ± 1cm Tank
Withdraw loggers from tank/well and STOP them with Leveloader
NOTE
Discharge into piezometer at maximum rate without causing air blocks or
surges in the discharge rate. If case fills then immediately stop the water
and start to monitor the recession rate
Pz-Mz-M## LOGGER_ID REQUIREMENTS
Bp-Mz-M00 1053517 Full Water Tank
Pz-Mz-M00 1054920 2 loggers
Pz-Mz-M01 1054911 2 buckets
Pz-Mz-M02 1054863 WL Dipper
Pz-Mz-M03 1054898 Pre-program loggers (use program #2)
Pz-Mz-M04 1054857 30 sec scan rate
Pz-Mz-M05 1054900
Pz-Mz-M06 1054868 PROCEDURE
Pz-Mz-M07 1054870 Dipper Water Level
Pz-Mz-M08 1054865 Remove Site Logger into bucket
Pz-Mz-M09 1054907 Record Logger_IDs
Pz-Mz-M10 1054871 Insert logger #1 to just below WL
Pz-Mz-M11 1054923 Insert logger #2 to bottom water tank
Pz-Mz-M12 1054896 Place discharge pipe into casing
Pz-Mz-M13 1054913 Record date & time
Pz-Mz-M14 1054904 Open valve until tank level drops 25%
Pz-Mz-M15 1054873 Close valve
testing 1054914 Monitor WL till it returns to ±10cm start leve
COMMENTS Open valve until tank level drops to 50%
Close valve
Monitor WL till it returns to ±10cm start leve
Repeat test #3 if sufficient water WL ▼

DOWNLOAD DATA FOR TEST PERIOD


Download both leveloggers into leveloader.
Save data to leveloader
STOP levelogger