Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Estimation of Remaining Bill of Quantity of Sabi Bridge Construction

Project :- Sabi/Didiba River Brigde Project Consultant:-JZRLO Consulting Engineers


Client:-C/botare Ana Roads and Logostic office Contractor:- _________________________
Span length 20m
Item No Description Unit Qty Rate Amount

8100 Foundation for structures


Additional foundation investigation LS - -
81.02 Excavation of material - -
81.02 A Excavation of soft material irrespective of depth range below the surface level m3 -
81.02 B Excavation of hard material irrespective of depth range below 3m m3 -
81.05 Backfill to excavation utilising -
81.05 A Material from the excavation m3 197.41 -
81.05 B Imported material with cover all haulage costs over any distance m3 1,700.00 586.13 996,421.00
81.05 C Selected granular backfill with cover all haulage costs over any distance m3 2,300.00 586.13 1,348,099.00
81.05 D Hand laid stone to be filled upon level A as shown on the drawing m3 520.00 1,185.34 616,376.80
Total Carried Summary - 2,960,896.80
8300 Steel reinforcement for structures - -
83.01 A Mild steel bars(grade300) ton 12.00 202,911.20 2,434,934.40
83.01 B High- yeild stress steel bars (grade 420) ton 9.80 213,056.76 2,087,956.25
Total Carried Summary 4,522,890.65
8400 Concrete for structures -
84.01 Cast in situ concrete -
84.01 A Grade c-30 class "A" concrete for superstructures including formwork m3 198.00 11,483.60 2,273,752.80
84.01 B Grade c-30 class "A" concrete for substructures(piers) including formwork m3 10,176.13 -
84.01 C Grade c-15 class concrete for substructure (abutment&piers) including formwork. m3 9,334.99 -
84.02 Epoxy bounding of new concrete surface to old m2 54.00 928.72 50,150.88
Total Carried Summary - 2,323,903.68
8700 Bridge Bearing Paraphet,Railling etc. - -
87.03 Elastomeric bearing, fressinet or similar no 8.00 81,805.00 654,440.00
87.08 Concrete bridge railing Im 54.00 3,540.91 191,209.14
87.09 PVC utility pipes Im 103.00 134.70 13,874.10
87.13 Expansion joints in steel angle as per the drawings Im 36.20 1,076.87 38,982.69
87.14 Filled joint-preformed expansion joint filler(25mm thi) Im 46.20 74.66 3,449.29
87.16 Sealing joint with preformed comperssible seals as per drawing m 277.47 -
87.19 Deck drain made of steel as per the drawing no 24.00 311.37 7,472.88
87.21 A Geotexile filter fabric at the inlet of each weep hole m2 100.00 111.65 11,165.00
Total Carried Summary - 920,593.11
8900 Stone masonry structures - -
89.01 Class A cement morted stone masonry walls including pointing works m3 238.93 5,144.89 1,229,268.57
89.02 Provide new 100mm dia drainage pipes ml 36.00 -
Total Carried Summary 1,229,268.57
5000 Road way and borrow excavation subbase, roads and gravel wearing course - -

Cut to fill Existing material classofied as suitable for forming the road bed shall,unless otherwise
approved by the engineer, be scarfied to a depth of 200mm watered or dried as necessary and
compacted to 95% of the maximum dry density determine in accordance with AASHTO-180
a) cut to fill of intermediate material m3 2,480.00 144.58 358558.4
b) cut to fill of hard material m3 3,720.00 330.84 1230724.8
c) Borrow to fill, compaction to 95% MDD, AASHATO-180 from any distance m3 12,300.00 237.71 2923833
d) Capping layer ,95% of modified AASHTO density m3 2,600.00 313.61 815386
e) backfill using slecting granular material including compaction m3 4,500.00 566.21 2547945
f) Gravel wearing course m3 840.00 632.02 530896.8
Total Carried Summary - 8,407,344.00
9100 Ancillary works - -
Foundation trench Excavation and backfillingin all other classes of material
91.01 B - -
91.02 surface preparation for bedding the gabions m2 65.00 75.21 4,888.65
91.03 Galvanised gabion boxes 80*100mm mesh m3 112.00 2,362.00 264,544.00
91.04 Synthetic - fiber filter, 210g/sq.m. m2 - -
a) no
Traffic Sign 3,069.55
b) Guide posts (reinforced concrete) no 6.00 2,188.61 13,131.66
c) Kilometer posts (reinforcement concrete) no 2.00 2,188.61 4,377.22
e) Sign support /sign post c-20 concrete no 2.00 2,483.28 4,966.56
Total Carried Summary 291,908.09
Total Summary 20,656,804.89
15% Vat 3,098,520.73
Total Summary With Vat 23,755,325.63

Prepared by checked by Approved by


Signed :- Signed :- Signed :-
_____________________ __________________ _____________________

You might also like